ENGINEERING AND CONSTRUCTION
DEPARTMENT
LUZON, VISAYAS AND MINDANAO
DECA HOMES PRECAST TECHNOLOGY
TIME DURATION: 8 DAYS
CONDITIONS:- GOOD WEATHER- FLAT TERRAIN- ALL EQUIPMENTS ARE OPERATIONAL- SUFFICIENT MANPOWER- COMPLETE MATERIALS- LAND DEVELOPMENT WORKS IN PLACE
DECA HOMES PRECAST TECHNOLOGY- CASTING
PROCUREMENT OF MATERIALS: DAY 1
DECA HOMES PRECAST TECHNOLOGY- CASTING
REINFORCING BARS PREPARATION: DAY 1
DECA HOMES PRECAST TECHNOLOGY- CASTING
FORM OIL APPLICATION: DAY 1
DECA HOMES PRECAST TECHNOLOGY- CASTING
PLACEMENT AND SETTING OF REINFORCING BARS: DAY 1
DECA HOMES PRECAST TECHNOLOGY- CASTING
QUALITY CONTROL INSPECTION: DAY 1
DECA HOMES PRECAST TECHNOLOGY- CASTING
RMC POURING: DAY 1
DECA HOMES PRECAST TECHNOLOGY- CASTING
RMC SAMPLING AND TESTING: DAY 1
DECA HOMES PRECAST TECHNOLOGY- GROUND SLAB (separate activity-should be advanced)
FOUNDATION (ZOCALLO FOOTING AND SLAB ON FILL)
DECA HOMES PRECAST TECHNOLOGY- GROUND SLAB (separate activity-should be advanced)
FOUNDATION (ZOCALLO FOOTING AND SLAB ON FILL)
DECA HOMES PRECAST TECHNOLOGY- GROUND SLAB (separate activity-should be advanced)
FOUNDATION (ZOCALLO FOOTING AND SLAB ON FILL)
DECA HOMES PRECAST TECHNOLOGY- ERECTION
LIFTING, TRANSPORT AND STOCK PILE OF PANELS: DAY 2
DECA HOMES PRECAST TECHNOLOGY- ERECTION
ERECTION OR ASSEMBLY: DAY 2
DECA HOMES PRECAST TECHNOLOGY- ERECTION
PANEL ALIGNMENT, LEVEL, AND WELDING – DAY 2
First panel installed shown with the support
Actual checking of alignment of a panel
Actual welding of interconnecting bar and
dowel on footing
DECA HOMES PRECAST TECHNOLOGY- ERECTION
DECA HOMES PRECAST TECHNOLOGY- FINISHING
MASONRY RETOUCHING: DAY 3 TO 5
DECA HOMES PRECAST TECHNOLOGY- FINISHING
CORNICE AND MOULDINGS: DAY 3 TO 5
TRELLIS ON FABRICATION FORM
WINDOW CORNICE ON FABRICATION FORM
DECA HOMES PRECAST TECHNOLOGY- FINISHING
CORNICE AND MOULDINGS: DAY 3 TO 5
ACTUAL INSTALLATION OF TRELLIS
WINDOW CORNICE (AS INSTALLED)
DECA HOMES PRECAST TECHNOLOGY- FINISHING
ROOFING: DAY 3 TO 5
EXTERIOR CEILING INSTALLATION (G.I. CEILING BOARDS)
INSTALLATION OF ROOFING SHEETS
INSTALLATION OF FLASHINGS
INSTALLATION OF ROOF RIDGE
DECA HOMES PRECAST TECHNOLOGY- FINISHING
CEILING WORKS: DAY 3 TO 5
INSTALLATION OF CEILING FRAMES
INSTALLATION OF CEILING BOARDS
DECA HOMES PRECAST TECHNOLOGY- FINISHING
PAINTING AND DETAILING WORKS: DAY 5 TO 8
DECA HOMES PRECAST TECHNOLOGY
FINISHED HOUSE UNIT
DECA HOMES PRECAST TECHNOLOGY
SAMPLE HOUSE IMPROVEMENTS (NOT INCLUDED DURING TURN OVER)
DECA HOMES PRECAST TECHNOLOGY
FINISHED HOUSE UNIT