Wall-Ties & Forms, Inc, (WTF) is one of the world's largest
companies in the concrete forming business, as well as the premier
designer and manufacturer of concrete forming systems. Over 33
years ago as a new business, WTF manufactured ties - thousands of
them. Today we produce and ship over 30 million ties a year and
over 200,000 aluminum concrete forms.
It started in 1976 when Orval Engelken and Ross Worley, two menwith extensive knowledge of the construction industry. They left long
and successful careers, one a national sales manager and the other
a product design and manufacturing expert, knowing they could do a
better job.
Three principles guided them:
1. Produce the best quality and most labor friendly product.
2. Offer unsurpassed customer service.
3. Provide it all at a competitive price.
The rest is history!
-
8/7/2019 Housing Construction Process
3/64
WTF Manufacturing Facility
160 Employees
Over a 120,000 Sq. Ft.
-
8/7/2019 Housing Construction Process
4/64
The WTF Formwork System (manufactured byWall Ties & Forms, Inc.) is unique because itforms all of the components in the structureincluding, walls, floor slabs, columns, beams,stairs, window details, balconies, and variousdecorative features in exact accordance with
the architect's design. No other system canmatch WTF Formwork flexibility to handle alldesign conditions.
-
8/7/2019 Housing Construction Process
5/64
The WTF System is erected by unskilled labor andwithout the need of hoisting cranes. The largestcomponent weight is not more than 32 kgs (70 Lbs).This enables a single worker to handle the WTFformwork components. The forms and other sections aresecured and fixed with steel pins and wedges with
formwork ties. The only tool required is a hammer. TheWTF System can save as much as 10 - 20% of the totalcost of construction and increase speed as much as 30 -50% over traditional methods such as block andpost/beam construction.
-
8/7/2019 Housing Construction Process
6/64
The WTF Aluminum Formwork System for concreteconstruction is the most versatile construction system inthe world. Unlike other systems, it is equally suited toconstruct both high and low rise structures.
-
8/7/2019 Housing Construction Process
7/64
The WTF Formwork System is specifically designed to allow the rapid construction of multiple unit projects.The system is cycled daily to achieve optimum productivity.
One and two story duplex project in Mexico consisting of 8,500 units
-
8/7/2019 Housing Construction Process
8/64
The simplicity of the WTF aluminum
formwork is ideal for unskilled labor andenables unskilled labor to achieve thehighest of production rates.
Every component is light enough to behandled by one worker, minimizing theneed for heavy lifting equipment.
The only toolneeded to erectthe formwork is ahammer.
-
8/7/2019 Housing Construction Process
9/64
WTF aluminum formwork enables the developer tocast most if not all elements of the structure.
This includes structural, non-structural, andarchitectural elements
-
8/7/2019 Housing Construction Process
10/64
The formwork for these structures included all elements, structural, non- structural, and architectural. Thearchitectural elements include, radius headers, decorative columns, pitched concrete roof, and rain gutters castdirectly into the decorative moldings.
-
8/7/2019 Housing Construction Process
11/64
Casting all elements achieves a costsavings of 10-20% over traditional methods.This home was constructed by Homex ofMexico. Homex is the largest builder inMexico with 51,000 home starts a year as of2009.
-
8/7/2019 Housing Construction Process
12/64
Casting all elements also speedsconstruction 30 - 50% over traditionalmethods. This is achieved by thespeed of the formwork system, thereduction of follow-on trades, and theease of finishing the surfaces.
-
8/7/2019 Housing Construction Process
13/64
One of the principal technical features whichenables the speed to be attained using asingle set of formwork is the unique deckbeam system. This allows the formworkremoval to take place while leaving the decksupports undisturbed. The deck panels canthen be reused immediately.
-
8/7/2019 Housing Construction Process
14/64
The precision of the WTF Formwork enables doors and window frames to be directly installed on sitewith no re-sizing required.
-
8/7/2019 Housing Construction Process
15/64
Because openings are so precise, the developer can beconfident in the pre-purchase of doors and windows.Often times the developer can purchase these items foran entire project with huge cost savings.
Th t f d d ith th
-
8/7/2019 Housing Construction Process
16/64
The concrete surface produced with theformwork allows the achievement of a highquality wall finish without the need forextensive plastering.
-
8/7/2019 Housing Construction Process
17/64
Formwork set for final inspection at manufacturing facility in Shawnee, Kansas, USA.
Because the WTF Formwork is constructed with the highest quality aluminum and
welded with robotics, developers can expect 2,000 uses or more with proper care.
-
8/7/2019 Housing Construction Process
18/64
Often times the formwork outlives the life of the project and can be cycled to a new project. Because
the formwork is modular 70- 90% of the forms are easily adapted to new construction projects.
-
8/7/2019 Housing Construction Process
19/64
From foundation to multi-story construction, the following pages illustrate the WTF Formwork process.
-
8/7/2019 Housing Construction Process
20/64
The process begins with compaction of the site. Trenches are
then dug, plumbing installed, and WTF slab formwork is set.
-
8/7/2019 Housing Construction Process
21/64
Once structural footings are dug, slab steel isinstalled in accordance with local code.
-
8/7/2019 Housing Construction Process
22/64
Concrete is then placed using local methods.
-
8/7/2019 Housing Construction Process
23/64
Wall steel is then tied in accordance with local building codes.
-
8/7/2019 Housing Construction Process
24/64
Electrical boxes and conduit are attached to the wall steel. Rigid or flexibleconduit may be used depending on local building codes.
-
8/7/2019 Housing Construction Process
25/64
When constructing mass housing projects it is wise toprep slabs well in advance. The WTF FormworkSystem can be cycled daily for very rapid construction.
-
8/7/2019 Housing Construction Process
26/64
The beginning of the WTF formwork process normallystarts in a corner or multiple corners depending on thenumber of workers. This process continues until all
walls are erected.
-
8/7/2019 Housing Construction Process
27/64
Once wall forms are set, decking can begin.Decking like wall formwork is hand-set andbegins in a corner.
-
8/7/2019 Housing Construction Process
28/64
Upon completion of
decking, steel andelectrical is installedin preparation ofconcrete placement.
-
8/7/2019 Housing Construction Process
29/64
When all prep work is complete,concrete is placed monolithically inwalls and deck. Concrete placementis normally completed using a boompump but is dictated by local marketequipment. This can include trailer
pumps, crane buckets, and evenhand bucketing.
-
8/7/2019 Housing Construction Process
30/64
The WTF formwork is removed
the very next day to begin thecycle again.
F lti t t t
-
8/7/2019 Housing Construction Process
31/64
For multi-story structuresscaffolding is then attached.The scaffolding not onlysupports the weight of theworkers but also supports theexterior wall forms.
-
8/7/2019 Housing Construction Process
32/64
Steel is tied, forms set, andconcrete placed repeatingthe daily cycle.
-
8/7/2019 Housing Construction Process
33/64
For markets with extreme climates, the WTFFormwork System easily incorporatesinsulation into the construction process. Theexpanded foam insulation is installed betweenformwork ties prior to setting exteriorformwork.
-
8/7/2019 Housing Construction Process
34/64
After concrete placement and curing, formwork is removed leavingfoam insulation permanently bonded to the concrete.
-
8/7/2019 Housing Construction Process
35/64
The WTF Formwork Systemis in use in over 45 countriesworldwide. The followingpages are just a fewexamples of the WTF globalpresence.
-
8/7/2019 Housing Construction Process
36/64
-
8/7/2019 Housing Construction Process
37/64
-
8/7/2019 Housing Construction Process
38/64
-
8/7/2019 Housing Construction Process
39/64
-
8/7/2019 Housing Construction Process
40/64
-
8/7/2019 Housing Construction Process
41/64
-
8/7/2019 Housing Construction Process
42/64
-
8/7/2019 Housing Construction Process
43/64
-
8/7/2019 Housing Construction Process
44/64
-
8/7/2019 Housing Construction Process
45/64
-
8/7/2019 Housing Construction Process
46/64
-
8/7/2019 Housing Construction Process
47/64
-
8/7/2019 Housing Construction Process
48/64
-
8/7/2019 Housing Construction Process
49/64
-
8/7/2019 Housing Construction Process
50/64
-
8/7/2019 Housing Construction Process
51/64
-
8/7/2019 Housing Construction Process
52/64
-
8/7/2019 Housing Construction Process
53/64
-
8/7/2019 Housing Construction Process
54/64
-
8/7/2019 Housing Construction Process
55/64
-
8/7/2019 Housing Construction Process
56/64
-
8/7/2019 Housing Construction Process
57/64
-
8/7/2019 Housing Construction Process
58/64
-
8/7/2019 Housing Construction Process
59/64
-
8/7/2019 Housing Construction Process
60/64
-
8/7/2019 Housing Construction Process
61/64
-
8/7/2019 Housing Construction Process
62/64
-
8/7/2019 Housing Construction Process
63/64
-
8/7/2019 Housing Construction Process
64/64