How one of the UK’s largest SAP implementations saved money and improved performance. Lee Harris, Programme Manager. Outline of Presentation. Background Programme Overview Functionality Implemented Benefits Achieved. Royal Mail. Facts & Figures Turnover £8,408m, 224k employees - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: How one of the UK’s largest SAP implementations saved money and improved performance

Hosted by

How one of the UK’s largest SAP implementations saved money and improved performance

Lee Harris, Programme Manager

Page 2: How one of the UK’s largest SAP implementations saved money and improved performance

Hosted by

Outline of Presentation

Background

Programme Overview

Functionality Implemented

Benefits Achieved

Page 3: How one of the UK’s largest SAP implementations saved money and improved performance

Hosted by

Royal Mail

Facts & Figures

Turnover £8,408m, 224k employees

Delivers letters and parcels to 27m UK addresses, Operates

17,500 retail outlets

1 Shareholder – UK Government

Regulated Industry (PostComm) but still required to provide

Universal Service Obligation.

Page 4: How one of the UK’s largest SAP implementations saved money and improved performance

Hosted by

Why are we doing this?

Page 5: How one of the UK’s largest SAP implementations saved money and improved performance

Hosted by

The Issues

De-centralised Businesses lack of

corporate focus

Page 6: How one of the UK’s largest SAP implementations saved money and improved performance

Hosted by

The Issues

Multiple Systems and processes 10 significant legacy financial systems (inc. JBA, Walker

Financials, Oracle and SAP).

Numerous variations on common processes mainly paper

driven or local PC solutions with no integration to financials.

Aspiration to become an e-business difficult to support with

current landscape.

Page 7: How one of the UK’s largest SAP implementations saved money and improved performance

Hosted by

The Issues

Financial Backdrop

Underlying profitability was deteriorating.

Availability and consistency of financial performance information.

Planning was an annual event with 1 year horizon, which took 6

months.

On-set of regulation would furnish additional information

demands.

Page 8: How one of the UK’s largest SAP implementations saved money and improved performance

Hosted by

The Solution

Single SAP ERP for Royal Mail

1 common Chart of accounts across all business operations

Common finance processes, e-enabled where ever possible

Cycle time improvements for results production from one-set

of numbers.

“Getting a grip of the numbers”

Page 9: How one of the UK’s largest SAP implementations saved money and improved performance

Hosted by

Programme Overview

Enterprise System Programme (ESP)

Programme initiated in early 2000, with SAP as strategic

technology choice.

ITT led to selection of implementation partner – Deloitte

Consulting.

Programme created with a mix of Internal process experts,

Royal Mail IT staff and supplemented with External Consultants

as required.

Page 10: How one of the UK’s largest SAP implementations saved money and improved performance

Hosted by

Programme Overview

Programme Scope

18 Individual Business Units

Over 7000 users (inc 4,000 EBP users).

8,500 Profit/Cost Centres.

40,000 vendors & 250,000 business customers

1.5m invoices per annum.

Page 11: How one of the UK’s largest SAP implementations saved money and improved performance

Hosted by

Programme Overview

Early Major Decisions

Single CO area.

Roll-out strategy (Functionality, Business Unit or by legacy system).

Business Unit ownership – Implementation Managers.

Technology Choices (Workplace, EBP).

Establish a specific governance group to chase benefit achievement.

Page 12: How one of the UK’s largest SAP implementations saved money and improved performance

Hosted by

Programme OverviewIMPLEMENTATION TIMELINE

Phase 1

04/00 - 11/00 11/00 – 07/01

Phase 2

12/01 – 03/02

Phase 3

08/01 –11/01

• EBP Pilot

R/3

• 5 BU’s

• FI/CO, EBP, AM, PM & MM

R/3

• 8 BU’s

• RE - Prototype

R/3

•6 BU’s

• RE, PS

Blueprint

R/3

• Blueprint

Page 13: How one of the UK’s largest SAP implementations saved money and improved performance

Hosted by

Functionality Overview

Page 14: How one of the UK’s largest SAP implementations saved money and improved performance

Hosted by

R/3 SCOPE : Version 4.6c

Procurement

InventoryManagement

PlantMaintenance

CashManagement

AssetManagement

Projects

RevenueManagement

EBP

MM

IM

PM

SD

FI-CA

AM

PS

TreasuryFinancial

Accounting

Inter-Business

ManagementReporting

FI

CO

Real EstateRE

Functionality Overview

Page 15: How one of the UK’s largest SAP implementations saved money and improved performance

Hosted by

Functionality Overview

Key Functionality:

EBP – new functionality, incomplete content, piloted the

technology first (100 days) – before productionising.

RE – Real Estate no previous UK versions, prototyped before

developed (prototyping didn’t expose all the integration

issues encountered later).

Page 16: How one of the UK’s largest SAP implementations saved money and improved performance

Hosted by

Functionality Overview

Gaps in Solution

Demands from Regulator starting to materialise, which pose

challenges for R/3 to handle.

• Costing

• Planning

Performance Management loop not closed by ERP alone.

Page 17: How one of the UK’s largest SAP implementations saved money and improved performance

Hosted by

Functionality Review

Programme Response

Initiated additional project to deliver:

• Business Warehouse Reporting Flexibility (BW2.1c)

• Strategic Enterprise Management (SEM 3.0)

Also replaced AB Costing solution with Oros (SAS), including

unique “bridge” to BW for distributed reporting.

Page 18: How one of the UK’s largest SAP implementations saved money and improved performance

Hosted by

R/3 Data Sources

SEM-BPSBusiness

Planning andSimulation

SEM-BPSBusiness

Planning andSimulation

OROSRevenue and Cost Model

OROSRevenue and Cost Model

Bridge

SEM-BCSBusiness

Consolidation

SEM-BCSBusiness

Consolidation

SDPRISDPRI

HUB

BW/SEM Scope

SAP BWReportingReporting

PayrollLedger

PayrollLedger

Page 19: How one of the UK’s largest SAP implementations saved money and improved performance

Hosted by

Programme OverviewIMPLEMENTATION TIMELINE

Phase 1

04/00 - 11/00 11/00 – 07/01

Phase 2

12/01 – 03/02

Phase 3

08/01 –11/01

• EBP Pilot

R/3

• 5 BU’s

• FI/CO, EBP, AM, PM & MM

R/3

• 8 Bu’s

• RE - Prototype

R/3 & BW

• 6 BU’s

• RE, PS & BW Functionality

03/02 – 10/02

Blueprint

R/3

• Blueprint

Phase 3 (a)

R/3, BW & SEM

•BCS / BPS Functionality

Page 20: How one of the UK’s largest SAP implementations saved money and improved performance

Hosted by

Somebody has to pay for all of this don’t they?

Page 21: How one of the UK’s largest SAP implementations saved money and improved performance

Hosted by

Programme Benefits

Targeted Benefits - Financial

Replacement of legacy applications.

Process Efficiencies – Reduction in Headcount.

Improved Control – Controlling demand (e.g.utilities / cleaning etc)

Supplier price reductions (conformance and supplier efficiencies)

Inventory reduction (JIT & automatic re-order levels)

Page 22: How one of the UK’s largest SAP implementations saved money and improved performance

Hosted by

Programme Benefits

Targeted Benefits – Non Financial Performance reporting, Product/Customer profitability,

regulatory and statutory accounts are all produced from a

common source.

Flash results available within 2 days of period close.

Actual product profitability reported on day 15 each month

(previously quarterly).

Business Plans consolidated in a day (previously 2 weeks).

Page 23: How one of the UK’s largest SAP implementations saved money and improved performance

Hosted by

Investment Costs & Benefits

0

20

40

60

80

100

120

140

99-01 01-02 02-03 03-04 04-05 05-06

Financial Year

£m

Cumulative Benefit

Cumulative Cost

Sunk £86mTotal £103m

Rec. Benefit

£37m

Page 24: How one of the UK’s largest SAP implementations saved money and improved performance

Hosted by

Programme Benefits

Measures of Success

Financial Benefit achievement

Stakeholder Perception of Programme

End user Perception

Non Financial Results.

Page 25: How one of the UK’s largest SAP implementations saved money and improved performance

Hosted by

Programme Benefits

Enablers of Success

Keep it lean and mean – provides pace!

Business Ownership – Solutions Team, Implementation

Managers, ASAP methodology.

Focused Board securing benefits (inc. Implementation

partners “skin in the game”).

LEADERSHIP – within the Programme and the Business..

Page 26: How one of the UK’s largest SAP implementations saved money and improved performance

Hosted by

Programme Benefits

Still to Finish!

Revenue management (SD/FI-CA).

Sustaining the gains!

Page 27: How one of the UK’s largest SAP implementations saved money and improved performance

Hosted by

Thank You