hkn asarco stack report
TRANSCRIPT
-
7/30/2019 HKN ASARCO Stack Report
1/46
1
Save The El Pa
828 Concrete
Octobe
Save The StacksEl Paso, TX
Asarco 828 Concrete Stack
-
7/30/2019 HKN ASARCO Stack Report
2/46
2
Save The El Pa
828 Concrete
Octobe
October 19, 2012
Geoffrey Wright
Save The Stacks2112 Murchison DriveEl Paso, TX 79930
Asarco 828 Concrete Stack
Mr. Wright,
Thank you for your cooperation during the performance of this inspection project. Included you will findthe Inspection Report, containing labeled photographs and recommendations for themaintenance of the Stack. It was a pleasure to work with you on this project. If you need anyfurther assistance, please do not hesitate to call.
Sincerely,
John Susong
-
7/30/2019 HKN ASARCO Stack Report
3/46
3
Save The El Pa
828 Concrete
Octobe
TABLE OF CONTENTS
SECTION I EXECUTIVE SUMMARY
SECTION II INTRODUCTION
SECTION III STACK DESCRIPTIONS
SECTION IV INSPECTION PROCEDURES
SECTION V STACK EXTERIOR INSPECTION
SECTION VI STACK ANNULUS INSPECTION
SECTION VII CONCLUSIONS
SECTION VIII RECOMMENDATIONS
-
7/30/2019 HKN ASARCO Stack Report
4/46
4
Save The El Pa
828 Concrete
Octobe
SECTION IExecutive Summary
In accordance with the Save The Stacks purchase order, Industrial Access, Inc. performed acondition assessment of thereinforced concrete column (windscreen) and reinforced concreteliner.
Activities included reviewing pertinent documents, photographing anomalies, examination ofthe exterior concrete chimney along with the interior annulus space and concrete liner.Furthermore, the examination of the chimneys structural and mechanical equipmentcomponents, accessories and appurtenances were also completed.
Evaluation of the significance of any detected degradation, deterioration, malfunction ordamage to the stacks, and their associated equipment systems, appurtenances or accessoriesand mechanical integrity were all completed within the inspection scope.
At this time we believe the chimney stack to be both structurally and mechanically sound. Thatis to say, it is able to perform its intended function of exhausting combustion byproducts me-
chanically and maintain its current configuration structurally for the foreseeable future barringacts of God type events outside of its original design parameters. There are, however, repairsthat need to be made in order to maintain the above status.
With the above statement in mind, the recommendations outlined in Section IX-Recommendations of this report should be addressed to acquire and insure the maximumpotential service life of the chimney stack as a structure.
-
7/30/2019 HKN ASARCO Stack Report
5/46
5
Save The El Pa
828 Concrete
Octobe
SECTION IIIntroduction
Industrial Access, Inc. was retained by Save The Stacks, LLC to conduct a mechanical condi-tion assessment of the Asarco 828 Smelter Stack at El Paso, TX. A comprehensive exteriorand interior inspection was performed at that time.
Based on the inspection findings, recommendations for repairs are mentioned and assigned acorrective action factor. The Action Items (AI) are classified into six (6) factors.
1A- Immediate concern or significant structural deficiency with imminent potential for lossof life, personal injury or structural failure of significance (potential forced outage).
1B- Immediate safety concern or significant non-structural deficiency with future potentialfor loss of life or personal injury.
2A- An examination scheduled as per the procedure guideline or sooner basedrecommendations made by plant observations or examinations.
2B- Moderate structural or non-structural deficiency which does not pose imminent potentialfor loss of life or structural collapse, but whose condition should either be corrected inthe near future or be closely monitored in the future for evidence of furtherdeterioration.
3A- Minor structural or non-structural deficiency which does not pose any threat to loss oflife or structural integrity. Functional defiance which may affect the structureperformance. Repairs are intended for better operation, maintenance. This priority willalso be used for identifying scheduled inspections.
3B- Non-structural deficiency which does not pose any threat to loss of life or structuralintegrity. Repairs are intended for better appearance.
Members of the Industrial Access Inspection Site Team were:
John Susong Project MangerBob Rielly Rope TechTommy Henderson Rope TechJohn Powell Rope TechVince Humble Robe Tech
This report presents our observations and together with our findings, conclusions,photographs, rehabilitation recommendations accompanied with recommended materialspecifications and pertinent publications.
-
7/30/2019 HKN ASARCO Stack Report
6/46
6
Save The El Pa
828 Concrete
Octobe
SECTION IIIStack Descriptions
Reinforced Concrete Column with Concrete Liner Constructed in 1966Wind load design 100MPH
Construction: 828 Concrete Reinforced Column 62 6od. Wall thickness at BOS 36TOS 9
Liner: 828 Concrete Reinforced Liner 200. Wall thickness BOS 36 TOS 10
Test Ports: Multiple Ports accessible @ 360 Personnel Platforms (3)
Platforms: (3) Full circumference platforms @ 800, 650, & 500 elevations.
LPS: Two Down-Lead System Grounding Stack. Air Terminals Mounted@ top of Concrete Stack
AWL: Triple Tier, Low Intensity Full Time Intermittent System @ 810 590AGL and Midpoint Platform
Ladder Irons: Steel Rungs with Safety Cage extending to the top segment of theConcrete Stack
Access Doors: 3x7 Door Accessible @ Base of Stack
Breeching: 2
-
7/30/2019 HKN ASARCO Stack Report
7/46
7
Save The El Pa
828 Concrete
Octobe
SECTION IVInspection Procedures
Upon arrival of our crew and equipment on the job site, personnel, ladders, scaffolding andsafety devices, all in strict accordance with OSHA and SPRAT safety regulations, were in-stalled to carry out the work.
The owner furnished 120 volts of power adjacent to the chimney termination for IndustrialAccess use.
After the inspection was completed, our crew removed all debris from the area and disposed ofthe remains at an authorized dumpsite, leaving the site in an As Found or better condition.
Exterior Inspection
Industrial Access utilized rope access techniques to give access throughout the exterior of theconcrete column (windscreen). Our crew performed an exterior visual inspection of the Stack.This inspection examined the surface for cracks, corrosion and other anomalies. During theexterior inspection the test ports, walkways, access plates, etc. were also examined.
Photographs and documentation were taken at different locations depicting the conditionsfound.
Annulus Inspection
Industrial Access utilized rope access techniques to give access throughout the Annulus of theconcrete column and liner. Our crew performed an extensive Annulus visual inspection of theStack. This inspection examined the surfaces for cracks, corrosion and other anomalies. Dur-ing the Annulus inspection the test ports, walkways, access plates, etc. were also examined.
Photographs and documentation were taken at different locations depicting the conditionsfound.
All recommendations can be found in Section IX-Recommendations of this inspection report.
-
7/30/2019 HKN ASARCO Stack Report
8/46
8
Save The El Pa
828 Concrete
Octobe
SECTION VStack Exterior Inspection
Exterior
Pictures are of the North, East, South, and West bearings of the exterior stack with elevations
listed below. The pictures are meant to be a visual sample of the stack at the given elevationand directional. The exterior inspection was done at 20ft intervals beginning at elevation 810ftAGL and ending at elevation 0ft. External Cracking and Spalling of the concrete shell wasfound in the upper 30 at TOS. Corrosion of rebar was not found to be evident at this time.
North East South West
810 Elevation
800 Elevation
780 Elevation
760 Elevation
-
7/30/2019 HKN ASARCO Stack Report
9/46
9
Save The El Pa
828 Concrete
Octobe
SECTION VStack Exterior Inspection
North East South West
740 Elevation
720 Elevation
700 Elevation
680 Elevation
660 Elevation
-
7/30/2019 HKN ASARCO Stack Report
10/46
10
Save The El Pa
828 Concrete
Octobe
SECTION VStack Exterior Inspection
North East South West
640 Elevation
620 Elevation
600 Elevation
580 Elevation
560 Elevation
-
7/30/2019 HKN ASARCO Stack Report
11/46
-
7/30/2019 HKN ASARCO Stack Report
12/46
12
Save The El Pa
828 Concrete
Octobe
SECTION VStack Exterior Inspection
North East South West
440 Elevation
420 Elevation
400 Elevation
380 Elevation
360 Elevation
-
7/30/2019 HKN ASARCO Stack Report
13/46
13
Save The El Pa
828 Concrete
Octobe
SECTION VStack Exterior Inspection
North East South West
340 Elevation
320 Elevation
300 Elevation
280 Elevation
260 Elevation
-
7/30/2019 HKN ASARCO Stack Report
14/46
14
Save The El Pa
828 Concrete
Octobe
SECTION VStack Exterior Inspection
North East South West
240 Elevation
220 Elevation
200 Elevation
180 Elevation
160 Elevation
-
7/30/2019 HKN ASARCO Stack Report
15/46
-
7/30/2019 HKN ASARCO Stack Report
16/46
16
Save The El Pa
828 Concrete
Octobe
SECTION VStack Exterior Inspection
North East South West
40 Elevation
20 Elevation
-
7/30/2019 HKN ASARCO Stack Report
17/46
17
Save The El Pa
828 Concrete
Octobe
SECTION VStack Exterior Inspection
Ladder System
The Ladder System is a Steel Rung Ladder with a Safety Climb Cage. The Ladder begins at the
40 el mark and is continuous to the Stacks Cap. The Ladder System was inspected by our team for
any damage, cracking, and anomalies associated with. Photographs below are presented with elevation
markers of the Ladder System.
Ladder System extending to the Cap Oxidation and Corrosion Heavily Present
790
770 Exposed Structural Rebar
-
7/30/2019 HKN ASARCO Stack Report
18/46
-
7/30/2019 HKN ASARCO Stack Report
19/46
19
Save The El Pa
828 Concrete
Octobe
SECTION VStack Exterior Inspection
Ladder System
670 Surface Cracks
660 Minor spalling and surface cracks
630
610
-
7/30/2019 HKN ASARCO Stack Report
20/46
20
Save The El Pa
828 Concrete
Octobe
SECTION VStack Exterior Inspection
Ladder System
590
570
550
530 Structural Bolts/Hardware need coating
-
7/30/2019 HKN ASARCO Stack Report
21/46
21
Save The El Pa
828 Concrete
Octobe
Exterior Conclusions
Schmidt Hammer Testing Results of the Exterior Concrete Stack are documented below.
Elevation (ft) North (psi) East (psi) South (psi) West (psi)
810 4500 4300 4200 4100
800 4500 4500 4600 4500
780 4400 4600 4400 4600
760 4400 4200 4400 4600
740 4400 4600 4000 4200
720 4400 4600 4400 4000
700 4600 4200 4000 4200
680 4600 4400 4000 4200
660 4900 4600 3800 4000
640 4600 4900 4000 4200
620 4600 4000 4000 3800
600 5000 4800 4400 4200
580 4600 5000 4000 3600
560 4200 4400 4000 4000
540 4800 5000 3800 4200
520 4800 4800 4200 4000
500 4100 4200 4400 4400
480 4800 4800 3800 4000
460 4600 4400 4200 4000
440 4800 4600 4000 3800
420 4200 4600 4600 4400
-
7/30/2019 HKN ASARCO Stack Report
22/46
22
Save The El Pa
828 Concrete
Octobe
Elevation (ft) North (psi) East (psi) South (psi) West (psi)
400 4600 4800 4200 4500
380 4600 4600 4400 4200
360 4800 4600 4200 4000
340 4800 5000 4000 4200
320 4600 4800 4400 4200
300 4600 4400 4200 4400
280 4400 4400 4000 4500
260 5000 4600 4400 4500
240 4800 4800 4200 4400
220 4900 4600 4000 4200
200 4600 4800 4400 4600
180 4800 4600 4600 4400
160 4600 4400 4200 4000
140 4800 4800 3800 3800
120 4400 4800 4400 4500
100 5000 4400 4200 4000
80 4600 4800 4400 4800
60 4600 4800 4200 4600
40 4000 4400 3800 4600
20 4400 5000 4000 4200
Exterior Conclusions
Schmidt Hammer Testing Results (continued)
-
7/30/2019 HKN ASARCO Stack Report
23/46
-
7/30/2019 HKN ASARCO Stack Report
24/46
24
Save The El Pa
828 Concrete
Octobe
SECTION VStack Exterior Inspection
Ladder System
400 Needs Coating
380
360
-
7/30/2019 HKN ASARCO Stack Report
25/46
25
Save The El Pa
828 Concrete
Octobe
SECTION VStack Exterior Inspection
Ladder System
340
320
300 Missing Structural Bolts
-
7/30/2019 HKN ASARCO Stack Report
26/46
26
Save The El Pa
828 Concrete
Octobe
SECTION VStack Exterior Inspection
Ladder System
280
260
240
220 Loose Structural Bolts
-
7/30/2019 HKN ASARCO Stack Report
27/46
27
Save The El Pa
828 Concrete
Octobe
SECTION VStack Exterior Inspection
Ladder System
200 Loose Structural Bolts
160
160 Oxidation Present
140
-
7/30/2019 HKN ASARCO Stack Report
28/46
-
7/30/2019 HKN ASARCO Stack Report
29/46
29
Save The El Pa
828 Concrete
Octobe
SECTION VStack Exterior Inspection
Ladder System
40 Ladder System Terminates
Missing lower 40 of ladder system and cage
Aviation Warning Light (AWL) System
AWL Located at the 500 el. Personnel Platform
-
7/30/2019 HKN ASARCO Stack Report
30/46
30
Save The El Pa
828 Concrete
Octobe
SECTION VStack Exterior Inspection
Aviation Warning Light (AWL) System
Mid point Marker Lights located at the 650 el. Personnel Platform
-
7/30/2019 HKN ASARCO Stack Report
31/46
-
7/30/2019 HKN ASARCO Stack Report
32/46
32
Save The El Pa
828 Concrete
Octobe
SECTION VStack Exterior Inspection
Personnel Platforms & Structural Supports
650 Personnel Platform Needs Coating
500 Personnel Platform
-
7/30/2019 HKN ASARCO Stack Report
33/46
33
Save The El Pa
828 Concrete
Octobe
SECTION VStack Exterior Inspection
Personnel Platforms & Structural Supports
800 Structural Supports of Personnel Platform
650 Structural Supports of Personnel Platform
500 Structural Supports of Personnel Platform
-
7/30/2019 HKN ASARCO Stack Report
34/46
34
Save The El Pa
828 Concrete
Octobe
SECTION VStack Exterior Inspection
Personnel Platforms & Structural Supports
420 Rest Platform /Oxidation Present
200 Rest Platform
-
7/30/2019 HKN ASARCO Stack Report
35/46
35
Save The El Pa
828 Concrete
Octobe
SECTION VStack Exterior Inspection
Lightning Protection (LPS) System
LPS surrounding the Cap of the Stack with Lightning Rods
Cap is in very poor condition. Many loose and missing pieces.Needs to be removed ASAP for safety reasons.
-
7/30/2019 HKN ASARCO Stack Report
36/46
36
Save The El Pa
828 Concrete
Octobe
SECTION VStack Exterior Inspection
Lightning Protection (LPS) System
LPS Grounding Connections
CAP
Cap is Covered in Oxidation and Heavy Corrosion. Sections have been removed.
-
7/30/2019 HKN ASARCO Stack Report
37/46
37
Save The El Pa
828 Concrete
Octobe
SECTION VStack Exterior Inspection
Cap
The Cap is completely covered in Oxidation and Corrosion. Cap is a complete Loss.
-
7/30/2019 HKN ASARCO Stack Report
38/46
38
Save The El Pa
828 Concrete
Octobe
SECTION VStack Exterior Inspection
Test Ports
Test Ports Accessible via Personnel Platforms
-
7/30/2019 HKN ASARCO Stack Report
39/46
39
Save The El Pa
828 Concrete
Octobe
SECTION VIStack Annulus Inspection
Annulus
The following documentation was collected in the Annulus of the Stack. Industrial Access util-ized Rope Access Techniques to Inspect the current condition of the Inner Wind Screen andouter Liner. The entire height of the Stack was documented from the Cap to the Base.
800 Elevation
750 Elevation
700 Elevation
-
7/30/2019 HKN ASARCO Stack Report
40/46
-
7/30/2019 HKN ASARCO Stack Report
41/46
41
Save The El Pa
828 Concrete
Octobe
SECTION VIStack Annulus Inspection
Annulus
500 Elevation
450 Elevation
400 Elevation
-
7/30/2019 HKN ASARCO Stack Report
42/46
42
Save The El Pa
828 Concrete
Octobe
SECTION VIStack Annulus Inspection
Annulus
350 Elevation
300 Elevation
250 Elevation
-
7/30/2019 HKN ASARCO Stack Report
43/46
-
7/30/2019 HKN ASARCO Stack Report
44/46
-
7/30/2019 HKN ASARCO Stack Report
45/46
45
Save The El Pa
828 Concrete
Octobe
Section VIIConclusions
Annulus Conclusions
Upon completion of the Annulus Inspection, Industrial Access has found the Annulus Space of
the Concrete Stack to be in Very Good. Taking into consideration the age of the Stack, the amount of
Spalling in the Annulus Space is minimal. There was no indication that there was any leaking flue gas
into the Annulus Space from the Chimney Liner. At this time there are no immediate concerns associ-
ated with the Annulus Space. No thermal cracks were found in the liner,
-
7/30/2019 HKN ASARCO Stack Report
46/46
Save The El Pa
828 Concrete
Octobe
Section VIIIRecommendations
Based on the Inspections findings, the following recommendations for the maintenance and re-
pair of the 828 Concrete Stack are submitted. Please see Section II forAction Item (IA) Classifica-
tions.
Exterior:
(1A) Remove existing Cap and Structural Steel
Install New Custom Cap
(1B) Replace Sections of LPS that are Heavily corroded or broken.
(2A) Tool Clean Ladder System
Replace & Repair Damaged Sections of the Ladder System and Anchor Points
Apply Tnemec Primer and 2 Coats of Tnemec Coating to Ladder System
(2B) Strip and Tool Clean Exterior Concrete WindScreen
Hydroblast Concrete WindscreenInject Concrete Epoxy to Cracking and Spalling sections as needed
Apply Tnemec Primer and 2 Coats of Tnemec Coating to Concrete Windscreen
(2B) Tool Clean Personnel Platforms and Safety Rails
Apply Tnemec Primer and 2 Coats of Tnemec Coating to Steel Structures
(2B) Repair/Replace AWS Electrical Conduit and Wiring in Damaged areas of Corrosion
(3A) Lower interior liner to level of outside wind screen
(3A) Prepare and Carbon fiber Wrap top 40 of stack
These recommendations should be addressed in a timely manner to avoid further loss of structural integ-
rity and mitigate Immediate Safety Hazards.