Henderson SettlementHenderson Settlement Campus Work Areas
As of 4/8/2020
Text3:HC01 ADMINISTRATION BUILDING
Project Description Skill Time/persons CostProj.Start
Replace 5 windows in east apartment (upper level)
$1,0002,3 1 week 4 peopleHC01-1Taken
Install gutter guards $3002,3 1 day 4 peopleHC01-2Taken
Make curtains for work camp office $1502,3 2 days 2 peopleHC01-3Taken
Build shelving in lower stock room $2001,2,3 2 days 2 peopleHC01-4Taken
Pressure wash deck near walking trail $251 1 day 2 peopleHC01-5Taken
Pressure wash front of building $251 1 day 2 peopleHC01-6Taken
Lay one row of concrete block at bottom of steps on east end of building
$1002,3 1 day 2 peopleHC01-7Taken
Pressure wash and apply stain to decking and post on lower section of front porch on building
$4001,2,3 3 days 4 peopleHC01-8Taken
Paint lower exterior wall on west end of building
$1251,2 1 day 3 peopleHC01-9Taken
Apply waterseal to steps to park on west side
$1251,2 1 day 3 peopleHC01-10Taken
Paint concrete blocks at tennis court retaining wall
$1751,2 1 day 4 peopleHC01-11Taken
Replace 4 lights with LED lights in workcamp office
$4002,3 1 day 4 peopleHC01-12Taken
Replace ceiling tiles with beadboard on ceiling in workcamp office
$9001,2,3 1 week 4 peopleHC01-13Taken
Replace 7 lights with LED lights in middle room and kitchen
$7002,3 2 days 4 peopleHC01-14Taken
Paint middle 2 rooms at main entrance $2751,2 2 days 4 peopleHC01-15Taken
Paint ceiling in mission advancement office
$751,2 1 day 3 peopleHC01-16Taken
Replace 3 lights with LED lights in mission advancement office
$3002,3 1 day 2 peopleHC01-17Taken
Replace 6 lights with LED lights in directors office
$6002,3 2 days 4 peopleHC01-18Taken
Build small wood retainer, apply landscaping cloth and gravel to create walkway in back of admin building
$6001,2 2 days 4 peopleHC01-19Taken
Replace 6 lights with LED lights in finance office and entry room
$6002,3 2 days 4 peopleHC01-20Taken
Replace 3 lights with LED lights in accountant office
$3002,3 2 people 1 dayHC01-21Taken
Clear small brush from behind parking $251 4 people 1 dayHC01-22Taken
As of 4/8/2020
Henderson SettlementHenderson Settlement Campus Work Areas
As of 4/8/2020
Text3:HC01 ADMINISTRATION BUILDING
Project Description Skill Time/persons CostProj.Start
lot fence and behind building
Pressure wash small porch on back of building
$251 2 people 1 dayHC01-23Taken
Sew curtains for 2 large windows and 3 standard windows
$2753 2 days 4 peopleHC01-24Taken
Text3:HC02 PARK AREA
Project Description Skill Time/persons CostProj.Start
Install (2) exterior doors in bath house $4502,3 2 days 3 peopleHC02-1Taken
Build retaining wall #1 $7001,2,3 2 days 6 peopleHC02-2Taken
Build retaining wall #2 $7001,2,3 2 days 6 peopleHC02-3Taken
Build retaining wall #3 $7001,2,3 2 days 6 peopleHC02-4Taken
Replace window in storage building $2002,3 1 day 2 peopleHC02-5Taken
Replace 6 picnic tables $4001,2,3 3 days 6 peopleHC02-6Taken
Remove wire fence around tennis/basketball court
$251,2 2 days 6 peopleHC02-7Taken
Build new wire fence (4 feet high) around tennis/basketball court
$6001,2,3 3 days 6 peopleHC02-8Taken
Remove wall with basketball goal and add 2 new basketball goals
$7501,2,3 3days 6 peopleHC02-9Taken
Remove non load bearing concrete block partition walls in park bathroom building
$501,2 3 days 6 peopleHC02-10Taken
Create doorway and at least 1 window opening in existing block wall
$1002,3 2 days 3 peopleHC02-11Taken
Replace ceiling in mens section of park bathroom building
$5001,2,3 3 days 4 peopleHC02-12Taken
Replace ceiling in womens section of park bathroom building
$5001,2,3 3 days 4 peopleHC02-13Taken
Apply insulation board and wall covering in mens section of park bathroom building
$8001,2,3 3 days 6 peopleHC02-14Taken
Apply insulation board and wall covering in womens section of park bathroom building
$8001,2,3 3 days 6 peopleHC02-15Taken
Paint all walls and ceilings in park bathroom building
$3001,2 2 days 4 peopleHC02-16Taken
Install floor over concrete in mens $1,0001,2,3 1 week 6 peopleHC02-17Taken
As of 4/8/2020
Henderson SettlementHenderson Settlement Campus Work Areas
As of 4/8/2020
Text3:HC02 PARK AREA
Project Description Skill Time/persons CostProj.Start
section of park bathroom building
Install floor over concrete in womens section of park bathroom building
$1,0001,2,3 1 week 6 peopleHC02-18Taken
Install ferring strips and vinyl siding to to park bathroom building
$2,0001,2,3 3 days 8 peopleHC02-19Taken
Repair/replace gutters on bathroom building
$2251,2,3 2 days 4 peopleHC02-20Taken
Pressure wash bridge on walking track $251,2 1 day 2 peopleHC02-21Taken
Pressure wash and water seal park shelter
$2001,2 2 days 4 peopleHC02-22Taken
Text3:HC04 HOPE CHURCH
Project Description Skill Time/persons CostProj.Start
Install 6 foot gates in chain link fence $4001,2,3 2 days 3 peopleHC04-1Taken
Build gravel walkway from gates to pavement
$5001,2 2 days 4 peopleHC04-2Taken
Text3:HC05 HOPE HOUSE
Project Description Skill Time/persons CostProj.Start
Remove ceiling tile and install sheetrock to back bedroom ceiling add mud, sand, and tape
$2501,2,3 3 days 3 peopleHC05-Taken
Install gutter guards $3002,3 1 day 4 peopleHC05-1Taken
Install shoe mold to floors $1502,3 2 day 4HC05-2Taken
Replace exterior basement door $2502,3 1 day 3 peopleHC05-3Taken
Remove ceiling tile and install sheetrock to kitchen ceiling and mud, sand, and paint
$2501,2,3 3 days 3 peopleHC05-4Taken
Remove ceiling tile and install sheetrock to kitchen ceiling and mud, sand, and paint
$2501,2,3 2 days 3 peopleHC05-5Taken
As of 4/8/2020
Henderson SettlementHenderson Settlement Campus Work Areas
As of 4/8/2020
Text3:HC06 PARSONAGE
Project Description Skill Time/persons CostProj.Start
Prepare site and pour 24x24 concrete pad
$1,4001,2,3 3 days 5 peopleHC06-1Taken
Install gutter guards $2502,3 1 day 4 peopleHC06-2Taken
Build (1) garage door $5001,2,3 3 days 4 peopleHC06-3Taken
Build second garage door $5001,2,3 3 days 4 peopleHC06-4Taken
Text3:HC07 EVANS HOUSE
Project Description Skill Time/persons CostProj.Start
Replace vanity tops, bowls and mirrors in (3) bathrooms
$7503 1 week 4HC07-1Taken 6/7/2020
Dig out and install 20' section of culvert 1st. Section
$2001,2,3 3 days 6 peopleHC07-2Taken
Dig out and install 20' section of culvert 2nd. Section
$2001,2,3 3 days 6 peopleHC07-3Taken
Dig out and install 20' section of culvert 3rd. Section
$2001,2,3 3 days 6 peopleHC07-4Taken
Apply furring strips and metal roofing over shingles on half of roof
$1,8001,2,3 1 week 8 peopleHC07-5Taken
Apply furring strips and metal roofing over shingles on second half of roof
$1,8001,2,3 1 week 8 peopleHC07-6Taken 6/7/2020
Pressure wash and water seal shelter $2001,2 2 days 4 peopleHC07-7Taken 6/7/2020
Pressure wash exterior of house $501,2 2 days 3 peopleHC07-8Taken
Replace back exterior door on house $2502,3 1 day 2 peopleHC07-9Taken
Remove aluminum siding and apply insulation board and vinyl siding to front of house
$1,3001,2,3 1 week 6 peopleHC07-10Taken
Remove aluminum siding and apply insulation board and vinyl siding to right side of house
$1,1001,2,3 3 days 6 peopleHC07-11Taken
Remove aluminum siding and apply insulation board and vinyl siding to back of house
$1,0001,2,3 3 days 6 peopleHC07-12Taken
Remove aluminum siding and apply insulation board and vinyl siding to left side of house
$1,0001,2,3 3 days 6 peopleHC07-13Taken
Build small roof over side deck $4501,2,3 2 days 4 peopleHC07-14Taken
As of 4/8/2020
Henderson SettlementHenderson Settlement Campus Work Areas
As of 4/8/2020
Text3:HC08 PARTIN HOUSE - YOUTH CENTER
Project Description Skill Time/persons CostProj.Start
Apply furring strips over shingles on garage roof and cover with metal
$1,0001,2,3 2 days 5 peopleHC08-1Taken
Install gutter guards $3502,3 2 days 4 peopleHC08-2Taken
Install wall cabinets in kitchen $8001,2,3 2 day 4HC08-3Taken
Install base cabinets in kitchen $8001,2,3 2 day 4HC08-4Taken
Pour concrete pad and install basketball goal
$7001,2,3 3 days 4 peopleHC08-5Taken
Remove wood parking bumps and spread gravel to enlarge parking lot
$7501,2 2 days 6 peopleHC08-6Taken
Pressure wash exterior of large building and garage
$501,2 2 days 3 peopleHC08-7Taken
Replace 5 lights with LED lights in garage
$4502,3 2 days 2 peopleHC08-8Taken
Replace 8 lights with LED lights in basement entry
$7002,3 3 days 4 peopleHC08-9Taken
Install LED light in basement closet $402,3 1 days 2 peopleHC08-10Taken
Install LED light in basement bathroom $402,3 1 day 2 peopleHC08-11Taken
Install 10 LED lights in activitys room $9002,3 3 days 4 peopleHC08-12Taken
Install 10 LED lights in activitys room part 2
$9002,3 3 days 4 peopleHC08-13Taken
Install 10 LED lights in activitys room part 3
$9002,3 3 days 4 peopleHC08-14Taken
Install 10 LED lights in activitys room part 4
$9002,3 3 days 4 peopleHC08-15Taken
Install 3 LED lights in stair way and hall $1502,3 1 day 2 peopleHC08-16Taken
Install 2 LED lights in kitchen $1002,3 1 day 2 peopleHC08-17Taken
Install 4 LED lights in hallway up stairs $3502,3 2 days 2 peopleHC08-18Taken
Install 1 LED light in library entry $502,3 1 day 2 peopleHC08-19Taken
Install 1 LED light in storage room $502,3 1 day 2 peopleHC08-20Taken
Install 1 LED light in music room $502,3 1 day 2 peopleHC08-21Taken
Install 1 LED light in craft room $502,3 1 day 2 peopleHC08-22Taken
Install 2 LED lights in computer lab $1802,3 1 day 2 peopleHC08-23Taken
Install 1 LED light in office $1002,3 1 day 2 peopleHC08-24Taken
Run electric from youth center to garage $2002,3 2 day 3 peopleHC08-25Taken
As of 4/8/2020
Henderson SettlementHenderson Settlement Campus Work Areas
As of 4/8/2020
Text3:HC09 FRAKES HOUSE
Project Description Skill Time/persons CostProj.Start
Build form and pour concrete slab $1,3001,2,3 3 days 8 peopleHC09-1Taken
Install laminate flooring to upstairs rooms and hallway
$1,2002,3 1 week 8 peopleHC09-2Taken
Install gutter guards $3502,3 2 day 4HC09-3Taken
Trim and caulk porch ceiling $2501,2,3 2 days 4 peopleHC09-4Taken
Replace full glass storm door on front entry
$2001,2,3 1 day 2 peopleHC09-5Taken
Replace step rail cap boards $1252,3 1 day 3 peopleHC09-6Taken
Replace (2) basement windows $3502,3 2 days 3 peopleHC09-7Taken
Remove concrete at lower entry and replace with gravel and pavers
$4001,2,3 3 days 4 peopleHC09-8Taken
Repair porch ceiling $3002,3 2 days 4 peopleHC09-9Taken
Finish window glazing and paint all wood work in dining area
$1252,3 1 day 2 peopleHC09-10Taken
Remove decking boards, add 4 more step stringers and reapply decking boards to front steps on Frakes House
$1501,2,3 2 days 3 peopleHC09-11Taken
Text3:HC11 BRICK HOUSE
Project Description Skill Time/persons CostProj.Start
Replace 5 lights with LED lights $4502,3 2 days 4 peopleHC11-3Taken
Replace 6 lights with LED lights $5002,3 2 days 4 peopleHC11-4Taken
Text3:HC12 LOG CABIN
Project Description Skill Time/persons CostProj.Start
Replace wood shingles $2,0002,3 1 weeek 6 HC12-1Taken
Text3:HC14 GREEN HOUSE
Project Description Skill Time/persons CostProj.Start
Replace stairs near high tunnel $5001,2,3 2 days 4 peopleHC14-1Taken
Build 12X12 storage building between high tunnel and green house
$1,8001,2,3 3 days 6 peopleHC14-2Taken
Apply vinyl sidding and soffit to storage building
$1,1001,2,3 2 days 6 peopleHC14-3Taken
As of 4/8/2020
Henderson SettlementHenderson Settlement Campus Work Areas
As of 4/8/2020
Text3:HC14 GREEN HOUSE
Project Description Skill Time/persons CostProj.Start
Build small shelter for green house tractor
$3751,2,3 1 day 3 peopleHC14-4Taken
Build 1st row of terracing below germination room
$1,5001,2,3 3 days 6 peopleHC14-5Taken
Build 2nd row of terracing below germination room
$1,5001,2,3 3 days 6 peopleHC14-6Taken
Build 3rd row of terracing below germination room
$1,5001,2,3 3 days 6 peopleHC14-7Taken
Repair downspouts and drain at germination room
$2502,3 2 days 4 peopleHC14-8Taken
Build custom greenhouse table $751,2,3 1 day 3 peopleHC14-9Taken 4/5/2020
Paint germination room exterior $1001,2 2 days 3 peopleHC14-10Taken
Lay block on concrete slab (slab already there) for 2 sided compost bin
$6001,2,3 2 days 4 peopleHC14-11Taken 3/15/2020
Pour concrete slab and lay block for 2 sided compost bin
$8001,2,3 3 days 4 peopleHC14-12Taken 3/15/2020
Pour 2nd slab and lay block for 3 sided compost bin
$8001,2,3 4 days 4 peopleHC14-13Taken 3/15/2020
Spread gravel near green house $9001,2 3 days 8 peopleHC14-14Taken
Text3:HC16 RED BARN
Project Description Skill Time/persons CostProj.Start
Replace (4) windows $8002,3 1 week 5 peopleHC16-1Taken
Text3:HC17 LOWER FARM HOUSE
Project Description Skill Time/persons CostProj.Start
Replace (2) access doors $1251,2,3 1 day 3 peopleHC17-1Taken
Build concrete wall, install exterior door on well house
$1,0002,3 1 week 3 peopleHC17-2Taken
Replace all base cabinets in kitchen $1,5502,3 3 days 4 peopleHC17-3Taken
Replace wall cabinets on (3) walls in kitchen
$1,3502,3 3 days 4 peopleHC17-4Taken
Replace kitchen storm door $2002,3 1 day 2 peopleHC17-5Taken
Replace (9) light exterior door at back porch
$2002,3 1 day 2 peopleHC17-6Taken
Clean gutters and install gutter guards $2502,3 1 day 4 peopleHC17-7Taken
As of 4/8/2020
Henderson SettlementHenderson Settlement Campus Work Areas
As of 4/8/2020
Text3:HC17 LOWER FARM HOUSE
Project Description Skill Time/persons CostProj.Start
Replace wood casing and basement door on Lower Farm House
$4002,3 2 days 2 peopleHC17-8Taken
Replace wood casing and back exterior door
$3002,3 2 days 3 peopleHC17-9Taken
Scrape and paint all wood trim on exterior of farm house
$1501,2 2 days 4 peopleHC17-10Taken
Scrape, clean, and paint concrete floor and post on back porch
$1501,2 1 day 2 peopleHC17-11Taken
Replace and trim 1 window $2002,3 1 days 2 peopleHC17-12Taken
Install exterior door and apply vinyl siding to 6x6 water tank building
$5001,2,3 2 days 3 peopleHC17-13Taken
Dig out some dirt and install steps on storage building
$1251,2 1 day 3 peopleHC17-14Taken
Replace front porch storm door $2001,2,3 1 day 2HC17-15Taken
Replace screen in window of one room $252 1 day 1 personHC17-16Taken
Trim and paint storage building doors $751,2 1 day 3 peopleHC17-17Taken
Install ceiling in shed $2001,2,3 2 days 4 peopleHC17-18Taken
Landscape front of house $2002,3 2 days 4 peopleHC17-19Taken
Replace porch gate $752,3 1 day 2 peopleHC17-20Taken
Install range hood $1502,3 1 day 2 peopleHC17-21Taken
Build 8X16 deck to front porch $8001,2,3 1 week 6 peopleHC17-22Taken
Enlarge parking area (install wood bumpers and spread gravel)
$1,0001,2,3 3 days 6 peopleHC17-23Taken
Text3:HC18 FARM
Project Description Skill Time/persons CostProj.Start
Board up 2 windows $8001,2,3 1 wk 6HC18-Taken
Build smooth wire fence #1 on main campus
$1,0001,2,3 1 week 8 peopleHC18-1Taken
Build smooth wire fence #2 on main campus
$1,0001,2,3 1 week 8 peopleHC18-2Taken
Build smooth wire fence #3 on main campus
$1,0001,2,3 1 week 8 peopleHC18-3Taken
Build smooth wire fence #4 on main campus
$1,0001,2,3 1 week 8 peopleHC18-4Taken
Build smooth wire fence #5 on main campus
$1,0001,2,3 1 week 8 peopleHC18-5Taken
As of 4/8/2020
Henderson SettlementHenderson Settlement Campus Work Areas
As of 4/8/2020
Text3:HC18 FARM
Project Description Skill Time/persons CostProj.Start
Build smooth wire fence #6 on main campus
$1,0001,2,3 1 week 8 peopleHC18-6Taken
Take shed down and move to lower farm $6001,2 3 days 6 peopleHC18-7Taken
Reinforce roof support system on lower farm barn
$1,1001,2,3 1 week 8 peopleHC18-8Taken
Gravel around water box and road to water box at lower farm
$7501,2 2 days 6 peopleHC18-9Taken
Replace metal roof on existing barn at ballfield
$1,0001,2,3 1 wk 6HC18-10Taken
Lime field at Charley Branch at lower farm
$7501,2 2 days 6 peopleHC18-11Taken
Gravel dirt perimeter at pond on lower farm
$7001,2 2 days 6 peopleHC18-12Taken
Pressure wash storage building near red barn
$501,2 1 day 2 peopleHC18-13Taken 9/27/2020
Close up opening under overhang at front entrance of red barn
$2001,2,3 2 days 3 peopleHC18-14Taken
Replace fence around wetland system $2,6001,2,3 2 days 6 peopleHC18-15Taken
Build a board fence at lower farm $1,3001,2,3 3 days 6 peopleHC18-16Taken
Spread lime on field at Smithy bottom at lower farm
$8501,2 2 days 6 peopleHC18-17Taken
Paint fencing with water seal at lower farm
$5001,2 2 days 4 peopleHC18-18Taken
Gravel behind barn at lower farm $1,1001,2 2 days 6 peopleHC18-19Taken
Gravel road tile to gate at lower farm $7001,2 2days 6 peopleHC18-20Taken
Gravel around barn at lower farm $4501,2 2 days 6 peopleHC18-21Taken
Replace boards on some fencing on lower farm
$1,0001,2 3 days 6 peopleHC18-22Taken
Reconfigure holding pen on main campus
$1,1001,2 2 days 6 peopleHC18-23Taken
Text3:HC19 CLINIC
Project Description Skill Time/persons CostProj.Start
Pressure wash exterior of building $751,2 2 days 4 peopleHC19-1Taken
Remove interior walls and misc items for redesign (Parts 2-8 must be done in order)
$251,2,3 1 week 6 peopleHC19-2Taken
As of 4/8/2020
Henderson SettlementHenderson Settlement Campus Work Areas
As of 4/8/2020
Text3:HC19 CLINIC
Project Description Skill Time/persons CostProj.Start
Build interior walls for new layout (Parts 2-8 must be done in order)
$1,5001,2,3 1 week 8 peopleHC19-3Taken
Apply insulation (where needed) and drywall to walls (Parts 2-8 must be done in order)
$1,5001,2,3 1 week 8 peopleHC19-4Taken
Mud, tape, sand all drywall (Parts 2-8 must be done in order)
$5002,3 1 week 6 peopleHC19-5Taken
Paint interior walls (Parts 2-8 must be done in order)
$5001,2,3 1 week 6 peopleHC19-6Taken
Install drop ceiling (Parts 2-8 must be done in order)
$1,5001,2,3 1 week 8 peopleHC19-7Taken
Repair/replace/clean floors in all rooms (Parts 2-8 must be done in order)
$5001,2,3 1 week 6 peopleHC19-8Taken
Text3:HC20 WATER STORAGE TANK SHED
Project Description Skill Time/persons CostProj.Start
Apply furring strips and metal over shingles on roof
$9501,2,3 3 days 6 peopleHC20-1Taken
Replace exterior doors $3002,3 1 day 3 peopleHC20-2Taken
Repair gutters on back of building $1001,2,3 1 day 2 peopleHC20-3Taken
Repair damage and applt ferring strips and metal to roof of water pump house
$6001,2,3 2 days 4 peopleHC20-4Taken
Lay concrete block on 2 walls inside clear well house
$6001,2,3 2 days 4 peopleHC20-5Taken
Set 2 steel post and an I beem then build block wall and enclose chlorine room
$5001,2,3 3 days 4 peopleHC20-6Taken
Text3:HC21 VEHICLE MAINTENANCE SHOP
Project Description Skill Time/persons CostProj.Start
Remove and raise front awning and apply new metal
$6001,2,3 2 days 6 peopleHC21-1Taken
Apply paint to metal on front awning $1501,2 1 day 3 peopleHC21-2Taken
As of 4/8/2020
Henderson SettlementHenderson Settlement Campus Work Areas
As of 4/8/2020
Text3:HC22 VEHICLE MAINTENANCE POLE BARN
Project Description Skill Time/persons CostProj.Start
Replace metal on two car shed $5501,2,3 2 days 6 peopleHC22-1Taken
Replace metal roofing on back section of car huts
$5501,2,3 2 days 6 peopleHC22-2Taken
Replace metal roofing on front section of car huts
$1,4001,2,3 3 days 6 peopleHC22-3Taken
Paint all metal roofing on shed type roofs $7001,2 2 days 4 peopleHC22-4Taken
Text3:HC23 ZOOCHIE HOUSE
Project Description Skill Time/persons CostProj.Start
Replace (4) windows upstairs $8002,3 1 week 4 peopleHC23-1Taken
Polyurethane floors $2502,3 2 days 4 peopleHC23-2Taken
Text3:HC24 COMMUNITY CENTER
Project Description Skill Time/persons CostProj.Start
Apply laminate flooring in senior office $1,7001,2,3 1 week 6 peopleHC24-1Taken
Install drop ceiling in first old pantry room $7001,2,3 1 wk 6HC24-2Taken
Close up interior of 2 unused windows in womens restroom
$1502,3 1 day 2 peopleHC24-3Taken
Paint walls in womens restrooms $1751,2 1 day 4 peopleHC24-4Taken
Build book shelf in thrift store $1001,2,3 1 day 2 peopleHC24-5Taken
Replace 2 faucets on sink in womens restrooms
$1252,3 1 day 2 peoplHC24-6Taken
Replace (8) attic windows $1,6002,3 4 days 4 peopleHC24-7Taken
Replace 4 lights with LED lights in womens restroom
$4002,3 2 days 3 peopleHC24-8Taken
Replace (4) senior center upper windows $8001,2,3 2 days 4 peopleHC24-9Taken
Install vinyl siding on wall of community center facing gym
$1,0001,2,3 3 days 6 peopleHC24-10Taken
Install gutter guards $4002,3 2 days 4 peopleHC24-11Taken
Remove and replace tile in senior kitchen $1,1001,2,3 1 week 6 peopleHC24-12Taken
Apply waterseal to large dumpster fence $1501,2 1 day 3 peopleHC24-13Taken
Remove wall paper border and paint walls in outreach director office
$1751,2 2 days 4 peopleHC24-14Taken
Replace double doors in hallway in Community Center
$3502,3 2 day 2HC24-15Taken
As of 4/8/2020
Henderson SettlementHenderson Settlement Campus Work Areas
As of 4/8/2020
Text3:HC24 COMMUNITY CENTER
Project Description Skill Time/persons CostProj.Start
Water seal small arch bridge $751,2 1 day 2 peopleHC24-16Taken 9/27/2020
Apply water seal to wood fence by entertainment stand
$1501,2 1 day 3 peopleHC24-17Taken 9/27/2020
Apply water seal to wood fence by senior ramp
$751,2 1 day 2 peopleHC24-18Taken 9/27/2020
Build hand rails and close in side of steps on front of building
$6001,2,3 2 days 3 peopleHC24-19Taken 7/26/2020
Build a 9x17 deck over concrete pad in front of building
$9501,2,3 2 days 4 peopleHC24-20Taken 7/26/2020
Build 36 foot wood walkway in front of building
$7001,2,3 2 days 4 peopleHC24-21Taken
Build 2nd 36 foot wood walkway in front of building
$7001,2,3 2 days 4 peopleHC24-22Taken
Repair floor and apply floor covering in stock room near mens section
$4501,2,3 2 days 4 peopleHC24-23Taken
Clean and apply polyurethane to floor in outreach directors office
$2251,2,3 2 days 4 peopleHC24-24Taken
Assemble new desk and apply chair mat in outreach directors office
$7001,2,3 2 days 3 peopleHC24-25Taken
Replace 4 lights with LED lights in outreach storage room
$4002,3 2 days 3 peopleHC24-26Taken
Replace 11 lights with LED lights in main hallway
$9502,3 3 days 4 peopleHC24-27Taken
Replace 4 lights with LED lights womens group room
$4002,3 2 days 3 peopleHC24-28Taken
Paint base and wall cabinets in womens group room
$1251,2 1 day 4 peopleHC24-29Taken
Paint walls in womens group room $2001,2 1 day 4 peopleHC24-30Taken
Take out wall shelf and relocate 2nd shelf in MIHOW room
$251,2 1 day 4 peopleHC24-31Taken
Replace 4 lights with LED lights in MIHOW room
$4002,3 2 days 3 peopleHC24-32Taken
Build doors on 3 shelves in sewing room $2002,3 2 days 2 peopleHC24-33Taken
Replace 4 lights with LED lights in sewing room
$4002,3 2 days 3 peopleHC24-34Taken
Apply louan and vinyl tile to floor in middle storage room (pnts rm)
$7001,2,3 3 days 4 peopleHC24-35Taken
Replace 3 lights with LED lights in middle storage room (pnts rm)
$3002,3 2 days 2 peopleHC24-36Taken
As of 4/8/2020
Henderson SettlementHenderson Settlement Campus Work Areas
As of 4/8/2020
Text3:HC24 COMMUNITY CENTER
Project Description Skill Time/persons CostProj.Start
Remove carpet, clean floor, and apply polyurethane to floor in front room of library
$4501,2,3 3 days 6 peopleHC24-37Taken
Remove carpet, clean floor and apply polyurethane to floor in back room in library
$4501,2,3 3 days 6 peopleHC24-38Taken
Build 2 shelves with plexiglass doors on front in library
$5501,2,3 3 days 3 peopleHC24-39Taken
Paint entry door at telephone room $501,2 1 day 2 peopleHC24-40Taken
Remove front stall and install bathroom vanity and mirror in mens restroom in main hallway
$6001,2,3 3 days 3 peopleHC24-41Taken
Replace 6 lights with LED lights in youth learning center
$6502,3 2 days 4 peopleHC24-42Taken
Replace 10 lights with LED lights in senior kitchen
$1752,3 3 days 4 peopleHC24-43Taken
Install ventless range hood in senior kitchen
$1752,3 1 day 2 peopleHC24-44Taken
Paint walls in senior kitchen $1751,2 1 day 4 peopleHC24-45Taken
Paint handrail and step kick plates from main hall to former food pantry
$1001,2 2 people 1 dayHC24-46Taken
Replace 3 small lights with LED lights in hallway by former food pantry
$2002,3 1 day 3 peopleHC24-47Taken
Clean, paint and apply sealer to concrete floor in hallway by former food pantry
$2501,2, 3 days 4 peopleHC24-48Taken
Paint walls in hallway by former food pantry
$1251,2 1 day 4 peopleHC24-49Taken
Clean, paint, and apply sealer to concrete floor in former food pantry
$3501,2 3 days 4 peopleHC24-50Taken
Paint walls in former food pantry $2251,2,3 1 day 4 peopleHC24-51Taken
Close in large door opening and install interior door in former food pantry
$2502,3 3 days 3 peopleHC24-52Taken
Apply water proofing to section of 1 wall, paint other walls, and replace baseboards in community development hallway
$6501,2,3 2 days 4 peopleHC24-53Taken
Replace 6 lights with LED lights in community development office and hallway
$6502,3 2 days 4 peopleHC24-54Taken
Build divider wall on pallets in food pantry $3001,2,3 1 day 4 peopleHC24-55Taken
As of 4/8/2020
Henderson SettlementHenderson Settlement Campus Work Areas
As of 4/8/2020
Text3:HC24 COMMUNITY CENTER
Project Description Skill Time/persons CostProj.Start
Pressure wash pathway to promise $751,2 1 day 3 peopleHC24-56Taken
Pressure wash and apply water seal to deck and shelter at senior center
$2001,2 2 days 4 peopleHC24-57Taken
Pressure was lower vinyl exterior wall below senior center
$751,2 1 day 3 peopleHC24-58Taken
Scrape and paint exterior wall by senior center
$1251,2 2 days 4 peopleHC24-59Taken
Remove and build new 2x24 raised garden at senior center
$9001,2,3 3 days 4 peopleHC24-60Taken
Build 3x24 wood walk with fence rail on 1 side at senior center raised garden
$7001,2,3 3 days 4 peopleHC24-61Taken
Dig trench, install underground conduit, electric wire and lights to both sides of pathway of promise
$9501,2,3 5 days 6 peopleHC24-62Taken
Build steps from middle road to sidewalk at senior center
$4001,2,3 2 days 4 peopleHC24-63Taken
Replace stalls and apply louan and vinyl rug to womens restroom and small utility room
$1001,2,3 1 week 4 peopleHC24-64Taken
Pressure wash and waterseal steps at senior center parking
$1001,2 1 day 3 peoplHC24-65Taken
Build and install 2 privacy doors on dumpster fence
$4501,2,3 2 days 4 peopleHC24-66Taken
Build small block retaining wall outside food pantry
$9001,2,3 2 days 4 peopleHC24-67Taken 4/5/2020
Pour concrete pad outside food pantry $8001,2,3 2 days 4 peopleHC24-68Taken
Pour 2nd concrete pad outside food pantry
$8001,2,3 2 days 4 peopleHC24-69Taken
Pour 3rd concrete pad outside food pantry
$8001,2,3 2 days 4 peopleHC24-70Taken
Apply floor tile over existing floor in womens section of thrift store
$9001,2,3 3 days 4 peopleHC24-71Taken
Apply floor tile over existing floor in mens section of thrift store
$8001,2,3 3 days 4 peopleHC24-72Taken
Replace 8 lights with LED lights in stock room
$8502,3 2 days 4 peopleHC24-73Taken
Replace 8 lights with LED lights in 2nd stock room
$8502,3 2 days 4 peopleHC24-74Taken
Replace 8 lights with LED lights in 3rd stock room
$8502,3 2 days 4 peopleHC24-75Taken
As of 4/8/2020
Henderson SettlementHenderson Settlement Campus Work Areas
As of 4/8/2020
Text3:HC24 COMMUNITY CENTER
Project Description Skill Time/persons CostProj.Start
Replace 9 lights with LED lights in 4th stock room
$9502,3 2 days 4 peopleHC24-76Taken
Place concrete blocks on floor and 3/4 plywood covering to create platform for storage in stock room
$1001,2 1 day 2 peopleHC24-77Taken
Replace 1 light with LED light in back stock room (old furnace room)
$1002,3 1 day 2 peopleHC24-78Taken
Sew curtains for 4 windows in senior kitchen
$1503 2 days 3 peopleHC24-79Taken
Sew curtains for 4 windows in former food pantry
$1503 2 day 2HC24-80Taken
Sew curtains for 4 windows in new thrift store stock room
$1503 2 day 2HC24-81Taken
Replace laminate flooring in intake office and 2 offices
$1,0001,2,3 1 week 4 peopleHC24-82Taken
Paint walls and ceiling in youth development office
$1501,2 2 days 4 peopleHC24-83Taken
Text3:HC25 GYMNASIUM
Project Description Skill Time/persons CostProj.Start
Create access door at stage area $2502,3 2 days 3 peopleHC25-1Taken
Apply metal sheeting to exterior wall and one side of building
$1,2001,2,3 1 week 8 peopleHC25-2Taken 4/5/2020
Install gutter guards $3002,3 1 day 4 peopleHC25-3Taken
Replace double door at gym entrance $6002,3 3 days 4 peopleHC25-4Taken
Create storage area in attic space $7501,2,3 3 days 4 peopleHC25-5Taken
Replace metal sheeting around 7 windows
$1,0001,2,3 3 day 6HC25-6Taken
Paint facia boards on eaves of gym $501,2 1 day 2HC25-7Taken
Paint and caulk inside window trim in gym
$1001,2 1 day 2HC25-8Taken
Pressure wash and water seal wood walk way
$2251,2 2 days 4 peopleHC25-9Taken
Assemble and install wall cabinets in concession area
$1,0001,2,3 3 days 4 peopleHC25-10Taken
Assemble and replace base cabinets and counter tops in concession area
$1,3001,2,3 3 days 4 peopleHC25-11Taken
Paint walls in concession area $1251,2 1 day 4 peopleHC25-12Taken
As of 4/8/2020
Henderson SettlementHenderson Settlement Campus Work Areas
As of 4/8/2020
Text3:HC25 GYMNASIUM
Project Description Skill Time/persons CostProj.Start
Pressure wash and apply waterseal to end porch on gym
$1751,2 1 day 4 peopleHC25-13Taken
Create opening and install slider window in concession area
$2502,3 1 day 2 peopleHC25-14Taken
Paint boys restroom walls and door $1751,2 2 days 5 peopleHC25-15Taken
Paint and apply sealer to concrete floor in boys restroom
$2251,2 2 days 3 peopleHC25-16Taken
Paint walls in girls restroom $1751,2 2 days 5 peopleHC25-17Taken
Paint and apply sealer to concrete floor in girls restroom
$2251,2 2 days 3 peopleHC25-18Taken
Replace vanity top in girls restroom $1002,3 1 day 2 peopleHC25-19Taken
Replace some banisters and install protective bumper guard on porch
$1001,2,3 1 day 3 peopleHC25-20Taken
Text3:HC26 MISSION DORMITORY
Project Description Skill Time/persons CostProj.Start
Dig out, form up, mix concrete, and pour 35x4 ' sidewalk #1
$5501,2,3 1 wk 6HC26-1Taken
Dig out, form up, mix concrete, and pour 35x4 ' sidewalk #2
$5501,2,3 1 wk 6HC26-2Taken
Dig out, form up, mix concrete, and pour 35x4 ' sidewalk #3
$5501,2,3 1 wk 6HC26-3Taken
Replace (1) window in upstairs lobby $7002,3 1 day 3 peopleHC26-4Taken
Replace (2nd) window in upstairs lobby $7002,3 1 day 3 peopleHC26-5Taken
Pressure wash and water seal front deck and handicap ramp
$3501,2 2 days 4 peopleHC26-6Taken
Pressure wash and water seal back and side decks
$4501,2 2 days 4 peopleHC26-7Taken
Clean walls and apply drylock in breaker box room
$2501,2 1 day 3 peopleHC26-8Taken
Water seal fence near retaining wall $1001,2 1 day 3 peopleHC26-9Taken
Water seal fence in front of Mission Dorm
$1001,2 1 day 4 peopleHC26-10Taken
Water seal fence near kitchen garbage house
$751,2 1 day 2 peopleHC26-11Taken
Water seal steps and handrails going to Mission Dorm
$751,2 1 day 2 peopleHC26-12Taken
As of 4/8/2020
Henderson SettlementHenderson Settlement Campus Work Areas
As of 4/8/2020
Text3:HC26 MISSION DORMITORY
Project Description Skill Time/persons CostProj.Start
Add LED step lights to stairs going down to Mission Dorm
$3002,3 1 day 2 peopleHC26-13Taken
Install gate to access HVAC and fire connection
$1002,3 1 day 2 peopleHC26-14Taken
Install 10 LED lights in lobby $9002,3 3 days 4 peopleHC26-15Taken
Install 10 LED lights in lobby $9002,3 3 days 4 peopleHC26-16Taken
Install 4 LED lights in lobby $3502,3 1 day 2 peopleHC26-17Taken
Install 10 LED lights in confrence room $9002,3 3 days 4 peopleHC26-18Taken
Install 10 LED lights in confrence room $9002,3 3 days 4 peopleHC26-19Taken
Install 10 LED lights in confrence room $9002,3 3 days 4 peopleHC26-20Taken
Install 6 LED lights in mens bathroom upstairs and 5 vanity lights
$1,0002,3 3 days 4 peopleHC26-21Taken
Install 10 LED lights in mens bunk area upstairs
$9002,3 3 days 4 peopleHC26-22Taken
Install 10 LED lights in mens bunk area upstairs
$9002,3 3 days 4 peopleHC26-23Taken
Install 7 LED lights in mens bunk area upstairs
$4502,3 2 days 4 peopleHC26-24Taken
Install 10 LED lights in womens bunk area upstairs
$9002,3 3 days 4 peopleHC26-25Taken
Install 10 LED lights in womens bunk area upstairs
$9002,3 3 days 4 peopleHC26-26Taken
Install 7 LED lights in womens bunk area upstairs
$4502,3 2 days 4 peopleHC26-27Taken
Install 6 LED lights in womens bathroom upstairs and 5 vanity lights
$1,0002,3 3 days 4 peopleHC26-28Taken
Install 2 LED lights in womens bathroom $1002,3 1 day 2 peopleHC26-29Taken
Install LED light in stairwell $502,3 1 day 2 peopleHC26-30Taken
Install 6 LED lights in front section of craft store
$5002,3 2 days 2 peopleHC26-31Taken
Install 9 LED lights in back section of craft store
$7502,3 3 days 4 peopleHC26-32Taken
Install 10 LED lights in mens bunk area down stairs
$9002,3 3 days 4 peopleHC26-33Taken
Install 10 LED lights in mens bunk area down stairs
$9002,3 3 days 4 peopleHC26-34Taken
Install 7 LED lights in mens bunk area down stairs
$4502,3 2 days 4 peopleHC26-35Taken
As of 4/8/2020
Henderson SettlementHenderson Settlement Campus Work Areas
As of 4/8/2020
Text3:HC26 MISSION DORMITORY
Project Description Skill Time/persons CostProj.Start
Install 10 LED lights in womens bunk area down stairs
$9002,3 3 days 4 peopleHC26-36Taken
Install 10 LED lights in womens bunk area down stairs
$9002,3 3 days 4 peopleHC26-37Taken
Install 7 LED lights in womens bunk area upstairs
$4502,3 2 days 4 peopleHC26-38Taken
Install 6 LED lights in mens bathroom down stairs and 5 vanity lights
$1,0002,3 3 days 4 peopleHC26-39Taken
Install 2 LED lights in mens bathroom down stairs
$1002,3 1 day 2 peopleHC26-40Taken
Install 1 LED light in cleaning closet $502,3 1 day 2 peopleHC26-41Taken
Text3:HC27 KITCHEN/DINING HALL
Project Description Skill Time/persons CostProj.Start
Clean and replant flower beds $501,2 1day 3 peopleHC27-1Taken
Replace (6) windows upstairs $1,0501,2,3 1 week 4 peopleHC27-2Taken
Install second half of drain pipe from dining hall to hwy 190
$5501,2,3. 3 days 4 peopleHC27-3Taken
Enclose window of west side mens bathroom
$1752,3 2 days 2 peopleHC27-4Taken
Gravel parking area at garbage house $7001,2,3 2 day 6HC27-5Taken
Repair some spots on roof of garbage house then cover with metal
$2001,2,3 2 days 4 peopleHC27-6Taken
Paint exterior freezer at back entrance $1251,2 1 day 3HC27-8Taken
Install gutter guards $4002,3 2 days 4 peopleHC27-9Taken
Wire and plumb room, install washer and dryer
$8002,3 2 day 3HC27-10Taken
Build wood walkway to connect existing walk to exterior pantry door
$2001,2,3 2 days 3 peopleHC27-11Taken
Build walls in, build handrail and replace door near cooler room going down steps at dining hall
$4502,3 2 day 2HC27-12Taken
Build wood support wall and fill with gravel at fire escape and freezer in back of dining hall
$6001,2,3 1 day 4HC27-13Taken
Pressure wash and water seal deck $3251,2 2 days 4 peopleHC27-15Taken
Replace 6 airflow vents upstairs and 1 downstairs
$1001,2 1 day 2HC27-19Taken
As of 4/8/2020
Henderson SettlementHenderson Settlement Campus Work Areas
As of 4/8/2020
Text3:HC27 KITCHEN/DINING HALL
Project Description Skill Time/persons CostProj.Start
Replace 1 large airflow vent in hallway upstairs
$501,2 1 day 2HC27-20Taken
Install crown molding in rooms #7 and #8 and in lobby
$1502,3 1 day 2 peopleHC27-21Taken
Scrape and paint womens bathroom walls upstairs
$751,2 1 day 2 people 2HC27-22Taken
Scrape and paint hallway ceiling and ceiling of rooms #9 and #10 upstairs
$1001,2 2 days 2 peopleHC27-23Taken
Pressure wash back block wall $1251,2 1 day 2 peopleHC27-24Taken
Install down spout to gutter at deck $752,3 1 day 2 peopleHC27-25Taken
Water seal tables on back deck $751,2 1 day 4 peopleHC27-26Taken
Paint concrete back wall on dining hall $2501,2 1 day 6 peopleHC27-27Taken
Replace exterior door on small pantry room in dining hall
$2752,3 1 day 2 peopleHC27-28Taken
Repair some soffit on back of dining hall $2002,3 1 day 2 peopleHC27-29Taken
Install elbow to down spout over roof on small back porch at dining hall
$752,3 1 day 2 peopleHC27-30Taken
Remove and replace carpet with laminate on upstairs livingroom floor
$6001,2,3 3 days 4 peopleHC27-31Taken
Enlarge opening and install exterior door at cooler room
$2502,3 1 day 3 peopleHC27-32Taken
Replace mop sink $3502,3 1 day 2 peopleHC27-33Taken
Replace 2 bathroom toilets $3502,3 2 days 2 peopleHC27-34Taken
Install 10 LED lights in dining room $9002,3 3 days 4 peopleHC27-35Taken
Install 10 LED lights in dining room $9002,3 3 days 4 peopleHC27-36Taken
Install 10 LED lights in dining room $9002,3 3 days 4 peopleHC27-37Taken
Install 5 LED lights in dining room $4502,3 2 days 4 peopleHC27-38Taken
Install 2 LED lights in dishwasher room $1802,3 1 day 2 peopleHC27-39Taken
Install 8 LED lights in middle dining room $7002,3 2 days 4 peopleHC27-40Taken
Install 2 LED lights in bathroom $1002,3 1 day 2 peopleHC27-41Taken
Install 10 LED lights in food prep area $9002,3 3 days 4 peopleHC27-42Taken
Install 5 LED lights in dry storage area near back door
$4502,3 2 days 4 peopleHC27-43Taken
Install 2 LED lights in small kitchen $1502,3 1 day 2 peopleHC27-44Taken
Install 3 LED lights in dry storage $2752,3 2 days 2 peopleHC27-45Taken
Install 2 LED lights in mens and womens bathroom upstairs
$1802,3 1 day 2 peopleHC27-46Taken
As of 4/8/2020
Henderson SettlementHenderson Settlement Campus Work Areas
As of 4/8/2020
Text3:HC27 KITCHEN/DINING HALL
Project Description Skill Time/persons CostProj.Start
Text3:HC28 ALLEN HOUSE DUPLEX
Project Description Skill Time/persons CostProj.Start
Replace (5)windows in East duplex $1,0002,3 1 wk 4HC28-1Taken
Replace (5) windows in West duplex $1,0002,3 1 week 4 peopleHC28-2Taken
Install new sheeting to ceiling of small porch
$1751,2,3 2 day 4HC28-3Taken
Text3:HC29 VALLEY HOUSE 1
Project Description Skill Time/persons CostProj.Start
Install (2) storm doors $4002,3 2 days 2 peopleHC29-1Taken
Pressure was exterior of house $501,2 2 days 4 peoplHC29-2Taken
Text3:HC30 VALLEY HOUSE 2
Project Description Skill Time/persons CostProj.Start
Install back exterior door and storm door $4502,3 2 days 3 peopleHC30-1Taken
Replace front exterior door and storm door
$4502,3 2 days 3 peopleHC30-2Taken
Replace bathroom vanity and medicine cabinet
$6002,3 2 days 3 peopleHC30-3Taken
Install backsplash to wall over bathroom vanity and kitchen sink
$1502,3 1 day 2 peopleHC30-4Taken
Replace 5 interior doors $5002,3 2 days 3 peopleHC30-5Taken
Paint bathroom walls $1001,2 1 day 2 peopleHC30-6Taken
Remove and replace front steps and hand rail
$4501,2,3 2 days 3 peopleHC30-7Taken
Remove and replace side steps and hand rail
$4501,2,3 2 days 3 peopleHC30-8Taken
Scrape and paint ramp and front porch $3501,2 1 day 3 peopleHC30-9Taken
Pressure was exterior of house $501,2 2 days 4 peopleHC30-10Taken
Paint front porch and ramp on house $1751,2 2 days 4 peopleHC30-11Taken
Build gate on side porch on house $751,2,3 1 day 2 peopleHC30-12Taken
As of 4/8/2020
Henderson SettlementHenderson Settlement Campus Work Areas
As of 4/8/2020
Text3:HC33 MAINTENANCE BUILDING
Project Description Skill Time/persons CostProj.Start
Repair leaks in roof and apply sheeting to ceiling in furniture room storage
$8001,2,3 1 wk 8HC33-1Taken
Build form and pour small concrete slab at furniture room
$8001,2,3 2 days 6 peopleHC33-2Taken
Water seal all wood on gazebo $1001,2 1 days 2 peopleHC33-3Taken
Apply louan to upstairs wall and paint then build shelves
$3001,2,3 3 days 3 peopleHC33-4Taken
Install gutter guards $3002,3 1 day 4 peopleHC33-5Taken
Replace skylight panels on part of building
$1002,3 1 day 3 peopleHC33-6Taken
Build small retaining wall around back of work camp shop
$1,0001,2,3 1 week 8 peopleHC33-7Taken
Build storage shelves in back shed on maintenance side
$4501,2,3 1 day 3 peopleHC33-8Taken
Build storage shelves over R room in maintenance side
$2501,2,3 1 day 2 peopleHC33-9Taken
Apply ferring strips and metal over old metal on new tool room
$4501,2,3 2 days 3 peopleHC33-10Taken
Text3:HC35 MISCELLANEOUS
Project Description Skill Time/persons CostProj.Start
Apply furring strips and metal over shingles on grounds equipment shed
$1,0001,2,3 3 days 6 peopleHC35-1Taken
Apply insulation board and vinyl siding to gables of grounds equipment shed
$2501,2,3 2 days 4 peopleHC35-2Taken
Apply insulation board and luan to ceiling of grounds equipment shed
$5001,2,3 2 days 4 peopleHC35-3Taken
Replace gutters on grounds shed $1001,2,3 1 day 3 peopleHC35-4Taken
Pressure wash and water seal deck at Vespers point
$1001,2 2 day 2 peopleHC35-5Taken
Install electric line in ground to light cross on hill
$2001,2,3 2 day 2 peopleHC35-6Taken
Text3:HC36 PARTIN RESIDENCE
Project Description Skill Time/persons CostProj.Start
Paint hallway and bathroom $1001,2 2 day 2HC36-Taken
As of 4/8/2020
Henderson SettlementHenderson Settlement Campus Work Areas
As of 4/8/2020
Text3:HC36 PARTIN RESIDENCE
Project Description Skill Time/persons CostProj.Start
Install gutter guards $2002,3 1 day 4 peopleHC36-1Taken
Pressure wash and water seal decks and ramp
$2001,2 2 days 3 peopleHC36-2Taken
Pressure wash exterior of house $501,2 1 day 3 peopleHC36-3Taken
Text3:HC37 GARDEN HOUSE
Project Description Skill Time/persons CostProj.Start
Pressure wash exterior of house $501,2 1 day 3 peopleHC37-1Taken
Pressure wash and water seal all decks and ramps
$1001,2 2 days 4 peopleHC37-2Taken
Text3:HC38 SOWER COTTAGE
Project Description Skill Time/persons CostProj.Start
Apply trim to exterior of door on lower section
$752,3 1 day 2 peopleHC38-1Taken
Build small retaining wall below cottages for walkway
$1,2001,2 1 wk 6HC38-2Taken
Pressure wash and water seal steps along side of building
$1001,2 2 days 3 peopleHC38-3Taken
Pressure wash exterior of house $501,2 1 day 3 peopleHC38-4Taken
Text3:HC39 BRANDON COTTAGE
Project Description Skill Time/persons CostProj.Start
Rake ground between cottages and spread pea gravel for sitting area
$8001,2,3 2 days 6 peopleHC39-1Taken
Pressure wash exterior of house $501,2 1 day 3 peopleHC39-2Taken
As of 4/8/2020