high purity water project presentation no unplanned downtime
DESCRIPTION
Installation of a High Purity Water and WFI system with no unplanned downtime. Latest available technology including online monitoring Microbial Detection, Reduced water consumption with start / stop / sanitize cycles of water pretreatment equipment. Both systems designed with full redundancy to provide reliability.TRANSCRIPT
![Page 1: High Purity Water Project Presentation No Unplanned Downtime](https://reader033.vdocument.in/reader033/viewer/2022052907/55942b921a28abbc5a8b4756/html5/thumbnails/1.jpg)
2014 ISPE Annual Meeting
Case Study ‐ New High Purity Water System Technologies Deliver
Reliability & Sustainability for GSK
1
![Page 2: High Purity Water Project Presentation No Unplanned Downtime](https://reader033.vdocument.in/reader033/viewer/2022052907/55942b921a28abbc5a8b4756/html5/thumbnails/2.jpg)
2014 ISPE Annual Meeting 2
BRIAN LIPKO, PESenior Project Manager Hargrove Life Sciences
BRIAN TERMINE, PEMaintenance Engineering Manager GlaxoSmithKline
STEVE WALTER, CPIPProcess Systems Technology Specialist Hargrove Life Sciences
PRESENTERS
![Page 3: High Purity Water Project Presentation No Unplanned Downtime](https://reader033.vdocument.in/reader033/viewer/2022052907/55942b921a28abbc5a8b4756/html5/thumbnails/3.jpg)
2014 ISPE Annual Meeting
ACKNOWLEDGMENTS
RANDY MINTO, PE, Program Manager, GlaxoSmithKline
DAN D’AQUILA, PE, Director of Engineering & Validation, GlaxoSmithKline
ED STEVENS, Engineering Manager, GlaxoSmithKline
ALEX TANJUTCO, Validation Project Manager, GlaxoSmithKline
TED DOMBROWSKI, Senior Project Engineer, Arcadis (on behalf of GSK)
ROBERT HOEPPNER, Project Executive, Henderson Constructors, Inc.
MIKE BILLUPS, Project Manager, Henderson Constructors, Inc.
![Page 4: High Purity Water Project Presentation No Unplanned Downtime](https://reader033.vdocument.in/reader033/viewer/2022052907/55942b921a28abbc5a8b4756/html5/thumbnails/4.jpg)
2014 ISPE Annual Meeting
Introduction
AGENDA
Execution Results
BackgroundObjectivesChallenges
BenefitsLessons Learned
Summary
DesignConstructionQualification
![Page 5: High Purity Water Project Presentation No Unplanned Downtime](https://reader033.vdocument.in/reader033/viewer/2022052907/55942b921a28abbc5a8b4756/html5/thumbnails/5.jpg)
2014 ISPE Annual Meeting
Introduction
INTRODUCTION
Execution Results
BackgroundObjectivesChallenges
BenefitsLessons Learned
Summary
DesignConstructionQualification
![Page 6: High Purity Water Project Presentation No Unplanned Downtime](https://reader033.vdocument.in/reader033/viewer/2022052907/55942b921a28abbc5a8b4756/html5/thumbnails/6.jpg)
2014 ISPE Annual Meeting 6
CTM (Clinical Trial Materials)
Facility
Manufactures purified drug substances for
clinical trials worldwide
INTRODUCTION: BACKGROUND
![Page 7: High Purity Water Project Presentation No Unplanned Downtime](https://reader033.vdocument.in/reader033/viewer/2022052907/55942b921a28abbc5a8b4756/html5/thumbnails/7.jpg)
2014 ISPE Annual Meeting 7
INTRODUCTION: BACKGROUND
Existing HPW & WFI Systems Obsolete
Parts no longer Available
Insufficient Capacity for Future
Expansion or Production Increase
Costly Systems Not Energy Efficient
Increased Plant downtime Risk due to insufficient
equipment reliability
![Page 8: High Purity Water Project Presentation No Unplanned Downtime](https://reader033.vdocument.in/reader033/viewer/2022052907/55942b921a28abbc5a8b4756/html5/thumbnails/8.jpg)
2014 ISPE Annual Meeting 8
INTRODUCTION: BACKGROUND
ProjectScope
Replace 2 Obsolete Water Systems
HPWHigh Purity
Water
WFIWater for Injection
New Reliable System Design
Supply HPW to Biopharm Development Pilot Plant
Change System Configuration from 3 to 2 Pumps
Replace WFI Control Panel
Install Redundant VC Stills
![Page 9: High Purity Water Project Presentation No Unplanned Downtime](https://reader033.vdocument.in/reader033/viewer/2022052907/55942b921a28abbc5a8b4756/html5/thumbnails/9.jpg)
2014 ISPE Annual Meeting
INTRODUCTION: OBJECTIVES
DELIVER SUSTAINABILITY
REDUCE WATER & ENERGY USAGE
DELIVER SUSTAINABILITY
REDUCE WATER & ENERGY USAGE
REPLACE OBSOLETE EQUIPMENT
REPLACE OBSOLETE EQUIPMENT
PROVIDE RELIABILITY THROUGH REDUNDANCY
PROVIDE RELIABILITY THROUGH REDUNDANCY
NO IMPACT TO ON‐GOING OPERATIONS
NO IMPACT TO ON‐GOING OPERATIONS
INCREASE SUPPLY&
STORAGE CAPACITY
INCREASE SUPPLY&
STORAGE CAPACITY
![Page 10: High Purity Water Project Presentation No Unplanned Downtime](https://reader033.vdocument.in/reader033/viewer/2022052907/55942b921a28abbc5a8b4756/html5/thumbnails/10.jpg)
2014 ISPE Annual Meeting
INTRODUCTION: OBJECTIVESRELIABILITY THROUGH REDUNDANCY
10
re∙dun∙dantserving as a duplicate for preventing failure of an entire system
HPW WFI Multi‐Media Filters Softeners Carbon Filters RO/CDI Skid Tank Nitrogen
Filters Distribution Pumps
Vapor Compression Stills
Tank Vent Filters Distribution
Pumps
No Unplanned Downtime
![Page 11: High Purity Water Project Presentation No Unplanned Downtime](https://reader033.vdocument.in/reader033/viewer/2022052907/55942b921a28abbc5a8b4756/html5/thumbnails/11.jpg)
2014 ISPE Annual Meeting 11
INTRODUCTION: OBJECTIVESINCREASE SUPPLY & STORAGE CAPACITY
Generation and Storage Capacity
Insufficient during Maintenance Activities
Need to be Adept & Flexible
Accommodate Emerging Technologies in Manufacturing
Generation Capacity Bottlenecked
Required Daily Water Usage Planning Activities
CLINICAL TRIALSCLINICAL TRIALS
HPWHPW
WFIWFI
![Page 12: High Purity Water Project Presentation No Unplanned Downtime](https://reader033.vdocument.in/reader033/viewer/2022052907/55942b921a28abbc5a8b4756/html5/thumbnails/12.jpg)
2014 ISPE Annual Meeting
Reverse Osmosis Pre‐Treatment System
(Built c.1987)
12
FRP High Purity Water Storage Tank
2000 Gallon (Built c.1987)
INTRODUCTION: OBJECTIVESOBSOLETE EQUIPMENT
![Page 13: High Purity Water Project Presentation No Unplanned Downtime](https://reader033.vdocument.in/reader033/viewer/2022052907/55942b921a28abbc5a8b4756/html5/thumbnails/13.jpg)
2014 ISPE Annual Meeting 13
Multi‐Effect WFI Still (5 MEF)(Built c. 1987)
(3) WFI Distribution Pumps One pump on each floor (Spares in Warehouse)
INTRODUCTION: OBJECTIVESOBSOLETE EQUIPMENT
![Page 14: High Purity Water Project Presentation No Unplanned Downtime](https://reader033.vdocument.in/reader033/viewer/2022052907/55942b921a28abbc5a8b4756/html5/thumbnails/14.jpg)
2014 ISPE Annual Meeting
Softener RegenerationBrine Tank
14
Softener Regeneration Salt Pellets
Palletized 40 lb bagsConsumed 400‐800 lb/day
INTRODUCTION: OBJECTIVESOBSOLETE EQUIPMENT
![Page 15: High Purity Water Project Presentation No Unplanned Downtime](https://reader033.vdocument.in/reader033/viewer/2022052907/55942b921a28abbc5a8b4756/html5/thumbnails/15.jpg)
2014 ISPE Annual Meeting 1
INTRODUCTION: OBJECTIVES
SC Microbial
Microbial Fermentation
Media PrepMicrobial
Purification
Buffer Prep
Building 5Building 38
Biopharm GMP Clinical Trial Production
Manufacturing
Building 4
BiopharmDevelopment Pilot Plant
NO IMPACT TO ON‐GOING OPERATIONS
Safety Assessment
Manufacturing
![Page 16: High Purity Water Project Presentation No Unplanned Downtime](https://reader033.vdocument.in/reader033/viewer/2022052907/55942b921a28abbc5a8b4756/html5/thumbnails/16.jpg)
2014 ISPE Annual Meeting 16
INTRODUCTION: CHALLENGES
WFI CONTROL PANEL CHANGE OUT
IMPACT TO ON‐GOING
OPERATIONS: PHASED
APPROACH
VENDOR COMMITMENT
FOR EQUIPMENT DELIVERY
INSTALL WINDOW
&AVAILABLE DOWNTIME
LIMITED SPACE
![Page 17: High Purity Water Project Presentation No Unplanned Downtime](https://reader033.vdocument.in/reader033/viewer/2022052907/55942b921a28abbc5a8b4756/html5/thumbnails/17.jpg)
2014 ISPE Annual Meeting 17
INTRODUCTION: CHALLENGES
Generation Equipment
Access
Utilities
BUILDING 38
EXISTING MECHANICAL
ROOM
![Page 18: High Purity Water Project Presentation No Unplanned Downtime](https://reader033.vdocument.in/reader033/viewer/2022052907/55942b921a28abbc5a8b4756/html5/thumbnails/18.jpg)
2014 ISPE Annual Meeting
EXECUTION
Introduction Execution Results
BackgroundObjectivesChallenges
BenefitsLessons Learned
Summary
DesignConstructionQualification
![Page 19: High Purity Water Project Presentation No Unplanned Downtime](https://reader033.vdocument.in/reader033/viewer/2022052907/55942b921a28abbc5a8b4756/html5/thumbnails/19.jpg)
2014 ISPE Annual Meeting 19
EXECUTION: DESIGN
SUSTAINABILITY EVALUATION
PROJECT LOCATIONS & CONSTRAINTS
EQUIPMENT EVALUATION
VISIT OTHER GSK SITES
![Page 20: High Purity Water Project Presentation No Unplanned Downtime](https://reader033.vdocument.in/reader033/viewer/2022052907/55942b921a28abbc5a8b4756/html5/thumbnails/20.jpg)
2014 ISPE Annual Meeting
Site 1: Christ System
20
Site 2: Siemens: PreVUE®
Other Site Tours (Gemba)
EXECUTION: DESIGN
![Page 21: High Purity Water Project Presentation No Unplanned Downtime](https://reader033.vdocument.in/reader033/viewer/2022052907/55942b921a28abbc5a8b4756/html5/thumbnails/21.jpg)
2014 ISPE Annual Meeting 21
Options Decision
HPW Single Pass vs. Double Pass RO Single Pass
Polisher vs. None Install Polisher
Carbon vs. Bi‐sulfite vs. UV Light Filtration Carbon Filtration
Service Type vs. Back Washable Carbon Filters Back Washable
Hot Water vs. Chemical Sanitization Hot Water Sanitization
FRP vs. SS HPW Storage Tank SS Tank
High Recovery RO vs. None High Recovery RO
Nitrogen Blanket on Storage Tank vs. None Nitrogen Blanket
Bulk Brine vs. Day Tank Both
Redundant vs. Single Storage Tank Filters Redundant Filters
EQUIPMENT EVALUATION
EXECUTION: DESIGN
![Page 22: High Purity Water Project Presentation No Unplanned Downtime](https://reader033.vdocument.in/reader033/viewer/2022052907/55942b921a28abbc5a8b4756/html5/thumbnails/22.jpg)
2014 ISPE Annual Meeting 22
Options Decision
WFI Vapor Compression vs. Multi Effect Vapor Compression
Separate Pump per Floor vs. Redundant Pumps Redundant Pumps
Redundant vs. Single Storage Tank Filters Redundant Filters
EQUIPMENT EVALUATION
EXECUTION: DESIGN
![Page 23: High Purity Water Project Presentation No Unplanned Downtime](https://reader033.vdocument.in/reader033/viewer/2022052907/55942b921a28abbc5a8b4756/html5/thumbnails/23.jpg)
2014 ISPE Annual Meeting 23
SUSTAINABILITY EVALUATION
Systems Design
Evaluations
Operating Cost
Comparisons
Wastewater Volume
Reduction
EXECUTION: DESIGN
![Page 24: High Purity Water Project Presentation No Unplanned Downtime](https://reader033.vdocument.in/reader033/viewer/2022052907/55942b921a28abbc5a8b4756/html5/thumbnails/24.jpg)
2014 ISPE Annual Meeting
Only Feasible Solution:
Utilize existingCourtyardbetween B5 & B38 (14’ W x 110’ L)
24
Project LocationsLimited
PROJECT LOCATIONS & CONSTRAINTS
EXECUTION: DESIGN
![Page 25: High Purity Water Project Presentation No Unplanned Downtime](https://reader033.vdocument.in/reader033/viewer/2022052907/55942b921a28abbc5a8b4756/html5/thumbnails/25.jpg)
2014 ISPE Annual Meeting
Top of Courtyard Looking NORTH
25
Bottom of Courtyard Looking SOUTH
EXECUTION: DESIGNPROJECT LOCATIONS & CONSTRAINTS
![Page 26: High Purity Water Project Presentation No Unplanned Downtime](https://reader033.vdocument.in/reader033/viewer/2022052907/55942b921a28abbc5a8b4756/html5/thumbnails/26.jpg)
2014 ISPE Annual Meeting 26
2‐Story Mechanical Room Design
EXECUTION: DESIGN
![Page 27: High Purity Water Project Presentation No Unplanned Downtime](https://reader033.vdocument.in/reader033/viewer/2022052907/55942b921a28abbc5a8b4756/html5/thumbnails/27.jpg)
2014 ISPE Annual Meeting 27
EXECUTION: DESIGN2‐Story Mechanical Room Design
![Page 28: High Purity Water Project Presentation No Unplanned Downtime](https://reader033.vdocument.in/reader033/viewer/2022052907/55942b921a28abbc5a8b4756/html5/thumbnails/28.jpg)
2014 ISPE Annual Meeting 28
Construct Addition
&Install HPW
System
Install WFI Pumps
& Control Panel
Demo Old HPW
System
Install WFI VC Stills
Demo Old Still
PhasedConstruction/Qualification
Approach
PHASE 1PHASE 1 PHASE 1APHASE 1A PHASE 2PHASE 2
NO IMPACT TO ON‐GOING OPERATIONS
EXECUTION: DESIGN
![Page 29: High Purity Water Project Presentation No Unplanned Downtime](https://reader033.vdocument.in/reader033/viewer/2022052907/55942b921a28abbc5a8b4756/html5/thumbnails/29.jpg)
2014 ISPE Annual Meeting
Construct 2‐Story Addition for HPW
29
Between 2 Buildings Limited AccessAdjacent GMP Operations
EXECUTION: DESIGNPHASE 1
![Page 30: High Purity Water Project Presentation No Unplanned Downtime](https://reader033.vdocument.in/reader033/viewer/2022052907/55942b921a28abbc5a8b4756/html5/thumbnails/30.jpg)
2014 ISPE Annual Meeting
Construct 2‐Story Addition for HPW
30
Between 2 Buildings Limited AccessAdjacent GMP Operations
EXECUTION: DESIGNPHASE 1
![Page 31: High Purity Water Project Presentation No Unplanned Downtime](https://reader033.vdocument.in/reader033/viewer/2022052907/55942b921a28abbc5a8b4756/html5/thumbnails/31.jpg)
2014 ISPE Annual Meeting 31
EXECUTION: DESIGNSYSTEM CONSIDERATIONS
Choose Vendor that Supplies Customizable PLC Controllers: Normalized Differential Pressure to determine cleaning interval Softener Regeneration is based on Hardness Softener Regeneration Rinse is based on Conductivity
Bulk Brine Tank System
Energy Efficiency
S3 Technology & Pump VFDs
Reduce Water Usage
S3 Technology & High Recovery RO
WFI: Pump Schemes
Fathom SoftwareComplexity of Flows – Multiple Floors
Online TOC, Conductivity &
Microbial Detection
![Page 32: High Purity Water Project Presentation No Unplanned Downtime](https://reader033.vdocument.in/reader033/viewer/2022052907/55942b921a28abbc5a8b4756/html5/thumbnails/32.jpg)
2014 ISPE Annual Meeting 32
EXECUTION: DESIGNPHASE 1A ‐WFI
No Redundancy
Difficult to Control Flow
Maintenance requires Shutdown
Single Pump affected Tank Temp and other Floor Availability
No Redundancy
Difficult to Control Flow
Maintenance requires Shutdown
Single Pump affected Tank Temp and other Floor Availability
OLD SYSTEMOLD SYSTEM
![Page 33: High Purity Water Project Presentation No Unplanned Downtime](https://reader033.vdocument.in/reader033/viewer/2022052907/55942b921a28abbc5a8b4756/html5/thumbnails/33.jpg)
2014 ISPE Annual Meeting 33
EXECUTION: DESIGNPHASE 1A ‐WFI
Redundancy
Control From Worst Case
Pump Maintenance = No downtime
VFD’s to manage fluctuations
Individual Loops can be Isolated
NEW SYSTEMNEW SYSTEM
Generated from Fathom Modeling
![Page 34: High Purity Water Project Presentation No Unplanned Downtime](https://reader033.vdocument.in/reader033/viewer/2022052907/55942b921a28abbc5a8b4756/html5/thumbnails/34.jpg)
2014 ISPE Annual Meeting 34
EXECUTION: DESIGNWFI CONTROL PANEL
Desktop Simulation
Only
20 Year Old System
No ‘Plan B’
Instruments = 86I/O Points = 106
Extensive Pre‐Planning
GREATEST RISK
![Page 35: High Purity Water Project Presentation No Unplanned Downtime](https://reader033.vdocument.in/reader033/viewer/2022052907/55942b921a28abbc5a8b4756/html5/thumbnails/35.jpg)
2014 ISPE Annual Meeting 35
EXECUTION: DESIGNHPW GENERATION SUMMARY
![Page 36: High Purity Water Project Presentation No Unplanned Downtime](https://reader033.vdocument.in/reader033/viewer/2022052907/55942b921a28abbc5a8b4756/html5/thumbnails/36.jpg)
2014 ISPE Annual Meeting
EXECUTION: CONSTRUCTIONTIMELINE
Week 1 25 33 41 49 57 65 73 81 89 97
Phase 2 Begins Shut Down & Phase 1 End
4/21/14
Shut Down Begins
12/16/13Construction
Begins
4/1/13
PHASE 2
PHASE 1A7 WKS
CONSTRUCTION AWARD
DESIGN 24 WEEKS
PHASE 1
9 10517
Construction Complete
6/16/14Design KO6/4/12
CM Award11/5/12
8 WKS
PROCUREMENT & DOCUMENTS29 WEEKS
44 WEEKS
CONSTRUCTION
9/3/12POs
![Page 37: High Purity Water Project Presentation No Unplanned Downtime](https://reader033.vdocument.in/reader033/viewer/2022052907/55942b921a28abbc5a8b4756/html5/thumbnails/37.jpg)
2014 ISPE Annual Meeting 37
EXECUTION: CONSTRUCTIONExisting Courtyard
Stone & Soil Excavation
1st Floor Slab Installation
PHASE 1
![Page 38: High Purity Water Project Presentation No Unplanned Downtime](https://reader033.vdocument.in/reader033/viewer/2022052907/55942b921a28abbc5a8b4756/html5/thumbnails/38.jpg)
2014 ISPE Annual Meeting
Maintain Building Integrity during Removal of Building Façade
38
EXECUTION: CONSTRUCTIONTEMPORARY PROTECTIONS
Removal of the façade exposed Utilities above occupied space inside
Installed Temporary Partition Walls inActive Areas & Issued Change Control
Updated Qualified Flow Drawings Continually During Construction
![Page 39: High Purity Water Project Presentation No Unplanned Downtime](https://reader033.vdocument.in/reader033/viewer/2022052907/55942b921a28abbc5a8b4756/html5/thumbnails/39.jpg)
2014 ISPE Annual Meeting 39
EXECUTION: CONSTRUCTION
Large Crane due to Limited Access
Building Structure Construction
PHASE 1
![Page 40: High Purity Water Project Presentation No Unplanned Downtime](https://reader033.vdocument.in/reader033/viewer/2022052907/55942b921a28abbc5a8b4756/html5/thumbnails/40.jpg)
2014 ISPE Annual Meeting 40
EXECUTION: CONSTRUCTION
Installation of HPW Equipment
PHASE 1
![Page 41: High Purity Water Project Presentation No Unplanned Downtime](https://reader033.vdocument.in/reader033/viewer/2022052907/55942b921a28abbc5a8b4756/html5/thumbnails/41.jpg)
2014 ISPE Annual Meeting 41
EXECUTION: CONSTRUCTION
Outdoor Bulk Brine Tank2nd Floor HPW
PHASE 1
![Page 42: High Purity Water Project Presentation No Unplanned Downtime](https://reader033.vdocument.in/reader033/viewer/2022052907/55942b921a28abbc5a8b4756/html5/thumbnails/42.jpg)
2014 ISPE Annual Meeting 42
EXECUTION: CONSTRUCTION
1st Floor Dual RO Skids
1st Floor HPW Tanks & Pumps
PHASE 1
![Page 43: High Purity Water Project Presentation No Unplanned Downtime](https://reader033.vdocument.in/reader033/viewer/2022052907/55942b921a28abbc5a8b4756/html5/thumbnails/43.jpg)
2014 ISPE Annual Meeting 43
EXECUTION: CONSTRUCTION
2nd Floor Dual Softeners & Multi‐Media Filters
2nd FloorDual Carbon Filters
PHASE 1
![Page 44: High Purity Water Project Presentation No Unplanned Downtime](https://reader033.vdocument.in/reader033/viewer/2022052907/55942b921a28abbc5a8b4756/html5/thumbnails/44.jpg)
2014 ISPE Annual Meeting 44
EXECUTION: CONSTRUCTION
B38 Mechanical RoomNew WFI Pumps
B38 Mechanical RoomExisting WFI Pumps to Demo
PHASE 1A
![Page 45: High Purity Water Project Presentation No Unplanned Downtime](https://reader033.vdocument.in/reader033/viewer/2022052907/55942b921a28abbc5a8b4756/html5/thumbnails/45.jpg)
2014 ISPE Annual Meeting 45
EXECUTION: CONSTRUCTION
B38 Mechanical RoomHPW System to Demo
Access Doors to B38 Mechanical Room
PHASE 2
6’6”
8’8”
![Page 46: High Purity Water Project Presentation No Unplanned Downtime](https://reader033.vdocument.in/reader033/viewer/2022052907/55942b921a28abbc5a8b4756/html5/thumbnails/46.jpg)
2014 ISPE Annual Meeting 46
EXECUTION: CONSTRUCTION
New WFI Stills in B38 Mechanical Room
New WFI Stills at FATSugarland, TX
PHASE 2
![Page 47: High Purity Water Project Presentation No Unplanned Downtime](https://reader033.vdocument.in/reader033/viewer/2022052907/55942b921a28abbc5a8b4756/html5/thumbnails/47.jpg)
2014 ISPE Annual Meeting 47
EXECUTION: CONSTRUCTIONLEVERAGED QUALIFICATION APPROACH
Vendor Qualification Documents Reformatted to GSK Standards PRIOR to Factory Acceptance Test (FAT)
PEOPLE
Qualification Team:ValidationEngineeringFacilitiesQA
EQUIPMENT CHECK
Resolve issues prior to shipment Equipment Still at Factory
DURATION
Reduced Document Development Time by 3 weeksDuplicated FAT during SAT
![Page 48: High Purity Water Project Presentation No Unplanned Downtime](https://reader033.vdocument.in/reader033/viewer/2022052907/55942b921a28abbc5a8b4756/html5/thumbnails/48.jpg)
2014 ISPE Annual Meeting 48
EXECUTION: CHALLENGESCONSTRUCTION
Constrained Area within the Middle of Operating Buildings
Delivery of High Purity Equipment
S3 Design Not Turn‐Key
Polisher Tank Delivery
Sartorius Filter Housings
DI Tank Filters
Failure of PQ1 Testing (Plan B)
Installation of High Purity Equipment
![Page 49: High Purity Water Project Presentation No Unplanned Downtime](https://reader033.vdocument.in/reader033/viewer/2022052907/55942b921a28abbc5a8b4756/html5/thumbnails/49.jpg)
2014 ISPE Annual Meeting 49
EXECUTION: QUALIFICATIONVALIDATION DOCUMENTATION
1 Validation Master Plan (HPW/WFI) including 3 Validation Interim Reports
5 User Requirement Specs
14 Change Controls
27 Installation Operation Qualification Documents
10 Standard Operating Procedure Updates
22 Functional Design Specifications
3 Factory Acceptance Test / Site Acceptance Test
2 Design Qualifications
EXTENSIVE
DOCU
MEN
T MAN
AGEM
ENT
![Page 50: High Purity Water Project Presentation No Unplanned Downtime](https://reader033.vdocument.in/reader033/viewer/2022052907/55942b921a28abbc5a8b4756/html5/thumbnails/50.jpg)
2014 ISPE Annual Meeting
RESULTS
Introduction Execution Results
BackgroundObjectivesChallenges
BenefitsLessons Learned
Summary
DesignConstructionQualification
![Page 51: High Purity Water Project Presentation No Unplanned Downtime](https://reader033.vdocument.in/reader033/viewer/2022052907/55942b921a28abbc5a8b4756/html5/thumbnails/51.jpg)
2014 ISPE Annual Meeting 51
RESULTS: BENEFITS
INCREASED SUPPLY & CAPACITY
IMPROVED RELIABILITY
& DELIVERED
SUSTAINABILITY
LOWER OPERATING EXPENSE
![Page 52: High Purity Water Project Presentation No Unplanned Downtime](https://reader033.vdocument.in/reader033/viewer/2022052907/55942b921a28abbc5a8b4756/html5/thumbnails/52.jpg)
2014 ISPE Annual Meeting 52
IMPROVED SUPPLY TO CLINICAL OPERATIONS
RESULTS: BENEFITS
Increased Capacity & Reliability
Redundant HPW & WFI
B38 B5 B4
![Page 53: High Purity Water Project Presentation No Unplanned Downtime](https://reader033.vdocument.in/reader033/viewer/2022052907/55942b921a28abbc5a8b4756/html5/thumbnails/53.jpg)
2014 ISPE Annual Meeting
RESULTS: BENEFITS Reduced ~11,000 gallons per day / ~4,050,000 gallons per year Cost savings of ~$32K per year (Water & Sewer) Supports GSK’s strategic goal to reduce Water Consumption
Annual carbon emissions reduction of 348 TONNES CO2 Supports GSK’s strategic goal to reduce Carbon Footprint
New System supplying HPW to Biopharm Development Pilot Plant Eliminated Resin Bed Train Service New Bulk Brine & Online Microbial Detection Systems Cost Savings of ~$147,500 per year
Water Consumption
Electrical Energy
Carbon Emissions
Operations
Pumping operations reduced by 88% Cost Savings of ~$28k per year
53
![Page 54: High Purity Water Project Presentation No Unplanned Downtime](https://reader033.vdocument.in/reader033/viewer/2022052907/55942b921a28abbc5a8b4756/html5/thumbnails/54.jpg)
2014 ISPE Annual Meeting
54
FUTURE OPERATING SAVINGS
RESULTS: BENEFITSOnline Microbial Detection System
Synchronized Optical
Monitoring
Particulate Size
Microbial Fluorescence
Reduces Regulatory Sampling
Doesn’t Eliminate
Similar EvaluationTOC/Conductivity
1,980 Samples/YearOnly 4th System Installed in US
![Page 55: High Purity Water Project Presentation No Unplanned Downtime](https://reader033.vdocument.in/reader033/viewer/2022052907/55942b921a28abbc5a8b4756/html5/thumbnails/55.jpg)
2014 ISPE Annual Meeting 55
RESULTS: LESSONS LEARNED
Full Control Replacement:
Demo Simulation of functionality
Integration of Automation Contractor
Selection of Construction Contractor
WHAT WENT WELL
Procurement Management
WFI Batcher Orifices
WFI Still & Clean Steam Supply Pressure
PQ1 Failure / ‘Plan B’
COULD HAVE DONE BETTER
![Page 56: High Purity Water Project Presentation No Unplanned Downtime](https://reader033.vdocument.in/reader033/viewer/2022052907/55942b921a28abbc5a8b4756/html5/thumbnails/56.jpg)
2014 ISPE Annual Meeting 56
SUCCESS!
RESULTS: SUMMARY
CONSTRUCTED & VALIDATED IN LESS THAN
1 YEAR
TWOVALIDATED SYSTEMS & NEW
GENERATION EQUIPMENT
MINIMAL IMPACT TO ON‐GOING OPERATIONS
![Page 57: High Purity Water Project Presentation No Unplanned Downtime](https://reader033.vdocument.in/reader033/viewer/2022052907/55942b921a28abbc5a8b4756/html5/thumbnails/57.jpg)
2014 ISPE Annual Meeting 57
RESULTS: SUMMARY
INCREASED RELIABILITY
DELIVEREDSUSTAINABILITY
MINIMIZED DOWNTIME
DELIVEREDSUSTAINABILITY
LOWEROPERATINGEXPENSE
INCREASED RELIABILITY
OBJECTIVES EXCEEDED!
![Page 58: High Purity Water Project Presentation No Unplanned Downtime](https://reader033.vdocument.in/reader033/viewer/2022052907/55942b921a28abbc5a8b4756/html5/thumbnails/58.jpg)
2014 ISPE Annual Meeting 58
RESULTS: SUMMARY
INCREASD RELIABILITY
DELIVERED SUSTAINABILITY
OBJECTIVES EXCEEDED!
We kept the Trains on the Tracks
![Page 59: High Purity Water Project Presentation No Unplanned Downtime](https://reader033.vdocument.in/reader033/viewer/2022052907/55942b921a28abbc5a8b4756/html5/thumbnails/59.jpg)
2014 ISPE Annual Meeting 59
QUESTIONS