hkn asarco stack report

Upload: jimhtolbert434

Post on 04-Apr-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/30/2019 HKN ASARCO Stack Report

    1/46

    1

    Save The El Pa

    828 Concrete

    Octobe

    Save The StacksEl Paso, TX

    Asarco 828 Concrete Stack

  • 7/30/2019 HKN ASARCO Stack Report

    2/46

    2

    Save The El Pa

    828 Concrete

    Octobe

    October 19, 2012

    Geoffrey Wright

    Save The Stacks2112 Murchison DriveEl Paso, TX 79930

    Asarco 828 Concrete Stack

    Mr. Wright,

    Thank you for your cooperation during the performance of this inspection project. Included you will findthe Inspection Report, containing labeled photographs and recommendations for themaintenance of the Stack. It was a pleasure to work with you on this project. If you need anyfurther assistance, please do not hesitate to call.

    Sincerely,

    John Susong

  • 7/30/2019 HKN ASARCO Stack Report

    3/46

    3

    Save The El Pa

    828 Concrete

    Octobe

    TABLE OF CONTENTS

    SECTION I EXECUTIVE SUMMARY

    SECTION II INTRODUCTION

    SECTION III STACK DESCRIPTIONS

    SECTION IV INSPECTION PROCEDURES

    SECTION V STACK EXTERIOR INSPECTION

    SECTION VI STACK ANNULUS INSPECTION

    SECTION VII CONCLUSIONS

    SECTION VIII RECOMMENDATIONS

  • 7/30/2019 HKN ASARCO Stack Report

    4/46

    4

    Save The El Pa

    828 Concrete

    Octobe

    SECTION IExecutive Summary

    In accordance with the Save The Stacks purchase order, Industrial Access, Inc. performed acondition assessment of thereinforced concrete column (windscreen) and reinforced concreteliner.

    Activities included reviewing pertinent documents, photographing anomalies, examination ofthe exterior concrete chimney along with the interior annulus space and concrete liner.Furthermore, the examination of the chimneys structural and mechanical equipmentcomponents, accessories and appurtenances were also completed.

    Evaluation of the significance of any detected degradation, deterioration, malfunction ordamage to the stacks, and their associated equipment systems, appurtenances or accessoriesand mechanical integrity were all completed within the inspection scope.

    At this time we believe the chimney stack to be both structurally and mechanically sound. Thatis to say, it is able to perform its intended function of exhausting combustion byproducts me-

    chanically and maintain its current configuration structurally for the foreseeable future barringacts of God type events outside of its original design parameters. There are, however, repairsthat need to be made in order to maintain the above status.

    With the above statement in mind, the recommendations outlined in Section IX-Recommendations of this report should be addressed to acquire and insure the maximumpotential service life of the chimney stack as a structure.

  • 7/30/2019 HKN ASARCO Stack Report

    5/46

    5

    Save The El Pa

    828 Concrete

    Octobe

    SECTION IIIntroduction

    Industrial Access, Inc. was retained by Save The Stacks, LLC to conduct a mechanical condi-tion assessment of the Asarco 828 Smelter Stack at El Paso, TX. A comprehensive exteriorand interior inspection was performed at that time.

    Based on the inspection findings, recommendations for repairs are mentioned and assigned acorrective action factor. The Action Items (AI) are classified into six (6) factors.

    1A- Immediate concern or significant structural deficiency with imminent potential for lossof life, personal injury or structural failure of significance (potential forced outage).

    1B- Immediate safety concern or significant non-structural deficiency with future potentialfor loss of life or personal injury.

    2A- An examination scheduled as per the procedure guideline or sooner basedrecommendations made by plant observations or examinations.

    2B- Moderate structural or non-structural deficiency which does not pose imminent potentialfor loss of life or structural collapse, but whose condition should either be corrected inthe near future or be closely monitored in the future for evidence of furtherdeterioration.

    3A- Minor structural or non-structural deficiency which does not pose any threat to loss oflife or structural integrity. Functional defiance which may affect the structureperformance. Repairs are intended for better operation, maintenance. This priority willalso be used for identifying scheduled inspections.

    3B- Non-structural deficiency which does not pose any threat to loss of life or structuralintegrity. Repairs are intended for better appearance.

    Members of the Industrial Access Inspection Site Team were:

    John Susong Project MangerBob Rielly Rope TechTommy Henderson Rope TechJohn Powell Rope TechVince Humble Robe Tech

    This report presents our observations and together with our findings, conclusions,photographs, rehabilitation recommendations accompanied with recommended materialspecifications and pertinent publications.

  • 7/30/2019 HKN ASARCO Stack Report

    6/46

    6

    Save The El Pa

    828 Concrete

    Octobe

    SECTION IIIStack Descriptions

    Reinforced Concrete Column with Concrete Liner Constructed in 1966Wind load design 100MPH

    Construction: 828 Concrete Reinforced Column 62 6od. Wall thickness at BOS 36TOS 9

    Liner: 828 Concrete Reinforced Liner 200. Wall thickness BOS 36 TOS 10

    Test Ports: Multiple Ports accessible @ 360 Personnel Platforms (3)

    Platforms: (3) Full circumference platforms @ 800, 650, & 500 elevations.

    LPS: Two Down-Lead System Grounding Stack. Air Terminals Mounted@ top of Concrete Stack

    AWL: Triple Tier, Low Intensity Full Time Intermittent System @ 810 590AGL and Midpoint Platform

    Ladder Irons: Steel Rungs with Safety Cage extending to the top segment of theConcrete Stack

    Access Doors: 3x7 Door Accessible @ Base of Stack

    Breeching: 2

  • 7/30/2019 HKN ASARCO Stack Report

    7/46

    7

    Save The El Pa

    828 Concrete

    Octobe

    SECTION IVInspection Procedures

    Upon arrival of our crew and equipment on the job site, personnel, ladders, scaffolding andsafety devices, all in strict accordance with OSHA and SPRAT safety regulations, were in-stalled to carry out the work.

    The owner furnished 120 volts of power adjacent to the chimney termination for IndustrialAccess use.

    After the inspection was completed, our crew removed all debris from the area and disposed ofthe remains at an authorized dumpsite, leaving the site in an As Found or better condition.

    Exterior Inspection

    Industrial Access utilized rope access techniques to give access throughout the exterior of theconcrete column (windscreen). Our crew performed an exterior visual inspection of the Stack.This inspection examined the surface for cracks, corrosion and other anomalies. During theexterior inspection the test ports, walkways, access plates, etc. were also examined.

    Photographs and documentation were taken at different locations depicting the conditionsfound.

    Annulus Inspection

    Industrial Access utilized rope access techniques to give access throughout the Annulus of theconcrete column and liner. Our crew performed an extensive Annulus visual inspection of theStack. This inspection examined the surfaces for cracks, corrosion and other anomalies. Dur-ing the Annulus inspection the test ports, walkways, access plates, etc. were also examined.

    Photographs and documentation were taken at different locations depicting the conditionsfound.

    All recommendations can be found in Section IX-Recommendations of this inspection report.

  • 7/30/2019 HKN ASARCO Stack Report

    8/46

    8

    Save The El Pa

    828 Concrete

    Octobe

    SECTION VStack Exterior Inspection

    Exterior

    Pictures are of the North, East, South, and West bearings of the exterior stack with elevations

    listed below. The pictures are meant to be a visual sample of the stack at the given elevationand directional. The exterior inspection was done at 20ft intervals beginning at elevation 810ftAGL and ending at elevation 0ft. External Cracking and Spalling of the concrete shell wasfound in the upper 30 at TOS. Corrosion of rebar was not found to be evident at this time.

    North East South West

    810 Elevation

    800 Elevation

    780 Elevation

    760 Elevation

  • 7/30/2019 HKN ASARCO Stack Report

    9/46

    9

    Save The El Pa

    828 Concrete

    Octobe

    SECTION VStack Exterior Inspection

    North East South West

    740 Elevation

    720 Elevation

    700 Elevation

    680 Elevation

    660 Elevation

  • 7/30/2019 HKN ASARCO Stack Report

    10/46

    10

    Save The El Pa

    828 Concrete

    Octobe

    SECTION VStack Exterior Inspection

    North East South West

    640 Elevation

    620 Elevation

    600 Elevation

    580 Elevation

    560 Elevation

  • 7/30/2019 HKN ASARCO Stack Report

    11/46

  • 7/30/2019 HKN ASARCO Stack Report

    12/46

    12

    Save The El Pa

    828 Concrete

    Octobe

    SECTION VStack Exterior Inspection

    North East South West

    440 Elevation

    420 Elevation

    400 Elevation

    380 Elevation

    360 Elevation

  • 7/30/2019 HKN ASARCO Stack Report

    13/46

    13

    Save The El Pa

    828 Concrete

    Octobe

    SECTION VStack Exterior Inspection

    North East South West

    340 Elevation

    320 Elevation

    300 Elevation

    280 Elevation

    260 Elevation

  • 7/30/2019 HKN ASARCO Stack Report

    14/46

    14

    Save The El Pa

    828 Concrete

    Octobe

    SECTION VStack Exterior Inspection

    North East South West

    240 Elevation

    220 Elevation

    200 Elevation

    180 Elevation

    160 Elevation

  • 7/30/2019 HKN ASARCO Stack Report

    15/46

  • 7/30/2019 HKN ASARCO Stack Report

    16/46

    16

    Save The El Pa

    828 Concrete

    Octobe

    SECTION VStack Exterior Inspection

    North East South West

    40 Elevation

    20 Elevation

  • 7/30/2019 HKN ASARCO Stack Report

    17/46

    17

    Save The El Pa

    828 Concrete

    Octobe

    SECTION VStack Exterior Inspection

    Ladder System

    The Ladder System is a Steel Rung Ladder with a Safety Climb Cage. The Ladder begins at the

    40 el mark and is continuous to the Stacks Cap. The Ladder System was inspected by our team for

    any damage, cracking, and anomalies associated with. Photographs below are presented with elevation

    markers of the Ladder System.

    Ladder System extending to the Cap Oxidation and Corrosion Heavily Present

    790

    770 Exposed Structural Rebar

  • 7/30/2019 HKN ASARCO Stack Report

    18/46

  • 7/30/2019 HKN ASARCO Stack Report

    19/46

    19

    Save The El Pa

    828 Concrete

    Octobe

    SECTION VStack Exterior Inspection

    Ladder System

    670 Surface Cracks

    660 Minor spalling and surface cracks

    630

    610

  • 7/30/2019 HKN ASARCO Stack Report

    20/46

    20

    Save The El Pa

    828 Concrete

    Octobe

    SECTION VStack Exterior Inspection

    Ladder System

    590

    570

    550

    530 Structural Bolts/Hardware need coating

  • 7/30/2019 HKN ASARCO Stack Report

    21/46

    21

    Save The El Pa

    828 Concrete

    Octobe

    Exterior Conclusions

    Schmidt Hammer Testing Results of the Exterior Concrete Stack are documented below.

    Elevation (ft) North (psi) East (psi) South (psi) West (psi)

    810 4500 4300 4200 4100

    800 4500 4500 4600 4500

    780 4400 4600 4400 4600

    760 4400 4200 4400 4600

    740 4400 4600 4000 4200

    720 4400 4600 4400 4000

    700 4600 4200 4000 4200

    680 4600 4400 4000 4200

    660 4900 4600 3800 4000

    640 4600 4900 4000 4200

    620 4600 4000 4000 3800

    600 5000 4800 4400 4200

    580 4600 5000 4000 3600

    560 4200 4400 4000 4000

    540 4800 5000 3800 4200

    520 4800 4800 4200 4000

    500 4100 4200 4400 4400

    480 4800 4800 3800 4000

    460 4600 4400 4200 4000

    440 4800 4600 4000 3800

    420 4200 4600 4600 4400

  • 7/30/2019 HKN ASARCO Stack Report

    22/46

    22

    Save The El Pa

    828 Concrete

    Octobe

    Elevation (ft) North (psi) East (psi) South (psi) West (psi)

    400 4600 4800 4200 4500

    380 4600 4600 4400 4200

    360 4800 4600 4200 4000

    340 4800 5000 4000 4200

    320 4600 4800 4400 4200

    300 4600 4400 4200 4400

    280 4400 4400 4000 4500

    260 5000 4600 4400 4500

    240 4800 4800 4200 4400

    220 4900 4600 4000 4200

    200 4600 4800 4400 4600

    180 4800 4600 4600 4400

    160 4600 4400 4200 4000

    140 4800 4800 3800 3800

    120 4400 4800 4400 4500

    100 5000 4400 4200 4000

    80 4600 4800 4400 4800

    60 4600 4800 4200 4600

    40 4000 4400 3800 4600

    20 4400 5000 4000 4200

    Exterior Conclusions

    Schmidt Hammer Testing Results (continued)

  • 7/30/2019 HKN ASARCO Stack Report

    23/46

  • 7/30/2019 HKN ASARCO Stack Report

    24/46

    24

    Save The El Pa

    828 Concrete

    Octobe

    SECTION VStack Exterior Inspection

    Ladder System

    400 Needs Coating

    380

    360

  • 7/30/2019 HKN ASARCO Stack Report

    25/46

    25

    Save The El Pa

    828 Concrete

    Octobe

    SECTION VStack Exterior Inspection

    Ladder System

    340

    320

    300 Missing Structural Bolts

  • 7/30/2019 HKN ASARCO Stack Report

    26/46

    26

    Save The El Pa

    828 Concrete

    Octobe

    SECTION VStack Exterior Inspection

    Ladder System

    280

    260

    240

    220 Loose Structural Bolts

  • 7/30/2019 HKN ASARCO Stack Report

    27/46

    27

    Save The El Pa

    828 Concrete

    Octobe

    SECTION VStack Exterior Inspection

    Ladder System

    200 Loose Structural Bolts

    160

    160 Oxidation Present

    140

  • 7/30/2019 HKN ASARCO Stack Report

    28/46

  • 7/30/2019 HKN ASARCO Stack Report

    29/46

    29

    Save The El Pa

    828 Concrete

    Octobe

    SECTION VStack Exterior Inspection

    Ladder System

    40 Ladder System Terminates

    Missing lower 40 of ladder system and cage

    Aviation Warning Light (AWL) System

    AWL Located at the 500 el. Personnel Platform

  • 7/30/2019 HKN ASARCO Stack Report

    30/46

    30

    Save The El Pa

    828 Concrete

    Octobe

    SECTION VStack Exterior Inspection

    Aviation Warning Light (AWL) System

    Mid point Marker Lights located at the 650 el. Personnel Platform

  • 7/30/2019 HKN ASARCO Stack Report

    31/46

  • 7/30/2019 HKN ASARCO Stack Report

    32/46

    32

    Save The El Pa

    828 Concrete

    Octobe

    SECTION VStack Exterior Inspection

    Personnel Platforms & Structural Supports

    650 Personnel Platform Needs Coating

    500 Personnel Platform

  • 7/30/2019 HKN ASARCO Stack Report

    33/46

    33

    Save The El Pa

    828 Concrete

    Octobe

    SECTION VStack Exterior Inspection

    Personnel Platforms & Structural Supports

    800 Structural Supports of Personnel Platform

    650 Structural Supports of Personnel Platform

    500 Structural Supports of Personnel Platform

  • 7/30/2019 HKN ASARCO Stack Report

    34/46

    34

    Save The El Pa

    828 Concrete

    Octobe

    SECTION VStack Exterior Inspection

    Personnel Platforms & Structural Supports

    420 Rest Platform /Oxidation Present

    200 Rest Platform

  • 7/30/2019 HKN ASARCO Stack Report

    35/46

    35

    Save The El Pa

    828 Concrete

    Octobe

    SECTION VStack Exterior Inspection

    Lightning Protection (LPS) System

    LPS surrounding the Cap of the Stack with Lightning Rods

    Cap is in very poor condition. Many loose and missing pieces.Needs to be removed ASAP for safety reasons.

  • 7/30/2019 HKN ASARCO Stack Report

    36/46

    36

    Save The El Pa

    828 Concrete

    Octobe

    SECTION VStack Exterior Inspection

    Lightning Protection (LPS) System

    LPS Grounding Connections

    CAP

    Cap is Covered in Oxidation and Heavy Corrosion. Sections have been removed.

  • 7/30/2019 HKN ASARCO Stack Report

    37/46

    37

    Save The El Pa

    828 Concrete

    Octobe

    SECTION VStack Exterior Inspection

    Cap

    The Cap is completely covered in Oxidation and Corrosion. Cap is a complete Loss.

  • 7/30/2019 HKN ASARCO Stack Report

    38/46

    38

    Save The El Pa

    828 Concrete

    Octobe

    SECTION VStack Exterior Inspection

    Test Ports

    Test Ports Accessible via Personnel Platforms

  • 7/30/2019 HKN ASARCO Stack Report

    39/46

    39

    Save The El Pa

    828 Concrete

    Octobe

    SECTION VIStack Annulus Inspection

    Annulus

    The following documentation was collected in the Annulus of the Stack. Industrial Access util-ized Rope Access Techniques to Inspect the current condition of the Inner Wind Screen andouter Liner. The entire height of the Stack was documented from the Cap to the Base.

    800 Elevation

    750 Elevation

    700 Elevation

  • 7/30/2019 HKN ASARCO Stack Report

    40/46

  • 7/30/2019 HKN ASARCO Stack Report

    41/46

    41

    Save The El Pa

    828 Concrete

    Octobe

    SECTION VIStack Annulus Inspection

    Annulus

    500 Elevation

    450 Elevation

    400 Elevation

  • 7/30/2019 HKN ASARCO Stack Report

    42/46

    42

    Save The El Pa

    828 Concrete

    Octobe

    SECTION VIStack Annulus Inspection

    Annulus

    350 Elevation

    300 Elevation

    250 Elevation

  • 7/30/2019 HKN ASARCO Stack Report

    43/46

  • 7/30/2019 HKN ASARCO Stack Report

    44/46

  • 7/30/2019 HKN ASARCO Stack Report

    45/46

    45

    Save The El Pa

    828 Concrete

    Octobe

    Section VIIConclusions

    Annulus Conclusions

    Upon completion of the Annulus Inspection, Industrial Access has found the Annulus Space of

    the Concrete Stack to be in Very Good. Taking into consideration the age of the Stack, the amount of

    Spalling in the Annulus Space is minimal. There was no indication that there was any leaking flue gas

    into the Annulus Space from the Chimney Liner. At this time there are no immediate concerns associ-

    ated with the Annulus Space. No thermal cracks were found in the liner,

  • 7/30/2019 HKN ASARCO Stack Report

    46/46

    Save The El Pa

    828 Concrete

    Octobe

    Section VIIIRecommendations

    Based on the Inspections findings, the following recommendations for the maintenance and re-

    pair of the 828 Concrete Stack are submitted. Please see Section II forAction Item (IA) Classifica-

    tions.

    Exterior:

    (1A) Remove existing Cap and Structural Steel

    Install New Custom Cap

    (1B) Replace Sections of LPS that are Heavily corroded or broken.

    (2A) Tool Clean Ladder System

    Replace & Repair Damaged Sections of the Ladder System and Anchor Points

    Apply Tnemec Primer and 2 Coats of Tnemec Coating to Ladder System

    (2B) Strip and Tool Clean Exterior Concrete WindScreen

    Hydroblast Concrete WindscreenInject Concrete Epoxy to Cracking and Spalling sections as needed

    Apply Tnemec Primer and 2 Coats of Tnemec Coating to Concrete Windscreen

    (2B) Tool Clean Personnel Platforms and Safety Rails

    Apply Tnemec Primer and 2 Coats of Tnemec Coating to Steel Structures

    (2B) Repair/Replace AWS Electrical Conduit and Wiring in Damaged areas of Corrosion

    (3A) Lower interior liner to level of outside wind screen

    (3A) Prepare and Carbon fiber Wrap top 40 of stack

    These recommendations should be addressed in a timely manner to avoid further loss of structural integ-

    rity and mitigate Immediate Safety Hazards.