HIE-ISOLDE Status Report
Y. Kadi, W. Venturini Delsolaro, O. Pirotte, J.A. Rodriguez, E. Siesling
for the HIE-ISOLDE project team
Outline:
Status of Phase 2
2018 HW Commissioning Highlights
Outstanding Issues
Spares Production
Final Cost to Completion of the Project
Summary
60th Meeting of the INTC – November 7th 2018
Phase2 reached completion in May 2018
SECISS
Miniball
CM4 and XT00
modifications
Main installation activities since last INTC, Feb 2018 were:1) Installation CM4 services (Cryo, Vac,
RF, etc.)2) Completion maintenance of the
compressor station and cold box3) Completion repair of the Cryo
Distribution System by CRIOTEC4) REX RF maintenance 5) XT00 WIC recommissioning6) XLN2 repair & Silicon detector XT02 &
XT03 cabling7) Survey smoothing campaign of HIE
LINAC & HEBT lines after cooldownOthers: Installation Solenoid power supply, CM4 RF amplifiers, ISS He filling, tunnel roof fences, REX power supplies consolidation (YETS)
HEBT & LINAC survey
smoothing campaign
60th Meeting of the INTC – November 7th 2018Courtesy E. Siesling
2018 HW Commissioning Highlight
60th Meeting of the INTC – November 7th 2018
QS17.2
(XLH3.
1)
QS19.1
(XLH3.
2)
QS22.2
(XLH3.
3)
QS23.1
(XLH3.
4)
QSS.1
(XLH3.
5)
SC
solenoid
Beam
Courtesy W. Venturini
SC Cavitiy Performance
• Cool down gradients over
Tc less favourable than in
the past
• Most cavities reaching 6
MV/m above specified Q
• 3 cases of field emission
(one new). For the moment,
no He processing
• CAV3 of CM4 will not be
used in 2018
Courtesy W. Venturini 60th Meeting of the INTC – November 7th 2018
Outstanding Issues
Courtesy E. Siesling
ISS
Miniball
CM1:
- Field emission
mostly in CAV5
(SRF5)
- non-conformity of
solenoid#1 – short
to ground (but able
to run)
CM2:
- Most problematic CM
- Running at low
gradients
- Mild Field emission in
CAV 3 (SRF8)
- Instabilities CAV 2 & 4
(SRF7 & SRF9)
- High vacuum at start of
run which disappeared
- Anomalous static heat
load and microphonics.
Not understood.
CM3:
- Close to specs at
5.5MV/m
- Very stable
- Best operational CM
CM4:
- Non-conformity for
CAV 3 (SRF18) – RF
coupler issue
- Two other cavities with
low Q
- All cavities running at
lower gradient
- Worst operational CM
Energy versus A/q Courtesy J.A. Rodriguez
SEC
60th Meeting of the INTC – November 7th 2018
Status of Spare Cavities
59th Meeting of the INTC – June 27th 2018
• QSS2, QS18, QS20 were fully qualified
as spares
• QS18 needs to be requalified after V5
incident
• QS20 has the lowest Q, it could be
stripped and re-coated
• QSS3 was coated cold test before
end 2018
• The fifth spare cavity should have come
from either QS6 or QS15, both
substrates are in bad conditions
• manufacture fourth seamless cavity
instead (QSS4) raw material is
available, pending acceptance
Cost to Completion of the Project
60th Meeting of the INTC – November 7th 2018
HIE‐ISOLDE Project Budget ‐ 1st November 2018
Cost to Completion (P+M ) in kCHF 78,187
P vs M distribution (without in‐kind)
Material CERN 26,440
Collaboration 12,551
In‐kind 382
Personnel CERN 33,946
Fellows EU 4,868
78,187
Material Budget in kCHF 39,373
Personnel Budget in FTE 252.7 in kCHF 38,814
C ET d a ta u p to 2017
A PT targ et fig u res from 2018
Funding Budget usage (CERN funding)
CERN26,440
67%
Collaboration12,551
32%
In‐kind3821%
26,352
26,398 26,440
0
5,000
10,000
15,000
20,000
25,000
30,000
Jan‐1
0
May‐1
0
Sep‐1
0
Jan‐1
1
May‐1
1
Sep‐1
1
Jan‐1
2
May‐1
2
Sep‐1
2
Jan‐1
3
May‐1
3
Sep‐1
3
Jan‐1
4
May‐1
4
Sep‐1
4
Jan‐1
5
May‐1
5
Sep‐1
5
Jan‐1
6
May‐1
6
Sep‐1
6
Jan‐1
7
May‐1
7
Sep‐1
7
Jan‐1
8
May‐1
8
Sep‐1
8
Jan‐1
9
May‐1
9
Sep‐1
9
HIE‐ISOLDE Material Expenses (CERN funding)
Charges Commitments MTP budget
Material50%
Fellows EU6%
Personnel44%
Material CERN34%
Collaboration16%
In‐kind1%
Personnel CERN43%
Fellows EU 6%
Material commitments26,398
Pipeline accounting
18
Not committed
24
0
10
20
30
40
50
60
2010 2011 2012 2013 2014 2015 2016 2017 2018
Staff Fellows DGP Fellows EU Total
FAP‐RPC 01‐Nov‐2018
Cost to Completion by Phase (kCHF)
60th Meeting of the INTC – November 7th 2018
2018
2017
Infrastructure
Machine Total
Phase 11 Phase 2 3rd beam line
CERN funding 21,739 4,199 415 784 27,137
Collaboration 8,329 4,472 12,801
In kind 341 41 382
Total 21,739 12,869 4,928 784 40,320
1 Including 115 kCHF of advanced procurement for Phase 3 that are funded by CERN
Infrastructure
Machine Total
Phase 11 Phase 2 3rd beam line
CERN funding 21,067 4,199 415 753 26,434
Collaboration 8,329 4,222 12,551
In kind 341 41 382
Total 21,067 12,869 4,678 753 39,367
1 Including 115 kCHF of advanced procurement for Phase 3 that are funded by CERN
Summary:
• HIE-ISOLDE phase 2 is completed
• 2 years delay
• +5 MCHF w.r.t initial estimate in 2010 +1.5%/yr !
• The Machine now in the hands of BE/OP
• Anomalous static heat load in CM2… not understood
• Issue with CAV3 of CM4: not a showstopper for 2018,
• Intervention during LS2 approved by LS2C
• Spares:
• 3 spare cavities already secured
• 2 spare solenoids in store
• 1 spare cryo compressor + 2 spare motors in store
60th Meeting of the INTC – November 7th 2018
Acknowledgement
• EN/EA : FABIO FORMENTI
• GS/SE : DANIEL PARCHET
• EN/ACE : STEPHANE MARIDOR, JEAN-CHRISTOPHE GAYDE, ESTRELLA FERNANDEZ, ANTJE BEHRENS, ALEX BEYNEL
• BE/ABP / OP : FREDERIK WENANDER, JOSE ALBERTO RODRIGUEZ, ELEFTHERIS FADAKIS, MIGUEL LOZANO BENITO
• EP/SME : MARIA BORGE, KARL JOHNSTON, GERDA NEYENS
• BE/RF : DANIEL VALUCH, WALTER VENTURINI DELSOLARO, MATHIEU THERRASSE, AKIRA MYAZAKI
• EN/CV : AZIZ AMAMOU, NICOLAS ROGET, HASSANE SABRI
• EN/EL,TE/EPC: RENE NECCA, GEORGI GEORGIEV, MICHELE MARTINO, PAWEL BURDELSKI, NICOLAS DAVID
• TE/CRG : JOS METSELAAR, OLIVIER PIROTTE, NICOLAS GUILLOTIN, REMI GUEYDAN
• EN/STI : RICHARD CATHERALL, ANA-PAULA BERNARDES
• GS/DI : CYRILLE BEDEL, YANNICK BERAUD
• TE/MSC : YANN LECLERCQ, LLOYD WILLIAMS, VITTORIO PARMA, JEREMIE BAUCHE, DAVID SMEKENS, GRAEME BARLOW, JEAN BAPTISTE DESCHAMPS
• HSE/RP : JOACHIM VOLLAIRE, ALEXANDRE DORSIVAL, ELODIE AUBERT
• TE/ABT/ MPE : MATTHEW FRASE, RICHARD MOMPO
• TE/VSC : JOSE FERREIRA SOMOZA, GUILLERMO FERNANDEZ, ABEL GUTIERREZ, PAUL DEMAREST
• BE/BI : WILLIAM ANDREAZZA, SERGEY SADOVICH
• EN/MME : ANTTI KOLEHMAINEN, MARC TIMMINS
• EN/HE : JEAN-LOUIS GRENARD, FRANCK SCHNEITER and the entire Transport Team
60th Meeting of the INTC – November 7th 2018
Acknowledgement
• EN/EA : FABIO FORMENTI
• GS/SE : DANIEL PARCHET
• EN/ACE : STEPHANE MARIDOR, JEAN-CHRISTOPHE GAYDE, ESTRELLA FERNANDEZ, ANTJE BEHRENS, ALEX BEYNEL
• BE/ABP / OP : FREDERIK WENANDER, JOSE ALBERTO RODRIGUEZ, ELEFTHERIS FADAKIS, MIGUEL LOZANO BENITO
• EP/SME : MARIA BORGE, KARL JOHNSTON, GERDA NEYENS
• BE/RF : DANIEL VALUCH, WALTER VENTURINI DELSOLARO, MATHIEU THERRASSE, AKIRA MYAZAKI
• EN/CV : AZIZ AMAMOU, NICOLAS ROGET, HASSANE SABRI
• EN/EL,TE/EPC: RENE NECCA, GEORGI GEORGIEV, MICHELE MARTINO, PAWEL BURDELSKI, NICOLAS DAVID
• TE/CRG : JOS METSELAAR, OLIVIER PIROTTE, NICOLAS GUILLOTIN, REMI GUEYDAN
• EN/STI : RICHARD CATHERALL, ANA-PAULA BERNARDES
• GS/DI : CYRILLE BEDEL, YANNICK BERAUD
• TE/MSC : YANN LECLERCQ, LLOYD WILLIAMS, VITTORIO PARMA, JEREMIE BAUCHE, DAVID SMEKENS, GRAEME BARLOW, JEAN BAPTISTE DESCHAMPS
• HSE/RP : JOACHIM VOLLAIRE, ALEXANDRE DORSIVAL, ELODIE AUBERT
• TE/ABT/ MPE : MATTHEW FRASE, RICHARD MOMPO
• TE/VSC : JOSE FERREIRA SOMOZA, GUILLERMO FERNANDEZ, ABEL GUTIERREZ, PAUL DEMAREST
• BE/BI : WILLIAM ANDREAZZA, SERGEY SADOVICH
• EN/MME : ANTTI KOLEHMAINEN, MARC TIMMINS
• EN/HE : JEAN-LOUIS GRENARD, FRANCK SCHNEITER and the entire Transport Team
60th Meeting of the INTC – November 7th 2018