home improvement project monsters second status report reporting period: feb 15-april 10, 2005...
TRANSCRIPT
HOME HOME IMPROVEMENTIMPROVEMENTProject MonstersProject Monsters
Second Status ReportReporting period: Feb 15-April 10, 2005
Project Manager: Hakki Isik
Team members: Chad Harms
Yilmaz BayazitNazimah Abdul Rahim
Asziliawati Ramli
PROJECT PROJECT DESCRIPTIONDESCRIPTION
• Project justification: Hakki Isik, the project sponsor, was not happy with his living room. He would like to replace the carpet in the living room with hardwood floor. He believes replacing the carpet and painting the walls will make the living room look better.
• Project scope: To do a makeover of the living room at Hakki’s house.
• Cost estimate: $1,500• Time goal: Feb 15 to May 6, 2005
FLOORING FLOORING TYPES TYPES
CONSIDEREDCONSIDERED
LAMINATE LAMINATE FLOORINGFLOORING
HARDWOOD HARDWOOD FLOORINGFLOORING
Cheaper than hardwood
Very high quality
FLOORING TYPES cont’dFLOORING TYPES cont’d
MAPLEMAPLEPrice: Price:
$3.17/sqft$3.17/sqft
RED OAKRED OAKPrice: Price:
$3.17/sqft$3.17/sqft
COLONIAL COLONIAL OAKOAK
Price: $2.99/sqftPrice: $2.99/sqft
REAL MAPLE REAL MAPLE WOODWOOD
Price: $6.49/sqftPrice: $6.49/sqft
LAMINATE FLOORINGLAMINATE FLOORING
HARDWOOD FLOORINGHARDWOOD FLOORING
• Decided to go with the real hardwood flooring – More expensive, but the project sponsor wanted
the living room floor to match the kitchen floor.– Kitchen floor has real maple hardwood floor.
SELECTIONSELECTION
Kitchen Kitchen floorfloor
• Stapling• Gluing• Floating
– Method of choice– Easier
INSTALLATION INSTALLATION METHODSMETHODS
WORK COMPLETEDWORK COMPLETED Walls painted from white to light weight beige
BEFOREBEFORE AFTERAFTER
WORK COMPLETED cont’dWORK COMPLETED cont’d Team website refined
Web screenshotWeb screenshot
Gantt chart updated Hardwood flooring ordered Weekly meeting
established: every Tuesday, 5.00pm @ ME building or after class
Project manager interviews completed
Topic presentation on “Hoover Dam” completed
WORK COMPLETED WORK COMPLETED cont’dcont’d
Decorate walls with pictures
Complete evaluating VPMi software
Prepare for team final presentation and project notebook
Update Gantt chart as the project progresses
WORK TO WORK TO BE COMPLETEDBE COMPLETED
WHAT WENT RIGHT?WHAT WENT RIGHT?
• Great communication among team members
• Team members successfully completed their assigned tasks on time
• Project manager manages the project efficiently
WHAT WENT WRONG?WHAT WENT WRONG?
• Delay of material delivery from Home Depot– Material was scheduled to be
received last week– Delivery date was changed
to the end of this week– Effect on project schedule:
One week behind
• ONE WEEK BEHIND SCHEDULE
• A BIT OVERBUDGET– The initial cost estimate does
not include the small pieces such as the T-molding, hard surface reducer, and carpet transition.
HOW’S OUR PROJECT HOW’S OUR PROJECT DOING?DOING?
LIVING ROOM AREALIVING ROOM AREA