hie-isolde status report · • te/msc : yann leclercq, lloyd williams, vittorio parma, jeremie...

13
HIE-ISOLDE Status Report Y. Kadi, W. Venturini Delsolaro, O. Pirotte, J.A. Rodriguez, E. Siesling for the HIE-ISOLDE project team

Upload: others

Post on 08-Oct-2019

1 views

Category:

Documents


0 download

TRANSCRIPT

HIE-ISOLDE Status Report

Y. Kadi, W. Venturini Delsolaro, O. Pirotte, J.A. Rodriguez, E. Siesling

for the HIE-ISOLDE project team

Outline:

Status of Phase 2

2018 HW Commissioning Highlights

Outstanding Issues

Spares Production

Final Cost to Completion of the Project

Summary

60th Meeting of the INTC – November 7th 2018

Phase2 reached completion in May 2018

SECISS

Miniball

CM4 and XT00

modifications

Main installation activities since last INTC, Feb 2018 were:1) Installation CM4 services (Cryo, Vac,

RF, etc.)2) Completion maintenance of the

compressor station and cold box3) Completion repair of the Cryo

Distribution System by CRIOTEC4) REX RF maintenance 5) XT00 WIC recommissioning6) XLN2 repair & Silicon detector XT02 &

XT03 cabling7) Survey smoothing campaign of HIE

LINAC & HEBT lines after cooldownOthers: Installation Solenoid power supply, CM4 RF amplifiers, ISS He filling, tunnel roof fences, REX power supplies consolidation (YETS)

HEBT & LINAC survey

smoothing campaign

60th Meeting of the INTC – November 7th 2018Courtesy E. Siesling

2018 HW Commissioning Highlight

60th Meeting of the INTC – November 7th 2018

QS17.2

(XLH3.

1)

QS19.1

(XLH3.

2)

QS22.2

(XLH3.

3)

QS23.1

(XLH3.

4)

QSS.1

(XLH3.

5)

SC

solenoid

Beam

Courtesy W. Venturini

SC Cavitiy Performance

• Cool down gradients over

Tc less favourable than in

the past

• Most cavities reaching 6

MV/m above specified Q

• 3 cases of field emission

(one new). For the moment,

no He processing

• CAV3 of CM4 will not be

used in 2018

Courtesy W. Venturini 60th Meeting of the INTC – November 7th 2018

Outstanding Issues

Courtesy E. Siesling

ISS

Miniball

CM1:

- Field emission

mostly in CAV5

(SRF5)

- non-conformity of

solenoid#1 – short

to ground (but able

to run)

CM2:

- Most problematic CM

- Running at low

gradients

- Mild Field emission in

CAV 3 (SRF8)

- Instabilities CAV 2 & 4

(SRF7 & SRF9)

- High vacuum at start of

run which disappeared

- Anomalous static heat

load and microphonics.

Not understood.

CM3:

- Close to specs at

5.5MV/m

- Very stable

- Best operational CM

CM4:

- Non-conformity for

CAV 3 (SRF18) – RF

coupler issue

- Two other cavities with

low Q

- All cavities running at

lower gradient

- Worst operational CM

Energy versus A/q Courtesy J.A. Rodriguez

SEC

60th Meeting of the INTC – November 7th 2018

Status of Spare Cavities

59th Meeting of the INTC – June 27th 2018

• QSS2, QS18, QS20 were fully qualified

as spares

• QS18 needs to be requalified after V5

incident

• QS20 has the lowest Q, it could be

stripped and re-coated

• QSS3 was coated cold test before

end 2018

• The fifth spare cavity should have come

from either QS6 or QS15, both

substrates are in bad conditions

• manufacture fourth seamless cavity

instead (QSS4) raw material is

available, pending acceptance

Cost to Completion of the Project

60th Meeting of the INTC – November 7th 2018

HIE‐ISOLDE Project Budget ‐ 1st November 2018

Cost to  Completion  (P+M ) in  kCHF 78,187

P  vs M  distribution  (without in‐kind)

Material CERN 26,440

Collaboration 12,551

In‐kind 382

Personnel CERN 33,946

Fellows EU 4,868

78,187

Material Budget in  kCHF 39,373

Personnel Budget in  FTE 252.7 in kCHF 38,814

C ET  d a ta  u p  to  2017

A PT  targ et  fig u res  from  2018

Funding Budget usage (CERN  funding)

CERN26,440

67%

Collaboration12,551

32%

In‐kind3821%

26,352

26,398 26,440

0

5,000

10,000

15,000

20,000

25,000

30,000

Jan‐1

0

May‐1

0

Sep‐1

0

Jan‐1

1

May‐1

1

Sep‐1

1

Jan‐1

2

May‐1

2

Sep‐1

2

Jan‐1

3

May‐1

3

Sep‐1

3

Jan‐1

4

May‐1

4

Sep‐1

4

Jan‐1

5

May‐1

5

Sep‐1

5

Jan‐1

6

May‐1

6

Sep‐1

6

Jan‐1

7

May‐1

7

Sep‐1

7

Jan‐1

8

May‐1

8

Sep‐1

8

Jan‐1

9

May‐1

9

Sep‐1

9

HIE‐ISOLDE Material Expenses (CERN funding)

Charges Commitments MTP budget

Material50%

Fellows EU6%

Personnel44%

Material CERN34%

Collaboration16%

In‐kind1%

Personnel CERN43%

Fellows EU 6%

Material commitments26,398

Pipeline accounting

18

Not committed

24

0

10

20

30

40

50

60

2010 2011 2012 2013 2014 2015 2016 2017 2018

Staff Fellows DGP Fellows EU Total

FAP‐RPC 01‐Nov‐2018

Cost to Completion by Phase (kCHF)

60th Meeting of the INTC – November 7th 2018

2018

2017

Infrastructure

Machine Total

Phase 11 Phase 2 3rd beam line

CERN funding 21,739 4,199 415 784 27,137

Collaboration 8,329 4,472 12,801

In kind 341 41 382

Total 21,739 12,869 4,928 784 40,320

1 Including 115 kCHF of advanced procurement for Phase 3 that are funded by CERN

Infrastructure

Machine Total

Phase 11 Phase 2 3rd beam line

CERN funding 21,067 4,199 415 753 26,434

Collaboration 8,329 4,222 12,551

In kind 341 41 382

Total 21,067 12,869 4,678 753 39,367

1 Including 115 kCHF of advanced procurement for Phase 3 that are funded by CERN

Summary:

• HIE-ISOLDE phase 2 is completed

• 2 years delay

• +5 MCHF w.r.t initial estimate in 2010 +1.5%/yr !

• The Machine now in the hands of BE/OP

• Anomalous static heat load in CM2… not understood

• Issue with CAV3 of CM4: not a showstopper for 2018,

• Intervention during LS2 approved by LS2C

• Spares:

• 3 spare cavities already secured

• 2 spare solenoids in store

• 1 spare cryo compressor + 2 spare motors in store

60th Meeting of the INTC – November 7th 2018

Acknowledgement

• EN/EA : FABIO FORMENTI

• GS/SE : DANIEL PARCHET

• EN/ACE : STEPHANE MARIDOR, JEAN-CHRISTOPHE GAYDE, ESTRELLA FERNANDEZ, ANTJE BEHRENS, ALEX BEYNEL

• BE/ABP / OP : FREDERIK WENANDER, JOSE ALBERTO RODRIGUEZ, ELEFTHERIS FADAKIS, MIGUEL LOZANO BENITO

• EP/SME : MARIA BORGE, KARL JOHNSTON, GERDA NEYENS

• BE/RF : DANIEL VALUCH, WALTER VENTURINI DELSOLARO, MATHIEU THERRASSE, AKIRA MYAZAKI

• EN/CV : AZIZ AMAMOU, NICOLAS ROGET, HASSANE SABRI

• EN/EL,TE/EPC: RENE NECCA, GEORGI GEORGIEV, MICHELE MARTINO, PAWEL BURDELSKI, NICOLAS DAVID

• TE/CRG : JOS METSELAAR, OLIVIER PIROTTE, NICOLAS GUILLOTIN, REMI GUEYDAN

• EN/STI : RICHARD CATHERALL, ANA-PAULA BERNARDES

• GS/DI : CYRILLE BEDEL, YANNICK BERAUD

• TE/MSC : YANN LECLERCQ, LLOYD WILLIAMS, VITTORIO PARMA, JEREMIE BAUCHE, DAVID SMEKENS, GRAEME BARLOW, JEAN BAPTISTE DESCHAMPS

• HSE/RP : JOACHIM VOLLAIRE, ALEXANDRE DORSIVAL, ELODIE AUBERT

• TE/ABT/ MPE : MATTHEW FRASE, RICHARD MOMPO

• TE/VSC : JOSE FERREIRA SOMOZA, GUILLERMO FERNANDEZ, ABEL GUTIERREZ, PAUL DEMAREST

• BE/BI : WILLIAM ANDREAZZA, SERGEY SADOVICH

• EN/MME : ANTTI KOLEHMAINEN, MARC TIMMINS

• EN/HE : JEAN-LOUIS GRENARD, FRANCK SCHNEITER and the entire Transport Team

60th Meeting of the INTC – November 7th 2018

Acknowledgement

• EN/EA : FABIO FORMENTI

• GS/SE : DANIEL PARCHET

• EN/ACE : STEPHANE MARIDOR, JEAN-CHRISTOPHE GAYDE, ESTRELLA FERNANDEZ, ANTJE BEHRENS, ALEX BEYNEL

• BE/ABP / OP : FREDERIK WENANDER, JOSE ALBERTO RODRIGUEZ, ELEFTHERIS FADAKIS, MIGUEL LOZANO BENITO

• EP/SME : MARIA BORGE, KARL JOHNSTON, GERDA NEYENS

• BE/RF : DANIEL VALUCH, WALTER VENTURINI DELSOLARO, MATHIEU THERRASSE, AKIRA MYAZAKI

• EN/CV : AZIZ AMAMOU, NICOLAS ROGET, HASSANE SABRI

• EN/EL,TE/EPC: RENE NECCA, GEORGI GEORGIEV, MICHELE MARTINO, PAWEL BURDELSKI, NICOLAS DAVID

• TE/CRG : JOS METSELAAR, OLIVIER PIROTTE, NICOLAS GUILLOTIN, REMI GUEYDAN

• EN/STI : RICHARD CATHERALL, ANA-PAULA BERNARDES

• GS/DI : CYRILLE BEDEL, YANNICK BERAUD

• TE/MSC : YANN LECLERCQ, LLOYD WILLIAMS, VITTORIO PARMA, JEREMIE BAUCHE, DAVID SMEKENS, GRAEME BARLOW, JEAN BAPTISTE DESCHAMPS

• HSE/RP : JOACHIM VOLLAIRE, ALEXANDRE DORSIVAL, ELODIE AUBERT

• TE/ABT/ MPE : MATTHEW FRASE, RICHARD MOMPO

• TE/VSC : JOSE FERREIRA SOMOZA, GUILLERMO FERNANDEZ, ABEL GUTIERREZ, PAUL DEMAREST

• BE/BI : WILLIAM ANDREAZZA, SERGEY SADOVICH

• EN/MME : ANTTI KOLEHMAINEN, MARC TIMMINS

• EN/HE : JEAN-LOUIS GRENARD, FRANCK SCHNEITER and the entire Transport Team

60th Meeting of the INTC – November 7th 2018

60th Meeting of the INTC – November 7th 2018