how flexible steel pipe helped solve five challenges of

19
© 2019 FlexSteel Pipeline Technologies, Inc. Kirill Kovalenko, Technical Services Engineer Cost-Effective Well Site Facilities Canada Congress February 28, 2019 How Flexible Steel Pipe Helped Solve Five Challenges of Pipeline Construction, Operation, and Maintenance

Upload: others

Post on 19-Feb-2022

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: How Flexible Steel Pipe Helped Solve Five Challenges of

© 2019 FlexSteel Pipeline Technologies, Inc.

Kirill Kovalenko, Technical Services Engineer

Cost-Effective Well Site Facilities Canada Congress

February 28, 2019

How Flexible Steel Pipe Helped Solve

Five Challenges of Pipeline Construction,

Operation, and Maintenance

Page 2: How Flexible Steel Pipe Helped Solve Five Challenges of

© 2019 FlexSteel Pipeline Technologies, Inc. | 2

Agenda

Operators Challenges

Flexible Steel Pipe

Case Studies

Summary

1

2

3

4

Page 3: How Flexible Steel Pipe Helped Solve Five Challenges of

© 2019 FlexSteel Pipeline Technologies, Inc. | 3

Copy

Challenges: Time + Resources

STEEL CONSTRUCTION AND MAINTENANCE

CHALLENGES

CORROSION CONTROL

MAINTENANCE AND REPAIR

RESOURCES AND TIME

Time + Resources = increased project cost

© 2019 FlexSteel Pipeline Technologies, Inc.

Page 4: How Flexible Steel Pipe Helped Solve Five Challenges of

© 2019 FlexSteel Pipeline Technologies, Inc. | 4

Solution: Spoolable Pipeline

• Comes in long sections:– 380 to 2,000 m

• Installs much faster than steel pipe

• Accelerated time to production

• Minimal manpower and equipment requirement

• Smaller Right-of-Way

• No welding, field bending, X-ray, and coating costs

Flexible Steel Pipe

Page 5: How Flexible Steel Pipe Helped Solve Five Challenges of

© 2019 FlexSteel Pipeline Technologies, Inc. | 5

Flexible Steel Pipe Structure

Steel Reinforcement

▪ Pressure Containment Layer

Corrosion Resistant Shield

▪ HDPE/PE-RT

Corrosion Resistant Liner

▪ HDPE/PE-RT

HDPE: High-Density Polyethylene

PE-RT: Polyethylene Raised-Temperature

Page 6: How Flexible Steel Pipe Helped Solve Five Challenges of

© 2019 FlexSteel Pipeline Technologies, Inc. | 6

Flexible Steel Pipe Specifications

2 in. 3 in. 4 in. 6 in. 8 in.

DESIGN PRESSURE RANGE

750 PSI to 3000 PSI

OPERATING TEMPERATURE RANGE

- 40°C >>> 65°C >>> up to 90°C

High-pressure and high-rate capability

Page 7: How Flexible Steel Pipe Helped Solve Five Challenges of

© 2019 FlexSteel Pipeline Technologies, Inc.

Copy

Copy

Welded Steel Flexible Steel Pipe

Installation significantly faster than conventional steel line pipe

© 2019 FlexSteel Pipeline Technologies, Inc.

Page 8: How Flexible Steel Pipe Helped Solve Five Challenges of

© 2019 FlexSteel Pipeline Technologies, Inc. | 8

Grande Prairie, Alberta

Case Study: Water Pipeline

• A new well pad was constructed by the customer

• Frac water supply daily cost: – 22 trucks/day = $115,000/day

• A 4,000-m pipeline was urgently needed

• 8” 1500 psi Flexible Steel Pipe was chosen

• The line installed ~30% faster than their previous solution– 7 HDD bores and crossings, the longest

bore 700 m

• Trucking costs eliminated sooner than expected

Page 9: How Flexible Steel Pipe Helped Solve Five Challenges of

© 2019 FlexSteel Pipeline Technologies, Inc.

Copy

Copy

TYPICAL STEEL QUALITY

& SAFETY CHALLENGES

EXTERNAL CORROSION

INTERNALCORROSION

© 2019 FlexSteel Pipeline Technologies, Inc.

Page 10: How Flexible Steel Pipe Helped Solve Five Challenges of

© 2019 FlexSteel Pipeline Technologies, Inc. | 10

Solution: Corrosion-Resistant Liner

FLEXSTEEL

STEEL

Page 11: How Flexible Steel Pipe Helped Solve Five Challenges of

© 2019 FlexSteel Pipeline Technologies, Inc. | 11

Corrosion-Resistant Shield

FLEXSTEELSTEEL

© 2019 FlexSteel Pipeline Technologies, Inc.

Page 12: How Flexible Steel Pipe Helped Solve Five Challenges of

© 2019 FlexSteel Pipeline Technologies, Inc. | 12

Case Study: Multi-Purpose Pipeline

• Operator was adding new wells on a well pad and needed several new pipelines

• Solution was to install a single line in the ditch for the following services:

1. Fuel gas supply2. Frac water supply3. Multiphase production

• 12% reduction in the total cost of installation

• 4200 m of 6” 1500 psi Flexible Steel Pipe installed

• Pipeline was run through 3 HDD bores up to 670 m long

• Shield Integrity Testing performed

Dawson Creek, British Columbia

Page 13: How Flexible Steel Pipe Helped Solve Five Challenges of

© 2019 FlexSteel Pipeline Technologies, Inc. | 13

Challenge: Integrity Management

EXPENSIVE INTEGRITY

MANAGEMENT PIPELINE

DOWNTIME

REDUCED

FLOW RATES

Page 14: How Flexible Steel Pipe Helped Solve Five Challenges of

© 2019 FlexSteel Pipeline Technologies, Inc. | 14

Solution: Pipeline Rehabilitation

Up to 2 km of flexible steel pipe can be installed in a single pull

HOST PIPE

PIPE IN PIPE METHODOLOGY:

• Permanent solution for leak

prevention

• Minimal ground disturbance

• Host pipe can serve as a

secondary containment if integrity

maintained

Page 15: How Flexible Steel Pipe Helped Solve Five Challenges of

© 2019 FlexSteel Pipeline Technologies, Inc. | 15

Rocky Mountain House, Alberta

Case Study: Oil Emulsion Line

• Customer had integrity issues with 5,000 m of existing NPS 8 Oil Effluent pipeline– 3 river crossings, densely populated area: high

risk– Could not shut down for a long time due to

lost production

• Pipeline was rehabilitated with 6” 1500 psi Flexible Steel Pipe using pipe-in-pipe methodology– 6 pulls performed– Longest pull 1100 m

• Risk level reduced• Significant time and cost savings

– Production restored with less than 2 weeks downtime

Page 16: How Flexible Steel Pipe Helped Solve Five Challenges of

© 2019 FlexSteel Pipeline Technologies, Inc. | 16

Challenge: Pipeline Leaks

Leaks negatively affect:

The environment

Your company’s reputation

Bottom line

Page 17: How Flexible Steel Pipe Helped Solve Five Challenges of

© 2019 FlexSteel Pipeline Technologies, Inc. | 17

Fewer Joints – Less Chance for Leakage

Sample 5 km 8-Inch Pipeline Project

FLEXSTEEL: 12 CONNECTIONS STEEL: 277 WELD JOINTS

WELD JOINTS

FLEXSTEEL PIPE CONNECTIONS

Page 18: How Flexible Steel Pipe Helped Solve Five Challenges of

© 2019 FlexSteel Pipeline Technologies, Inc. | 18

Case Study: Edson, Alberta

Fiber-Optics Monitoring

4-Inch 3000 psi Flexible Steel Pipe

Installed through HDD bore

Fiber optic cables in a carrier installed

alongside FlexSteel

High-Fidelity Dynamic Sensing: integrated

acoustic + temperature + strain/vibration

- Pipeline leak detection

- 3rd party interference

*Pictures courtesy of HiFi Engineering

Page 19: How Flexible Steel Pipe Helped Solve Five Challenges of

© 2019 FlexSteel Pipeline Technologies, Inc. | 19

Summary

Fast deployment with less resources1

Environmentally friendly – HDD under sensitive areas2

Corrosion-resistant solution with little to no maintenance3

Excellent choice for cyclic service applications4

Great solution for pipeline rehabilitation using pipe-in-pipe methodology5

Leak detection capabilities reduce the chance of a leak6

Reduces overall construction and operating costs7