HIDD HEIGHTS PROGRESS REPORT About the Project: Project Developer Bin Faqeeh Real Estate Investment Company S.P.C. Title of Project Hidd Heights Project Reference BFHH/22/0102-2802/2019 Design & Supervision Consultant Salah Alkooheji Interior Design Consultant Dar Al Décor Main Contractor Al Jameel Construction SPC About Progress Report: Title of Document Progress Report of Hidd Heights Reporting Period February 1, 2019 to February 28, 2019 Authors & project role United Arab Construction Co. (UACC) Date March 14, 2019

Upload: others

Post on 08-Oct-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: HIDD HEIGHTS PROGRESS REPORT About the Projectbinfaqeeh.com/wp-content/uploads/progress-reports/BFHH.pdf · HIDD HEIGHTS PROGRESS REPORT About the Project: Project Developer Bin Faqeeh

HIDD HEIGHTS PROGRESS REPORT About the Project:

Project Developer Bin Faqeeh Real Estate Investment Company S.P.C.

Title of Project Hidd Heights

Project Reference BFHH/22/0102-2802/2019

Design & Supervision Consultant

Salah Alkooheji

Interior Design Consultant

Dar Al Décor

Main Contractor Al Jameel Construction SPC

About Progress Report:

Title of Document Progress Report of Hidd Heights

Reporting Period February 1, 2019 to February 28, 2019

Authors & project role United Arab Construction Co. (UACC)

Date March 14, 2019

Page 2: HIDD HEIGHTS PROGRESS REPORT About the Projectbinfaqeeh.com/wp-content/uploads/progress-reports/BFHH.pdf · HIDD HEIGHTS PROGRESS REPORT About the Project: Project Developer Bin Faqeeh

DESCRIPTION PERCENTAGE

(%) OF COMPLETION

REMARKS

SUB STRUCTURE

1. Excavation 100% Completed

2. Dewatering 100% Completed

3. Pile Cutting 100% Completed

4. Back Filling and Compaction for Pile Cap 100% Completed

5. Pile Cap 100% Completed

6. Tie Beam 100% Completed

7. Water Tank 100% Completed

8. Grade Slab 100% Completed

9. Septic Tank 100% Completed

10. Substation 99% In Progress

SUPER STRUCTURE

Ground Floor

1. Lift Core Wall 100% Completed

2. Column and Shear Wall 100% Completed

3. Ramp and Staircase 100% Completed

4. 1st Floor Slab 100% Completed

1st Floor

1. Lift Core Wall 100% Completed

2. Column and Shear Wall 100% Completed

3. Ramp and Staircase 100% Completed

4. 2nd Floor Slab 100% Completed

2nd Floor

1. Lift Core Wall 100% Completed

2. Column and Shear Wall 100% Completed

3. Ramp and Staircase 100% Completed

4. 3rd Floor Slab 100% Completed

3rd Floor

1. Lift Core Wall 100% Completed

2. Column and Shear Wall 100% Completed

3. Shear Wall 100% Completed

4. 4th Floor Slab 100% Completed

4th Floor to 11th Floor

- Column and Shear Wall 100% Completed

- Lift Core Wall 100% Completed

- 5th to 12th Floor Slab 100% Completed

Page 3: HIDD HEIGHTS PROGRESS REPORT About the Projectbinfaqeeh.com/wp-content/uploads/progress-reports/BFHH.pdf · HIDD HEIGHTS PROGRESS REPORT About the Project: Project Developer Bin Faqeeh

12th Floor

- Column 100% Completed

- Shear Wall 100% Completed

- Lift Core Wall 100% Completed

- Roof 100% Completed

SUPERSTRUCTURE

Block Work

- Ground Floor 100% Completed

- 1st Floor to 2nd Floor 100% Completed

- Podium Floor 100% Completed

- 1st to 9th Typical Floor 100% Completed

- Roof 100% Completed

Plastering Work

- Ground Floor 100% Completed

- 1st Floor to 2nd Floor 100% Completed

- 1st to 9th Typical Floor 100% Completed

- Podium Floor 100% Completed

Painting Work – Wall and Ceiling (1st Primer & 1st Coat Filler / 2nd Coat Filler & 1st Coat Paint)

- 1st Floor to 2nd Floor 100% Completed

- 1st Typical Floor to 3rd Typical Floor 100% Completed

- 4th Typical Floor to 9th Typical floor 100% Completed

Painting Work – Wall and Ceiling (2nd Coat Filler / 2nd Coat Paint)

- GF 80% In Progress

- 1st Floor 10% In Progress

- 2nd Floor, Stair 2 & Podium Floor 100% Completed

- 1st Typical to 8th Typical (Flats) 100% Completed

Gypsum Work

- 1st Typical Floor to 9th Typical Floor (Living, Kitchen, Bedrooms & Toilets)

100% Completed

- Podium Floor 100% Completed

Wall Cladding

- 1st Typical Floor to 9th Typical Floor 100% Completed

- Ground to Podium Floor 100% Completed

Lift Lobby Wall Cladding

- 1st to 9th Typical Floor 100% Completed

- Ground to Podium 100% Completed

Floor Tile

- 1st Typical Floor to 9th Typical Floor 100% Completed

- Podium 100% Completed

Wall Tile

- 1st to 9th Typical Floor 100% Completed

- Podium 100% Completed

Page 4: HIDD HEIGHTS PROGRESS REPORT About the Projectbinfaqeeh.com/wp-content/uploads/progress-reports/BFHH.pdf · HIDD HEIGHTS PROGRESS REPORT About the Project: Project Developer Bin Faqeeh

Marble Work

- GF to 9th Typical Floor - Corridor 100% Completed

WATERPROOFING

Toilets

- 1st Typical Floor to 9th Typical Floor 100% Completed

Balcony

- 1st Typical Floor to 9th Typical Floor - Corridor

100% Completed

ROOF WATERPROOFING

Roof – PU Foam 100% Completed

Geotextile covering 100% Completed

Light Weight Screed 100% Completed

Membrane 100% Completed

Ground Floor Paving and Curbe Work

- Parking in Ground Floor 100% Completed

- Parking in Entrance Area 100% Completed

Epoxy Floor in Super Structure

- 1st Parking 100% Completed

- 2nd Parking 100% Completed

Parking Wheel Stopper

- 1st and 2nd Parking 100% Completed

Corner Guard

- GF, 1st and 2nd Parking 100% Completed

Page 5: HIDD HEIGHTS PROGRESS REPORT About the Projectbinfaqeeh.com/wp-content/uploads/progress-reports/BFHH.pdf · HIDD HEIGHTS PROGRESS REPORT About the Project: Project Developer Bin Faqeeh

On-site photos:

(Structural Elevation)

Page 6: HIDD HEIGHTS PROGRESS REPORT About the Projectbinfaqeeh.com/wp-content/uploads/progress-reports/BFHH.pdf · HIDD HEIGHTS PROGRESS REPORT About the Project: Project Developer Bin Faqeeh

(Structural Elevation)

Page 7: HIDD HEIGHTS PROGRESS REPORT About the Projectbinfaqeeh.com/wp-content/uploads/progress-reports/BFHH.pdf · HIDD HEIGHTS PROGRESS REPORT About the Project: Project Developer Bin Faqeeh

(Final coat paints for Electricl Room at GF) (Final coat painting at Poduim Floor)

(Fixing of wheel stopper and number at 1st & 2nd parking floor)