DGA/XXXX 14-Mar-03 Diapositive N°1 / 000MINISTÈRE DE LA DÉFENSE
How T&E reduces defense programs risks :a French perspective
By LtGen Daniel ReydelletDirector Test & Evaluation centers
DGA/DCE 25 February 2003 Slide N°2MINISTÈRE DE LA DÉFENSE
Organization Chart :Organization Chart : MoD MoD
Armament GeneralDelegation
Ministry of Defense
Air Force Army Navy
Joint Chief of Staff Strategic Affairs Delegation
OrganizationOrganization
DGA/DCE 25 February 2003 Slide N°3MINISTÈRE DE LA DÉFENSE
Organization Chart : DGAOrganization Chart : DGA
Armament programs
Directorate forForce systems and
Prospective analysisDSP
Deputy-Directorfor
Weapon systemsAD-A
Directorate forProcurement policyand Quality control
DPM
Directorate forTest and Evaluation
CentersDCE
Directorate forTest and Evaluation
CentersDCE
Service forAeronauticalMaintenance
SMA
Directorate forManagement and
OrganizationDGO
Directorate forCooperation and
Industrial strategyDCI
Directorate forInternational
RelationsDRI
Directorate forHuman resources
DRH
SPARTSPAé SPN
SPMT SPOTI SPNuc
DGA/DCE 25 February 2003 Slide N°4MINISTÈRE DE LA DÉFENSE
CEV, CAP
DIRECTOR
Military advisor
Deputy DirectorGeneral affairs
Deputy DirectorOperations
Technical Human resources Cooperation &marketing
Accounting &Procurement
CEPr, CAEPE, CEAT
CEL, Monge, CEMGESMA, GERBAM
LRBA, CELARBASSIN, CTSN
ETAS, CEBCTA, CEG, ETBS
Flight Tests
Airframe, Equipmentand
Propulsion TestingMissile Testing
Ground Systems,Pyrotechnics andProtection Trials
Naval Systemsand RecurrentTechnology
Overall OrganizationOverall Organization
DGA/DCE 25 February 2003 Slide N°5MINISTÈRE DE LA DÉFENSE
A decentralized organizationA decentralized organization
TOULON
LORIENTANGERS
BOURGES
VERT le PETIT
GRAMAT
ST-MEDARD
BRÉTIGNY
ARCUEIL
PARIS
VERNON
SACLAY
ST-CLOUD
VAL de REUIL
RENNES
BREST
BISCARROSSE CAZAUX
ISTRESTOULOUSE
• 18 CENTERS
• Workforce of 8,000including 1,900scientists, professionalengineers and high levelmanagers
• Investment M€ 100
• Turnover G€ 0,7
DGA/DCE 25 February 2003 Slide N°6MINISTÈRE DE LA DÉFENSE
DIRECTOR
BU1 BU2 BU3 BU4 BU5
Business developement &
management
Technical& investmentmanagement
18 « production » centers
5 Business Units
CUSTOMER
A matrix approach for the mainA matrix approach for the maintransverse functionstransverse functions
DGA/DCE 25 February 2003 Slide N°7MINISTÈRE DE LA DÉFENSE
Close Close links with programs officeslinks with programs offices
l based upon 2 key principles :
n A systematic contract for each task performed
n A focal point in charge of T&E issues isdesignated for each program as part of theIntegrated Project Team : the “RESA”
DGA/DCE 25 February 2003 Slide N°8MINISTÈRE DE LA DÉFENSE
How T&E reduces defense How T&E reduces defenseprograms risksprograms risks
l T&E too often seen as a programmatic riskl T&E only to check the performances
n Too laten Risks added to the program
l Technology outbidding / Cost effectivenessn risk reduction
Spend money on T&E earlier
DGA/DCE 25 February 2003 Slide N°9MINISTÈRE DE LA DÉFENSE
Toward a modeling of T&E Costs ...Toward a modeling of T&E Costs ...
0
1
2
3
4
5
6
7
8
9
10
Préparation Faisabilité Définition Développement - indus Production
Global
Expertise
Essais
High Risk / Low T&E Costs
Low Risk / High T&E Costs
DGA/DCE 25 February 2003 Slide N°10MINISTÈRE DE LA DÉFENSE
How T&E reduces defense How T&E reduces defenseprograms risksprograms risks
l Risk management is today a major issue
l T&E has a major role to play
l Relationship between the T&E communityand the program managers at all stages ofthe acquisition process
DGA/DCE 25 February 2003 Slide N°11MINISTÈRE DE LA DÉFENSE
How T&E reduces defense How T&E reduces defenseprograms risksprograms risks
l T&E has a crucial role to play during theScience & Technology phase
n reduce technical risks
n Expertise, Test & Evaluation
l Involvement of DCE as early as possible
DGA/DCE 25 February 2003 Slide N°12MINISTÈRE DE LA DÉFENSE
How T&E reduces defense How T&E reduces defenseprograms risksprograms risks
l T&E community must define all the tasksneeded to be performed during theconception and realization phases
l Risk sharing with industryn evaluation through a balanced and
contradictory analysisn high level of expertise required
l Test servicesl Expert and independent advice
DGA/DCE 25 February 2003 Slide N°13MINISTÈRE DE LA DÉFENSE
How T&E reduces defense How T&E reduces defenseprograms risksprograms risks
ConceptionPreparation Realization In service Use
Feasibility Definition
Risk reductionRisk Management Plan
DGA/DCE 25 February 2003 Slide N°14MINISTÈRE DE LA DÉFENSE
Airworthiness of the integration of anon-piloted aircraft
DGA/XXXX 14-Mar-03 Diapositive N°15 / 000MINISTÈRE DE LA DÉFENSE
FREE-JET TESTING AT CEPrFREE-JET TESTING AT CEPr« CHEFREN » TEST INSTALLATION« CHEFREN » TEST INSTALLATION
A new test installation, unique in the worldA new test installation, unique in the world
•• means required means required to to produce produce aafree-jet testfree-jet test
••CHEFREN test installationCHEFREN test installationspecificitiesspecificities
•• advantages advantages to gain to gain fromfromCHEFREN test installationCHEFREN test installation
DGA/DCE 25 February 2003 Slide N°16MINISTÈRE DE LA DÉFENSE
Means requiredMeans required to to produce produce a free-jet testa free-jet test
The test cell :
altitude test cell
Downstream :
Air extraction
(low pressurearound thetested missileless than 0.1bar)
Upstream :
Air supply
• hot(300-400°C)
• compressed(7 bars)
• dry
• high massflow rate(>200 kg/s)
FREE-JET TESTING = TEST CELL + AIR FLOW GENERATION MEANS
DGA/DCE 25 February 2003 Slide N°17MINISTÈRE DE LA DÉFENSE
CHEFREN Test Installation : CHEFREN Test Installation : means means of of reduction reduction of of risksrisks
⌦ …and two specificities that are unique in theworld :
• Dynamic variation of altitude
• Dynamic variation of attitude (incidence etsideslip)
Reproductionof the flight
TRAJECTORY
⌦Common specificities with free-jet testing...
•Production of speed conditions by acceleratingthe compressed hot air inside the Mach nozzle,
• Production of altitude conditions thanks to thelow pressure around the missile, equal to thestatic pressure of the real flight
Reproductionof real flightconditionsaround the
missile
DGA/DCE 25 February 2003 Slide N°18MINISTÈRE DE LA DÉFENSE
Advantages Advantages to gain to gain from from CHEFREN testCHEFREN testinstallation ?installation ?
GLOBAL COST REDUCTION
RELIABILITY
RISKS REDUCTION
ADAPTABILITY
ADAPTABILITY :
- the speed can change by adapting the Mach nozzle,
- the altitude range can be extended within the specimen dimensions
GLOBAL COST REDUCTION on the assessment on weapon systems :- non destructive and renewable test,
- continuous air flow generation at CEPr enables to carry on many testswithin a day,
RELIABILITY: a significant number of high altitude test points can becarried on before real flight tests, and repeated if required during thedevelopment,
RISKS REDUCTION :
- exploration of non tested points during real flight tests to validate runningmargins,
- exhaustiveness of measured data (no limitation due to telemetry as on realflight tests),
DGA/DCE 25 February 2003 Slide N°19MINISTÈRE DE LA DÉFENSE
Conclusion Conclusion
l Independent T&E functionl Involvement in the very early stage of the
programl High level of technical expertisel Implementation of an integrated process with
the Program Officel “Testing is for learning and reducing the
risks”