how flexible steel pipe helped solve five challenges of
TRANSCRIPT
© 2019 FlexSteel Pipeline Technologies, Inc.
Kirill Kovalenko, Technical Services Engineer
Cost-Effective Well Site Facilities Canada Congress
February 28, 2019
How Flexible Steel Pipe Helped Solve
Five Challenges of Pipeline Construction,
Operation, and Maintenance
© 2019 FlexSteel Pipeline Technologies, Inc. | 2
Agenda
Operators Challenges
Flexible Steel Pipe
Case Studies
Summary
1
2
3
4
© 2019 FlexSteel Pipeline Technologies, Inc. | 3
Copy
Challenges: Time + Resources
STEEL CONSTRUCTION AND MAINTENANCE
CHALLENGES
CORROSION CONTROL
MAINTENANCE AND REPAIR
RESOURCES AND TIME
Time + Resources = increased project cost
© 2019 FlexSteel Pipeline Technologies, Inc.
© 2019 FlexSteel Pipeline Technologies, Inc. | 4
Solution: Spoolable Pipeline
• Comes in long sections:– 380 to 2,000 m
• Installs much faster than steel pipe
• Accelerated time to production
• Minimal manpower and equipment requirement
• Smaller Right-of-Way
• No welding, field bending, X-ray, and coating costs
Flexible Steel Pipe
© 2019 FlexSteel Pipeline Technologies, Inc. | 5
Flexible Steel Pipe Structure
Steel Reinforcement
▪ Pressure Containment Layer
Corrosion Resistant Shield
▪ HDPE/PE-RT
Corrosion Resistant Liner
▪ HDPE/PE-RT
HDPE: High-Density Polyethylene
PE-RT: Polyethylene Raised-Temperature
© 2019 FlexSteel Pipeline Technologies, Inc. | 6
Flexible Steel Pipe Specifications
2 in. 3 in. 4 in. 6 in. 8 in.
DESIGN PRESSURE RANGE
750 PSI to 3000 PSI
OPERATING TEMPERATURE RANGE
- 40°C >>> 65°C >>> up to 90°C
High-pressure and high-rate capability
© 2019 FlexSteel Pipeline Technologies, Inc.
Copy
Copy
Welded Steel Flexible Steel Pipe
Installation significantly faster than conventional steel line pipe
© 2019 FlexSteel Pipeline Technologies, Inc.
© 2019 FlexSteel Pipeline Technologies, Inc. | 8
Grande Prairie, Alberta
Case Study: Water Pipeline
• A new well pad was constructed by the customer
• Frac water supply daily cost: – 22 trucks/day = $115,000/day
• A 4,000-m pipeline was urgently needed
• 8” 1500 psi Flexible Steel Pipe was chosen
• The line installed ~30% faster than their previous solution– 7 HDD bores and crossings, the longest
bore 700 m
• Trucking costs eliminated sooner than expected
© 2019 FlexSteel Pipeline Technologies, Inc.
Copy
Copy
TYPICAL STEEL QUALITY
& SAFETY CHALLENGES
EXTERNAL CORROSION
INTERNALCORROSION
© 2019 FlexSteel Pipeline Technologies, Inc.
© 2019 FlexSteel Pipeline Technologies, Inc. | 10
Solution: Corrosion-Resistant Liner
FLEXSTEEL
STEEL
© 2019 FlexSteel Pipeline Technologies, Inc. | 11
Corrosion-Resistant Shield
FLEXSTEELSTEEL
© 2019 FlexSteel Pipeline Technologies, Inc.
© 2019 FlexSteel Pipeline Technologies, Inc. | 12
Case Study: Multi-Purpose Pipeline
• Operator was adding new wells on a well pad and needed several new pipelines
• Solution was to install a single line in the ditch for the following services:
1. Fuel gas supply2. Frac water supply3. Multiphase production
• 12% reduction in the total cost of installation
• 4200 m of 6” 1500 psi Flexible Steel Pipe installed
• Pipeline was run through 3 HDD bores up to 670 m long
• Shield Integrity Testing performed
Dawson Creek, British Columbia
© 2019 FlexSteel Pipeline Technologies, Inc. | 13
Challenge: Integrity Management
EXPENSIVE INTEGRITY
MANAGEMENT PIPELINE
DOWNTIME
REDUCED
FLOW RATES
© 2019 FlexSteel Pipeline Technologies, Inc. | 14
Solution: Pipeline Rehabilitation
Up to 2 km of flexible steel pipe can be installed in a single pull
HOST PIPE
PIPE IN PIPE METHODOLOGY:
• Permanent solution for leak
prevention
• Minimal ground disturbance
• Host pipe can serve as a
secondary containment if integrity
maintained
© 2019 FlexSteel Pipeline Technologies, Inc. | 15
Rocky Mountain House, Alberta
Case Study: Oil Emulsion Line
• Customer had integrity issues with 5,000 m of existing NPS 8 Oil Effluent pipeline– 3 river crossings, densely populated area: high
risk– Could not shut down for a long time due to
lost production
• Pipeline was rehabilitated with 6” 1500 psi Flexible Steel Pipe using pipe-in-pipe methodology– 6 pulls performed– Longest pull 1100 m
• Risk level reduced• Significant time and cost savings
– Production restored with less than 2 weeks downtime
© 2019 FlexSteel Pipeline Technologies, Inc. | 16
Challenge: Pipeline Leaks
Leaks negatively affect:
The environment
Your company’s reputation
Bottom line
© 2019 FlexSteel Pipeline Technologies, Inc. | 17
Fewer Joints – Less Chance for Leakage
Sample 5 km 8-Inch Pipeline Project
FLEXSTEEL: 12 CONNECTIONS STEEL: 277 WELD JOINTS
WELD JOINTS
FLEXSTEEL PIPE CONNECTIONS
© 2019 FlexSteel Pipeline Technologies, Inc. | 18
Case Study: Edson, Alberta
Fiber-Optics Monitoring
4-Inch 3000 psi Flexible Steel Pipe
Installed through HDD bore
Fiber optic cables in a carrier installed
alongside FlexSteel
High-Fidelity Dynamic Sensing: integrated
acoustic + temperature + strain/vibration
- Pipeline leak detection
- 3rd party interference
*Pictures courtesy of HiFi Engineering
© 2019 FlexSteel Pipeline Technologies, Inc. | 19
Summary
Fast deployment with less resources1
Environmentally friendly – HDD under sensitive areas2
Corrosion-resistant solution with little to no maintenance3
Excellent choice for cyclic service applications4
Great solution for pipeline rehabilitation using pipe-in-pipe methodology5
Leak detection capabilities reduce the chance of a leak6
Reduces overall construction and operating costs7