housing authority of the borough of highland park 242 so...
TRANSCRIPT
1
Bathroom Modifications Addendum #1
Housing Authority of the Borough of Highland Park
242 So. Sixth Avenue, Highland Park, NJ 08904 Phone: (732) 572-4420 Fax: (732) 985-6485
Donna Brightman, Executive Director
March 2, 2018 Re: Bathroom Modifications at the Samuel J. Kronman Building
Addendum #1
Please be advised that Addendum #1 has been issued for the above referenced project. The following changes/additions/clarifications have been issued for each portion or the project (Exhaust System and Shower Install): Page 2: Exhaust System changes submitted by TJD Engineering Associates, Inc. Page 3: Revised Drawing M101 Pages 4-16: Shower clarification issued by LS Engineering Associates Corp. Pages 17-18: Minutes taken by TJD Pages 19-20: Minutes taken by LSEA Pages 21-23: Revised Bid Form Please be advised of the following:
1. The Bid opening date shall remain March 9, 2018 at 2:00 p.m. 2. All bidders must acknowledge all pages of this Addendum #1 on the
Acknowledgement of Receipt of Addenda’ document included in the original Invitation for Bid.
THANK YOU!
2
Bathroom Modifications Addendum #1
Exhaust System changes submitted by TJD Engineering Associates, Inc.
A. General: This Addendum Number 1 modifies and supplements the requirements of the Drawings and Specifications (Contract Documents) for the Highland Park Housing Authority Samuel Kronman Apts. Bathroom Exhaust Modifications Project. The drawings that are modified are dated February 14, 2018. The Specifications that are modified and supplemented are dated for delivery of bids on March 9, 2018.
B. Drawings: The following changes will apply to the referenced drawings:
a. Drawing M101 Mechanical Floor Plans:
i. Added Note Number 13. b. Refer to the revised bid form to add unit pricing for 1-hour dampers.
LS Engineering Associates Corporation
150 River Road, Building E, Suite E2, Montville NJ 07045 Ph. 973-588-3122 Fax. 973-588-3123
February 28, 2018
Mr. Larry Stecker
Director of Maintenance
Highland Park Housing Authority
242 South 6th Avenue
Highland Park, New Jersey
RE: Samuel Kronman Apartments Shower Stalls Design &
Construction Administration Services
CLARIFICATION #1
ITEM 1:
The “General Conditions” section have been included in the bid documents. Please see attached.
ITEM 2:
The Title Sheet A-1 have been revised to indicate correct project title. Please see attached.
ITEM 3:
Shower glass doors, as indicated in the drawings and specifications, to be tempered safety glass
sliding shower door.
ITEM 4:
Provide mock-up of shower stall with sliding glass door installed in an existing bathroom unit
prior to ordering and will be subject to approval from the Housing Authority and
Architect/Engineer.
ITEM 5:
Install wall sheathing behind shower stall walls with 1-hr. fire rating.
ACKNOWLEDGMENT OF RECEIPT OF CLARIFICATION #1
The undersigned Respondent hereby acknowledges receipt of this Clarification:
Company: Name: Date:
_________________________ _________________________ _____________
_________________________ _________________________ _____________
_________________________ _________________________ _____________
_________________________ _________________________ _____________
_________________________ _________________________ _____________
Note:
This Clarification letter should be attached to the Bid Documents.
GENERAL CONDITIONS
REPLACEMENT OF BATHTUBS WITH SHOWER STALLS
Samuel Kronman Apartments 242 South 6th Avenue
Highland Park, New Jersey
Prepared For:
Highland Park Housing Authority New Jersey
Prepared By:
LS Engineering Associates Corporation 150 River Road, Building E, Suite E2
Montville, NJ 07045 NJ Certificate of Authorization No: 24GA2791380
February 2018
2018-20
____________________________________________________________________________________________
Shower Stalls
Kronman Apts., Highland Park, NJ
1
GENERAL CONDITIONS
Replacement of Bathtubs with Shower Stalls
Kronman Apartments Highland Park, New Jersey
PART 1 PROJECT REQUIREMENTS
1.01 GENERAL
A. Work under this division includes the furnishing of all labor, materials,
equipment, and all incidental items necessary or reasonably implied for the
completion of the Work in accordance with the Specifications.
B. Before submitting a Proposal, the Contractor shall carefully examine the
Specifications, visit the site of the Work; and become thoroughly familiar with
all existing conditions and limitations. The submission of a Proposal will be construed as evidence that such an examination has been made, and later
claims for labor, equipment, or materials required or for difficulties
encountered which could have been foreseen had such an examination been made, will not be recognized.
C. The Contractor shall note the limits of the space within which all activities
must be confined. Space for storage of materials is available only as approved
by the Housing Authority.
1.02 INDEMNIFICATION
A. The Contractor shall indemnify and save harmless the Owner, and its respective agents, officers, employees and Architect/Engineer (A/E), herein collectively called the
"indemnities", from and against any and all liability, loss, damages, interest, judgments
and liens growing out of, and any and all costs and expenses (including, but not limited
to, counsel fees and disbursements) arising out of, or incurred in connection with, any and all claims, demands, suits, actions, or proceedings which may be made or brought
against any of the indemnities for or in relation to any violation of this Contract, the
laws, statutes, ordinances, rules, regulations, executive orders and agreements herein provided here or any injuries, including death at any time resulting there-from,
sustained by any person or persons, or on account of any damage to property, arising
out of or in consequence of the performance of or the failure to perform the contract, whether or not such injuries to persons or damage to property are due or claimed to be
due to any negligence of the Contractor or its employees, agents, subcontractors or
material-men, the indemnities or any other person.
1.03 WARRANTIES
Shower Stalls
Kronman Apts., Highland Park, NJ
2
A. The Contractor shall correct defective work at the Contractor's expense which appears within one year's time from final acceptance of work. Failure of Contractor to correct
such defects within a reasonable time after being notified to do so shall permit the
Owner to cause such defects to be corrected and charge the Contractor the cost of corrections.
B. The Contractor shall submit to the Housing Authority all material warranties supplied
by manufacturers.
1.04 GENERAL QUALITY ASSURANCE
A. References and Standards: The Contractor shall comply with all rules, regulations,
laws and ordinances of all Authorities having jurisdiction. All labor, materials,
equipment, and services necessary to make the work comply with such requirements shall be provided without additional cost. All Standards shall be the latest edition and
revisions.
B. The Contractor shall deliver material to the site, in the approved Manufacturer's original and unopened containers and packaging, bearing labels as to type of material,
brand name and manufacturer's name. Delivered materials shall be identical to
approved samples. Certifications for materials shall be included with the shipment.
C. The Contractor shall store material under cover (if appropriate) in a clean, dry, above-
ground location, and remove materials which are damaged or otherwise not suitable for
installation from the job site and replace with acceptable materials.
1.05 SECURITY
A. Protect work, existing premises Housing Authority’s operations from theft, vandalism,
and unauthorized entry.
B. Initiate and maintain security program throughout construction period until Housing
Authority’s acceptance precludes the need for Contractor security.
C. Restrict entrance of persons and vehicles into project site and existing facilities. Allow entrance only to authorized persons with proper identification. Maintain log of
workers and visitors, make available to Housing Authority on request.
1.06 SAFETY PROVISIONS:
A. Site safety is entirely the responsibility of the Contractor. The Contractor is hereby
made aware that the A/E does not have the authority to stop the work on the grounds of
unsafe work practices.
1.07 SUBMITTALS:
Shower Stalls
Kronman Apts., Highland Park, NJ
3
A. The Contractor shall submit to the A/E sufficient documentation from the manufacturers that all material and products used by the Contractor meet the required
specifications. Such documentation shall be submitted no less than 72 hours prior to
the delivery of the material.
This documentation shall include shop drawings, vendor drawings, manufacturer's
specifications and catalog cuts. The shop drawings shall include plans, elevations,
sections and details of the work showing in detail the methods of installations and all data and assumptions considered in the design.
B. The A/E will review and approve appropriate documentation for general compliance to the specifications prior to delivery. The A/E’s review will be made on a timely basis.
C. The approval of the A/E or failure to review shall not be constructed as permitting any departure from Contract requirements, or as relieving the Contractor of responsibility
for any errors, including details, dimensions or materials. If submittals show variations
from Contract requirements, the A/E may approve such variations, subject to a proper
adjustment in the Contract. If the Contractor fails to describe such variations, he shall not be relieved of the responsibility for executing work in accordance with the Contract
documents even though such submittals identifying other variations have been
approved.
D. All submittals required by specifications shall be submitted, unless otherwise stated
herein, as follows:
1. Specifications - Four copies of material specifications will be submitted to the
A/E unless agreed that less copies will be sufficient.
2. Shop Drawings - A reproducible and three copies will be submitted to the A/E.
E. The work shall not begin until all required submittals for each segment of work have been approved.
1.08 PROJECT COORDINATION
A. Cooperate with the Housing Authority in allocation of mobilization areas of site; for
field offices and storage, for access, traffic, and parking facilities.
B. Comply with A/E’s procedures for intra-project communications; submittals, reports
and records, schedules, coordination drawings, and recommendations; and resolution
of ambiguities and conflicts.
C. Comply with instructions of the Housing Authority for use of temporary utilities and
construction facilities.
D. Coordinate field engineering and layout work per the Documents.
Shower Stalls
Kronman Apts., Highland Park, NJ
4
E. Submit preliminary progress schedule and coordinate with project construction schedule.
F. Provide information required by A/E for preparation of coordination drawings.
1.09 PROGRESS SCHEDULE
A. Prepare project schedule using the critical path method. Use a sequence of listings corresponding to the Table of Contents of this Project Manual or the chronological
order of the start of each item of work.
B. Progress schedule to have a minimum 22 x 17 inches sheet size.
C. Progress schedule shall indicate the following:
1. Show complete sequence of construction by activity, with dates for beginning
and completion of each element of construction.
2. Identify each item by specification section number.
3. Identify work of separate stages and other logically grouped activities.
4. Provide sub-schedule to define critical portions of the entire schedule.
5. Show accumulated percentage of completion of each item, and total percentage of work completed, as of the first day of each month.
1.10 PERMIT APPLICATIONS AND COMPLIANCE
A. The Contractor is responsible for obtaining permits as well as all other outstanding
permits (such as local construction, plumbing, electrical, etc) relating to the full completion of the project at his/her own expense.
B. The Contractor shall carefully plan and coordinate his/her work so as to comply with
all criteria, conditions and the intent of all project permits.
1.11 ENVIRONMENTAL PROTECTION
A. It is the Contractor's responsibility to assure themselves that all applicable Federal,
State and local laws, concerning pollution and environmental protection are being
complied with by his personnel and subcontractors.
B. When Contractor is in, or it is anticipated that any part of the work may become in
non-compliance with applicable Federal, State, and local laws or regulations, A/E will
notify the Housing Authority who may issue an order stopping all or part of the work until satisfactory corrective actions have been taken, or may order supplemental
actions to be taken to stay in, or come into, compliance. No part of the time lost due to
Shower Stalls
Kronman Apts., Highland Park, NJ
5
any such stop order shall be made subject of a claim for extensions of time, or for extra compensation or damages by the Contractor.
C. In particular, the Contractor shall not allow the discharge of concrete, mortar, grout, gasoline, diesel, or the washing from vessels containing these materials, or other
construction materials, into public areas or the sewage systems.
D. Contractor shall provide and maintain all facilities necessary for pollution control under this Contract as long as construction operations continue.
1.12 CONTRACTOR'S REPRESENTATIVES
A. The Contractor shall provide and maintain a capable and experienced field person to
oversee all contract operations. The representative shall be on-site during all operating hours of the project.
B. As appropriate, the Contractor or his subcontractors shall provide qualified supervisory
personnel for specialist aspects of the work, such as for electrical, concrete, landscaping, and rigging.
1.13 JOB OFFICE
A. The Contractor may provide and maintain a suitable job office for the use of his
supervising personnel at a location approved by the Housing Authority.
If used, the offices shall be equipped with telephones listed in the Contractor's name
and other appropriate facilities. If used, the cost for maintaining and servicing the
office facilities shall be paid for by the Contractor for the duration of the project.
B. The Contractor shall provide and maintain in a neat and sanitary condition such
temporary sanitary conveniences and accommodations for the use of their employees as may be necessary to comply with the requirements and regulations of the
Department of Health and other governing agencies having legal jurisdiction.
1.14 SITE ACCESS
A. No unauthorized personnel shall be permitted access to the site area. The Contractor’s
access to the building will be per arrangement with Housing Authority.
B. Parking for construction vehicles shall be designated by the Housing Authority. All
other parking, un-loading, etc is the responsibility of the Contractor, without further cost to the project. Traffic, other than construction traffic necessary to accomplish the
work, shall be limited to areas outside of the site.
C. Off-site roadways which are soiled by construction traffic shall be immediately swept clean of spoil/debris.
1.15 EXISTING UTILITIES AND STRUCTURES
Shower Stalls
Kronman Apts., Highland Park, NJ
6
A. Verify Locations: Locations of existing underground utilities and structures as shown
on the Plans are approximate and may not necessarily be complete. These locations
must be verified by the Contractor.
B. Avoid Damage: The Contractor shall exercise care to avoid damage to all existing
structures, poles, utilities, pipes, etc. which are scheduled to remain. In locations
where the excavation is carried beneath or adjacent to such facilities, the Contractor shall adequately support such structures, utilities or pipes as necessary to maintain
them in operation and their original position. The Contractor shall be responsible for
any damage caused to any utilities by this work, without charge to the Owner.
1.16 MAINTENANCE OF RECORD DOCUMENTS AND SAMPLES
A. Contractor shall maintain at the site one record copy which will be kept available for
review by the A/E and Housing Authority of:
1. Design Drawings 2. Technical Specifications
3. Addenda and Modifications to Drawings and Specifications
4. Progress Schedule and Critical Path Diagram 5. Change Orders and other modifications to the Contract
B. The Contractor shall also maintain on-site copy of other documents: manufacturer's
certifications, inspection certifications, field test records required by individual Specification Sections.
C. Record Documents are to be kept in a clean, dry, and legible conditions, and are not to be used for construction purposes.
1.17 TEMPORARY ELECTRIC POWER (At contractor’s option)
A. The Contractor may use portable generator(s) to provide temporary power.
B. Contractor may install a temporary electrical service at locations approved by the Housing Authority and PSE&G, as appropriate. Temporary light and power
installations, wiring, and miscellaneous electrical hardware must meet the National
Electric Code.
C. The Contractor shall provide and pay for all maintenance, servicing, operation and
supervision of the service and distribution facilities. He shall also connect, maintain, and service any electrical equipment installed which may be necessary for maintaining
heat whenever heat is required in the job office whether from the temporary or
permanent system.
1.18 CONSTRUCTION WATER CONTROL
Shower Stalls
Kronman Apts., Highland Park, NJ
7
A. The Contractor shall dispose of all water with due care and shall not infringe on the right of others on the site, of adjacent property owners and of the public. All cost in
connection with the removal of such water shall be paid by the Contractor.
1.19 FIRE PREVENTION CONTROL
A. Comply with the safety provisions of the National Fire Protection Association’s
“National Fire Codes” pertaining to the work and, particularly, in connection with any cutting or welding performed as part of the work.
1.20 DEBRIS & RUBBISH REMOVAL
A. The Contractor shall:
1. Keep the work area free from rubbish at all times.
2. Remove rubbish from the site at least once a week.
B. The Contractor shall conform with the following:
1. Burning of rubbish shall not be permitted.
2. Remove from the site all surplus materials as the work progresses.
C. All materials, fixtures and equipment, etc, removed in the process of the work shall become the property of the City, with the exceptions that Housing Authority may
direct that certain elements may be stockpiled onsite to be retained for its ownership
and re-use.
1.21 AS-BUILT DOCUMENTS
A. As-built documents are required for all proposed improvements outlined in the
drawings.
B. The Contractor shall provide and maintain, at his own expense, one set of black and white prints of the Contract Drawings on the Site. The Contractor shall maintain an
up-to-date record on these prints showing all demolished, relocated and/or installed
utilities or related facilities as the work progresses. Such recording of the installation shall include final and actual sizes as well as location and elevation thereof by figures
and off-set distances in feet and inches to permanent surface improvements such as
buildings, retaining walls or curbs. Upon completion of the work, the information on these drawings shall be incorporated into a set of As-Built Drawings prepared by the
Contractor. The number, titles, and scales of these As-Built Drawings shall equal the
Contract Drawings. These As-Built Drawings shall be accurate reductions of the
existing conditions in the scale indicated in the Contract Drawings.
C. The Contractor shall include the following on the final hard copy As-Built Drawings:
Shower Stalls
Kronman Apts., Highland Park, NJ
8
- Company names, address, and telephone number, project title, contract number and drawing date.
- The words "As-Built".
- The statement, "I hereby certify that this As-Built Drawing is correct, complete, and accurate."
- Contractor's signature.
D. The As-Built Drawings and Autocad diskette must be submitted to the A/E within ten (10) days of the issuance of the Certificate of Substantial Completion for verification
by the Housing Authority. Acceptance of the As-Built Drawings is subject to
verification. (Percentage of retention monies will be withheld pending receipt and approval of the As-Built Drawings.)
1.22 PROJECT CLOSEOUT
A. Notify A/E when work is considered ready for substantial completion. Accompany
A/E on preliminary inspection to determine items to be listed for completion or
correction in Contractor's Notice of Substantial Completion and punchlist.
B. Notify A/E when work is considered finally complete. Accompany A/E on final
inspection.
C. Comply with A/E's instructions to correct items of work listed in punchlist and A/E's
final inspection..
D. Remove all temporary facilities, temporary erosion and sediment controls, and all
construction waste, for legal disposal in an off-site location.
E. Leave site in a tidy, orderly condition.
PART 2 MATERIALS
2.01 GENERAL
A. Use materials appropriate to the work, and meeting with the Housing Authority’s and
/or A/E's approval.
PART 3 EXECUTION
3.01 GENERAL
A. Execute general measures as appropriate, and meeting with the Housing Authority’s
and /or A/E’s approval.
LSEA CORPORATION
LSEA
A-1
TITLE SHEETAND
LOCATION MAP
DRAWING LIST:
A1 TITLE SHEET, GEN. NOTES & LOCATION MAPA2 2ND TO 6TH KEY FLOOR PLANSA3 DETAILS
LOCATION MAP1
SCALE: N.T.S.
PROPOSED SHOWER STALLS
(BATHTUB REPLACEMENT)
HIGHLAND PARK
HOUSING AUTHORITY
SAMUEL KRONMAN APARTMENTS
242 SOUTH 6TH AVENUE
HIGHLAND PARK, NEW JERSEY
PROPOSED SHOWER STALLSHIGHLAND PARK HOUSING AUTHORITY
SAMUEL KRONMAN APTS.242 SOUTH 6TH AVENUE
HIGHLAND PARK, NEW JERSEY
1
TJD ENGINEERING ASSOCIATES, INC.
2 HANCOCK DRIVE
WEST MILFORD, NEW JERSEY 07480
TELEPHONE: (973) 208-0054
FAX: (973) 208-0851
EMAIL: [email protected]
Highland Park Housing Authority
TJD File 17201A
February 27, 2018
Report of Meeting Held on 02/23/18
In attendance
Highland Park Housing Authority Larry Stecker
Joe Thurston
Ocean Contractors Inc. George Stavrou
(Unknown Name)
TNT Construction (Unknown Name)
GMT Contracting Jose Santos
LSEA Corp Jose Ortiz
Francois Rosefort
TJD Engineering (TJD) Thomas Tamayne
On 2/23/18 a meeting took place at 242 South 6th Avenue Highland Park, New Jersey to
discuss the Samuel Kronman Apartments Bathroom Exhaust Modifications Project. The
following is a list of the key issues and decisions that transpired at this meeting.
NEW BUSINESS
1. The purpose of the meeting was to discuss the Bathroom Exhaust
Modifications Project.
2. A general discussion was had concerning the following project facets:
2
• The existing bathroom exhaust risers are not connected
to the grilles in the bathrooms and the systems are not
performing properly.
• the Bathroom Exhaust Modifications Project will be
performed in conjunction with the Proposed Shower
Stalls (Bathtub Replacement) Project.
• The contractor was directed to note the Alternate 1 Bid
requirements in the bid form as well as the Unit Pricing
Requirements.
3. 2 sample apartments were inspected. They were Apartments 2-B & 2-
M.
We believe the foregoing to be an accurate summary of the decisions and related
discussions. Please provide any exceptions to these minutes within five business days to
TJD Engineering Associates (via fax or email to the attention of T. Tamayne). Failing
such notification, we will consider these minutes a matter of record. Corrections to the
minutes will be addressed at the next meeting and incorporated in the next set of minutes.
Distribution: All Attendees
Housing Authority of the Borough of Highland Park Revised Form of Bid-Page 1
Bathroom Modifications at the Samuel J. Kronman Building
TO: Housing Authority of the Borough of Highland Park 242 So. Sixth Street, Highland Park, NJ 08904
I have received the Contract Documents entitled “Bathroom Modifications at the Samuel J. Kronman Building” issued by the Housing Authority of the Borough of Highland Park, New Jersey. I have examined all parts of the Documents, including the Technical Specifications, Drawings, federal, state and local requirements, and all Addenda. I have visited the site and have clear understanding of the Scope of Work for which I submit the following bid. In submitting this bid, I agree: 1. To hold my bid open for ninety (90) days after bid opening.
2. To enter into and execute a contract, if awarded on the basis of this bid, and to furnish insurance and other requirements as stated and required in the Contract Documents.
3. To accomplish the work in accordance with the requirements of the Contract Documents.
4. To complete the work on time and to the quality required in the Contract Documents. Base Bid for Entire Project: I will furnish all labor, materials, equipment, tools, apparatus, appliances, transportation, supervision, taxes and other services required for the complete project in accordance with the specifications and plans provided by LS Engineering Associates Corp. and TJD Engineering Associates, Inc. for, INCLUSIVE OF THE SHOWER INSTALLATION AND EXHAUST SYSTEM MODIFICATIONS, for the Lump Sum of: ___________________________________________________ dollars. ($__________.___) Words The above Base Bid shall be broken down according to the following Schedule of Prices.
Schedule of Prices:
SCHEDULE OF PRICES FOR SHOWERS
UNIT PRICES: The unit prices shall include all labor, material, removal, overhead, profit, insurance, and all incidental item required to complete the project. ITEM 1: Prefabricated shower stall and accessories including, but not limited to: shower with grab bar assembly, grab bars, shower valve, floor drain and associated fittings to existing sanitary system, support frame for shower as necessary. UNIT PRICE (per bathroom): ________________________ ($___________________)
Housing Authority of the Borough of Highland Park Revised Form of Bid-Page 2
Bathroom Modifications at the Samuel J. Kronman Building
ITEM 2:
Replace alcove above shower stall affected by exhaust modifications. Match size, frame, and finish with
existing. Patch existing floor, walls, and ceiling finishes in work area as necessary.
UNIT PRICE (per bathroom): _______________________________ ($___________________)
ITEM 3:
Glass door enclosure to fit within shower stall.
UNIT PRICE (per bathroom): _______________________________ ($___________________)
SCHEDULE OF PRICES FOR EXHAUST SYSTEM
1. ALTERNATES:
If ALTERNATE NO. 1 as described in these Specifications on Drawing M101 Notes 2,6,8,9 is accepted, the following amount shall be (ADDED TO) – (DEDUCTED FROM) our proposed price: circle one
______________________________________________________ ($___________________)
written words numbers
2. UNIT PRICES ITEM 1:
The unit price as described in the specifications on Drawing M101 Note 3 shall be:
_____________________________________________________ ($___________________)
written words numbers
ITEM 2:
The unit price as described in the specifications on Drawing M101 Note 5 shall be:
_____________________________________________________ ($___________________)
written words numbers
ITEM 3:
The unit price as described in the specifications on Drawing M101 Note 10 shall be
_____________________________________________________ ($___________________)
written words numbers
ITEM 4:
The unit price as described in the specifications on Drawing M101 Note 13 shall be
13 x 10 _________________________________________dollars ($___________________)
written words numbers
11 x 10 _________________________________________dollars ($___________________)
written words numbers
11 x 8 _________________________________________dollars ($___________________)
written words numbers
Housing Authority of the Borough of Highland Park Revised Form of Bid-Page 3
Bathroom Modifications at the Samuel J. Kronman Building
11 x 6 _________________________________________dollars ($___________________)
written words numbers
10 x 6 _________________________________________dollars ($___________________)
written words numbers
10 x 4 _________________________________________dollars ($___________________)
written words numbers
6 x 4 _________________________________________dollars ($___________________)
written words numbers
Please note that time is of the essence in the performance of the contract.
If the contractor receives written notice of the acceptance of this bid within 90 days after the opening thereof, or at any time thereafter before this bid is withdrawn, the undersigned agrees to execute and deliver a Contract in prescribed form within 7 days following receipt of a written Notice to Proceed. Time of Completion: The Contractor agrees to complete all work as specified within (ninety) 90 days of receipt of a written Notice to Proceed or receipt of applicable permits, if any. If the Contractor fails to complete the work within 90 days, the Contractor shall pay the Authority as liquidated damages, the sum of $150.00 for each day of delay as outlined in form HUD-5370. To the extent that the Contractor’s delay or nonperformance is excused, liquidated damages shall not be due to the Authority. The Contractor remains liable for damages caused other than by delay.
Submitted By:
COMPANY NAME ____________________________________________________________
Federal ID# _______________________
Address ___________________________________________________________________
Signature of Authorized Agent / Title ___________________________________________
Print or Type Name _____________________________Date ________________________
Phone Number_____________________________ Fax Number ________________________ Email Address _________________________________________________________________ SIGNED AND SEALED THIS _________ DAY OF ______________, 2018 WITNESSED BY: ____________________________________________
END OF REVISED FORM OF BID