Application of New Engineering
Contract (NEC) –Joy and Tears from a Main Contractor's
Perspective
Contract No. DC/2012/03 Happy Valley Underground Stormwater Storage Scheme
Hong Kong Institute of Construction Managers
1David Tung26 June 2015
2
Project Background
Flooding in Happy Valley– 24.08.2000, 24.04.2006, 07.06.2008
Happy Valley Recreation Ground
Junction between Morrison Hill Road and Queen’s Road East Wong Nai Chung Road Happy Valley Racecourse 3
Project Background
Leighton Rd
Lowest point at Lap Tak Lane +4.1 mPD
Flem
ing Rd
Gloucester Road
mPD Invert level of drain
Legend
Lowest point at WNCR+5.2 mPD
Sea level ranges between 0.00 mPD and 2.50 mPD On 24 Sep 2009, max. sea level for typhoon Hagupit was 3.35mPD
0.26mPD
Upstream
Mid-levels
Downstream
Catchment Area of Hong Kong West Drainage Tunnel (140 hectare)
Catchment Area of Happy Valley Underground Stormwater Storage Tank (130 hectare)
Catchment Area of Lower Catchment Drainage Improvement Works(80 hectare)
4.5mPD
2.00mPD
1.05mPD
0.46mPD
-0.3mPD
0.26mPD
4
5
Happy Valley
Underground Stormwater
Storage Scheme
MidstreamMidstreamMidstreamMidstream
Storage
Lower catchment
works
Hong Kong West
Drainage Tunnel
DownstreamDownstreamDownstreamDownstream UpstreamUpstreamUpstreamUpstream
Replacement Interception
Drainage Improvement Measures
Project Information
6
Employer Drainage Services Department
Supervisor Drainage Services Department
Contractor Chun Wo Construction & Engineering Co. Ltd.
Project Estimate HK$ 678M
Duration Sep 2012 – Apr 2018 (67 months)
NEC3 Option Option C – Target contract with activity schedule
QS consultant Mott MacDonald Hong Kong Limited
NEC Advisor EC Harris / JCP
Capacity:
60,000m3
Project Background
7
Capac
ity:
60,00
0m3
Capac
ity:
60,00
0m3
Scope of Works:• Underground storage tank with capacity of 60,000m 3
• Pumping station with design capacity of 1.5 m 3/s• 2km long stormwater drain and sewer• Reprovision of sport pitches surface and landscape associated works
Project Background
8
9
Challenge
暴雨警告信號暴雨警告信號暴雨警告信號暴雨警告信號
黃雨黃雨黃雨黃雨 紅雨紅雨紅雨紅雨 黑雨黑雨黑雨黑雨
年平均年平均年平均年平均 20 4.5 1
2014年度年度年度年度 32 9 2
Challenge 1: 天天天天
Challenge 2: 地地地地
11
•軟泥軟泥軟泥軟泥, 硬石硬石硬石硬石
Challenge 2: 地地地地
12
•暗暗暗暗渠渠渠渠, 水水水水喉喉喉喉
Challenge 2: 地地地地
13
•電電電電纜纜纜纜
Challenge 2: 地地地地
14
Proposed drainage works
Horizontal pipe pile wall to
retain the soil on top for
protection of existing trees
Challenge 3: 人人人人
15
搶搶搶搶工工工工人人人人搶搶搶搶石石石石屎屎屎屎
Challenge 4: 時間時間時間時間
16
6.6.14 – 19.10.14
Challenge 4: 時間時間時間時間
17
HEC Substation
Oct 2014Nov 201424 Dec 2014
Challenge 4: 時間時間時間時間
18
No. of monthNo. of monthNo. of monthNo. of month 1111 2222 3333 4444 5555 6666 7777 8888 9999 10101010 11111111 12121212 13131313 14141414 15151515 16161616 17171717 18181818 19191919 20202020 21212121 22222222 23232323 24242424 25252525 26262626 27272727 28282828 29292929 30303030 31313131 32323232 33333333 34343434 35353535 36363636 37373737 38383838 39393939 40404040
YearYearYearYear 2012201220122012 2013201320132013 2014201420142014 2015201520152015
MonthMonthMonthMonth 9999 10101010 11111111 12121212 1111 2222 3333 4444 5555 6666 7777 8888 9999 10101010 11111111 12121212 1111 2222 3333 4444 5555 6666 7777 8888 9999 10101010 11111111 12121212 1111 2222 3333 4444 5555 6666 7777 8888 9999 10101010 11111111 12121212
Time elapsed Time elapsed Time elapsed Time elapsed
1st Milestone: Commissioning of Stage 1 Scheme on 03-2015
19
No. of No. of No. of No. of monthmonthmonthmonth
1111 2222 3333 4444 5555 6666 7777 8888 99991010101011111111121212121313131314141414151515151616161611117777
18181818191919192020202021212121222222222323232322224444
25252525262626262727272728282828292929293030303033331111
32323232333333333434343435353535363636363737373733338888
39393939404040404141414142424242434343434444444444445555
46464646474747474848484849494949505050505151515155552222
53535353545454545555555556565656575757575858585855559999
60606060616161616262626263636363646464646565656566666666
67676767686868686969696970707070717171717272727277773333
747474747575757576767676
YearYearYearYear 2012201220122012 2013201320132013 2014201420142014 2015201520152015 2016201620162016 2017201720172017 2018201820182018
MonthMonthMonthMonth 999911110000
1111111112121212 1111 2222 3333 4444 5555 6666 7777 8888 9999101010101111111112121212 1111 2222 3333 4444 5555 6666 7777 8888 9999101010101111111112121212 1111 2222 3333 4444 5555 6666 7777 8888 999911110000
1111111112121212 1111 2222 3333 4444 5555 6666 7777 8888 9999101010101111111111112222
1111 2222 3333 4444 5555 6666 7777 8888 9999101010101111111112121212 1111 2222 3333 4444 5555 6666 7777 8888 9999101010101111111112121212
Time Time Time Time elapsed elapsed elapsed elapsed
二期二期二期二期一期一期一期一期
20
Team Building
Mutual Trust
Co-operation
Cultural Change
Team Building
Relationship Management
• Establish partnering spirit – Start-up partnering workshop– Joint NEC training– Set up joint office
• Maintain and improve– Setup common goal– Champion Group meeting
22
“10.1 – The Employer, the Contractor, the Project Manager and the Supervisor shall act as stated in this contract and in a spirit of mutual trust and co-operation”
Training Programme
Partnering workshop
23
Stakeholder workshop
NEC workshops
September 2012
October 2012
November 2012
March 2013 NEC advisor’s review
December 2012 Extension of NEC pre-contract advisor
April 2013 NEC Computer Software
May 2013 NEC Post-contract advisor
“Know You Know Me” Workshop
24
- Joint office
- Joint organisation chart
- Project Logo
Good Practice
25
26
Subletting
Inventory
Joint Organization
Chart
Morning Briefing
27
• Solve site issue
• EWN
• Focus Group
•Mobile Device
Partnering Scores
28
Time Cost Quality Safety Environmental Public Relation Trust Cooperation
Down Trend(due to increased difficulties on site)
Up Trend(after some success cases)
Champion Group
29
Communication with Community
Communication with Community
30
Fun Day with DSD and LCSD
�Communication
�Education
Communication with Community
31
School Visit
32St. Paul’s Primary School visit and Drama Performanc e
School Visit
33
Student printing posted on the site hoarding
Stakeholder Workshop
34Partnering Workshop with Stakeholder
District Council Hong Kong Jockey Club
Hong Kong Football ClubSchools
LCSD
Consultants
Contractors
Sub-contractors
Experience Sharing
35
Site Visit ListNo. Date Title1 15/2/2014 Construction Industry Council 建造業議會
2 19/2/2014 Civil Engineering and Development Department 土木工程拓展署
3 21/2/2014 Civil Service Brueau (CSB) Staff Exchange 北京市水务局 排水管理处
4 26/2/2014 Construction Industry Council 建造業議會
5 1/3/2014 Hong Kong University of Science and Technology 香港科技大學
6 28/5/2014 Considerate Contractors Site Award Scheme 德地盤嘉許計劃
7 6/6/2014 Beijing Water Authority 北京市水务局
8 21/7/2014 DSD’s 25th anniversary (1) 渠務署25周年銀禧活動 (一)
9 26/6/2014 Hong Kong University of Science and Technology 香港科技大學
10 28/6/2014 The Hong Kong Institution of Engineers 香港工程師學會
11 5/7/2014 The Hong Kong Construction Association 香港建造商會
12 25/8/2014 Pearl River Water Resources Commission 香港科技大學湯有光教授帶領水利部珠江水利委员会
13 31/7/2014 Radio Television Hong Kong (RTHK) Shooting Day 香港電台拍攝
14 15/8/2014 Xinhaua visit 新華社CNC 採訪 (SWSPS)15 15/8/2014 DSD’s 25th anniversary (Part 2) 渠務署25周年銀禧活動 (二)16 25/8/2014 Dr Kwan (Hong Kong University) Site Visit 關博士(香港大學)實地考察
17 22/9/2014Water Supplies Department - The New Engineering Contract (NEC )Special Interest Group
水務署 新工程合約特別小組
18 27/9/2014 DSD's 25th Anniversary (Part 3) 渠務署25周年銀禧活動 (三)
19 26/9/2014The Hong Kong Institution of Engineers - HKIE
香港工程師學會
20 18/10/214 The Institution of Civil Engineers (ICE) 英國土木工程師學會
21 8/11/2014 H.K.U.Engineering Alumni Association 香港大學工程舊生會
Site Visit for HKIE membersSite Visit for HKIE members
Experience Sharing
36
� Sharing in difference media in Hong Kong and International
Experience Sharing in MingPao & SingTao
Sharing in GreenMAG #04 2014
NEC Website and Newsletter
37
Commendations
Considerate Contactor Award
38
� Silver award in 21 th Considerate Contactor (CCSA) organised by Developme nt Bureau and Construction Industry Council.
� Gold award in 21 st Considerate Contactor (OEMPA) organised by Developm ent Bureau and Construction Industry Council.
DSD Housekeeping Award
39
� Gold Award in DSD Construction Sites Housekeeping Award Scheme 2013 & 2014
Environmental Award
40
� Silver award in Hong Kong Awards for Environmental Excellence 2014 organised by HKPC
Environmental Award
41
� Silver award in Hong Kong Green Award 2014 organised by Hong Kong Green Council
NEC Award
42
� Highly Commended New Engineering Contract (NEC) Large Project of the Year 2015 award
43
Conclusion
GCC vs. NEC
• Traditional Contracts – are driven by a desire to maximum risk transfer .
• New Engineering Contracts – places emphasis on the collaborative management of risk to ensure successful project outcomes .
Source: NEC: A User’s Guide, Jon Broom
Contractor
RSS / Consultant
StakeholderSubcontractor
In Tradition Contracts:
Employer
Joy and Tear
ContractorSupervisor
Stakeholder
Subcontractor
In NECs:
Employer
Joy and Tear
In Tradition Contracts:
EmployerContractor
DISPUTE
• Lawyer• QS• prolongation
Claims $ Relationship
Joy and Tear
In NECs:
Employer / PMContractor
RiskRisk
Reduction
• quick resolution• without lawyer• maintain progress
• low cost • Relationship
Joy and Tear
Subcontract in NEC:
BUT………– Designer’s/Employer’s view on subcontracting arrangement
and strategies– Reply to tenderers’ queries in tender interview
-> minimize speculation; lower tender prices– Revise design / clarification before award of subco ntract by
tender addendum-> less dispute & reduce in tender price
– Alternative options (artificial turf)
Joy and Tear
– PM more involvement subletting procedure– Contractor cannot choose their favor subcontractor
50