holy cross energy
TRANSCRIPT
-
8/9/2019 Holy Cross Energy
1/3
Renewable Energy RebatesRenewable Energy Rebates
Consumer-Sited Renewable Energy GenerationConsumer-Sited Renewable Energy Generation within Holy Cros s’s service territorywithin Holy Cros s’s service territory
Holy Cross Energy offers incentives to consumers who install qualifying renewable generation at their homes or businesses.
Eligible systems include those using solar, hydro, biomass, geothermal or wind energy to generate electricity. We will allow
consumers who install generators up to 500 kW for photovoltaic systems or 50 kW for other systems to net meter the
generation against the electric consumption at the same meter.
Any consumer who wishes to install a generator behind their meter must complete and submit a Generator Interconnect
Application to via e-mail to [email protected] or via mail to:
Holy Cross Energy
Attn: Renewables
PO Box 2150
Glenwood Springs, CO 81601
Generator Interconnect Application (Click HERE)
Effective on June 1, 2015 an interconnection study fee of $100 must accompany each interconnection application for systems
with a nameplate capacity of 12-100 kW and $250 for systems with a nameplate capacity greater than 100 kW.
Net meteringNet metering
Holy Cross will provide net metering service to consumers who install eligible generation behind their electric service meter.
Under net metering, the meter will record net generation when the generator is producing more power than is being used on site
and record net usage whenever consumption exceeds production. At the end of the billing month, Holy Cross will carry any
excess generation forward to offset any net consumption on the next month’s bill. This will continue for 12 months, and any
excess power delivered to Holy Cross will be purchased at the average retail rate for each consumer class at the end of May
through 2015. For each following year, excess energy will be purchased at the average cost of purchased power for the previous
year.
Holy Cross will net meter photovoltaic generators up to 500 kW and other generators up to 50 kW. Generators must be
designed to supply no more than 120% of the electrical consumption at a meter over the prior 12 billing months (at the time of
application). If insufficient billing history exists, Holy Cross will estimate usage and specify a maximum allowable system size.
See T ariff Sheet 29 for further details on Holy Cross’ net metering program.
Interconnection RequirementsInterconnection Requirements
All generators designed to operate in parallel with the Holy Cross distribution system for any length of time must provide a
Generator Interconnection Application prior to beginning construction. A Holy Cross engineer review and approval is required for
interconnection for all generators. Information on Holy Cross’ requirements and evaluation process can be found at our
Generator Interconnect Policy page.
http://www.holycross.com/pages/rebates/renewable-energy-rebates/generator-interconnect-policyhttp://localhost/var/www/apps/conversion/tmp/scratch_1/assets/userfiles/files/rebates/HCE_Interconnection_Application_20140102.pdfmailto:[email protected]
-
8/9/2019 Holy Cross Energy
2/3
IncentivesIncentives
Incentives are available to Holy Cross Energy consumers who install and own renewable generation for net metering at their
premises. Current incentive levels are shown below. Incentives may be denied to consumers who proceed with installation of their
systems prior to submitting a Generator Interconnection Application to Holy Cross as described above.
Holy Cross will reserve incentives for 120 days starting on the day the Generator Interconnection Application is deemed
complete. Any installations not completed (including all required documentation) before the reservation expires will lose their
reservation. Any system that has forfeited their reservation may be eligible for an incentive payment based on the incentive
program in effect at the time all requirements are met, subject to the availability of funds.
Payment of any incentive is contingent on the assignment of all rights, title and interest in and associated with all RECs, green
attributes or environmental offsets produced by the system, including the right to use all RECs for compliance with the Colorado
Renewable Energy Standard.
For complete interconnection applications received before the close of business on or before April 30, 2015, the following
incentives are available.
0-6 kW $1,250/kW
6-12 kW $1,000/kW
12-25 kW $500/kW
For example, the incentive for a 15 kW system can be calculated as shown:
6 kW x $1,250/kW = $7,500
12-6 kW x $1,000/kW = $6,000
15-12 kW x $500/kW = $1,500
Total available: $15,000
For applications received on or after May 1, 2015, the following incentives are available on a first-come, first-served basis. The
following incentives will also apply to any open application that is missing required information on May 1, 2015, or any generator
that has not provided all documentation required for system completion, in an acceptable form, by the close of business on
August 30, 2015.
0-6 kW $750/kW
6-12 kW $500/kW
12-25 kW $200/kW
For example, the incentive for a 15 kW system can be calculated as shown:
6 kW x $750/kW = $4,500
12-6 kW x $500/kW = $3,000
15-12 kW x $200/kW = $600
Total available: $8,100
For non-taxable entities, Holy Cross will provide an incentive equal to 40% of the installed cost of a system (on a $ per KW basis)
up to $1,500/kW for the first 25 kW installed at a site. Any eligible consumer must include documentation of their non-profit
status at the time of application and directly own the generator. Any generator leased to a non-profit entity is eligible for
incentives under the tiered structure discussed above.
For example, a 50 kW system owned by a non-taxable organization that cost $3,000/kW to install could expect a rebate of
$30,000 (40% x $3,000/kW x 25 kW).
Systems installed to avoid energy offset fees or for compliance with local or county program or code requirements, such asREMP or Eco-Build, are not eligible to receive an incentive payment. Any generation installed in excess of the requirement is
eligible for incentives as discussed above. Holy Cross will purchase all RECs associated with generation for such facilities and for
facilities owned by third parties and leased to Holy Cross consumers. For complete interconnection applications received before
the close of business on April 30, 2015, the purchase price is $250/kW for the first 25 kW installed at a site. For applications
received after April 30, 2015, the REC purchase price shall be $150/kW for the first 25 kW installed at a site.
-
8/9/2019 Holy Cross Energy
3/3
Program rules & limitationsProgram rules & limitations
The following rules apply to all generation incentives:
Generation must be sized to supply no more than 120% of their previous 12 months electrical consumption. For new
construction, Holy Cross will estimate on-site electrical consumption and specify a maximum allowable system size.
No member may receive more than $50,000 related to the ownership of renewable generation.
Incentive payments will be reduced so that they do not exceed 40% of the installed cost of any project.
No rebates will be paid for any generation capacity in excess of 25 kW at any location, inclusive of ownership of capacity in a
community solar garden.
Incentives are available on a first-come, first-served basis. No payment is guaranteed for expired incentive reservations.
No incentive will be paid without a detailed accounting of the system cost, including for leased systems.Holy Cross will not interconnect any system selling power to a consumer under a Power Purchase Agreement.
Customers must be in good standing on all electric accounts at the date the payment is issued to be eligible for incentive
payments. Good standing means no more than two disqualifying marks (late payments, disconnect for non-pay, etc) on
any electric account in the previous 12 billing months. Customers will lose their eligibility to receive any incentive payment if
they fall out of good standing with Holy Cross.
Consumer’s generation facilities must be connected to Holy Cross’s electric distribution system to qualify for incentives.
Incentive FundingIncentive Funding
Incentives for renewable generation are funded through the WE CARE rider on each Holy Cross consumer's electric bill.
Incentives will be funded at the current level unless a change in funding is announced.
Glenwood Springs: 970-945-5491
Vail Valley: 970-949-5892
Pay-by-Phone: 877-833-2555
Business Hours:
Monday-T hursday: 7:30 AM - 4 :30 PM
Friday: 7:30 AM - 3:30 PM
© 2015 Holy Cross Energy