how 3d model coordination eliminates risks from ... panel 2 - rahman.pdfc a p t u r e a n d l e v e...
TRANSCRIPT
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
How 3D Model Coordination Eliminates Risks from Challenging Healthcare Renovations
October 18, 2017
Shurid Rahman, Sutter Health
Brett Paloutzian, HED
Matthew Jogan, Ghafari Associates
Nicholas Grage, IntegraBIM
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
© LEAN CONSTRUCTION INSTITUTE
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
What you will learn
2
• What are critical risks for a existing renovation
project in healthcare
• Early Design
• Permit
• Construction
• How model coordination can document,
manage and solve these risks
• Specific examples from our project Alta
Bates Summit Medical Center
• Things we would have liked to know earlier
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
Project Context
© LEAN CONSTRUCTION INSTITUTE
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
Alta Bates Summit Medical Center
4
• Campus in Oakland, CA
• Pill Hill Neighborhood
• 2015 SB90 Seismic Compliance and Master
Facility Plan
• Merritt Ground Floor Renovation
• Dietary Department
• MRI Suite
• Doctors Lounge
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
Sutter ABSWR- Dietary, MRI, Doctor’s Lounge
5
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
Site Advantages and Challenges
6
• Advantages
• Compliance
• Availability
• Proximity and connectivity
• Challenges in existing spaces
• Floor-to-floor heights
• Existing utilities to remain
• Non-conforming conditions
• Disruptions
• Unexpected/discovered conditions
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
Critical Risk Assessment – Early Construction
7
ELEMENT RISKS
Issue you can solve now.
PROCESS RISKS
Issues that materialize with time, which
you cannot fully solve now.
+
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
Critical Risk Assessment – Early Construction
8
• ELEMENT RISKS
• Incomplete Design Scope
• Cooking Hood Exhaust
• Grease Duct
• Walk-in Refrigerators/Freezers
• Lagging MRI Suite Design
• Cryogen Vent Routing
• Variable Existing Conditions
• Waterproofing
• Slab Levelness
• PROCESS RISKS
• Schedule Delays
• Design to field handoff
• Changing site conditions
• Unexpected Design Issues
• Hidden existing conditions not captured
• No trade partner input in the design
• Incomplete design scope going into
construction
• Late MRI selection
• Procurement Risks
• Restaurant equipment
• MRI
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
What does Sutter want to achieve?
9
• Three goals
• Fast and reliable construction schedule
• Accuracy and customization of design
• Informed change management
• How can critical risks be eliminated to achieve
these goals?
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
LCI CONGRESS PRESENTATION STYLE GUIDEModeling Culture and Workflows
© LEAN CONSTRUCTION INSTITUTE
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
BIM Principles
11
BIM is a tool for Risk Management.
Focus on Workflow First, Model Creation Next.
Use BIM to Establish a Single Source of Truth.
Engage Trades and Vendors Early to create informed
models during Design.
Plan the Work to define the workflows that will
determine how 3D content needs to be developed.
Model the Build, then Build the Model.
Create processes that enable Design for Fabrication.
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
BIM - Focus on Workflow First
12
Improve the Information Supply Chain via
Process Mapping.
Re-align Team Workflow to Optimize the Overall
Outcome.
Align the workflow to Leverage 3D.
Eliminate Waste within Information Production and
Exchange.
Process Mapping information handoffs for
Integrated Mechanical Design
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
BIM - Establish a Single Source of Truth
13
Documentation as a direct output from fabrication informed 3D models
Create a culture where there is only One Source of
3D Information for each system.
Share Incomplete Information, often.
Team reviews the Design in 3D on a regular basis.
Use the 3D Model information to Inform all Outputs.
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
BIM - Plan the Work
14
Early and detailed development of inflexible systems. Handoff Work Planning in Design using vPlanner
Define the Team Workflows that determine how
the 3D Content needs to be developed, not the
other way around.
Development of 3D models is directly related to
the Team’s Plan.
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
BIM - Best Practices
15
Develop workflows to support a ‘Build the Model’ approach.
ALL work is in 3D.
Models are kept Updated & Accurate.
The team is Sharing Incomplete Information, often.
Team is Managing the Content via 3D models, and Managing the Work via collaborative visual planning.
Team members are modeling work with Direct Input from trades & vendors.
Model review outcomes include a set of Clearly Captured Action Items that resolve issues.
3D Model Design Review = Action Items are
captured as activities in the Team’s Plan and
managed via LPS using vPlanner.
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
LCI CONGRESS PRESENTATION STYLE GUIDEExamples
© LEAN CONSTRUCTION INSTITUTE
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
Accommodating Disparate Programs - MRI
17
• Challenges:
• Getting it to fit in the volume of space
available
• ADA clearances
• Magnetic Gauss fields that can kill people
• Imaging department above
• Sterile processing department below
• Dining seating on other side of the wall
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
MRI Gauss Field Concerns
18
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
MRI Gauss Field 2D to 3D
19
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
MRI Gauss Field- Analyze the Impact
20
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
Existing Conditions Complexity – Hoods and Exhaust
21
• Challenges:
• Floor to underside of beams = 10’-5”
• Fire sprinkler could not penetrate beams
• Grease ducts slope
• Long distance from hoods to exterior
• Solutions:
• Lowered ceilings from 9’ to 8’
• Changed light fixture type (low profile)
• Re-routed electrical racks
• Facilities Management included in the process
• Moved access doors
• Added valves to systems to improve maint’
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
Design Intent vs. Constructability - Soffits
22
• “I am most comfortable with the state of details on this project than any other currently” Framer.
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
Design Intent vs. Constructability - Soffits
23
• In coordination
we found that a
soffit just would
not work
• The above ceiling
conditions were
too congested
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
Design Intent vs. Constructability - Soffits
24
• With a materials
change, the design
intent was
maintained and
constructability
achieved
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
Weaving around existing conditions
25
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
LCI CONGRESS PRESENTATION STYLE GUIDEWhat’s Next and Lessons Learned
© LEAN CONSTRUCTION INSTITUTE
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
Critical Risk Assessment – Early Construction
27
• ELEMENT RISKS
• Incomplete Design Scope
• Cooking Hood Exhaust
• Grease Duct
• Walk-in Refrigerators/Freezers
• Lagging MRI Suite Design
• Cryogen Vent Routing
• Variable Existing Conditions
• Waterproofing
• Slab Levelness
• PROCESS RISKS
• Schedule Delays
• Design to field handoff
• Unexpected site conditions
• Post demolition scan and effort
• Design Variability
• Hidden existing conditions not captured
• No trade partner input in the design
• Incomplete design scope going into
construction
• Change Management Analysis
• Late MRI selection
• Procurement Risks
• Restaurant and MRI equipment
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
What we would have liked to learn sooner
28
• Team understanding that design as an evolving
iterative process
• Sooner is better
• Modeling sooner creates better content to
inform design
• Having better existing information sooner
• Developing model based workflows sooner
• Alignment between Management and BIM
team
• Context of a small team and limited
resources
© LEAN CONSTRUCTION INSTITUTE
C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
In the spirit of continuous improvement, we would like to remind you to complete this session’s survey in the Congress app! We look forward to receiving your feedback. Highest rated presenters will be recognized.
© LEAN CONSTRUCTION INSTITUTE