HIGH RADIATION TO MATERIALS WG3 – EXPERIMENTAL AREA
HiRadMat project Team Meeting14/04/2011
Activities TS week 13 Production for test area On-going design studies Activities TS week 19&25
Ans Pardons– EN/MEF
HiRadMat2
Installed week 13, total dose ~1mSvTS week 13: Construction Dump 4m downstream of T9
Ans Pardons EN/MEF
Dump4m
Support TED
Dump4m
T9
HiRadMat3
TED support&dump installed, TED installed (and removed), new collimator installed, roof closed (±)
Total dose preparation: ~0.9mSv, installation: ~0.2mSv
TS week 13: Installation TED
Ans Pardons EN/MEF
HiRadMat4
TED support&dump installed, TED installed (and removed), new collimator installed, roof closed (±)
TS week 13: Installation TED
Ans Pardons EN/MEF
Interference between crane lifting beam and new (downstream) roofblock
Solution: use intermediate hooks (made for test tables)
Intermediate hook Short hook (for comparison)
No interference
HiRadMat5
Priority: base tables:
Reception aluminium support structure: week 15 assembly week 16 Reception tables plates: week 17 add to support structure & paint
week 17 Reception additional small pieces (wedges, ...): week 18 final
assembly of entire table week 18 &start of week 19 for installation week 19
Intermediate crane hooks (also for closing T9 shielding) Reception hooks: week 16 closing roof can in short access (assuming
we can use “monte-charge”) Structure for passage of cables to test stand
Study on-going, orders week 16, reception probably for week 19
Production for Test area & Muon Dump
Ans Pardons EN/MEF
HiRadMat6
Passage cables in TNC
Material – slope – remote installation & dismounting
Design studies
Ans Pardons EN/MEF
HiRadMat7
Remote dismounting base tables
Chariot for test tables
Design studies
Ans Pardons EN/MEF
HiRadMat8
(liste non-exhaustive, en ordre chronologique) Installation ventilation autour de T9 (2 jours, PP) Ouverture toit, installation TED, fermeture toit T9 (1 à 2 jours, YS,
DG) prêt pour installation BPKG Installation tables de base et alignement (2 jours, ML, DDP, KB) (plus
test de manutention si temps disponible, autrement pendant prochain arrêt) prêt pour installation BLMs
Pose peigne et pose câbles d’expérience (à confirmer, GG) Installation supports en zone de décroissance (ML, DDP) (plus test de
manutention si temps disponible, autrement prochain arrêt) Installation supports plaques marbres et blocs acier (si temps
disponible, autrement pendant prochain arrêt) Nettoyage, peinture
Activities week 19 (pardon my French)
Ans Pardons EN/MEF