hart project oversight committeehartdocs.honolulu.gov/docushare/dsweb/get/document... · 10/3/2019...

30
HART Construction on Dillingham Boulevard October 3, 2019 HART Project Oversight Committee

Upload: others

Post on 28-Dec-2019

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: HART Project Oversight Committeehartdocs.honolulu.gov/docushare/dsweb/Get/Document... · 10/3/2019  · • 6 minutes to the Daniel K. Inouye International Airport • 10 minutes

HART Construction on Dillingham Boulevard

October 3, 2019

HART Project Oversight Committee

Page 2: HART Project Oversight Committeehartdocs.honolulu.gov/docushare/dsweb/Get/Document... · 10/3/2019  · • 6 minutes to the Daniel K. Inouye International Airport • 10 minutes

Community Benefits Dillingham Boulevard

• Improved public transit mobility for the community • Renewed community infrastructure including wider and uniform sidewalks, new

roadways, and the undergrounding of overhead utilities • Supports community reinvestment and Transit-Oriented Development

3

Page 3: HART Project Oversight Committeehartdocs.honolulu.gov/docushare/dsweb/Get/Document... · 10/3/2019  · • 6 minutes to the Daniel K. Inouye International Airport • 10 minutes

• Trains will arrive every 5 minutes at the four transit stations along Dillingham Blvd. during peak travel times and and every 11 minutes during off-peak hours

• Travel times from the Mokauea Station (Kalihi): • 6 minutes to the Daniel K. Inouye International Airport

• 10 minutes to Kalia (Ala Moana Center)

• 21 minutes to Pouhala Station (Waipahu Transit Center)

• About 12,000 – 16,000 in total daily boardings at the four stations

4

Community Benefits Dillingham Boulevard

Mokauea Station (Kalihi) (design concept)

Page 4: HART Project Oversight Committeehartdocs.honolulu.gov/docushare/dsweb/Get/Document... · 10/3/2019  · • 6 minutes to the Daniel K. Inouye International Airport • 10 minutes

• Currently, about 20,000 to 40,000 cars drive along Dillingham Boulevard each day

• By 2030, about 60,000 daily rail transit riders will be on electrically powered trains passing through Kalihi each day

• Potential new customers

5

Community Benefits Dillingham Boulevard

Page 5: HART Project Oversight Committeehartdocs.honolulu.gov/docushare/dsweb/Get/Document... · 10/3/2019  · • 6 minutes to the Daniel K. Inouye International Airport • 10 minutes

Construction Work Areas Dillingham Boulevard

Work Area 1A Middle Street – Mokauea Street

Work Area 1B Mokauea – Kapālama Stream

Work Area 1C Kapālama Stream – Kaaahi Street

7

Mokauea Station

Kalihi

OCCC

Kahauiki Station

Middle Street –

Kalihi Transit Center

Niuhelewai Station

Kapālama

Kūwili Station

Iwilei

COSTCO Honolulu

Community

College Kalihi Kai

Elementary

School

Dillingham

Shopping Plaza

Airgas

Marukai

Page 6: HART Project Oversight Committeehartdocs.honolulu.gov/docushare/dsweb/Get/Document... · 10/3/2019  · • 6 minutes to the Daniel K. Inouye International Airport • 10 minutes

Construction Objectives Dillingham Boulevard

• Maintain budget/schedule • Moving at 60 feet per day

• Clear first 4,000 feet to optimize CCGS

• Create 80 feet of work space on Dillingham to optimize CCGS

• Utility relocation and guideway construction: substantially completed

within 24 months

• Reduce duration of construction disruption

• Waterline and powerline critical to the community • Avoid impacts to 42” water line (Board of Water Supply)

• Maintain serviceability of power lines

• Holistically deliver utility relocation and guideway construction activities

from beginning to end

8

Page 7: HART Project Oversight Committeehartdocs.honolulu.gov/docushare/dsweb/Get/Document... · 10/3/2019  · • 6 minutes to the Daniel K. Inouye International Airport • 10 minutes

• Maintain bus service near its current schedule

(DTS reviewing benefits of a shuttle service)

• Maintaining sidewalk access with some detours as needed

• Keep all intersections open

(controlled left-hand turns and U-turns)

• Maintain 24/7 access for all businesses and residents

9

Construction Objectives Dillingham Boulevard

Page 8: HART Project Oversight Committeehartdocs.honolulu.gov/docushare/dsweb/Get/Document... · 10/3/2019  · • 6 minutes to the Daniel K. Inouye International Airport • 10 minutes

Dry Utility Relocations Dillingham Boulevard

10

Page 9: HART Project Oversight Committeehartdocs.honolulu.gov/docushare/dsweb/Get/Document... · 10/3/2019  · • 6 minutes to the Daniel K. Inouye International Airport • 10 minutes

Construction Plan Dillingham Boulevard

• Day and night work • Two 10- to 12-hour shifts Monday through Friday

• Some crews may work 24/7 (weekend work as needed)

• Controlled access lanes (local traffic only) • One lane in each direction (eastbound/westbound)

• Special duty officers and flaggers to assist vehicles and pedestrians at intersections

• Construction Noise, Dust & Vibration Controls

11

Page 10: HART Project Oversight Committeehartdocs.honolulu.gov/docushare/dsweb/Get/Document... · 10/3/2019  · • 6 minutes to the Daniel K. Inouye International Airport • 10 minutes

Construction Phasing/Sequencing Dillingham Boulevard

12

New right-of-way

Dillingham Boulevard at Mokauea Street (view towards Koko Head)

Takara Printing

Central Pacific Rebuilders

Page 11: HART Project Oversight Committeehartdocs.honolulu.gov/docushare/dsweb/Get/Document... · 10/3/2019  · • 6 minutes to the Daniel K. Inouye International Airport • 10 minutes

Construction Phasing/Sequencing Dillingham Boulevard

13

Existing conditions (view looking Koko Head)

Page 12: HART Project Oversight Committeehartdocs.honolulu.gov/docushare/dsweb/Get/Document... · 10/3/2019  · • 6 minutes to the Daniel K. Inouye International Airport • 10 minutes

Construction Phasing/Sequencing Dillingham Boulevard

14

Excavation for distribution duct begins in new right-of-way along the makai side of Dillingham Boulevard

Distribution Duct Trench

Page 13: HART Project Oversight Committeehartdocs.honolulu.gov/docushare/dsweb/Get/Document... · 10/3/2019  · • 6 minutes to the Daniel K. Inouye International Airport • 10 minutes

Construction Phasing/Sequencing Dillingham Boulevard

15

• Distribution duct complete

• Overhead lines removed • Power line relocation

begins

Distribution Duct

Power Line Trench

Page 14: HART Project Oversight Committeehartdocs.honolulu.gov/docushare/dsweb/Get/Document... · 10/3/2019  · • 6 minutes to the Daniel K. Inouye International Airport • 10 minutes

Construction Phasing/Sequencing Dillingham Boulevard

16

• 138-kv power lines are removed

• Road is widened into new right-of-way

• Construction of guideway foundations and columns begin

New Power Lines Widened Roadway

Page 15: HART Project Oversight Committeehartdocs.honolulu.gov/docushare/dsweb/Get/Document... · 10/3/2019  · • 6 minutes to the Daniel K. Inouye International Airport • 10 minutes

Construction Phasing/Sequencing Dillingham Boulevard

17

• Guideway superstructure and systems are installed

• New center median is constructed

• Construction completed

Page 16: HART Project Oversight Committeehartdocs.honolulu.gov/docushare/dsweb/Get/Document... · 10/3/2019  · • 6 minutes to the Daniel K. Inouye International Airport • 10 minutes

19 Dillingham Construction Access Middle Street to Puuhale Road

Page 17: HART Project Oversight Committeehartdocs.honolulu.gov/docushare/dsweb/Get/Document... · 10/3/2019  · • 6 minutes to the Daniel K. Inouye International Airport • 10 minutes

20

Dillingham Construction Access Puuhale Road to Kalihi Street

Page 18: HART Project Oversight Committeehartdocs.honolulu.gov/docushare/dsweb/Get/Document... · 10/3/2019  · • 6 minutes to the Daniel K. Inouye International Airport • 10 minutes

21

Dillingham Construction Access Kalihi Street to Waikamilo Road

Page 19: HART Project Oversight Committeehartdocs.honolulu.gov/docushare/dsweb/Get/Document... · 10/3/2019  · • 6 minutes to the Daniel K. Inouye International Airport • 10 minutes

22

Dillingham Construction Access Waikamilo Road to Alakawa Street

Page 20: HART Project Oversight Committeehartdocs.honolulu.gov/docushare/dsweb/Get/Document... · 10/3/2019  · • 6 minutes to the Daniel K. Inouye International Airport • 10 minutes

23 Dillingham Construction Access Alakawa Street to Kaaahi Street

Page 21: HART Project Oversight Committeehartdocs.honolulu.gov/docushare/dsweb/Get/Document... · 10/3/2019  · • 6 minutes to the Daniel K. Inouye International Airport • 10 minutes

25 Community Outreach Planning Schedule Dillingham Boulevard

Thursday, October 3 CCUR Presentation to the HART Board Project Oversight Committee and position on City Council Resolution 19-234

Friday, October 4 Invitation to be sent out for October 11 Stakeholders Alliance Group Meeting

Friday, October 11 Stakeholders Alliance Group Meeting

Thursday, October 24 Dillingham/Kalihi Community-wide Construction Outreach Meeting

Meeting Promotion:

• Saturday, October 12 – Community Canvassing at Kalihi Open Market (Kalakaua School)

• Monday, October 14 – Canvassing of Residents & Businesses (Multiple Language Fliers)

• Friday, October 18 – Honolulu Star-Advertiser & Midweek

• Monday, October 21 – Direct mail postcard in-home/in-business

• Thursday, October 24 - Honolulu Star-Advertiser (meeting day)

Page 22: HART Project Oversight Committeehartdocs.honolulu.gov/docushare/dsweb/Get/Document... · 10/3/2019  · • 6 minutes to the Daniel K. Inouye International Airport • 10 minutes

26 Community Outreach Planning Schedule Dillingham Boulevard

Friday, October 25 HART 14-Day Mobilization Notice to the public for the start of construction

Friday, October 25 Community Canvassing

Friday, October 25 Honolulu Star-Advertiser/MidWeek

Friday, October 25 Direct mail postcard in-home/in-business delivery date

Friday, October 25 HART website and social media posts

Tuesday, Nov. 12 Major construction work can begin on Dillingham Blvd.

• Controlled access lanes in each direction (eastbound/westbound)

• Message boards situated at Middle Street and Kaaahi Street (west/east)

• Work may commence with construction crews deployed in all three designated work areas along Dillingham Blvd. (1A/1B/1C)

Page 23: HART Project Oversight Committeehartdocs.honolulu.gov/docushare/dsweb/Get/Document... · 10/3/2019  · • 6 minutes to the Daniel K. Inouye International Airport • 10 minutes

28

Business Outreach Program Dillingham Boulevard

Business Outreach Activities

• HART Business Outreach Center on Dillingham Blvd.

• Construction Information Kiosk at Kapalama Hale

• Dillingham Construction Section on HART Website

• Bi-weekly Construction Advisory Ads

• Launch of HART Stakeholders Alliance Group

• Contractor’s Monthly Business & Community Meetings

Page 24: HART Project Oversight Committeehartdocs.honolulu.gov/docushare/dsweb/Get/Document... · 10/3/2019  · • 6 minutes to the Daniel K. Inouye International Airport • 10 minutes

29

• Business contact database • Log of all canvassing outreach

touches, discussions and resolutions

• Provides critical business information to contractors • Hours of operation • Deliveries • Customer access • Parking • Follow-up & Consultations

HART Business Outreach Canvasser Database

Page 25: HART Project Oversight Committeehartdocs.honolulu.gov/docushare/dsweb/Get/Document... · 10/3/2019  · • 6 minutes to the Daniel K. Inouye International Airport • 10 minutes

30

• Secondary access program • HART produced fliers to notify

customers about alternative access routes to Dillingham Blvd. impacted businesses

• Fliers and posters produced free of charge Includes custom information

• Social media and website graphics provided to each business

• Google Maps and GPS integration

Dillingham Alternative Access Program

Page 26: HART Project Oversight Committeehartdocs.honolulu.gov/docushare/dsweb/Get/Document... · 10/3/2019  · • 6 minutes to the Daniel K. Inouye International Airport • 10 minutes

31

• HART branded to assist businesses with “Open for Business” or “Access Here” issues during construction

• Custom signage and banners will be produced for impacted businesses

• HART is working with the City DPP to get long-term signage in place for small businesses during construction.

“Open for Business” & Access Signage

Page 27: HART Project Oversight Committeehartdocs.honolulu.gov/docushare/dsweb/Get/Document... · 10/3/2019  · • 6 minutes to the Daniel K. Inouye International Airport • 10 minutes

32

• Program includes Dillingham, Kaka`ako, Downtown and Ala Moana area business offers

• Free printed offer brochures distributed at major events

• Free custom 60-second social media and website video

• Ad buys in Star-Advertiser and Midweek to promote small business offers

“Shop & Dine on the Line”

Page 28: HART Project Oversight Committeehartdocs.honolulu.gov/docushare/dsweb/Get/Document... · 10/3/2019  · • 6 minutes to the Daniel K. Inouye International Airport • 10 minutes

33

• Free custom web page for impacted businesses at www.ShopTheCommunity.com

• Profile information includes:

• Business name • Address (location and map) • Phone/email • Description of services • Hours of operation • Photos • Promotional offer or

message

Small Business Webpage Program

Page 29: HART Project Oversight Committeehartdocs.honolulu.gov/docushare/dsweb/Get/Document... · 10/3/2019  · • 6 minutes to the Daniel K. Inouye International Airport • 10 minutes

34

“Navigating Rail Construction” • Symposium tailored to prepare businesses for long-term rail construction • National keynote presenter on best practices for small businesses and construction preparedness • Lessons learned panel discussions • Seminar workshops • Targeted for January 2020

• Kalihi/Dillingham

Business Outreach Symposium

Page 30: HART Project Oversight Committeehartdocs.honolulu.gov/docushare/dsweb/Get/Document... · 10/3/2019  · • 6 minutes to the Daniel K. Inouye International Airport • 10 minutes

35