harmonic analysis

Upload: hiepkhacha13

Post on 09-Jan-2016

63 views

Category:

Documents


5 download

DESCRIPTION

Harmonic Analysis

TRANSCRIPT

  • KOREA NATIONAL OIL CORPORATION VIETNAM OFFICE

    RONG DOI GAS FIELD DEVELOPMENT PROJECT

    HARMONIC PENETRATION ANALYSIS

    DISCIPLINE ARCH CONST ELECT INSTR MATRL MECH PIPING PIPELINE PROCESS SAFETY STRUC

    SIGN/DATE - - - - - - - - - - -

    D1 28-APR-05 APPROVED FOR CONSTRUCTION YSN JUB/MSH BSK

    C1 28-APR-05 APPROVED FOR DESIGN YSN JUB/MSH BSK

    B1 28-JAN-05 ISSUED FOR APPROVAL HFS BK KCG TM

    A1 26-JAN-05 ISSUED FOR DIC / IDR HFS BK - - -

    Rev. Date Description By Checked Approved QA Client

    This document is the property of KECS any unauthorized use of the same will be prosecuted.

    Total or partial reproduction and/or utilization of this document are forbidden without prior written authorization of the Owner

    Category Code Description

    Facility 200 Common

    Korea National Oil Corporation Vietnam Office

    Phase 30 Detailed Engineering

    Discipline E Electrical Engineering Type CA Calculation

    Project Number

    Facility Phase Discipline Type Sequence Number

    Revision Code

    VN01 200 30 E CA 8007 D1

    As per MOM KNOC UL-0004 DEV/S dated 27th April 05, it is concluded that detailed

    harmonic analysis calculation is not necessary for Electrical Power System of Rong Doi Gas

    Field Development Project. Accordingly this document is issued without change and shall be

    treated as final.

  • Kvaerner E&C Singapore Pte Ltd VN01-200-30-E-CA-8007 i Rev. D1

    RONG DOI GAS FIELD DEVELOPMENT PROJECT

    HARMONIC PENETRATION ANALYSIS

    TABLE OF CONTENTS

    SECTION DESCRIPTION PAGE

    1.0 INTRODUCTION 1

    2.0 OBJECTIVE 2

    3.0 ACCEPTABLE HARMONIC DISTORTION LIMITS 2

    4.0 STUDIES 3

    4.1 CURRENT TOTAL HARMONIC DISTORTION (THDI) 3

    4.2 VOLTAGE TOTAL HARMONIC DISTORTION (THDU) 3

    5.0 SYSTEM PARAMETERS 4

    6.0 HARMONIC PARAMETERS 4

    6.1 VSD FOR STARTING MOTOR 5

    6.2 UPS AND DC CHARGERS 6

    6.3 THYRISTER HEATER 6

    6.4 LIGHTING 7

    7.0 SYSTEM CONSIDERATION 9

    7.1 OPERATING CONDITIONS 9

    7.2 ASSUMPTION 9

    8.0 METHODOLOGY 10

    9.0 CALCULATION 10

    10.0 RESULTS 10

    11.0 RESULT ANALYSIS 11

  • SECTION DESCRIPTION PAGE

    Kvaerner E&C Singapore Pte Ltd VN01-200-30-E-CA-8007 ii Rev. D1

    12.0 RECOMMENDATION 12

    13.0 REFERENCES 12

    APPENDICES

    APPENDIX A HARMONIC ANALYSIS REPORT CASE - I

    APPENDIX B HARMONIC ANALYSIS REPORT CASE - II

  • Kvaerner E&C Singapore Pte Ltd VN01-200-30-E-CA-8007 1 of 12 Rev. D1

    1.0 INTRODUCTION

    The Kvaerner Engineering and Construction Singapore Pte Ltd (KECS) has

    been engaged by a HHI who have been awarded EPIC contract for the project to

    undertake certain design and engineering activities for a Rong Doi Gas

    Development Project operated by KNOC.

    The Rong Doi and Rong Doi Tay Fields are located in Block 11-2 in the Nam Con

    Son Basin offshore Vietnam.

    The Rong Doi and Rong Doi Tay Fields (RD and RDT) are located approximately

    320km to the south-east of Vung Tau and were discovered in 1995 and 1996

    respectively by KNOC, working as the Operator on behalf of a consortium of seven

    Korean companies. The Rong Doi Tay Field is located approximately 2.5km to the

    west of Rong Doi.

    The current development schedule will achieve a First Gas Date of 30 September

    2006. The field and facilities are designed to deliver an average of 130MMscfd of

    sales gas but will have the capacity to produce up to 175MMscfd of sales gas for

    short periods.

    The objective of the Rong Doi and Rong Doi Tay development is to design, install,

    produce and deliver pipeline specification gas to the gas purchaser PetroVietnam, as

    per the terms of the Gas Sales and Purchase Agreement (GSPA).

    The facilities shall consist of a Wellhead Platform bridge connected (80m) to a

    Production Utilities Quarters Compression Platform (PUQC). An FSO will be

    installed to receive stabilized condensate stripped from the gas via a 2.5 Km long 6"

    line. The gas will be transported by a 58 Km 18 pipeline to a Wye in Namcon Son

    gas trunk line operated by BP.

    Drilling activities will be performed by a jack-up rig with all weather capability.

  • Kvaerner E&C Singapore Pte Ltd VN01-200-30-E-CA-8007 2 of 12 Rev. D1

    2.0 OBJECTIVE

    Harmonic analysis has been carried out to study the performance of the electrical

    system with harmonic loads. The purpose of harmonic analysis is to arrive at the

    total harmonic distortion at various locations due to harmonic producing loads in

    the network and to determine the corrective measures required to reduce the

    harmonic distortion to acceptable levels. Normally harmonic analysis is conducted

    when harmonic producing loads exceed 10% of total load. In Rong Doi Gas Field

    Development Project, the harmonic producing loads such as UPS, rectifiers,

    variable speed drives, thyrister control heaters and lighting constitutes more than

    10% of total running loads. This has necessitated to conduct detail harmonic

    analysis for the complete Generation and Distribution System for Rong Doi Project.

    This study considered the impact of the harmonic producing equipment installed on

    Wellhead Platform (WHd) and Production Utilities Quarters Compression Platform

    (PUQC).

    3.0 ACCEPTABLE HARMONIC DISTORTION LIMITS

    The total harmonic voltage distortion shall be limited to following values as

    indicated in Table 3.1 in compliance to IEC 61000.

    TABLE 3.1

    LOAD DESCRIPTION TOTAL HARMONIC DISTORTION

    (VOLTAGE) THDU

    Sensitive Loads (UPS, Computer, PCS, Printers, Monitors)

    5%

    Industrial Loads (Motors, Heaters, Capacitor Lighting,

    Actuators) 8%

    Note : As per agreed design basis, the THD (V) shall be limited to 5% in Rong Doi

    Electrical Power Distribution System.

    The total harmonic current distortion limits THD (I) is not well defined in IEC for

    power distribution system. The total current distortion limits are considered as per

    IEEE 519-1992. The individual harmonic current and total harmonic current

    distortion limits are defined in IEEE Std 519 Table 10.3 and the same is reproduced

    below for information. The current distortion limits for distribution system are

  • Kvaerner E&C Singapore Pte Ltd VN01-200-30-E-CA-8007 3 of 12 Rev. D1

    indicated in Table 3.2 below.

    TABLE 3.2 - CURRENT DISTORTION LIMITS FOR GENERAL DISTRIBUTION SYSTEM (120V THROUGH 69,000V

    MAXIMUM HARMONIC CURRENT DISTORTION IN PERCENTAGE OF IL

    Individual Harmonic Order (Odd Harmonics)

    Isc/IL

  • Kvaerner E&C Singapore Pte Ltd VN01-200-30-E-CA-8007 4 of 12 Rev. D1

    VHL : Rms value of fundamental voltage.

    5.0 SYSTEM PARAMETERS

    The electrical network for Rong Doi Gas Field Development Project has been

    planned as per Electrical Overall Key Single Line Diagram drawing number VN01-

    200-30-E-DW-1100. Harmonic Penetration Analysis has been carried out for the

    entire system network in WHd and PUQC considering all harmonic sources. The

    basic network parameters for the Electrical Distribution System are as follows:

    TABLE 5.1 - GENERATOR PARAMETERS

    DESCRIPTION RATING %

    IMPEDANCE

    MAX. POWER OUTPUT AT

    SITE CONDITION

    REMARKS

    Generator 230-GT-8001A 1500 kVA /

    400 V 12.0 % 1000 kW -

    Generator 230-GT-8001B 1500 kVA /

    400 V 12.0 % 1000 kW -

    Generator 230-GT-8001C 1500 kVA /

    400 V 12.0 % 1000 kW -

    Emergency Generator 230-GD-8002 750 kVA /

    400 V 9.0 % 600 kW -

    TABLE 5.2 - NER PARAMETERS

    DESCRIPTION IMPEDANCE REMARKS

    230-NER-8001A 4.6 -

    230-NER-8001B 4.6 -

    230-NER-8001C 4.6 -

    230-NER-8002 4.6 -

    6.0 HARMONIC PARAMETERS

    The electrical network at Rong Doi Gas Field Development Project WHd and

    PUQC Platform feeds various types of loads. The major harmonic producing loads

    are as follows:

    Variable speed drives for Generator & Compressor starting motor

    AC UPS

    Battery chargers (GT & Nav Aids)

  • Kvaerner E&C Singapore Pte Ltd VN01-200-30-E-CA-8007 5 of 12 Rev. D1

    Thyrister heater

    6.1 VSD FOR STARTING MOTOR

    There are three (3) VSD drives for gas turbine generator starting motor and one (1)

    VSD drive for flash gas compressor starting motor. However, each VSD is

    assumed to produce the harmonic current content as per IEEE 519 and same is

    detailed in Table 5.2. This assumption is made in view of VSD shall be procured to

    meet IEEE 519 requirement.

    Under normal operation, one (1) VSD drive for flash gas compressor is considered

    as continuous harmonic source contributing to the electrical network. While during

    emergency operation, one (1) VSD drive for gas turbine generator shall be deem as

    harmonic source. They are connected to LVS A switchboard and Table 6.1 shows

    the VSD rating considered for this study.

    TABLE 6.1 VSD LOAD RATING

    VSD TAG VSD RATING (kVA)

    SWB-8301

    A-8001A 98.8

    KM-2401 384.3

    TABLE 6.2 - HARMONIC CURRENT IN VSD

    HARMONIC ORDER COMPONENT CURRENT % OF

    FUNDAMENTAL

    1 100

    5 4

    7 4

    11 2

    13 2

    17 1.5

    19 1.5

    23 0.6

    25 0.6

    29 0.6

    31 0.6

    35 0.3

  • Kvaerner E&C Singapore Pte Ltd VN01-200-30-E-CA-8007 6 of 12 Rev. D1

    HARMONIC ORDER COMPONENT CURRENT % OF

    FUNDAMENTAL

    37 0.3

    Note : The above data used is defined by IEEE Std 519-1992 Table 10.3. This value shall

    be applied for all VSD. However actual vendor data shall be used once it becomes available.

    6.2 UPS AND DC CHARGERS

    There are two (2) UPS, each rated at 40kVA output, four (4) Gas Turbine DC

    Battery Chargers each rated at 12kVA, and one (1) Navigational Aids battery

    Charger rated at 3kVA (Refer section 7.1 for operational consideration). In this

    harmonic study, the UPS loads are separately modelled while the Battery Charger

    loads are lumped at respective switchboard. The harmonic current content at UPS

    and DC Chargers is also considered as per IEEE 519 and same is given in Table 6.3

    below.

    TABLE 6.3 - HARMONIC CURRENT IN UPS & BATTERY CHARGER

    HARMONIC ORDER COMPONENT CURRENT % OF

    FUNDAMENTAL

    1 100

    5 4

    7 4

    11 2

    13 2

    17 1.5

    19 1.5

    23 0.6

    25 0.6

    29 0.6

    31 0.6

    35 0.3

    37 0.3

    Note : The above data used is defined by IEEE Std 519-1992 Table 10.3. This value shall

    be applied for all UPS and Battery Charger. However actual vendor data shall be used once it becomes available.

    6.3 THYRISTER HEATER

  • Kvaerner E&C Singapore Pte Ltd VN01-200-30-E-CA-8007 7 of 12 Rev. D1

    Heater load that utilised thyrister control will contribute harmonic and thus

    considered as harmonic source. There are three (3) heater loads considered for

    harmonic study as shown in Table 6.4. The harmonic current content is assumed o

    be the same for all heaters as detailed in Table 6.5.

    TABLE 6.4 HEATER LOAD RATING

    Continuous Load TAG NO. DESCRIPTION

    kW kVAR

    SWB-8301 Switchboard A

    E-4401 Fuel Gas Superheater 69.0 44.6

    SWB-8401 Switchboard B

    E-4101 HP Flare Drum Heater 31.6 0.0

    E-4801 Closed Drains Drum Heater 125.0 142.3

    TABLE 6.5 - HARMONIC CURRENT IN THYRISTER HEATER

    HARMONIC ORDER COMPONENT CURRENT % OF

    FUNDAMENTAL

    1 100

    5 4

    7 4

    11 2

    13 2

    17 1.5

    19 1.5

    23 0.6

    25 0.6

    29 0.6

    31 0.6

    35 0.3

    37 0.3

    Note : The above data used is defined by IEEE Std 519-1992 Table 10.3. However actual

    vendor data shall be used once it becomes available.

    6.4 LIGHTING

  • Kvaerner E&C Singapore Pte Ltd VN01-200-30-E-CA-8007 8 of 12 Rev. D1

    Lighting Loads (Fluorescent fixture, high pressure sodium vapour incandescent

    lamp) under normal operating conditions does not produce harmonics. However

    during starting specially the chokes do produce harmonics. The impact of

    harmonics during starting of chokes operated lighting fixture are ignored due to

    short duration

    The emergency light fitting with inbuilt battery charger do produce harmonics

    continuously. The light fitting with electronic controls also produces harmonics.

    The harmonics content of such light fittings shall be limited to IEEE 519.

    The impact of harmonic producing lighting loads is evaluated. The harmonic

    current content is assumed to be same as per IEEE 519. The emergency lighting

    loads is estimated as follows;

    TABLE 6.6 - EMERGENCY LIGHTING LOAD

    Continuous Load S/No. DESCRIPTION

    kW kVAR

    1 Platform 15.0 7.26

    2 Living Quarter 12.0 5.81

    TABLE 6.7 - HARMONIC CURRENT IN LIGHTING LOAD

    HARMONIC ORDER COMPONENT CURRENT % OF

    FUNDAMENTAL

    1 100

    5 4

    7 4

    11 2

    13 2

    17 1.5

    19 1.5

    23 0.6

    25 0.6

    29 0.6

    31 0.6

    35 0.3

    37 0.3

  • Kvaerner E&C Singapore Pte Ltd VN01-200-30-E-CA-8007 9 of 12 Rev. D1

    Note : The above data used is defined by IEEE Std 519-1992 Table 10.3. However actual vendor data shall be used once it becomes available.

    7.0 SYSTEM CONSIDERATION

    7.1 OPERATING CONDITIONS

    Harmonic analysis has been carried out using EDSA with the above parameters.

    Normal electrical power system operation has been considered, while the harmonic

    sources in the electrical network have been considered under full production

    condition.

    The impact of harmonics on the system is highest where the system has maximum

    impedance. The harmonic contribution of the VSD drive for starting AC motor has

    been considered despite the short duration during starting. To check maximum

    impact, however it may not be necessary to consider for sizing filter etc. Only one

    (1) such VSD drive shall be connected at any one time depending on the operation.

    The complete interconnected network has been simulated for harmonic study.

    Both 40kVA AC UPS are normally loaded to 50% capacity but during emergency

    generator operation, only one is considered as 100% loaded. Although DC battery

    chargers for Gas Turbines shall be operating at full capacity for short duration but to

    observe maximum impact they have been considered as continuous load.

    For the purpose of harmonic analysis, all the major loads have been considered

    including all supporting process loads in the network. The harmonic source is

    separately modelled where individual load has been represented in the network. The

    lump load model that contain harmonic, its contribution is lumped under the

    respective LVS A or LVS B switchboard.

    Note : Please note that Electrical Power Generation and Distribution System for Rong Doi Gas

    Field Development project has been designed to feed electrical loads of PUQC platform & WHd platform only. The drilling loads, workover loads or any other external loads are not considered in design and shall not be feed from this power system. The drilling and workover loads usually have high harmonic content and may adversely affect the power system.

    7.2 ASSUMPTION

    a) The amplitude of all the harmonic sources considered is based on IEEE

  • Kvaerner E&C Singapore Pte Ltd VN01-200-30-E-CA-8007 10 of 12 Rev. D1

    standards 519 Table 10.3.

    b) Cable impedance has been considered as per Kukdong Cable Vendor data

    available, and Motor parameters where not available are assumed based on

    IEC / IEEE standards, while generator sub transient reactance used are based

    on data supplied by KNOC / HHI.

    c) Non harmonic loads are simulated as lumped load where not indicated.

    Harmonic producing loads are combined together with non harmonic

    producing loads under LVS A and LVS B switchboard for harmonic

    analysis.

    8.0 METHODOLOGY

    Harmonic study has been carried out on the EDSA Technical 2004 (Electrical

    Design and System Analysis) Software of EDSA Micro Corporation USA.

    9.0 CALCULATION

    Refer to Appendix A and B for EDSA computer printout report.

    10.0 RESULTS

    Below is a series of tabulated result for two (2) cases of the Harmonic Analysis

    conducted under Normal Operation where all loads for production are connected,

    and Emergency Operation where only essential loads in switchboard LVS A are

    connected.

    Although relative harmonic impact will be higher during start up of emergency

    generator as loads on it will comprise of mainly AC UPS and lighting. But it will

    persist for small duration i.e. switching transients and step loading till other loads

    on Living Quarters are activated. This transitional period should be minimised. The

    emergency transitional period is not analysed due to short duration.

    The total harmonic voltage distortion THD(V) and total harmonic current distortion

    THD(I) are evaluated on each bus / link and same is reported under respective case.

  • Kvaerner E&C Singapore Pte Ltd VN01-200-30-E-CA-8007 11 of 12 Rev. D1

    Case I - Normal Operation

    TABLE 10.1

    LOCATION(BUS) VOLTAGE (VOLTS)

    THD(V)

    %

    THD(I) %

    PUQC Platform

    SWB-8301 400 1.02 1.59

    SWB-8401 400 1.02 1.17

    MCC-8302 400 1.00 5.22

    DP-8203 400 0.31 6.79

    DP-8204 400 0.31 6.79

    WHD Platform

    MCC-8402 400 1.02 0.49

    Case II - Emergency Operation

    TABLE 10.2

    LOCATION(BUS) VOLTAGE (VOLTS)

    THD(V)

    %

    THD(I) %

    PUQC Platform

    SWB-8301 400 0.84 2.68

    SWB-8401 - - -

    MCC-8302 400 0.82 8.15

    DP-8203 400 0.62 6.79

    DP-8204 - - -

    WHD Platform

    MCC-8402 - - -

    11.0 RESULT ANALYSIS

    The harmonic analysis indicates that voltage distortion on all the switchboards,

    MCC and distribution buses are within normal industry acceptable level of 5%. The

    maximum total voltage distortion THD(V) for the two (2) cases is only 1.02% on

    SWB-8301, SWB-8401 & MCC-8402 switchboard. This is not considered to be

    significant to the system network and is acceptable for industrial loads. The

  • Kvaerner E&C Singapore Pte Ltd VN01-200-30-E-CA-8007 12 of 12 Rev. D1

    maximum total current distortion THD(I) 8.15% is observed at switchboard MCC-

    8302 for living quarter loads. This information shall be used when sizing circuit

    breakers along this path. Further UPS vendor to limit output harmonic current

    distortion less than 5%, in view of the 6.79% THD(I) at the AC UPS distribution

    panel.

    12.0 RECOMMENDATION

    The Electrical distribution network at Rong Doi Gas Field Development Project has

    been analysed in detail to check the suitability under normal and emergency

    operating conditions with harmonic producing loads. Since the harmonic distortion

    is within acceptable limits, there is no need to apply separate harmonic filter in

    Rong Doi distribution system.

    13.0 REFERENCES

    VN01-200-25-E-PH-0001 Electrical Systems Philosophy

    VN01-200-30-E-DW-1100 Electrical Overall Key Single Line Diagram

    VN01-200-30-E-CA-8001 Load Flow Analysis

    VN01-200-30-E-ST-8002 Electrical Load List - Normal, Emergency & UPS

    VN01-200-30-E-CA-8003 Short Circuit Analysis

    VN01-200-30-E-CA-8004 Voltage Drop And Cable Sizing Calculations

    VN01-200-30-E-CA-8005 Motor Start-up Analysis On Large Load

    VN01-200-30-E-CA-8009 Main & Emergency Generator Capacity Study &

    Calculations

  • Kvaerner E&C Singapore Pte Ltd VN01-200-30-E-CA-8007 Rev. D1

    APPENDIX A

    HARMONIC ANALYSIS REPORT

    CASE - I

    (9 SHEETS)

  • Kvaerner E&C Singapore Pte Ltd VN01-200-30-E-CA-8007 Rev. D1

    APPENDIX B

    HARMONIC ANALYSIS REPORT

    CASE - II

    (7 SHEETS)