hpcl-mittal pipelines...

34
HPCL-MITTAL PIPELINES LIMITED (A wholly owned Subsidiary of HMEL) Registered Office : Village Phulokhari, Taluka Talwandi Saboo, Bathinda, Punjab-151301 Corporate Office : Inox Towers, Plot No. 17, Sector 16A, Noida-201301 in the State of Uttar Pradesh. Tel : 0120 – 463 4500/4610, Fax : 0120-42719 38/39/40. Application as per Form 1 of the EIA Notification 2006: Mundra – Bathinda Pipeline Capacity Expansion Project NOVEMBER 2015

Upload: vuongdien

Post on 16-May-2018

222 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: HPCL-MITTAL PIPELINES LIMITEDenvironmentclearance.nic.in/writereaddata/modification/PreviousTOR/... · HPCL-MITTAL PIPELINES LIMITED (A wholly owned Subsidiary of HMEL) Registered

HPCL-MITTAL PIPELINES LIMITED (A wholly owned Subsidiary of HMEL)

Registered Office : Village Phulokhari, Taluka Talwandi Saboo, Bathinda, Punjab-151301

Corporate Office : Inox Towers, Plot No. 17, Sector 16A, Noida-201301 in the State of Uttar Pradesh. Tel : 0120 – 463 4500/4610, Fax : 0120-42719 38/39/40.

Application as per Form 1 of the EIA Notification 2006: Mundra – Bathinda Pipeline Capacity Expansion Project

NOVEMBER 2015

Page 2: HPCL-MITTAL PIPELINES LIMITEDenvironmentclearance.nic.in/writereaddata/modification/PreviousTOR/... · HPCL-MITTAL PIPELINES LIMITED (A wholly owned Subsidiary of HMEL) Registered

M/S HPCL-MITTAL PIPELINES LTD CAPACITY EXPANSION OF MUNDRA – BATHINDA CRUDE OIL PIPELINE FORM 1

M/S HPCL-MITTAL PIPELINES LTD | NOVEMBER’ 2015 1

Application as per Form 1 of the EIA Notification 2006: Mundra – Bathinda Pipeline Capacity Expansion Project

This report is released for the use of the HPCL-Mittal Pipelines Limited, Regulators and relevant

stakeholders solely as part of the subject project’s Environmental Clearance process. Information

provided (unless attributed to referenced third parties) shall not be used for any other purpose

without the written consent of HPCL-Mittal Pipelines Limited.

QUALITY CONTROL

Name of

Publication Form 1: Mundra – Bathinda Pipeline Capacity Expansion Project

Project

Number 2015-16-01

Report

No. 1 Version 1 Released November 2015

Prepared By Prodip Kumar Biswas, AGM - Pipeline

Reviewed By Pawan Kumar Agarwal, GM - Pipeline

Released By Prodip Kumar Biswas, AGM - Pipeline

DISCLAIMER

HPCL-Mittal Pipelines Limited has taken all reasonable precautions in the preparation of this report as per its

auditable quality plan. HPCL-Mittal Pipelines Limited also believes that the facts presented in the report are

accurate as on the date it was written. However, it is impossible to dismiss absolutely, the possibility of errors or

omissions. HPCL-Mittal Pipelines Limited therefore specifically disclaims any liability resulting from the use or

application of the information contained in this report. The information is not intended to serve as legal advice

related to the individual situation.

Page 3: HPCL-MITTAL PIPELINES LIMITEDenvironmentclearance.nic.in/writereaddata/modification/PreviousTOR/... · HPCL-MITTAL PIPELINES LIMITED (A wholly owned Subsidiary of HMEL) Registered

M/S HPCL-MITTAL PIPELINES LTD CAPACITY EXPANSION OF MUNDRA – BATHINDA CRUDE OIL PIPELINE FORM 1

M/S HPCL-MITTAL PIPELINES LTD | NOVEMBER’ 2015 2

CONTENTS

1 SCOPING .................................................................................. 5

2 PROPOSED TERMS OF REFERENCE ............................................... 19

Page 4: HPCL-MITTAL PIPELINES LIMITEDenvironmentclearance.nic.in/writereaddata/modification/PreviousTOR/... · HPCL-MITTAL PIPELINES LIMITED (A wholly owned Subsidiary of HMEL) Registered

M/S HPCL-MITTAL PIPELINES LTD CAPACITY EXPANSION OF MUNDRA – BATHINDA CRUDE OIL PIPELINE FORM 1

M/S HPCL-MITTAL PIPELINES LTD | NOVEMBER’ 2015 3

LIST OF ANNEXURES

1 SCOPING .................................................................................. 5

2 PROPOSED TERMS OF REFERENCE ............................................... 19

ANNEXURE 1: PIPELINE ROUTE MAP ............................................................... 22

ANNEXURE 2: TOPOGRAPHY OF IPS-1, IPS-2, IPS-3, IPS-4 & IPS-5 LOCATIONS AND

AREAS WITHIN 10 KM RADIUS SHOWING ROADS, ADJACENT

LOCALITIES, FORESTS, WATER BODIES, PROTECTED AREAS, STATE &

NATIONAL BOUNDARIES (IF ANY) ............................................... 23

ANNEXURE 3: CGWA CATEGORIZATION OF TALUKAS . ........................................ 28

ANNEXURE 4: HAZARDOUS WASTE – TYPE, MODE AND DISPOSAL ........................ 32

Page 5: HPCL-MITTAL PIPELINES LIMITEDenvironmentclearance.nic.in/writereaddata/modification/PreviousTOR/... · HPCL-MITTAL PIPELINES LIMITED (A wholly owned Subsidiary of HMEL) Registered

M/S HPCL-MITTAL PIPELINES LTD CAPACITY EXPANSION OF MUNDRA – BATHINDA CRUDE OIL PIPELINE FORM 1

M/S HPCL-MITTAL PIPELINES LTD | NOVEMBER’ 2015 4

ABBREVIATIONS

API American Petroleum Institute

ASME American Society of Mechanical Engineers

DG Diesel generator

ESD Emergency Shut Down

FV Full Vacuum

HDPE High Density Polyethylene

IEC International Electro technical Commission

IJ Insulating Joint

IPS Intermediate Pigging Station

ISA International Society of Automation

MOC Material of Construction

MBPL Mundra-Bathinda Pipeline

MMTPA Million Metric ton per Annum

MSL Mean Sea Level

NBP Nominal Boiling Point

OFC Optical Fiber Cable

OISD Oil Industry Safety Directorate

PFD Process Flow Diagram

PUF Polyurethane Foam

PE Polyethylene

RCC Reinforced Cement Concrete

RJ Rajasthan

SCADA Supervisory Control And Data Acquisition

XSV Emergency Shutdown Valve

Page 6: HPCL-MITTAL PIPELINES LIMITEDenvironmentclearance.nic.in/writereaddata/modification/PreviousTOR/... · HPCL-MITTAL PIPELINES LIMITED (A wholly owned Subsidiary of HMEL) Registered

M/S HPCL-MITTAL PIPELINES LTD CAPACITY EXPANSION OF MUNDRA – BATHINDA CRUDE OIL PIPELINE FORM 1

M/S HPCL-MITTAL PIPELINES LTD | NOVEMBER’ 2015 5

1 SCOPING

The scoping for the project has been done based on FORM 1, as per EIA Notification, dated September 14, 2006

amended as on date. The scoping details are as follows:

I. Basic Information

S.

No. Item Details

1 Name of the Project/s Mundra – Bathinda Pipeline Capacity Expansion Project

2 S. No. in the Schedule 6(a) & 6(b)

3

Proposed capacity / area / length /

tonnage to be handled/ command

area / lease area / no. of wells to

be drilled

Capacity expansion of Mundra – Bathinda Crude Oil Pipeline from 9 MMTPA to

11.25 MMTPA by converting 2 of its existing intermediate pigging stations into

pumping stations.

4 New / Expansion / Modernization Expansion

5 Existing Capacity / Area etc. 9 MMTPA

6 Category of Project (A or B) A

7 Does it attract the general

conditions? If yes, please specify.

Yes. The general condition no. ii. specifies that “There will be no change in the

pipeline route, design, capacity without the prior approval of this Ministry. While

laying the pipeline, OISD standards with regard to distance etc. from private

buildings, industrial buildings or places or habitation etc. should be followed.”

8 Does it attract specific condition? If

yes, please specify No

9

Location

Khasra no. 141/P, Village Mundra, Taluka Mundra, District Kutch in Gujarat

to

Mastile No. 123, Kila no. 27, Village Ramsara, Taluka Talwandi Saboo, District

Bathinda, Punjab.

Plot Survey / Khasra No.

Please refer Pipeline Route Map attached as Annexure 1

Location of Intermediate Pigging

Stations out of which 1 will be

converted to pumping stations

after detailed engineering study.

Location of Intermediate

Pigging Stations out of which 1

will be converted to pumping

stations after detailed

engineering study.

Existing

Intermediate

Pumping

Station

IPS-1 IPS-2 IPS-4 IPS-5 IPS-3

Survey

Nos.

103/2-

P1&P2,

104,

105

Survey Nos. 90/1P, 91,

92P1 Survey No. 219 Survey No. 67

Survey Nos.

152, 156, 157,

172, 173

Village Dedarva Juna Raviyana Jud Shri Dungargarh Dhansa

Tehsil / Taluka / Mandal Taluka

Rapar Taluka Kankrej Tehsil Osian

Tehsil Shri

Dungargarh

Tehsil

Jaswantpura

District Kutch Banaskantha Jodhpur Bikaner Jalore

State Gujarat Gujarat Rajasthan Rajasthan Rajasthan

Page 7: HPCL-MITTAL PIPELINES LIMITEDenvironmentclearance.nic.in/writereaddata/modification/PreviousTOR/... · HPCL-MITTAL PIPELINES LIMITED (A wholly owned Subsidiary of HMEL) Registered

M/S HPCL-MITTAL PIPELINES LTD CAPACITY EXPANSION OF MUNDRA – BATHINDA CRUDE OIL PIPELINE FORM 1

M/S HPCL-MITTAL PIPELINES LTD | NOVEMBER’ 2015 6

S.

No. Item Details

10 Nearest railway station / airport /

along with distance in km.

IPS-1 IPS-2 IPS-4 IPS-5 IPS-3

Chitrod

Railway

Station ~1.5

km in South

direction

Airport

Kandla, ~70

km in South-

West

direction,

Bhuj, ~134

km in West

direction

Deodar

Railway

Station ~13

km in West

direction

Airport

Deesa (small

airstrip), ~36

km in North-

East direction,

Ahmedabad,

~135 km in

South-East

direction

Mathania

Railway

Station ~7.7

km in South-

West

direction

Airport

Jodhpur, ~37

km in South

direction

Shri

Dungargarh

Railway

Station ~12.5

km in South

direction

Airport

Nal (Bikaner),

~77 km in

West

direction

Modaran

Railway

Station ~12.5

km in South

direction

Airport

Noon

(Jalore),

~17.5 km in

East

direction,

Jodhpur,

~133.5 km in

North-East

direction

11

Nearest town, city, district

headquarters along with distances

in kms

IPS-1 IPS-2 IPS-4 IPS-5 IPS-3

Nearest Town

(population

>5,000)

Rapar;

distance of

~14 km in

North

direction

Nearest City

(population

>1,00,000)

Gandhidham;

distance of

~70 km in

South-West

direction

Nearest

District

Headquarters

Bhuj;

distance of

~107 km in

West-South-

West

direction

Nearest Town

(population

>5,000)

Mehsana;

distance of

~73 km in

South-East

direction

Nearest City

(population

>1,00,000)

Mehsana;

distance of

~73 km in

South-East

direction

Nearest District

Headquarters

Palanpur;

distance of

~52 km in

East direction

Nearest Town

(population

>5,000)

Jodhpur;

distance of

~37.9 km in

South

direction

Nearest City

(population

>1,00,000)

Jodhpur;

distance of

~37.9 km in

South

direction

Nearest

District

Headquarters

Jodhpur;

distance of

~37.9 km in

South

direction

Nearest Town

(population

>5,000)

Shri

Dungargarh;

distance of

~9.6 km in

South-South-

East direction

Nearest City

(population

>1,00,000)

Bikaner;

distance of

~69 km in

West-South-

West

direction

Nearest

District

Headquarters

Bikaner;

distance of

~69 km in

West-South-

West

direction

Nearest Town

(population

>5,000)

Bhinmal;

distance of

~25 km in

South-South-

West

direction

Nearest City

(population

>1,00,000)

Pali; distance

of ~114 km

in North-East

direction

Nearest

District

Headquarters

Jalore;

distance of

~28.6 km in

North-East

direction

Page 8: HPCL-MITTAL PIPELINES LIMITEDenvironmentclearance.nic.in/writereaddata/modification/PreviousTOR/... · HPCL-MITTAL PIPELINES LIMITED (A wholly owned Subsidiary of HMEL) Registered

M/S HPCL-MITTAL PIPELINES LTD CAPACITY EXPANSION OF MUNDRA – BATHINDA CRUDE OIL PIPELINE FORM 1

M/S HPCL-MITTAL PIPELINES LTD | NOVEMBER’ 2015 7

S.

No. Item Details

12

Village Panchayat, Zilla Parishad,

Municipal Corporation, Local Body

(complete postal address with

telephone nos. to be given)

IPS-1 IPS-2 IPS-4 IPS-5 IPS-3

Gram

Panchayat

Dedarva,

Post Chitrod

Taluka Rapar

District

Kutch,

Gujarat -

370145

Telephone

No. : N.A.

Gram

Panchayat

Raviyana,

Post Raviyana

Taluka Kankrej

District

Banaskantha,

Gujarat -

385550

Telephone No.

: N.A.

Gram

Panchayat

Newra Road,

Post Jud

Tehsil Osiyan

District

Jodhpur,

Rajasthan -

342305

Telephone No.

: N.A.

Municipality

Shri

Dungargarh,

Post Shri

Dungargarh

Tehsil Shri

Dungargarh

District

Bikaner,

Rajasthan -

331803

Telephone No.

: N.A.

Gram

Panchayat

Dhansa,

Post Dhansa

Tehsil

Jaswantpura

District Jalore,

Rajasthan -

343023

Telephone No.

: N.A.

13 Name of the applicant HPCL-Mittal Pipelines Limited,

14 Registered address Village Phulokhari, Taluka Talwandi Saboo, District Bathinda, Punjab- 151301.

15

Address for correspondence

Name Prodip Kumar Biswas

Designation AGM - Pipeline

Address INOX Towers, Plot No. 17, Sector – 16A,

Noida, Uttar Pradesh.

Pin Code 201301

E-mail [email protected]

Telephone no. +91 120 463 4610, +91 9811436258

Fax no. 0120-4271940

16

Details of alternative sites

examined, if any. Location of these

sites should be shown on the

Toposheet

Not Applicable. The pipeline is already laid and is operational. The stations IPS-2,

IPS-4, IPS-5 are operational pigging stations having adequate land for conversion

into pumping stations. IPS-1 land on the pipeline route is in the name of HPCL-Mittal

Pipelines Ltd that can be converted into pigging cum pumping station.

17 Interlinked Projects No

18

Whether separate application of

interlinked project has been

submitted?

Not applicable

19 If yes, date of submission Not Applicable

20 If no, reason Not applicable

21

Whether the proposal involves

approval / clearance under: if yes,

details of the same and their status

to be given:

The Forest (Conservation) Act, 1980

The Wildlife (Protection) Act, 1972

The C.R.Z Notification, 1991

Forest Conservation Act: No

The Wildlife (Protection) Act, 1972: No

The C.R.Z Notification, 1991 : Not Applicable

22

Whether there is any Government

order / policy, relevant / relating to

the site

No

Page 9: HPCL-MITTAL PIPELINES LIMITEDenvironmentclearance.nic.in/writereaddata/modification/PreviousTOR/... · HPCL-MITTAL PIPELINES LIMITED (A wholly owned Subsidiary of HMEL) Registered

M/S HPCL-MITTAL PIPELINES LTD CAPACITY EXPANSION OF MUNDRA – BATHINDA CRUDE OIL PIPELINE FORM 1

M/S HPCL-MITTAL PIPELINES LTD | NOVEMBER’ 2015 8

S.

No. Item Details

23 Forest land involved (ha.) No

24

Whether there is any litigation

pending against the project and / or

land in which the project is

proposed to be set up?

Name of the Court

Case No.

Order / directions of the Court, if

any and its relevance with the

proposed project

No

II. Activity

1. Construction, operation or decommissioning of the project involving actions, which will cause

physical changes in the locality (topography, land use, changes in water bodies, etc.)

S. No. Information/Checklist

Confirmation

Yes /

No?

Details thereof (with approximate quantities /

rates, wherever possible) with source of

information data

1.1

Permanent or temporary change in

land use, land cover or topography

including increase in intensity of

land use (with respect to local land

use plan)

Yes Additional facilities will be built within the existing

stations/land leading to increase in intensity of land use

1.2 Clearance of existing land,

vegetation and buildings? No Not Applicable

1.3 Creation of new land uses? No The pumping stations will be built on existing land owned

by M/s HPCL Mittal Pipelines Ltd.

1.4 Pre-construction investigations e.g.

bore houses, soil testing? Yes

Although preconstruction investigations will be carried out,

these will not cause physical changes in the locality.

1.5 Construction works? Yes The pumping stations will have built-up structures which

will change the physical layout of the area.

1.6 Demolition works? Yes

The existing buildings may need to be demolished for

construction of other plant buildings like control room,

substation, fire engine shed, DG shed, parking shed, pump

house/shed, fire water pump house, warehouse etc.

1.7

Temporary sites used for

construction works or housing of

construction workers?

No

These workers will be brought from the nearby

town/village and will be at site for the duration of their

shifts. Few portable and temporary cabins (functioning as

site office/ware house) are likely to be placed at the site

for the duration of the project.

1.8

Above ground buildings, structures

or earthworks including linear

structures, cut and fill or

excavations

Yes

Two licensed underground tanks of 20 m3 storage capacity

each exist at IPS-2, IPS-3, IPS-4 & IPS-5 respectively. Two

underground tanks of 20 m3 storage capacity each will be

constructed at IPS-1 in addition to other ancillary facilities

covered in the pre-feasibility report submitted along with

this Form I application.

1.9 Underground works including No Not Applicable

Page 10: HPCL-MITTAL PIPELINES LIMITEDenvironmentclearance.nic.in/writereaddata/modification/PreviousTOR/... · HPCL-MITTAL PIPELINES LIMITED (A wholly owned Subsidiary of HMEL) Registered

M/S HPCL-MITTAL PIPELINES LTD CAPACITY EXPANSION OF MUNDRA – BATHINDA CRUDE OIL PIPELINE FORM 1

M/S HPCL-MITTAL PIPELINES LTD | NOVEMBER’ 2015 9

S. No. Information/Checklist

Confirmation

Yes /

No?

Details thereof (with approximate quantities /

rates, wherever possible) with source of

information data

mining or tunneling?

1.10 Reclamation works? No Not Applicable

1.11 Dredging? No Not Applicable

1.13 Production and manufacturing

processes? No Not Applicable

1.14 Facilities for storage of goods or

materials? Yes As mentioned in S. No 1.7

1.15 Facilities for treatment or disposal

of solid waste or liquid effluents? No

Solid Wastes

Although solid waste will be generated, these will be only

stored temporarily and disposed to a GPCB/RSPCB

authorized TSDF

Liquid Effluents

No liquid effluents will be generated other than domestic

effluent (sewage) which will be disposed off in a soak pit/

septic tank within the site.

1.16 Facilities for long term housing of

operational workers? No Not Applicable

1.17 New road, rail or sea traffic during

construction or operation? Yes

Construction phase

During construction phase, vehicles transporting

construction equipment and workers will be used

Operation phase

Very few (one or two) vehicles transporting staff and

workers for operational phase will be used.

1.18

New road, rail, air, waterborne or

other transport infrastructure

including new or altered routes and

stations, ports, airports etc?

No

The project is for developing pumping stations for

boosting the pressure of the crude oil inside the pipeline

that is required to increase the flow in the pipeline covered

under category 6(a) of EIA notification 2006

1.19

Closure or diversion of existing

transport routes or infrastructure

leading to changes in traffic

movements?

No Not Applicable

1.20 New or diverted transmission lines

or pipelines? No Please read S. No 1.18

1.21

Impoundment, damming,

culverting, realignment or other

changes to the hydrology of

watercourses or aquifers?

No Not Applicable

1.22 Stream crossings? No Not Applicable

1.23 Abstraction or transfers of water

from ground or surface waters? Yes

~ 24.2 KLD for each station

Source: Ground Water, few users residing in nearby areas

also utilize ground water for their domestic and irrigation

Page 11: HPCL-MITTAL PIPELINES LIMITEDenvironmentclearance.nic.in/writereaddata/modification/PreviousTOR/... · HPCL-MITTAL PIPELINES LIMITED (A wholly owned Subsidiary of HMEL) Registered

M/S HPCL-MITTAL PIPELINES LTD CAPACITY EXPANSION OF MUNDRA – BATHINDA CRUDE OIL PIPELINE FORM 1

M/S HPCL-MITTAL PIPELINES LTD | NOVEMBER’ 2015 10

S. No. Information/Checklist

Confirmation

Yes /

No?

Details thereof (with approximate quantities /

rates, wherever possible) with source of

information data

purposes.

1.24

Changes in water bodies or the land

surface affecting drainage or run-

off?

No

1. There is no impact on surface drainage due to waste

water generation since waste water will be

discharged into a soak pit/ septic tank.

2. The area of IPS-1, IPS-2, IPS-4 & IPS-5 are flat and

do not have a pronounced slope. Rainfall is scanty

consequently no significant change in surface

drainage is envisaged.

1.25

Transport of personnel or materials

for construction, operation or

decommissioning?

Yes Please read S. No 1.17

1.26

Long-term dismantling or

decommissioning or restoration

works?

Yes

Existing Temporary IPS-1 facilities will be dismantled and

shifted to permanent IPS-1 land plot in case, this station is

chosen after detailed engineering for conversion to

pumping station.

1.27

Ongoing activity during

decommissioning which could have

an impact on the environment?

No Not Applicable

1.28 Influx of people to an area either

temporarily or permanently? No

Although some people will be present at the site during

the construction period, the no of persons cannot be called

an “influx”.

1.29 Introduction of alien species? No Not Applicable

1.30 Loss of native species or genetic

diversity? No Not Applicable

1.31 Any other actions? No None identified.

2. Use of Natural resources for construction or operation of the Project (such as land, water,

materials or energy, especially any resources which are non-renewable or in short supply):

S. No. Information/Checklist

confirmation

Yes /

No?

Details thereof (with approximate quantities / rates,

wherever possible) with source of information data

2.1 Land especially undeveloped or

agricultural land (ha) No

The IPS-1, IPS-2, IPS-3 & IPS-4, IPS-5 are already existing out of

which IPS-2, IPS-3 & IPS-4, IPS-5 are being used as part of the

Mundra – Bhatinda Pipeline. Only IPS-1 land that is in the name of

HPCL-Mittal Pipelines Limited is not under any use as of now.

2.2 Water (expected source & competing

users) unit: KLD Yes

~ 24.2 KLD for each station

Source: Ground Water, few users residing in nearby areas also

utilize ground water for their domestic and irrigation purposes.

2.3 Minerals (MT) No None other than those mentioned in S. No 2.4

2.4

Construction material stone,

aggregates, sand / soil (expected

source, MT)

Yes These will be purchased from nearby suppliers.

2.5 Forests and timber (source, MT) No Not Applicable

Page 12: HPCL-MITTAL PIPELINES LIMITEDenvironmentclearance.nic.in/writereaddata/modification/PreviousTOR/... · HPCL-MITTAL PIPELINES LIMITED (A wholly owned Subsidiary of HMEL) Registered

M/S HPCL-MITTAL PIPELINES LTD CAPACITY EXPANSION OF MUNDRA – BATHINDA CRUDE OIL PIPELINE FORM 1

M/S HPCL-MITTAL PIPELINES LTD | NOVEMBER’ 2015 11

S. No. Information/Checklist

confirmation

Yes /

No?

Details thereof (with approximate quantities / rates,

wherever possible) with source of information data

2.6

Energy including electricity and fuels

(source, competing users) unit: fuel

(MT), energy (MW)

Yes

Construction

Electricity from grid.

Emergency Power from DG set.

Diesel from nearby retail outlet.

Operations

Electricity from grid.

Emergency Power from DG set (320 kVA running on HSD sourced

from nearby retail outlet).

2.7 Any other natural resources (use

appropriate standard units) No Not Applicable

3. Use, storage, transport, handling or production of substances or materials, which could be

harmful to human health or the environment or raise concerns about actual or perceived risks to

human health.

S. No. Information / Checklist

confirmation

Yes /

No?

Details thereof (with approximate quantities / rates,

wherever possible) with source of information data

3.1

Use of substances or materials, which

are hazardous (as per MSIHC rules) to

human health or the environment (flora,

fauna, and water supplies)

Yes

1. HSD used for running the standby DG sets in case of

electricity outages and Fire water pumps in case of fire.

2. Crude oil, which is being transported in the pipeline is also

hazardous.

3.2

Changes in occurrence of disease or

affect disease vectors (e.g. insect or

water borne diseases)

No No correlation between project activities and occurrence of

diseases or disease vectors has been established.

3.3 Affect the welfare of people e.g. by

changing living conditions? Yes

Some additional (direct and indirect) employment will be generated

due to the project and this will add to the wellbeing of nearby

communities.

3.4

Vulnerable groups of people who could

be affected by the project e.g. hospital

patients, children, the elderly etc.,

No None identified

3.5 Any other causes No None identified

4. Production of solid wastes during construction or operation or decommissioning (MT/month)

S. No. Information/Checklist confirmation Yes/

No?

Details thereof (with approximate quantities / rates,

wherever possible) with source of information data

4.1 Soil, overburden or mine wastes No Not Applicable

4.2 Municipal waste (domestic and or

commercial wastes) Yes Minor amount (< 5 kg/day) of municipal waste will be generated.

4.3 Hazardous wastes (as per Hazardous

Waste Management Rules) Yes Please refer Annexure-4

4.4 Other industrial process wastes No Not Applicable

4.5 Surplus product No Not Applicable

4.6 Sewage sludge or other sludge from Yes ~ 2.43 KLD Sewage for each station

Page 13: HPCL-MITTAL PIPELINES LIMITEDenvironmentclearance.nic.in/writereaddata/modification/PreviousTOR/... · HPCL-MITTAL PIPELINES LIMITED (A wholly owned Subsidiary of HMEL) Registered

M/S HPCL-MITTAL PIPELINES LTD CAPACITY EXPANSION OF MUNDRA – BATHINDA CRUDE OIL PIPELINE FORM 1

M/S HPCL-MITTAL PIPELINES LTD | NOVEMBER’ 2015 12

S. No. Information/Checklist confirmation Yes/

No?

Details thereof (with approximate quantities / rates,

wherever possible) with source of information data

effluent treatment

4.7 Construction or demolition wastes Yes

Some construction waste will be generated and this will be sent

to recyclers/re-users/scrap dealers or in case of inert waste will

be used for land filling.

4.8 Redundant machinery or equipment No

All construction related equipment will be removed from the site

by the contractors at the end of the construction phase. During

the operation phase no redundant machinery or equipment will be

generated.

4.9 Contaminated soils or other materials No These will not be generated in the normal condition.

4.10 Agricultural wastes No Not Applicable

4.11 Other solid wastes No None identified

5. Release of pollutants or any hazardous, toxic or noxious substances to air(kg/hr)

S. No. Information/Checklist confirmation Yes/No?

Details thereof (with approximate quantities /

rates, wherever possible) with source of

information data

5.1 Emissions from combustion of fossil fuels from

stationary or mobile sources Yes

A 320 kVA stand-by DG set will be used at each station

respectively during times of power failure and will emit

PM, SO2, NOx. Three 284 KW Fire Water Engines will also

be used at each station respectively. The DG Sets as well

as the engines will run on Diesel (HSD).

5.2 Emissions from production processes No

There is no production process and in the normal course

pumping and transfer of crude oil will be done using grid

power.

5.3 Emissions from materials handling including

storage or transport No Please read S. No 5.1 & 5.2 above

5.4 Emissions from construction activities including

plant and equipment Yes

Certain emissions such as from batch mixing plant and

other diesel operated construction equipment and

vehicles will be generated.

5.5

Dust or odours from handling of materials

including construction materials, sewage and

waste

Yes Minor dust will be generated during the construction

phase of the project.

5.6 Emissions from incineration of waste No Not Applicable

5.7 Emissions from burning of waste in open air

(e.g. slash materials, construction debris) No Not Applicable

5.8 Emissions from any other sources No None identified

6. Generation of Noise and Vibration, and Emissions of Light and Heat:

S. No. Information/Checklist confirmation Yes / No? Details thereof (with approximate quantities / rates,

wherever possible) with source of information data

6.1 From operation of equipment e.g. engines,

ventilation plant, crushers

Yes Noise

Construction Phase:

Noise and vibration will occur due to different construction

Page 14: HPCL-MITTAL PIPELINES LIMITEDenvironmentclearance.nic.in/writereaddata/modification/PreviousTOR/... · HPCL-MITTAL PIPELINES LIMITED (A wholly owned Subsidiary of HMEL) Registered

M/S HPCL-MITTAL PIPELINES LTD CAPACITY EXPANSION OF MUNDRA – BATHINDA CRUDE OIL PIPELINE FORM 1

M/S HPCL-MITTAL PIPELINES LTD | NOVEMBER’ 2015 13

S. No. Information/Checklist confirmation Yes / No? Details thereof (with approximate quantities / rates,

wherever possible) with source of information data

materials and vehicles.

Operation Phase:

Noise from DG set for emergency power requirement during

grid power outages.

Noise from fire water pumps during firefighting only (if any)

All noise levels will be within CPCB prescribed limits.

Light

Construction Phase:

Light emissions will occur due to construction operations

during the night time and floodlighting arrangements for the

same as also from vehicles or equipment used for

construction purposes.

Operation Phase:

Light emissions will occur due to operation of the facility

during the night time and floodlighting arrangements for the

same.

6.2 From industrial or similar processes Yes Noise and vibration from pumps within plant limit

conforming to CPCB guidelines

6.3 From construction or demolition Yes As mentioned in S. No 6.1

6.4 From blasting or piling Yes Possibly from laying of pile foundations (if required).

6.5 From construction or operational traffic Yes As mentioned in S. No 6.1

6.6 From lighting or cooling systems Yes As mentioned in S. No 6.1. No cooling systems are required

as part of the operating system

6.7 From any other sources No None identified

7. Risks of contamination of land or water from releases of pollutants into the ground or into

sewers, surface waters, groundwater, coastal waters or the sea

S. No. Information/Checklist confirmation Yes/No?

Details thereof (with approximate quantities /

rates, wherever possible) with source of

information data

7.1 From handling, storage, use or spillage of

hazardous materials No Pipeline along with its pump stations is a closed system.

7.2

From discharge of sewage or other effluents

to water or the land (expected mode and

place of discharge)

Yes Domestic sewage will be disposed into soak pit within the

premises.

7.3 By deposition of pollutants emitted to air into

the land or into water No Not Applicable during normal operations

7.4 From any other sources No None identified

7.5

Is there a risk of long term buildup of

pollutants in the environment from these

sources?

No Not Applicable

Page 15: HPCL-MITTAL PIPELINES LIMITEDenvironmentclearance.nic.in/writereaddata/modification/PreviousTOR/... · HPCL-MITTAL PIPELINES LIMITED (A wholly owned Subsidiary of HMEL) Registered

M/S HPCL-MITTAL PIPELINES LTD CAPACITY EXPANSION OF MUNDRA – BATHINDA CRUDE OIL PIPELINE FORM 1

M/S HPCL-MITTAL PIPELINES LTD | NOVEMBER’ 2015 14

8. Risk of accidents during construction or operation of the Project, which could affect human

health or the environment

S. No. Information/Checklist confirmation Yes/No?

Details thereof (with approximate quantities /

rates, wherever possible) with source of

information data

8.1

From explosions, spillages, fires etc from

storage, handling, use or production of

hazardous substances

Yes Due to failure of plant and equipment

8.2 From any other causes No Not Applicable

8.3

Could the project be affected by natural

disasters causing environmental damage e.g.

floods, earthquakes, landslides, cloudburst

etc)?

Yes

Earthquake

The IPS-1 site lies in Seismic Zone V and IPS-2 site lies in

Seismic Zone IV. IPS-4 and IPS-5 sites lie in Seismic Zone

III & II respectively. Therefore, all construction, design

and other features of the project at these sites that can be

impacted due to earthquakes will be as per earthquake

sensitive designs and construction

Floods

The project areas are unlikely to be prone to flooding.

9. Factors which should be considered (such as consequential development) which could lead to

environmental effects or the potential for cumulative impacts with other existing or planned

activities in the locality

S. No. Information/Checklist confirmation Yes / No? Details thereof (with approximate quantities/ rates,

wherever possible) with source of information data

9.1

Lead to development of supporting facilities,

ancillary development or development

stimulated by the project which could have

impact on the environment e.g.: supporting

infrastructure (roads, power supply, waste or

waste water treatment, etc.) housing

development extractive industries supply

industries, (other)

No

The project is a closed system comprising two licensed

underground tanks of 20m3 storage capacity each at the

respective stations and a pumping system for boosting the

pressure of the crude oil inside the pipeline that is required

to increase the flow in the pipeline as mentioned above.

9.2 Lead to after-use of the site, which could have

an impact on the environment No

Not likely, further the site is likely to be used for the

existing activities well into the foreseeable future.

9.3 Set a precedent for later developments No Not Applicable

9.4

Have cumulative effects due to proximity to

other existing or planned projects with similar

effects

No

There are no related or similar structures nearby such as

pipelines or storages others than those operated by M/s

HPCL-Mittal Pipelines Ltd

III. Environmental Sensitivity

S.

No. Areas

Name /

Identity

Aerial Distance (within 10 km) of the proposed project location

boundary

1

Areas protected under

international conventions,

national or local legislation for

their ecological, landscape,

cultural or other related value

No

None identified. Please refer Annexure-2.

Our understanding of the situation is that the nearest protected area including

wildlife sanctuary is more than 10 km away from each of the IPS-1, IPS-2,

IPS-3, IPS-4 & IPS-5 locations respectively.

2 Areas which are important or No IPS-1 IPS-2 IPS-4 IPS-5 IPS-3

Page 16: HPCL-MITTAL PIPELINES LIMITEDenvironmentclearance.nic.in/writereaddata/modification/PreviousTOR/... · HPCL-MITTAL PIPELINES LIMITED (A wholly owned Subsidiary of HMEL) Registered

M/S HPCL-MITTAL PIPELINES LTD CAPACITY EXPANSION OF MUNDRA – BATHINDA CRUDE OIL PIPELINE FORM 1

M/S HPCL-MITTAL PIPELINES LTD | NOVEMBER’ 2015 15

S.

No. Areas

Name /

Identity

Aerial Distance (within 10 km) of the proposed project location

boundary

sensitive for ecological

reasons - Wetlands,

watercourses or other water

bodies, coastal zone,

biospheres, mountains, forests

Wetlands: No

Wetlands are

present near

the area,

Watercourses

or other water

bodies: The

water bodies

present near

the area are

given as

follows:

River:

Khari River,

~1.92 km in

South - West,

Pond:

Govindpar,

~4.3km in

South - West

direction,

Jadavas,

~13.97 km in

East

Coastal Zone:

No, not present

within 10 km of

the area

Biosphere:

No, not present

within 10 km of

the area

Mountains:

No, not present

within 10 km of

the area

Forests:

No, Reserved

Forest not

present within

10 km of the

area. However,

Social Forestry

is present in

the ROW of SH-

51

Wetlands: No

Wetlands are

present near

the area,

Watercourses

or other water

bodies: The

water bodies

present near

the area are

given as

follows:

River:

Banas River,

~13 km in East,

Pond:

Juna Raviyana,

~1km in South

direction,

Two ponds in

Village Khoda,

~1.65 km in

North and ~3

km in North-

West direction,

Raiya, ~6.6 km

in West of

North-West

direction

Deodar, ~12.37

km in West

direction,

Sanodar, ~10

km in West

direction,

Zalmor, ~3km

in West

direction.

Coastal Zone:

No, not present

within 10 km of

the area

Biosphere:

No, not present

within 10 km of

the area

Mountains:

No, not present

within 10 km of

the area

Forests:

No, Reserved

Wetlands: No

Wetlands are

present near

the area,

Watercourses

or other water

bodies: The

water bodies

present near

the area are

given as

follows:

River:

No, not present

within 10 km of

the area

Pond:

No, not present

within 10 km of

the area

Coastal Zone:

No, not present

within 10 km of

the area

Biosphere:

No, not present

within 10 km of

the area

Mountains:

No, not present

within 10 km of

the area

Forests:

No, Reserved

Forest not

present within

10 km of the

area. However,

Social Forestry

is present in

the ROW of SH-

58

Wetlands: No

Wetlands are

present near

the area,

Watercourses

or other water

bodies: The

water bodies

present near

the area are

given as

follows:

River:

No, not present

within 10 km of

the area

Pond:

One pond in

Shri

Dungargarh,

~9.26 km in

South direction

Coastal Zone:

No, not present

within 10 km of

the area

Biosphere:

No, not present

within 10 km of

the area

Mountains:

No, not present

within 10 km of

the area

Forests:

No, Reserved

Forest not

present within

10 km of the

area. However,

Social Forestry

is present in the

ROW of NH-11

Wetlands: No

Wetlands are

present near

the area,

Watercourses

or other water

bodies: The

water bodies

present near

the area are

given as

follows:

River:

Sukhri River,

~3 km in

North-North

East,

Pond:

No, not present

within 10 km of

the area

Coastal Zone:

No, not present

within 10 km of

the area

Biosphere:

No, not present

within 10 km of

the area

Mountains:

No, not present

within 10 km of

the area

Forests:

No, Reserved

Forest not

present within

10 km of the

area. However,

Social Forestry

is present in

the ROW of

SH-16

Page 17: HPCL-MITTAL PIPELINES LIMITEDenvironmentclearance.nic.in/writereaddata/modification/PreviousTOR/... · HPCL-MITTAL PIPELINES LIMITED (A wholly owned Subsidiary of HMEL) Registered

M/S HPCL-MITTAL PIPELINES LTD CAPACITY EXPANSION OF MUNDRA – BATHINDA CRUDE OIL PIPELINE FORM 1

M/S HPCL-MITTAL PIPELINES LTD | NOVEMBER’ 2015 16

S.

No. Areas

Name /

Identity

Aerial Distance (within 10 km) of the proposed project location

boundary

Forest not

present within

10 km of the

area. However,

Social Forestry

is present in

the ROW of SH-

72

3

Areas used by protected,

important or sensitive species

of flora or fauna for breeding,

nesting, foraging, resting,

over wintering, migration

No None identified

4 Inland, coastal, marine or

underground waters Yes

There is no costal and marine water present at these sites and within the 10 km of

the area,

Information about the water bodies is presented in Section 2 of Environmental

Sensitivity,

Groundwater is present at the site and will be used for the project after due

clearance from the CGWA

5 State, National boundaries No Not present. Please refer Annexure-2

6

Routes or facilities used by the

public for access to recreation

or other tourist, pilgrim areas

No Routes:

IPS-1 IPS-2 IPS-3 IPS-4 IPS-5

State Highway-

51 (SH-51),

1.25 km in

West direction,

National

Highway-15

(NH-15), 4.82

km in South

direction

No such route

identified.

National

Highway 15 can

be used by the

Tourists and

Pilgrims

heading

towards Mount

Abu and Ambaji

Temple. But

these areas are

typically not

accessed using

the road near

the project area

State Highway-72

(SH-72), 1.15 km

in North direction,

National Highway-

27 (NH-27), 3.85

km in East

direction

No such route

identified.

National Highway

27 can be used by

the Tourists and

Pilgrims heading

towards Mount

Abu and Ambaji

Temple. But these

areas are typically

not accessed

using the road

near the project

area

State Highway-

16 (SH-16), 9.89

km in North

direction,

State Highway-

31 (SH-31),

20.81 km in East

direction

No such route

identified. State

Highway 31 can

be used by the

Tourists and

Pilgrims heading

towards Mount

Abu and Ambaji

Temple. But

these areas are

typically not

accessed using

the road near

the project area

State

Highway-58

(SH-58),

1.15 km in

South

direction,

National

Highway-65

(NH-65),

12.1 km in

East

direction

No such

route

identified.

National

Highway 65

can be used

by the

Tourists and

Pilgrims

heading

towards

Karni Mata

Temple. But

these areas

are typically

not

accessed

using the

State Highway-

6 (SH-6), 8.91

km in South -

East direction,

National

Highway-11

(NH-11), 9.75

km in South

direction

No such route

identified.

National

Highway 11

can be used by

the Tourists

and Pilgrims

heading

towards Karni

Mata Temple.

But these areas

are typically

not accessed

using the road

near the

project area

Page 18: HPCL-MITTAL PIPELINES LIMITEDenvironmentclearance.nic.in/writereaddata/modification/PreviousTOR/... · HPCL-MITTAL PIPELINES LIMITED (A wholly owned Subsidiary of HMEL) Registered

M/S HPCL-MITTAL PIPELINES LTD CAPACITY EXPANSION OF MUNDRA – BATHINDA CRUDE OIL PIPELINE FORM 1

M/S HPCL-MITTAL PIPELINES LTD | NOVEMBER’ 2015 17

S.

No. Areas

Name /

Identity

Aerial Distance (within 10 km) of the proposed project location

boundary

road near

the project

area

7 Defense installations No -

8 Densely populated or built-up

area Yes

IPS-1 IPS-2 IPS-4 IPS-5 IPS-3

Rapar ~ 14 km

in north –

northwest

direction,

Bhachau, ~37

km in west -

southwest

direction

Deodar, ~12 km

in west direction,

Deesa, ~31 km in

North-East

direction

Osiyan, ~19 km

in northwest

direction,

Jodhpur, ~38

km in south

direction

Shri

Dungargarh,

~9 km in

south -

southeast

direction

Bhinmal ~ 25

km in south –

southwest

direction,

Jalore, ~27.5

km in

Northeast

direction

9

Areas occupied by sensitive

man-made land uses

(hospitals, schools, places of

worship, community facilities)

Yes

IPS-1 IPS-2 IPS-4 IPS-5 IPS-3

Such facilities

are present in

Rapar Town

Such facilities are

present in Deodar

Town

Such facilities

are present in

Jodhpur City

Such facilities

are present

in Shri

Dungargarh

Town

Such facilities

are present in

Bhinmal Town

10

Areas containing important,

high quality or scarce

resources (ground water

resources, surface resources,

forestry, agriculture, fisheries,

tourism, minerals)

Yes

IPS-1 IPS-2 IPS-4 IPS-5 IPS-3

There is no

scarcity of

ground water in

the area.

Please refer

Annexure

Ground water

resources are

scarce in the area

and therefore the

area is considered

over-exploited

from the ground

water angle.

Please refer

Annexure .

Ground water

resources are

scarce in the

area and

therefore the

area is

considered over-

exploited from

the ground

water angle.

Please refer

Annexure

Ground

water

resources

are scarce in

the area and

therefore the

area is

considered

over-

exploited

from the

ground

water angle.

Please refer

Annexure

Ground water

resources are

scarce in the

area and

therefore the

area is

considered

over-exploited

from the

ground water

angle. Please

refer

Annexure

11

Areas already subjected to

pollution or environmental

damage. (Those where

existing legal environmental

standards are exceeded)

No

IPS-1 IPS-2 IPS-4 IPS-5 IPS-3

No such areas

identified.

Distance to the

nearest

critically

polluted area

as per ENVIS is

Ahmedabad,

~200 km in

East -

Southeast

direction.

No such areas

identified.

Distance to the

nearest critically

polluted area as

per ENVIS is

Ahmedabad,

~135 km in

South-East

direction.

No such areas

identified.

Distance to the

nearest critically

polluted area as

per ENVIS is

Jodhpur, ~37

km in South

direction.

No such

areas

identified.

Distance to

the nearest

critically

polluted area

as per ENVIS

is Jodhpur,

~232 km in

South –

Southwest

direction.

No such areas

identified.

Distance to the

nearest

critically

polluted area

as per ENVIS

is Pali, ~107

km in North-

East direction.

12 Areas susceptible to natural

hazard which could cause the Yes The study areas are susceptible to earthquakes. Please read S. No. 8.3

Page 19: HPCL-MITTAL PIPELINES LIMITEDenvironmentclearance.nic.in/writereaddata/modification/PreviousTOR/... · HPCL-MITTAL PIPELINES LIMITED (A wholly owned Subsidiary of HMEL) Registered

M/S HPCL-MITTAL PIPELINES LTD CAPACITY EXPANSION OF MUNDRA – BATHINDA CRUDE OIL PIPELINE FORM 1

M/S HPCL-MITTAL PIPELINES LTD | NOVEMBER’ 2015 18

S.

No. Areas

Name /

Identity

Aerial Distance (within 10 km) of the proposed project location

boundary

project to present

environmental problems

(earthquakes, subsidence,

landslides, erosion, flooding or

extreme or adverse climatic

conditions)

DECLARATION:

“I hereby give an undertaking that the data and information given in the application and enclosures are true to the best

of my knowledge and belief and I am aware that if any part of the data and information submitted is found to be false

or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our

risk and cost”.

Date:18.11.2015

Place: NOIDA Signature of the applicant with full name and address

Name : Prodip Kumar Biswas

Designation : AGM - Pipeline

Address : HPCL – Mittal Pipelines Limited,

INOX Towers,

Plot No. 17, Sector – 16A,

NOIDA – 201301,

Uttar Pradesh.

Page 20: HPCL-MITTAL PIPELINES LIMITEDenvironmentclearance.nic.in/writereaddata/modification/PreviousTOR/... · HPCL-MITTAL PIPELINES LIMITED (A wholly owned Subsidiary of HMEL) Registered

M/S HPCL-MITTAL PIPELINES LTD

CAPACITY EXPANSION OF MUNDRA – BATHINDA

CRUDE OIL PIPELINE PROPOSED TERMS OF REFERENCES

M/S HPCL-MITTAL PIPELINES LTD | NOVEMBER’ 2015 19

2 PROPOSED TERMS OF REFERENCE

The proposed terms of reference are suggested in

Table 2-1: Terms of Reference for preparing EIA Report

S. No. Proposed Terms of Reference

1. Justification of the project

2. Promoters and their background

3. Regulatory framework

4. A map indicating location of the project and distance from severely polluted area

5. Project location and plant layout

6. Infrastructure facilities including power sources

7. Total cost of the project along with total capital cost and recurring cost/annum for environmental pollution control measures.

8. Project site location along with site map of 10 km area and site details providing

various industries, surface water bodies, forests etc, along with landuse around 5 or 10 kms of the study area

9. Location of National Park/Wild life sanctuary/Reserve Forest within 10 km radius of the project.

10. Details of the total land and break-up of the land use for green belt and other

uses.

11. List of products along with the production capacities and list of solvents and its recovery plan

12. Detailed list of raw materials required and source, mode of storage and transportation

13. Manufacturing process details along with the chemical reactions and process flow chart.

14. Action plan for the safe transportation of raw material required

15. Site-specific micro-meteorological data using temperature, relative humidity, hourly wind speed and direction and rainfall is necessary.

16. Ambient air quality monitoring at 6 locations within the study area of 5 km., aerial coverage from project site as per NAAQES notified on 16th September,

2009. Location of one AAQMS in downwind direction.

17. One season site-specific micro-meteorological data covering temperature, relative humidity, hourly wind speed and direction and rainfall.

Twice weekly AAQ data (except monsoon) for PM2.5, PM10, SO2 and NOx at five

stations. CO, VOC, HC should be collected five times during the study at these

stations.

The monitoring stations should take into account the pre-dominant wind direction,

population zone and sensitive receptors including reserved forests.

Data for surface water, groundwater and noise monitoring should also be included.

18. Air pollution control measures proposed for the effective control of gaseous emissions within permissible limits.

Page 21: HPCL-MITTAL PIPELINES LIMITEDenvironmentclearance.nic.in/writereaddata/modification/PreviousTOR/... · HPCL-MITTAL PIPELINES LIMITED (A wholly owned Subsidiary of HMEL) Registered

M/S HPCL-MITTAL PIPELINES LTD

CAPACITY EXPANSION OF MUNDRA – BATHINDA

CRUDE OIL PIPELINE PROPOSED TERMS OF REFERENCES

M/S HPCL-MITTAL PIPELINES LTD | NOVEMBER’ 2015 20

S. No. Proposed Terms of Reference

19. An action plan to control and monitor secondary fugitive emissions

20. Determination of atmospheric inversion level and assessment of ground level

concentration of pollutants from the stack emission based on site-specific

meteorological features. Air quality modelling for proposed expansion.

21. Ground water monitoring at 6 locations should be carried out. Geological features and Geo-hydrological status of the study area and ecological status (Terrestrial and Aquatic).

22. The details of solid and hazardous wastes generation, storage, utilization and disposal particularly related to the hazardous waste calorific value of hazardous

waste and detailed characteristic of the hazardous waste.

23. Precautions to be taken during storage and transportation of hazardous chemicals should be clearly mentioned and incorporated

24. Details of landfill alongwith design details as per CPCB guidelines. Location of

secured land fill / TSDF.

25. Authorization/Membership for the disposal of solid/hazardous waste in TSDF.

26. Risk assessment for storage, handling, transportation of crude and any other

hazardous material being handled. Action Plan for implementing the recommendations of the risk assessment.

27. An action plan to develop green belt

28. Action plan for rainwater harvesting measures at plant site should be included to harvest rainwater from the roof tops and storm water drains to recharge the

ground water.

29. Occupational health of the workers needs elaboration including evaluation of noise, heat, illumination, dust, any other chemicals, metals being suspected in

environment and going into body of workers either through inhalation, ingestion or

through skin absorption and steps taken to avoid musculo-skeletal disorders

(MSD), backache, pain in minor and major joints, fatigue etc. Occupational

hazards specific pre-placement and periodical monitoring should be carried out.

30. Socio-economic development activities, with an Action Plan for implementing

future CSR activities with schedule and budget

31. Detailed Environment management Plan (EMP) with specific reference to details of air pollution control system, water & wastewater management, monitoring

frequency, responsibility and time bound implementation plan for mitigation measure should be provided.

32. EMP should include the concept of waste-minimization, recycle / reuse / recover

techniques, Energy conservation, and natural resource conservation.

33. Any litigation pending against the project and/or any direction/order passed by

any Court of Law against the project, if so, details thereof.

Page 22: HPCL-MITTAL PIPELINES LIMITEDenvironmentclearance.nic.in/writereaddata/modification/PreviousTOR/... · HPCL-MITTAL PIPELINES LIMITED (A wholly owned Subsidiary of HMEL) Registered

M/S HPCL-MITTAL PIPELINES LTD

CAPACITY EXPANSION OF MUNDRA – BATHINDA

CRUDE OIL PIPELINE ANNEXURE

M/S HPCL-MITTAL PIPELINES LTD | NOVEMBER’ 2015 21

ANNEXURES

Page 23: HPCL-MITTAL PIPELINES LIMITEDenvironmentclearance.nic.in/writereaddata/modification/PreviousTOR/... · HPCL-MITTAL PIPELINES LIMITED (A wholly owned Subsidiary of HMEL) Registered

M/S HPCL-MITTAL PIPELINES LTD

CAPACITY EXPANSION OF MUNDRA – BATHINDA CRUDE OIL

PIPELINE ANNEXURE

M/S HPCL-MITTAL PIPELINES LTD | NOVEMBER’ 2015 22

Annexure 1: Pipeline Route Map

Page 24: HPCL-MITTAL PIPELINES LIMITEDenvironmentclearance.nic.in/writereaddata/modification/PreviousTOR/... · HPCL-MITTAL PIPELINES LIMITED (A wholly owned Subsidiary of HMEL) Registered

M/S HPCL-MITTAL PIPELINES LTD

CAPACITY EXPANSION OF MUNDRA – BATHINDA CRUDE OIL

PIPELINE ANNEXURE

M/S HPCL-MITTAL PIPELINES LTD | NOVEMBER’ 2015 23

Annexure 2: Topography of IPS-1, IPS-2, IPS-3, IPS-4 & IPS-5 locations and areas within 10 km radius showing Roads, Adjacent localities, Forests, Water bodies, Protected Areas, State & National Boundaries (if any)

1. IPS-1, Dedarva

10 Km

Page 25: HPCL-MITTAL PIPELINES LIMITEDenvironmentclearance.nic.in/writereaddata/modification/PreviousTOR/... · HPCL-MITTAL PIPELINES LIMITED (A wholly owned Subsidiary of HMEL) Registered

M/S HPCL-MITTAL PIPELINES LTD

CAPACITY EXPANSION OF MUNDRA – BATHINDA CRUDE OIL

PIPELINE ANNEXURE

M/S HPCL-MITTAL PIPELINES LTD | NOVEMBER’ 2015 24

2. IPS-2, Juna Raviyana

10 Km

Page 26: HPCL-MITTAL PIPELINES LIMITEDenvironmentclearance.nic.in/writereaddata/modification/PreviousTOR/... · HPCL-MITTAL PIPELINES LIMITED (A wholly owned Subsidiary of HMEL) Registered

M/S HPCL-MITTAL PIPELINES LTD

CAPACITY EXPANSION OF MUNDRA – BATHINDA CRUDE OIL

PIPELINE ANNEXURE

M/S HPCL-MITTAL PIPELINES LTD | NOVEMBER’ 2015 25

3. IPS-3, Dhansa

10 Km

Page 27: HPCL-MITTAL PIPELINES LIMITEDenvironmentclearance.nic.in/writereaddata/modification/PreviousTOR/... · HPCL-MITTAL PIPELINES LIMITED (A wholly owned Subsidiary of HMEL) Registered

M/S HPCL-MITTAL PIPELINES LTD

CAPACITY EXPANSION OF MUNDRA – BATHINDA CRUDE OIL

PIPELINE ANNEXURE

M/S HPCL-MITTAL PIPELINES LTD | NOVEMBER’ 2015 26

4. IPS-4, Jud

10 Km

Page 28: HPCL-MITTAL PIPELINES LIMITEDenvironmentclearance.nic.in/writereaddata/modification/PreviousTOR/... · HPCL-MITTAL PIPELINES LIMITED (A wholly owned Subsidiary of HMEL) Registered

M/S HPCL-MITTAL PIPELINES LTD

CAPACITY EXPANSION OF MUNDRA – BATHINDA CRUDE OIL

PIPELINE ANNEXURE

M/S HPCL-MITTAL PIPELINES LTD | NOVEMBER’ 2015 27

5. IPS-5, Shri Dungargarh

10 Km

Page 29: HPCL-MITTAL PIPELINES LIMITEDenvironmentclearance.nic.in/writereaddata/modification/PreviousTOR/... · HPCL-MITTAL PIPELINES LIMITED (A wholly owned Subsidiary of HMEL) Registered

M/S HPCL-MITTAL PIPELINES LTD

CAPACITY EXPANSION OF MUNDRA – BATHINDA CRUDE OIL

PIPELINE ANNEXURE

M/S HPCL-MITTAL PIPELINES LTD | NOVEMBER’ 2015 28

Annexure 3: CGWA Categorization of Talukas .

A. Gujarat

Page 30: HPCL-MITTAL PIPELINES LIMITEDenvironmentclearance.nic.in/writereaddata/modification/PreviousTOR/... · HPCL-MITTAL PIPELINES LIMITED (A wholly owned Subsidiary of HMEL) Registered

M/S HPCL-MITTAL PIPELINES LTD

CAPACITY EXPANSION OF MUNDRA – BATHINDA CRUDE OIL

PIPELINE ANNEXURE

M/S HPCL-MITTAL PIPELINES LTD | NOVEMBER’ 2015 29

B. Rajasthan

Page 31: HPCL-MITTAL PIPELINES LIMITEDenvironmentclearance.nic.in/writereaddata/modification/PreviousTOR/... · HPCL-MITTAL PIPELINES LIMITED (A wholly owned Subsidiary of HMEL) Registered

M/S HPCL-MITTAL PIPELINES LTD

CAPACITY EXPANSION OF MUNDRA – BATHINDA CRUDE OIL

PIPELINE ANNEXURE

M/S HPCL-MITTAL PIPELINES LTD | NOVEMBER’ 2015 30

Page 32: HPCL-MITTAL PIPELINES LIMITEDenvironmentclearance.nic.in/writereaddata/modification/PreviousTOR/... · HPCL-MITTAL PIPELINES LIMITED (A wholly owned Subsidiary of HMEL) Registered

M/S HPCL-MITTAL PIPELINES LTD

CAPACITY EXPANSION OF MUNDRA – BATHINDA CRUDE OIL

PIPELINE ANNEXURE

M/S HPCL-MITTAL PIPELINES LTD | NOVEMBER’ 2015 31

Page 33: HPCL-MITTAL PIPELINES LIMITEDenvironmentclearance.nic.in/writereaddata/modification/PreviousTOR/... · HPCL-MITTAL PIPELINES LIMITED (A wholly owned Subsidiary of HMEL) Registered

M/S HPCL-MITTAL PIPELINES LTD

CAPACITY EXPANSION OF MUNDRA – BATHINDA CRUDE OIL

PIPELINE ANNEXURE

M/S HPCL-MITTAL PIPELINES LTD | NOVEMBER’ 2015 32

Annexure 4: Hazardous Waste – Type, Mode and Disposal

The hazardous waste listing is provided in the following Annexure Table 1.

Annexure Table 1: Hazardous Wastes for each pumping station, with Type, Mode and Disposal

S. No. Items

Category

as per HW

Rules

Unit Quantity

Treatment /

Disposal

Method

1 Pigging Waste 3.3 MT/ month 0.5 TSDF

2

Sludge from Tank

Cleaning, used Filter

Elements

3.3 Tons / 5 Years 2 TSDF

3 Used Lube Oil 5.1 MT/year 2 Authorised

Recyclers

4

Used Pig

Cups/Discarded

Containers/Barrels

33.3 Nos./year

16 pig cups

5 Discarded

Containers/Barrels

TSDF

Page 34: HPCL-MITTAL PIPELINES LIMITEDenvironmentclearance.nic.in/writereaddata/modification/PreviousTOR/... · HPCL-MITTAL PIPELINES LIMITED (A wholly owned Subsidiary of HMEL) Registered