how we retro-cx 4m sf in four months

32
How We Retro-Cx 4M sf in Four Months St. Louis Green Business Challenge

Upload: nguyenque

Post on 01-Jan-2017

212 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: How We Retro-Cx 4M sf in Four Months

How We Retro-Cx 4M sf in Four Months

St. Louis Green

Business Challenge

Page 2: How We Retro-Cx 4M sf in Four Months

David Meyers, AIA, CxA, PMP, LEED AP

Manager of Commissioning Mr. Meyers is a Certified Commissioning Authority and Program Manager who has been responsible for the commissioning of more than 9.2 million square feet of combined construction costing more than $4.4 billion. He has additionally been responsible for leading the retro-commissioning of over 6.3 million square feet of existing building space, and specializes in leading complex programs comprised of diverse technical disciplines.

Carl Poettker, EIT, LEED AP, CxA

Commissioning Agent Mr. Poettker has managed and executed comprehensive commissioning and retro-commissioning services for new construction and existing facilities in the higher education, mission critical data center and healthcare industries. He has interfaced with clients, design teams, vendors and trades while aiding in the design of MEP systems, and implemented solutions to adapt to field conditions and post-bid owner requests. Carl’s experience also includes the design of custom HVAC solutions for commercial and light industrial applications.

Presenters

Page 3: How We Retro-Cx 4M sf in Four Months

Strength ► $2.0B Revenue

► Full Service

► Engineering, Construction, Consulting

► 11 Global Practices

► Licensed in all 50 states

Stability ► Growth during recession

► <4% employee turnover

Service ► 85%+ repeat client base

► Relationship driven

► Top 10 MEP Giant CSE

► #18 ENR Top 500

Company Profile

Page 4: How We Retro-Cx 4M sf in Four Months

Resources ► Dedicated Cx Practice

► 118 Cx Professionals

► Discipline Specific

Capability ► New Construction Cx

► Existing Building Cx

► Building Enclosure Cx

► Monitoring Based Cx

► Energy Audits

► M&V

Recent Experience ► > $8 Bil new Cx

► > 23 Mil SF Retro-Cx

► >200 LEED Projects

National Commissioning Practice

Page 5: How We Retro-Cx 4M sf in Four Months

United States Airport System - Terminal Retro-Cx

► Four Terminals / 4,500,000 square feet

► HVAC Investigation Phase Only

► Condition Assessment

► O&M Staff Involvement / CMMS Integration

► 12 Commissioning Specialists

► Over $1,600,000 Annual Energy Savings

Page 6: How We Retro-Cx 4M sf in Four Months

► Restores and enhances owner’s performance requirements Comfort

Energy

Reliability

Productivity

O&M, etc.

► Custom Database Software Retro-Cx

Condition Assessment

GIS Location

CMMS Integration

Barcode Tracking

Real Time Database

Web Enabled

• Digital Photos

Burns & McDonnell Existing System Commissioning

Page 7: How We Retro-Cx 4M sf in Four Months

Energy Conservation Measures (ECMs) The Issues We Find Save Energy

Low Cost/No Cost ECMs

► Equipment Scheduling

Reduce operating schedules where possible

► Simultaneous Heating and Cooling

Eliminate (dehumidification is an exception)

► Controls and Sensor Calibration

Is the BAS controlling to the actual conditions

► Control Volume of Outside Air

Minimize heating cold air, and cooling hot air

Page 8: How We Retro-Cx 4M sf in Four Months

Double click on Terminal Asset Collection Icon

Retro-Cx & Condition Assessment Software

CMMS

Page 9: How We Retro-Cx 4M sf in Four Months

The App – GIS Spatial Location of

Assets

Page 10: How We Retro-Cx 4M sf in Four Months

The Web Site – Realtime Database Portal

Page 11: How We Retro-Cx 4M sf in Four Months

Asset Information Collect data on the equipment

Page 12: How We Retro-Cx 4M sf in Four Months

The App – Collect Asset Data In the Field

Page 13: How We Retro-Cx 4M sf in Four Months

The Web Site – View Collected Data in Realtime

Page 14: How We Retro-Cx 4M sf in Four Months

Retro-Cx Tab Energy Savings Data Collection

Page 15: How We Retro-Cx 4M sf in Four Months

The App – Equipment Configuration

Page 16: How We Retro-Cx 4M sf in Four Months

The App – Motor Data

Page 17: How We Retro-Cx 4M sf in Four Months

The App – Fan Configuration

Page 18: How We Retro-Cx 4M sf in Four Months

• Hr/Day and Hr/Week calculate automatically

• When entering 24 hr/day operation, use 12:00

AM Occupied, 11:30 PM Unoccupied

The App – Schedule Information

Page 19: How We Retro-Cx 4M sf in Four Months

The App – Temperature and Trend Data

Page 20: How We Retro-Cx 4M sf in Four Months

Fluid Flow Section is primarily

used for date entry associated

with heat exchangers.

Enter data from field

observations, name plate, BAS,

or mechanical schedules as

they are available.

The App – Fluid Flow Information

Page 21: How We Retro-Cx 4M sf in Four Months

The App – VAV Flow Information

Page 22: How We Retro-Cx 4M sf in Four Months

The App – VFD Parameters

Page 23: How We Retro-Cx 4M sf in Four Months

The App – Pump Operating Data

Page 24: How We Retro-Cx 4M sf in Four Months

The App – Diagram As-Built Configuration

Page 25: How We Retro-Cx 4M sf in Four Months

The Web Site – Realtime Reporting and Editing

Page 26: How We Retro-Cx 4M sf in Four Months

Functional Performance Test Dynamically test the system

Page 27: How We Retro-Cx 4M sf in Four Months

The App – Functional Performance Test

Page 28: How We Retro-Cx 4M sf in Four Months

The Web Site – Realtime Test Data

Page 29: How We Retro-Cx 4M sf in Four Months

Issues Identify and track issues

Page 30: How We Retro-Cx 4M sf in Four Months

The App – Photographic Issue Identification

Page 31: How We Retro-Cx 4M sf in Four Months

The Web Site – Realtime Issue Review & Verification

Page 32: How We Retro-Cx 4M sf in Four Months

Questions