General
Meeting will be in this room all day today and tomorrow two 20 min. scheduled breaks each day with
refreshments lunch duration is 1 hour and 15 minutesnearest restrooms are on the other side of the
east elevators security---this room will not be locked at lunch
time, so unattended items may be at risk
Harry Carter – T4CM Design Meeting #2 7/13-14/2006 4
Meeting Format
Meeting format is open. We are one working group and very few formal presentations are planned. Issues with supporting information will be raised and then discussed
Presentations and reference information will be posted on the web at a location TBD. Please provide me with
copies of information presented.
Harry Carter – T4CM Design Meeting #2 7/13-14/2006 5
Goals for this meeting are:
Further definition of the T4CM designWhat new or revised features are to be
incorporated into the design Implementation of the EDMS system Establish a timeline for T4CM design
completion
Harry Carter – T4CM Design Meeting #2 7/13-14/2006 6
Arriving at a T4CM Design (Revised)
1st Qtr
2006
Define design features
Perform engineering analyses
Complete drawing packages
All Components in house and ready for assembly
2007
2nd Qtr 3rd Qtr 4th Qtr 1st Qtr 2nd Qtr 3rd Qtr 4th Qtr
Procure components
2008
1st Qtr
Now