highway reconstruction program presentation to agc...the prhta is executing the most aggressive...
TRANSCRIPT
Highway Reconstruction Program
Presentation to AGC
June 4, 2020
Jan 26, 2017
Pre-COVID Year to Date Results
Construction Industry Readiness
General Mitigation Strategies during Lockdown◦ Personnel Activation
(Teleworking)◦ Contractor’s Certification
Process◦ CO/EWO processing◦ Consultants Invoices processing◦ Material testing SOP
2
Other Initiatives◦ Operational Requirements
◦ Pre-Construction
◦ Bid Process modifications
2020 Bid Program
Final Remarks
Pre-COVID YTD Results
3
The PRHTA is executing the most aggressive highway reconstruction program in recent decades
Most of the efforts are related to recontruction of the entire highway network with an investmentof $1,900 millions, creating over 48,900 jobs.
6/5/2020
4
Program Focused On: Investment
Abriendo Caminos – High Quality PavementRepair Program
Pavement Repair Island-wide $327,000,000
Abriendo Caminos – FHWA ProgramReconstruction of federal Aid Highway
System$250,000,000
Abriendo Caminos - Programa Estatal de Modernización de Carreteras (PEMOC)
Reconstruction of highways focused ontertiary system (Low AADTs)
$75,000,000
DTL – Dynamic Toll Lanes from San Juan a Caguas
Managed Lanes with BRT $184,000,000
Congestión Relief ProgramReduce congestión on critical
interchanges/corridors$249,000,000
ER Program (Hurricanes Irma y Maria) Landslides, Signage, Bridges $836,000,000
ER Program (2020 Earthquake) Hwys, bridges / Miscellaneous Structures $40,000,000
TOTAL $1,961,000,000
Historical Bids Awards Data
5
• Historically, PRHTA has been successful at obligating federal funds and using state funds to implement its capital improvement program (CIP) using a combination of external and internal resources
• The clawback of dedicated tax revenues and PR financial crisis resulted in a reduced CIP between 2013 and 2016. The main reason this occurred was due its inability to procure external support for the implementation of the CIP
• In 2017, the CIP could not be implemented due to Hurricane María
• In 2017, the implementation of the MOA and additional fund allocation to procure external support resulted in record amounts in bid awarded in 2018 and 2019, thus, PRHTA is back on track in terms of implementation of its CIP through and enhanced project delivery process and toward a new record in 2020
PRHTA: A Historical Perspective
PRHTA 2020 Projections
6
Programmed
TOTAL= 51 NTP
7
PRHTA 2020 Projections
Programmed
8
PRHTA: FY20 Towards Record Disbursements
9
Federal-Aid Billing Process
438CERTIFICATIONS
TOTAL
* Data after Construction Directive #4-2019 was issued by May 2019* Days considers since the certification is Received for Review by the Designated Person at Regional Office
<4040793%
>40317%
20 d
average
103
183
81
4031
0-10 11-20 21-30 31-40 >40
Construction Industry Readiness
10
Most of the Highway Contractors proved to be aheadin the construction industry in terms of readiness torestart construction projects while assuring allmeasures to avoid COVID spreading are in place.
A survey prepared by the PRHTA helped in providingthe most needed input from the AGC members.
With the input of the Highway Committee, from theAGC, the PRHTA provided guidelines andrecommendations to the Governor for a safe restart ofthe highway construction projects.
The PRHTA’s projects were selected among the firstprojects to restart.
THANK YOU!!!!!11
Mitigation Strategies
12
13
Personnel Activation (Teleworking)
Disbursement Process
Resume Construction Work / Operations
Top Management Officials full time teleworking since day 1
Teleworking – Activation / IT Support◦ Construction Personnel
◦ Finance
◦ Pre-intervention Personnel
◦ Administration
◦ Human Resources
◦ Pre-Construction Management / Consulting Services (Design, Environmental)
14
Directive # 3 – March 31, 2020 – Contractor’s Certification Processing
15
Standard Operating Procedure (SOP) for remotely processing Contractor’s Certifications. Defines all steps required for evaluation and approval of the before mentioned documents, considering personnel is teleworking, and in compliance with FHWA requirements.
Directive # 4 – April 8, 2020 – For CO and EWO
16
SOP for remotely processing Change Orders and Extra Work Orders. Defines all steps required for evaluation and approval of the before mentioned documents, considering personnel is teleworking, and in compliance with FHWA requirements.
Directive # 5 – April 9, 2020 – Remotely Processing Consultants' Invoices
17
SOP for remotely processing invoices from consultants providing services to the PRHTA.
Directive # 6 – April 14, 2020 – Materials Certifications
18
SOP for remotely processing the Initial Certificate of Compliance and the Contractor Quality Control Certification for Material Testing.
19
Total Disbursement $47,272,091
Ongoing Process
“Plan de Control de Exposición” a COVID-19 for PRHTA facilities, including:◦ Central Offices
◦ Material Testing Office
◦ Construction Area20
Consultants Teleworking Plan – For management / general consulting services
Designers working at an average 50% capacity before May 11, 2020. Steadily increasing capacity thereafter.
Closely coordinating with FHWA for PS&E approval and having ready bid packages.
Coordinating final steps with EFLHD for Signage & Safety Projects. Bid announcement starting within the next three months.
21
Purchase of Bid Packages at the Treasurer Office on 7th Floor (Minillas South Bldg), Tuesday to Friday, from 9am to 2pm.
Bidders to submit evidence of payment via email to the Board of Awards: [email protected], including bid number.
Boards of Award will send bid package by email.
Pre-Bid meeting will be held using video conference (Webex). PRHTA will send a meeting request with instructions.
Bidders will submit their proposal package (hard copy) to the Board of Award office, located on the 11th floor, Suite 1103 of Roberto Sánchez VilellaGovernment Center, on the date and time indicated.
Board of award will send a meeting request to bidders (video conference using Webex) with instructions for the bid opening and reading outload the results.
22
Abriendo Caminos - Resuming damage assessments and preparingBid Packages
Continue geotechnical investigations, surveying, lead and asbestosstudies, environmental studies for the regular CIP projects.
Starting the WTBP development for Critical bridges repair /Earthquake ER repairs
Final PS&E review for Accelerated Reconstruction Program
Coordinating with regulatory agencies issuingpermits/endorsements
23
24
AC Code Description Region Estimate from Engineer
AC-000314Abriendo caminos Ronda 3 - PR-908, PR-181, PR-964, PR-7787,
PR-956, PR-3East $ 4,607,500.00
AC-000315Abriendo caminos Ronda 3 - PR-842, PR-831, PR-845, PR-8869,
PR-176, PR-39, PR-41Metro $ 4,073,662.52
AC-000316Abriendo caminos Ronda 3 - PR-2, PR-146, PR-159, PR-137, PR-
164, PR-686, PR-615, PR-111, PR-647North $ 7,480,278.53
AC-000317Abriendo caminos Ronda 3 - PR-139, PR-372, PR-140, PR-3375,
PR-3, PR-545, PR-378, PR-565South $ 5,681,475.86
AC-000318Abriendo caminos Ronda 3 - PR-116, PR-422, PR-3301, PR-368,
PR-429, PR-103, PR-426, PR-345, PR-362, PR-121West $ 7,979,767.30
AC-000319Abriendo caminos Ronda 3 - PR-777, PR-188, PR-978, PR-171, PR-987, PR-946, PR-9966, PR-985, PR-181, PR-31, PR-935, PR-
7761, PR-902East $ 6,141,750.00
AC-000321Abriendo Caminos Ronda 3 - PR-814, PR-770, PR-693, PR-819,
PR-872, PR-140, PR-854, PR-808, PR-769, PR-667, PR-677North $ 4,332,000.00
AC-000322Abriendo caminos Ronda 3 - PR-772, PR-703, PR-452, PR-7752, PR-375, PR-3372, PR-3336, PR-5141, PR-557, PR-512, PR-386,
PR-5520South $ 4,541,000.00
AC-000323Abriendo caminos Ronda 3 - PR-109, PR-117, PR-120, PR-414,
PR-434, PR-343, PR-365, PR-317West $ 4,835,500.00
AC-000324Abriendo Caminos Ronda 3 - PR-634, PR-622, PR-8809, PR-531,
PR-129, PR-647, PR-487North $ 6,297,550.00
AC-000326Abriendo caminos Ronda 3 - PR-492, PR-8809, PR-681, PR-134,
PR-622, PR685, PR-621, PR635, PR-531, PR-129, PR-647, PR-656, PR-487, PR-134
North $ 6,027,750.00
25
AC Code Description Region Estimate from Engineer
AC-000814Highway Safety Improvements of PR-8 from km. 0.00
to km. 4.6, San JuanMetro $ 4,819,491.09
AC-005384
Pavement Rehabilitation and Reconstruction of PR-53 from km. 86.863 to km. 94.0 Fase II, Guayama-
SalinasSouth $ 16,767,480.70
AC-005386
Pavement Rehabilitation and Reconstruction of PR-53 form km. 81.0 to km. 86.862 Fase 1, Guayama-
SalinasSouth $ 11,635,425.15
AC-010166Construction of Recreational Trail for Bycicles and Pedestrians from Río Bayamón to PR-165, Toa Baja
North $ 4,508,477.80
AC-010266 Bridge 1096 Replacement West $ 5,643,692.00
AC-012331Pavement Rehabilitation and Reconstruction of PR-
123 from Km. 38.0 to Km. 48.0, UtutadoNorth $ 3,307,429.81
AC-017630Highway Safety Improvements of PR-176 from Km.
0.0 to Km. 4.0, San JuanMetro $ 4,834,516.05
AC-018348Highway Safety Improvements of PR-183 from km 1.2
to km 10.0, Caguas-San LorenzoEast $ 8,050,000.00
AC-018932Pavement Rehabilitation and Reconstruction of PR-
189 from km. 0.0 to km. 13.0, Caguas-Gurabo-JuncosEast $ 5,327,324.12
AC-020311Highway Safety Improvements of PR-203 from km 0.0
to km 7.1, Gurabo-San LorenzoEast $ 10,120,000.00
26
AC Code Description Region Estimate from Engineer
AC-200309Traffic signal at intersection of PR-2 and PR-419,
AguadaWest $ 700,000.00
AC-200310Traffic signal at intersection of PR-2 and PR-650,
AreciboNorth $ 435,000.00
ER – Lighting Improvements (PR-52, PR-18, PR-26, PR-53, PR-30) - $21MM
Signage and Safety (PR-53, PR-54, PR-18, PR-26) - $8MM
Minor Landslides / Karen Storm WTBPs - $7.5MM
January 2020 Earthquake Emergency Repairs WTBPs - $8MM
HTA successfully implemented safety procedures toadequately start inspection and material testing work.
HTA has implemented the expeditious approval of timeextensions of 56 days for every project bringing the projectsto the Pre-Covid-19 situation. Contract amendments ongoing.
27