hs eq ma s -...

33
HS SEQ Nois Ma seMa nag anagem eme ment ent S SubP Teleph Fax 02 20 Syst Plan S V hone 02 826 2 9269 0717 013 tem SICTL Version 2 68 8000 3

Upload: doanhanh

Post on 30-May-2018

213 views

Category:

Documents


0 download

TRANSCRIPT

  

 

  

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

HS

 

SEQ 

Nois

Ma

se Ma

nag

anagem 

eme

ment 

ent S

Sub‐P

Teleph

Fax 02

20

Syst

Plan ‐ S

V

hone 02 826

2 9269 0717 

013

tem

SICTL

Version 2

68 8000 

Health Safety Enviroment and Quality Management System 

Noise Management Sub‐Plan ‐ SICTL 

Document Reference:   HSEQ5.1.7d  Document Title:  Noise Management Sub‐Plan ‐ SICTL  Version: 2

Document Owner:  HSEQ Department  Approved Date:  30 August 2013  Page 2 of 33

Printed Version is uncontrolled ‐ controlled version available on Sharepoint 

Document Control: Document control shall be in accordance with the HPA Document Control and Records Management Policy 

(HSEQ9.1) and the Document Control & Information Management Procedure (HSEQ9.1.1), ensuring that: 

An up to date version of this HSEQ Management System document is maintained; 

Records of superseded versions of the document are retained for a minimum of 7 year; and 

Current version of the document is readily available to all Managers, Employees and Key Stakeholders.  

Register of Amendments 

Ver No Page no 

Date  Description of amendments  Prepared by  Approved by 

Draft 0  All  3 June 2013  Consultation Draft  John Ieroklis  Trevor Ballantyne 

Draft 1  All  10 July 2013  Consultation Draft  John Ieroklis  Trevor Ballantyne 

1  All  31 July 2013  External stakeholder consultation comments incorporated 

John Ieroklis  Trevor Ballantyne 

2  All  30 August 2013 

DP&I comments incorporated  John Ieroklis  Trevor Ballantyne 

           

A person using Hutchison Ports Australia documents or data accepts the risk of: 

a) Using the documents or data in electronic form without requesting and checking them for accuracy 

against the original hard copy version; and 

b) Using the documents or data for any purpose not agreed to in writing by Hutchison Ports Australia 

 

 

 

 

 

 

 

 

 

 

 

 

 

This document is Copyright, other than for the purposes of and subject to the provisions of the Copyright Act, no part of it may be reproduced in any form or by any process without the prior permission of Hutchison Ports Australia 

The information contained in this manual is Confidential and is not to be used or disclosed to any person without the prior approval of Hutchison Ports Australia 

Health Safety Enviroment and Quality Management System 

Noise Management Sub‐Plan ‐ SICTL 

Document Reference:   HSEQ5.1.7d  Document Title:  Noise Management Sub‐Plan ‐ SICTL  Version: 2

Document Owner:  HSEQ Department  Approved Date:  30 August 2013  Page 3 of 33

Printed Version is uncontrolled ‐ controlled version available on Sharepoint 

1  Purpose .................................................................................................................................. 5 

2  Objective ................................................................................................................................ 6 

2.1  Environmental Issues Overview .............................................................................................................. 6 

2.2  Key Performance Areas Overview ........................................................................................................... 7 

2.3  OEMP Sub‐Plans Overview ...................................................................................................................... 7 

2.4  Key Performance Indicators Overview .................................................................................................... 7 

3  Legislative Framework ........................................................................................................... 8 

3.1  Applicable Legislation.............................................................................................................................. 8 

3.2  Conditions of Development Consent ...................................................................................................... 8 

4  Strategic Approach ............................................................................................................... 11 

4.1  Risk Identification .................................................................................................................................. 11 

4.1.1  Exclusions to the Scope of this Sub‐Plan ............................................................................................................... 11 

4.2  Potential Operational Noise Impacts .................................................................................................... 12 

4.2.1  Noise from Operational Plant, Machinery and Equipment ................................................................................... 12 

4.2.2  Noise from Container Handling ............................................................................................................................. 12 

4.2.3  Noise from Freight Trains and Rail Activities ........................................................................................................ 13 

4.2.4  Noise from Ships ................................................................................................................................................... 13 

5  Implementation of This Sub‐Plan ......................................................................................... 14 

5.1  Operational Controls ............................................................................................................................. 15 

5.1.1  Gradual Commencement Timetabling .................................................................................................................. 15 

5.1.2  Noise Wall ............................................................................................................................................................. 16 

5.1.3  Controls on Noise from Operational Plant and Vehicles ....................................................................................... 16 

5.1.4  Controls on Noise from Containers Landing ......................................................................................................... 17 

5.1.5  Controls on Noise from Freight Trains and Rail Activities ..................................................................................... 18 

5.1.6  Controls on Noise from Ships ................................................................................................................................ 18 

5.1.7  Assessment of Operational Noise Impacts at the Relevant Receivers .................................................................. 19 

5.1.8  Procedures for Notifying Residents ...................................................................................................................... 20 

5.2  Training of personnel ............................................................................................................................ 21 

5.3  Monitoring and Response ..................................................................................................................... 21 

5.3.1  Background Noise Monitoring Strategy ................................................................................................................ 21 

5.3.2  Operational Noise Monitoring Strategy ................................................................................................................ 21 

5.3.3  Proactive and Reactive Strategies for Dealing with Complaints ........................................................................... 22 

6  Performance Expectations ................................................................................................... 24 

6.1  Opportunities for Improvement ........................................................................................................... 24 

6.2  Management of Noise Complaints ....................................................................................................... 25 

6.2.1  Management of Complaints or Common Issues involving Neighbouring Stevedores .......................................... 27 

6.3  Documentation and Record Keeping .................................................................................................... 28 

6.3.1  Reporting Obligations ........................................................................................................................................... 29 

7  Responsibility, Accountability and Authority........................................................................ 30 

7.1  SICTL as Tenant ..................................................................................................................................... 30 

7.1.1  HSEQ Officer .......................................................................................................................................................... 30 

7.1.2  Environmental and Safety Compliance Engineer .................................................................................................. 30 

Health Safety Enviroment and Quality Management System 

Noise Management Sub‐Plan ‐ SICTL 

Document Reference:   HSEQ5.1.7d  Document Title:  Noise Management Sub‐Plan ‐ SICTL  Version: 2

Document Owner:  HSEQ Department  Approved Date:  30 August 2013  Page 4 of 33

Printed Version is uncontrolled ‐ controlled version available on Sharepoint 

7.1.3  National HSEQ Manager (Environmental Representative) ................................................................................... 30 

7.1.4  Terminal Manager ................................................................................................................................................. 30 

7.1.5  Work Crews and Plant Operators ......................................................................................................................... 30 

8  Identification of Stakeholders .............................................................................................. 31 

8.1.1  Internal Stakeholders ............................................................................................................................................ 31 

8.1.2  External Stakeholders ........................................................................................................................................... 31 

8.2  Consultation with Stakeholders ............................................................................................................ 32 

8.2.1  Ongoing consultation ............................................................................................................................................ 32 

8.2.2  Key Personnel Contact Details ‐ SICTL ................................................................................................................... 32 

8.2.3  Key Personnel Contact Details – Operational Community Consultative Committee ............................................ 32 

9  Referenced Documents ........................................................................................................ 33 

10  Review and Auditing of this Sub‐Plan ................................................................................... 33 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Health Safety Enviroment and Quality Management System 

Noise Management Sub‐Plan ‐ SICTL 

Document Reference:   HSEQ5.1.7d  Document Title:  Noise Management Sub‐Plan ‐ SICTL  Version: 2

Document Owner:  HSEQ Department  Approved Date:  30 August 2013  Page 5 of 33

Printed Version is uncontrolled ‐ controlled version available on Sharepoint 

Noise Management Sub‐Plan 

1 Purpose This Noise Management Sub‐Plan (NMSP) has been created as a means by which Sydney International 

Container Terminals (SICTL) can comply with the relevant conditions and operational noise limits outlined in 

the Instrument of Development Consent DA‐494‐11‐2003‐i listed in Schedule C – Terminal Operations (the 

Development Consent). The NMSP is a component of the HSEQ5.1.7 Operational Environmental Management 

Plan (OEMP) – SICTL and as such is a Tier 3 document within the Hutchison Ports Australia (HPA) Health, 

Safety, Environment and Quality (HSEQ) Management System. This sub‐plan is an example of the commitment 

of HPA to comply with the Development Consent and work with external stakeholders co‐operatively to 

achieve good operational outcomes. The indicative process of how OEMP sub plans control the operations of 

the SICTL Terminal is shown below. 

 

Figure 1 Illustration of how the KPAs and sub‐plan control Operations 

Health Safety Enviroment and Quality Management System 

Noise Management Sub‐Plan ‐ SICTL 

Document Reference:   HSEQ5.1.7d  Document Title:  Noise Management Sub‐Plan ‐ SICTL  Version: 2

Document Owner:  HSEQ Department  Approved Date:  30 August 2013  Page 6 of 33

Printed Version is uncontrolled ‐ controlled version available on Sharepoint 

2 Objective The objective of this sub plan is to guide the direction of SICTL’s operations so that operational staff can carry 

out their duties whilst remaining aware that their work may impact nearby residents. Through this awareness, 

SICTL can best manage foreseeable impacts successfully. Ultimately, awareness and management of impacts 

will lead to compliance with the Development Consent. SICTL will utilise this sub‐plan in the following ways: 

as an management instrument so that good performance by SICTL and its contractors in the Noise 

Management Key Performance Area (KPA) can be assured; 

as an instrument that complements HPA’s commercial agreements with shipping lines enabling SICTL 

to support the actions of vessels with the intent of compliance to the Development Consent (where 

the Development Consent applies to vessels directly); 

as a measure of compliance with the Development Consent in the form of a Key Performance Indicator 

(KPI) target and a KPI goal; 

as a description of what the KPI actually is and its context for measurement; 

as a basis for consultation with relevant stakeholders in regards to minimising or eliminating noise 

impacts, and 

as a tool for promoting an ongoing relationship between the relevant stakeholders and SICTL so that 

any operational problems can quickly be solved. 

2.1 Environmental Issues Overview 

The environmental issues that influence the operation of the SICTL terminal are either identified directly in the 

Development Consent or are the outcomes of an operational risk assessment carried out by Hutchison Ports 

Australia (HPA). In either case, the environmental issues are what SICTL will manage. The 10 issues identified in 

section 1.5.1 of the OEMP are: 

environmental management interface with work health and safety; 

training personnel in environmental management; 

quality of stormwater runoff/ separator tank discharges; 

odour and dust management; 

noise and traffic management; 

waste management; 

the handling and transit of chemicals and dangerous goods containers; 

storage of fuels on site; 

impacts on Sydney Airport; 

the management of native and feral animals; 

energy usage. and 

community & complaints handling. 

Independent issues or related issues may be grouped together and managed under Key Performance Areas. 

 

 

 

 

 

 

Health Safety Enviroment and Quality Management System 

Noise Management Sub‐Plan ‐ SICTL 

Document Reference:   HSEQ5.1.7d  Document Title:  Noise Management Sub‐Plan ‐ SICTL  Version: 2

Document Owner:  HSEQ Department  Approved Date:  30 August 2013  Page 7 of 33

Printed Version is uncontrolled ‐ controlled version available on Sharepoint 

2.2 Key Performance Areas Overview 

KPAs are an important concept within environmental management because they describe unique and relevant 

fields of compliance, i.e. ‘areas’. The KPAs identified in section 1.6.3 of the OEMP are: 

air quality; 

aviation operational impacts; 

noise and complaints; 

operational traffic; 

water quality; 

Dangerous Goods and Hazardous Substances cargo management; 

waste generation; 

native and feral animal management, and 

energy. 

Independent issues or related issues may be grouped together and managed under Key Performance Areas. 

2.3 OEMP Sub‐Plans Overview 

The sub plans to the OEMP are the management instrument which will guide SICTL to achieve compliance in 

the KPAs. The OEMP sub plans identified in sections 1.6.3 and 4.2.1 of the OEMP are:  

the Air Quality Management Sub‐Plan; 

the Aviation Operational Impacts Sub‐ Plan; 

the Bird Hazard Management Sub‐ Plan; 

the Noise Management Sub‐ Plan; 

the Operational Traffic  Management Sub‐ Plan; 

the Stormwater Management Sub‐ Plan; 

the Handling of Dangerous Goods and Hazardous Substances Sub‐ Plan; 

the Waste Management On‐Site Sub‐ Plan; 

the Water and Wastewater Management Sub‐ Plan; 

the Shorebird Management Sub‐Plan; 

the Feral Animal management Sub‐Plan, and 

the Energy Management Action Sub‐Plan. 

2.4 Key Performance Indicators Overview 

A KPI is an objective and concise measure of one facet of operational performance managed by each sub‐plan. 

By comparing operational data to KPI targets and goals, SICTL can assess its own performance and identify 

opportunities for improvement. Each OEMP sub‐plan has at least one KPI. The context for all KPI’s is per 

Twenty‐foot Equivalent Unit (TEU) of throughput. In some instances where the KPI is expected to be low, it is 

measured for every thousand TEU throughput for convenience. The KPIs managed under this sub‐plan are 

detailed in section 6. 

The relationship between the KPI under this sub‐plan and the relationship to statutory compliance is discussed 

in section 6. 

 

 

 

 

 

Health Safety Enviroment and Quality Management System 

Noise Management Sub‐Plan ‐ SICTL 

Document Reference:   HSEQ5.1.7d  Document Title:  Noise Management Sub‐Plan ‐ SICTL  Version: 2

Document Owner:  HSEQ Department  Approved Date:  30 August 2013  Page 8 of 33

Printed Version is uncontrolled ‐ controlled version available on Sharepoint 

3 Legislative Framework 

3.1 Applicable Legislation 

The legislation that applies to the implementation of this sub‐plan is listed below: 

Protection of the Environment (Operations) Act 1997 (NSW) 

Environmental Planning and Assessment Act, 1979 (NSW) 

3.2 Conditions of Development Consent  

The Conditions of Development Consent relating to noise are outlined below in table 1. 

Table 1: Conditions of Development Consent 

Condition  Conditions of Development Consent 

C2.5  Operation Noise Management Plan 

Prior to the commencement of operations, the Applicant must prepare an Operation Noise Management Plan in consultation with DEC, DOP, Botany and Randwick Councils. The Plan shall include noise management, mitigation monitoring and reporting to ensure that local acoustic amenity is not adversely impacted. In addition, the Operation Noise Management Plan must: 

Identify general activities that will be carried out and associated noise sources; 

Assess operation noise impacts at the relevant receivers; 

A primary objective of achieving the operational noise limits outlined in this consent; 

Provide details of overall management methods and procedures that will be 

implemented to control noise from the development; 

Include a pro‐active and reactive strategy for dealing with complaints including 

achieving the operation noise limits, particularly with regard to verbal and 

written responses; 

Detail noise monitoring, reporting and response procedures consistent with the 

requirements of DEC; 

Provide for internal audits of compliance of all plant and equipment; 

Indicate site establishment timetabling to minimise noise impacts; 

Include procedures for notifying residents of operation activities likely to affect 

their noise amenity; 

Address the requirements of DEC; 

A strategy to identify operational practices and noise controls that can minimise 

or reduce noise levels from container impacts, audible alarms and other short 

duration, high level noise events; 

Identify opportunities to reduce operational noise levels including, but not 

necessarily limited to, selection of equipment, engineering noise controls and 

shore‐based power; and, 

Be approved by the Director‐General prior to the commencement of operation. 

C2.6  Noise Limits 

Noise from the premises must not exceed the sound pressure levels (noise) limits 

Health Safety Enviroment and Quality Management System 

Noise Management Sub‐Plan ‐ SICTL 

Document Reference:   HSEQ5.1.7d  Document Title:  Noise Management Sub‐Plan ‐ SICTL  Version: 2

Document Owner:  HSEQ Department  Approved Date:  30 August 2013  Page 9 of 33

Printed Version is uncontrolled ‐ controlled version available on Sharepoint 

Condition  Conditions of Development Consent 

presented in the table below. Note the limits represent the sound pressure level (noise) 

contribution at the nominated receiver locations in the table. 

Most Affected 

Residential 

Location 

Day  Evening  Night 

LAeq (15 min)  LAeq (15 min)  LAeq (15 min)  LAeq (9 hrs)  LA1 (1 min) 

Chelmsford 

Avenues 

40  40  40  38  53 

Dent Street  45  45  45  43  59 

Jennings Street  36  36  36  35  55 

Botany Road 

(north of Golf 

Club) 

47  47  47  45  59 

Australia 

Avenue 

35  35  35  35  57 

Military Road  42  42  42  40  60 

For the purpose of this condition; 

Day is defined as the period from 7am to 6pm Monday to Saturday and 8am to 6pm Sundays and Public Holidays, 

Evening is defined as the period from 6pm to 10pm 

Night is defined as the period from 10pm to 7am Monday to Saturday and 10pm to 8am Sundays and Public Holidays 

C2.7  Noise from the premises is to be measured at the most affected point within the 

residential boundary, or at the most affected point within 30 metres of the dwelling 

where the dwelling is more than 30 metres from the boundary, to determine compliance 

with the noise limits in Condition C2.6 unless otherwise stated. 

C2.8  Noise from the premises is to be measured at 1m from the dwelling façade to determine 

compliance with the LA1 (1 min) noise level in Condition C2.6. 

C2.9  Where it can be demonstrated that a direct measurement of noise from the premises is 

impractical, the DEC may accept alternative means of determining compliance. See 

Chapter 11 of the NSW Industrial Noise Policy. 

C2.10  The modification factors presented in Section 4 of the NSW Industrial Noise Policy shall 

also be applied to the measures noise levels where applicable. 

C2.11  The noise emission limits identified in Condition C2.6 apply under meteorological 

conditions of wind speed up to 3 metres per second at 10 metres above ground level, 

and temperature inversion conditions up to 1.5°C/ 100m positive lapse rate. 

Health Safety Enviroment and Quality Management System 

Noise Management Sub‐Plan ‐ SICTL 

Document Reference:   HSEQ5.1.7d  Document Title:  Noise Management Sub‐Plan ‐ SICTL  Version: 2

Document Owner:  HSEQ Department  Approved Date:  30 August 2013  Page 10 of 33

Printed Version is uncontrolled ‐ controlled version available on Sharepoint 

N.B: The Department of Environment and Conservation (DEC) is now known as the Environment Protection 

Authority (EPA). 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Health Safety Enviroment and Quality Management System 

Noise Management Sub‐Plan ‐ SICTL 

Document Reference:   HSEQ5.1.7d  Document Title:  Noise Management Sub‐Plan ‐ SICTL  Version: 2

Document Owner:  HSEQ Department  Approved Date:  30 August 2013  Page 11 of 33

Printed Version is uncontrolled ‐ controlled version available on Sharepoint 

4 Strategic Approach 

4.1 Risk Identification 

The risks identified by SICTL to be managed by this sub‐plan are: 

noise generated by operational and maintenance plant, machinery and equipment within the 

Terminal; 

noise from containers landing on hardstand areas, train cars and truck trailers; 

noise generated by freight trains on the railway siding, and 

noise from the rail siding gate  when trains are in motion. 

A detailed risk assessment and evaluation of control measures will be undertaken by SICTL prior to 

commencement to ensure the risks are controlled to be as low as reasonably practicable. The mitigation 

measures specified in this sub plan will be updated to correspond with ongoing changes to the Environmental 

Risk Assessment. 

4.1.1 Exclusions to the Scope of this Sub‐Plan 

Unless noted otherwise, this sub‐plan does not cover noisy activities: 

not listed in the Development Consent; 

on board vessels; 

and actions by vessels (movements, noise, emissions etc) 

in Botany Bay beyond the quay line of the SICTL Terminal; 

outside the lease area of the SICTL Terminal; 

of future construction phases (covered in separate CEMP’s), and 

beyond the reasonable control or responsibility of SICTL. 

Note: Traffic noise management is addressed in section 5.1.1 of HSEQ5.1.7e Operational Traffic Management 

Sub‐Plan. 

 

 

 

 

 

 

 

 

 

 

 

 

Health Safety Enviroment and Quality Management System 

Noise Management Sub‐Plan ‐ SICTL 

Document Reference:   HSEQ5.1.7d  Document Title:  Noise Management Sub‐Plan ‐ SICTL  Version: 2

Document Owner:  HSEQ Department  Approved Date:  30 August 2013  Page 12 of 33

Printed Version is uncontrolled ‐ controlled version available on Sharepoint 

4.2 Potential Operational Noise Impacts 

4.2.1 Noise from Operational Plant, Machinery and Equipment 

The SICTL Terminal will feature a combination of electric and diesel plant, machinery and equipment (assets) 

used in the general operation of the terminal and for maintenance activities. It is expected that noise from 

these assets will have some impact on nearby residents unless adequately managed. The main areas of 

concern are engine noise and reversing alarms. 

Under the requirements for safe work, all mobile plant and structures within the Terminal must be fitted with 

audible motion and reversing alarms. The noise from high pitched ‘beeper’ type reversing alarms is known to 

carry for long distances and may present a nuisance to nearby residents. Additionally, SICTL does not have any 

control over the type of reversing alarms fitted to customer’s trucks. 

Traffic noise management is addressed in section 5.1.1 of HSEQ5.1.7e Operational Traffic Management Sub‐

Plan. 

Table 2: The expected noise impacts from operational plant 

Vehicle or Item of Plant  Motion / Reversing Alarm 

Quay Crane  Fitted, active when long‐travelling along quay line 

Automated Stacking Crane  Fitted: 

Alarms inactive when in ‘auto’ mode as these cranes work in a 

personnel exclusion zone; 

Alarms active when in in manual mode for maintenance or when 

hoisting above the Land Side Exchange. 

Shuttle Carrier  Fitted, active when reversing 

Reach Stacker  Fitted, active when reversing 

Small plant (EWP, forklift)  Fitted, active when transiting in both directions 

SICTL Utes  Fitted, active when reversing 

Yard Trucks  Fitted, active when reversing 

Customers Trucks  Fitted, active when reversing 

In contrast, the Quay Cranes and Automated Stacking Cranes used within the Terminal are electrically driven 

and are not expected to impact nearby residents. 

4.2.2 Noise from Container Handling 

The noise from containers landing on hard surfaces is expected to occasionally impact nearby residents in 

certain environmental conditions such as wind direction and high speeds. The main sources of noise at the 

terminal are shown in figure 2. 

D

D

 

S

h

4

In

c

a

u

c

F

a

s

im

B

s

g

4

N

s

t

W

p

p

Document Refere

Document Owner

SICTL anticipat

handling will b

4.2.3 Nois

n accordance

cargo using th

approximatel

unit separate

commencem

Freight trains

an available s

iding. This m

mpact nearb

Before a train

afe work, op

gate is closed

4.2.4 Nois

Noise emana

ound the sh

he Internatio

When berthe

powering gen

practice gene

Lan

ence:   HSEQ5.1

r:  HSEQ De

Fig

tes the noise l

be done by the

e from Frei

e with the le

he rail netwo

ly 600m long

e to SICTL. Du

ent with the

s longer than

siding until it

marshalling p

by residents. 

n enters or le

pening the si

d.  The audib

e from Ship

ting from sh

ip’s horn in o

onal Regulat

ed, the usual 

nerators for t

erates signifi

ndside Exchang

.7d 

epartment 

Printed Vers

gure 2 Diagra

levels from co

e Automated 

ight Trains a

ease conditio

ork. the SICT

g.. The rail te

ue to constru

e remainder t

n 600m will n

t reaches the

rocess and t

eaves the rai

ding gate ac

le alarm is e

ps 

ips is outside

order to com

ion for the P

practice is f

the operatio

cantly less n

ge 

Document Title

Approved Date

sion is uncontrolle

am showing 

ontainer hand

Stacking Cran

and Rail Ac

ons applicabl

TL Terminal w

erminal will b

uction phasin

to be commi

need to use t

e end, then u

he locomotiv

il terminal, th

tivates flash

xpected to c

e the contro

mmunicate hi

Prevention of

or crews to s

on of the ship

oise than us

:  Noise Manag

:  30 August 20

ed ‐ controlled ve

likely origins

ling to be low

nes (ASCs) whi

ctivities 

e to the Term

will eventual

be managed 

ng, only two

issioned in fu

two sidings. T

uncoupling a

ves themselv

he siding gat

ing lights an

create some 

l of SICTL. W

is intentions

f Collisions a

shut down th

p’s systems a

ing the main

Rail sidi

Health Sa

gement Sub‐Plan 

013 

ersion available o

s of containe

wer than existi

ich have more

minal, SICTL 

ly feature a f

by Hutchiso

of these sid

uture phases

This will be a

nd moving t

ves are expe

te must be o

d audible ala

noise that m

When underw

 to other ves

at Sea. 

heir main en

and the pres

n engines. 

ings 

afety Enviroment

Noise Man

‐ SICTL 

on Sharepoint 

r landing no

ng terminals b

e control than

is obligated 

four siding ra

n Logistics A

ings will be c

s. 

achieved by 

he remainde

ected to crea

pened. Unde

arms which r

may affect ne

way, the vess

ssels under N

gines and ru

ervation of r

Qua

bert

nt and Quality Ma

agement Su

V

ise. 

because the m

n a manual op

to move a p

ail terminal o

Australia (HLA

commissione

marshalling 

er into the ad

ate some noi

er the requir

remain activa

earby residen

sel Master is 

NSW maritim

un smaller en

refrigerated 

ay apron at 

ths 3 and 4 

Watersid

and Exc

Quay apr

berths 1 a

anagement Syste

b‐Plan ‐ SICT

Version:

Page 13 of 

majority of 

eration. 

ercentage of

of 

A), a busines

ed upon 

the train into

djacent 

se that may 

rements for 

ated until th

nts. 

required to 

me law and 

ngines 

cargo.  This 

de Exchange 

change Pad 

ron at 

and 2 

em 

TL 

2

33

 

ss 

Health Safety Enviroment and Quality Management System 

Noise Management Sub‐Plan ‐ SICTL 

Document Reference:   HSEQ5.1.7d  Document Title:  Noise Management Sub‐Plan ‐ SICTL  Version: 2

Document Owner:  HSEQ Department  Approved Date:  30 August 2013  Page 14 of 33

Printed Version is uncontrolled ‐ controlled version available on Sharepoint 

5 Implementation of This Sub‐Plan The implementation of this sub‐plan will follow a closed‐loop approach developed to suit the nature of the 

Development Consent (listed in section 3.2) that are related to Noise Management. This method is an 

extension of the process shown in figure 1 and has the primary objective of achieving the operational noise 

limits outlined in the Development Consent. The closed‐loop is explained diagrammatically below:  

Sub‐plan specifies the noise controls 

required

Noise controls implemented 

during operations

Operations generate noise

Noise measured at residential receivers

Results of monitoring reviewed by 

SICTL

SICTL can amend sub‐plan or introduce new controls

 

Figure 3 Closed‐loop operations of this sub‐plan. 

 

The range of noise mitigation controls specified in section 5.1 of this sub‐plan will be applied to the operations 

of the terminal by SICTL. Noise monitoring will be undertaken as a means of confirming the effectiveness of 

the noise control measures and to detect any exceedances. These results will be collected and reviewed by the 

HSEQ department where the operational activities will also be assessed against the data. Changes to the 

methods of operations can be made or additional controls implemented by SICTL depending on the noise 

levels received at the monitoring station with the aim of complying with the noise limits listed in the 

Development Consent. 

 

 

 

Health Safety Enviroment and Quality Management System 

Noise Management Sub‐Plan ‐ SICTL 

Document Reference:   HSEQ5.1.7d  Document Title:  Noise Management Sub‐Plan ‐ SICTL  Version: 2

Document Owner:  HSEQ Department  Approved Date:  30 August 2013  Page 15 of 33

Printed Version is uncontrolled ‐ controlled version available on Sharepoint 

5.1 Operational Controls 

Details of the overall management methods and procedures that will be implemented to control noise from 

the SICTL Terminal are explained in this section. The controls correspond with the potential operational 

impacts raised in section 4.3. 

5.1.1 Gradual Commencement Timetabling 

the SICTL Terminal will become progressively operational over three phases outlined below thus minimising 

noise impacts through a gradual increase in throughput. 

Phase 1 – 2013: 

the terminal buildings will be built; 

the first 2 berths will be commissioned; 

the first 4 Quay Cranes (QCs) will be installed and commissioned; 

the first 3 Automated Stacking Crane (ASC) stacks will be opened, and 

the shuttles, reach stackers and forklifts begin operating. 

Phase 2 – 2014: 

the last 2 berths will be commissioned (total four); 

the next 3 ASC stacks will be opened (now six), and 

additional shuttles, reach stackers and forklifts will operate. 

Phase 3 – 2014 ‐ 2015: 

the last 2 QCs will be installed and are commissioned (total six); 

the last 7 ASC stacks will be opened (total thirteen); 

additional shuttles, reach stackers and forklifts will operate; 

the new railway siding will be built and commissioned, and 

freight trains begin service to the SICTL Terminal. 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Health Safety Enviroment and Quality Management System 

Noise Management Sub‐Plan ‐ SICTL 

Document Reference:   HSEQ5.1.7d  Document Title:  Noise Management Sub‐Plan ‐ SICTL  Version: 2

Document Owner:  HSEQ Department  Approved Date:  30 August 2013  Page 16 of 33

Printed Version is uncontrolled ‐ controlled version available on Sharepoint 

5.1.2 Noise Wall 

The terminal is built with a noise wall along its northern edge as depicted below. The noise wall was designed 

in accordance with the acoustic modelling detailed in chapter 22 of the Port Botany Expansion Environmental 

Impact Statement (EIS) and is: 

3 metres high when parallel to the railway siding, and 

4 metres high along other areas of the terminal. 

 

Figure 4 Diagram showing the extent of the noise wall. 

 

As shown in the noise modelling in chapter 22 of the EIS and in the application for Development Consent this 

noise wall is expected to attenuate the noise emanating from the terminal. It is worth noting that a key 

assumption in the modelling was the absence of stacked containers within the terminal. During operation, 

containers will be stacked up to five high in the ASC stacks thus further shielding noise sources and minimising 

the impact beyond the modelling.  

5.1.3 Controls on Noise from Operational Plant and Vehicles 

One of the criteria for selecting operational plant such as Reach Stackers and Shuttle Carriers was low noise 

emissions. The plant selected for use at the Terminal are all bought new and are fitted with the manufacturer’s 

noise control devices. These machines will be maintained by the SICTL in‐house maintenance personnel who 

will ensure the noise control devices such as mufflers and insulated panels are always working adequately or 

that defective units are replaced. 

Under the requirements for safe working, all plant owned or operated by SICTL must be fitted with reversing 

alarms. The type of alarms fitted will be the broadband ‘quacker’ type as opposed to the alternative tonal 

‘beeper’ type. Broadband type reversing alarms are equally effective but minimise noise impacts on nearby 

residents and do not project their sound as far as the tonal type. Prior to operating an item of plant, the 

operator will check the fitted noise control devices and reversing alarms are adequate and are working 

Gap in noise wall for 

vehicles 

3m high Noise wall 

along railway siding 

Tug berth 

(not SICTL) 

4m high Noise wall 

along all other areas 

Health Safety Enviroment and Quality Management System 

Noise Management Sub‐Plan ‐ SICTL 

Document Reference:   HSEQ5.1.7d  Document Title:  Noise Management Sub‐Plan ‐ SICTL  Version: 2

Document Owner:  HSEQ Department  Approved Date:  30 August 2013  Page 17 of 33

Printed Version is uncontrolled ‐ controlled version available on Sharepoint 

correctly as part of the pre‐start checking procedure for each machine. Any rectifications will be managed 

through the SICTL maintenance department and recorded on the pre‐start checklist for each machine. SICTL 

would undertake a safety assessment to identify where audible alarms could be replaced with visual alarms 

and where it is safe to do so, audible alarms for the period between 10pm and 6am would be switched off.  

As the number of operational plant will increase over the operational start‐up period, this safety assessment 

will be conducted within 12 months of operational commencement in order to be applied to a larger 

compliment of operational plant rather than the smaller initial fleet. 

Carrier’s trucks will arrive at the terminal to load or unload containers and will be fitted with a variety of 

reversing alarms (broadband and tonal types). SICTL will encourage its customers to fit broadband type 

reversing alarms to their trucks in order to minimise the noise impacts on nearby residents. 

Management methods for minimising the noise from operational plant and vehicles will be communicated to 

visitors, operators and contractors through the SICTL induction program. Equipment idle time will be 

minimised through throttling down and switching off idle equipment. Operators and truck drivers will be  

encouraged to identify practices and opportunities to reduce operational noise emanating from plant. 

Generally, the noise from operational, maintenance and carrier’s vehicles will be assessed by the HSEQ Officer 

or the Environmental and Safety Compliance Engineer during regular terminal inspections and internal process 

audits. Items of plant or vehicles that have malfunctioning or damaged noise control devices will be removed 

from service, documented and referred to the SICTL maintenance department for repairs. Repairs will be 

undertaken in a timely manner. 

Traffic noise management is addressed in section 5.1.1 of HSEQ5.1.7e Operational Traffic Management Sub‐

Plan. 

5.1.4 Controls on Noise from Containers Landing 

The majority of the controls to minimise noise from containers landing on hard surfaces are built into the 

machines that lift them. Soft landings are achieved by programming the machine control systems to slowly 

lower containers when approaching ground level. The Automated Stacking Cranes will do this as they are 

guided by laser systems which track the progress of a container being lowered. Similarly, the Quay Crane 

enters ‘slow mode’ when approaching the level of the quay apron. 

Table 3: The noise mitigation management methods for all plant on the terminal 

Landing surface  Landed by  Noise Mitigation Control 

Concrete (quay apron)  Quay Crane  The cranes have inbuilt mechanisms to land containers 

slowly to avoid banging that are complimented by operator 

awareness and training 

Concrete (waterside 

exchange, exchange pad) 

Shuttle Carrier  The shuttle carriers have inbuilt mechanisms to land 

containers slowly to avoid banging that are complimented 

by operator awareness and training 

Another container  ASC in auto 

mode 

The ASC is guided by laser systems and has been 

programmed to land containers slowly to avoid banging 

Truck trailer  ASC in manual 

mode 

The ASC Operator is guided by laser systems and has been 

trained to land containers slowly to avoid banging 

Health Safety Enviroment and Quality Management System 

Noise Management Sub‐Plan ‐ SICTL 

Document Reference:   HSEQ5.1.7d  Document Title:  Noise Management Sub‐Plan ‐ SICTL  Version: 2

Document Owner:  HSEQ Department  Approved Date:  30 August 2013  Page 18 of 33

Printed Version is uncontrolled ‐ controlled version available on Sharepoint 

Landing surface  Landed by  Noise Mitigation Control 

Train car  Reach Stacker        Operators are trained to land containers slowly so as to 

line up container with the twistlocks on the rail car thus 

avoiding banging 

Ship’s hold (container may 

strike the insertion guides of 

cells when being lowered 

below deck) 

Quay Crane  Operators are trained to line up container with insertion 

guides carefully to avoid banging 

5.1.5 Controls on Noise from Freight Trains and Rail Activities 

The noise wall erected alongside the entire length of the rail sidings is the main management measure that will 

attenuate most noise emanating from trains and rail activities. When the siding gate is opened the safety 

alarm will be activated for a continuous period. Rail operations will be planned and controlled so that the 

siding gate is not opened for longer than necessary thus avoiding unnecessary noise. SICTL would undertake a 

safety assessment to identify where audible alarms could be replaced with visual alarms and where it is safe to 

do so, audible alarms for the period between 10pm and 6am would be switched off. 

HLA and SICTL staff working within the rail siding will undergo training on the correct marshalling of trains 

within these sidings to foster awareness of noise issues. 

The unnecessary use of whistles or horns by trains on the SICTL rail siding is not permitted, to prevent 

disturbances to shorebirds in Penrhyn Estuary and local residents. Under the requirements for safe work, the 

use of train horns (where necessary) will prevail. 

5.1.6 Controls on Noise from Ships 

SICTL will liaise with the Shipping Lines so that noise emanating from ships deemed to have adverse impacts 

on nearby residents is mitigated as much as practicable. If a ship is identified as particularly noisy, Sydney Ports 

VTS Centre may be contacted and port officers can be dispatched to the ship to attempt to identify and 

remedy the noise issues. 

Proposed controls on noise from ships whilst berthed include shutting off the main engine(s) and running 

smaller engines to drive generators or the (future) use of Shore Based Power. 

Although the infrastructure has been installed during construction of the Terminal, Shore Based Power is not 

immediately available for use as a noise mitigation measure upon commencement. SICTL will commission 

Shore Based Power at all berths in future construction phases which will compliment other controls for noise 

mitigation. 

 

 

 

 

 

 

 

D

D

5

In

e

a

 

 

 

 

 

 

 

 

 

 

 

 

Document Refere

Document Owner

5.1.7 Asse

n addition to

expected at t

availability of

Figu

SICT

Term

Footp

ence:   HSEQ5.1

r:  HSEQ De

essment of O

o the noise m

the various lo

f noise monit

ure 5 Ambien

TL 

minal 

print 

.7d 

epartment 

Printed Vers

Operationa

modelling und

ocations surr

toring result

nt Noise Mon

Document Title

Approved Date

sion is uncontrolle

al Noise Imp

dertaken in c

rounding the

ts. 

nitoring Loca

:  Noise Manag

:  30 August 20

ed ‐ controlled ve

pacts at the

chapter 22 o

e SICTL Term

ations (numb

Health Sa

gement Sub‐Plan 

013 

ersion available o

e Relevant R

of the EIS, thi

minal. This ass

bers 1 to 6, a

afety Enviroment

Noise Man

‐ SICTL 

on Sharepoint 

Receivers 

is sub‐plan a

sessment wi

dapted from

nt and Quality Ma

agement Su

V

assesses the 

ll be replace

m EIS figure 2

anagement Syste

b‐Plan ‐ SICT

Version:

Page 19 of 

noise impact

ed upon the 

22.1). 

em 

TL 

2

33

ts 

 

Health Safety Enviroment and Quality Management System 

Noise Management Sub‐Plan ‐ SICTL 

Document Reference:   HSEQ5.1.7d  Document Title:  Noise Management Sub‐Plan ‐ SICTL  Version: 2

Document Owner:  HSEQ Department  Approved Date:  30 August 2013  Page 20 of 33

Printed Version is uncontrolled ‐ controlled version available on Sharepoint 

Table 4: Assessment of Operational Noise Impacts at the Relevant Receivers 

Relevant Receiver  No. On Map  Assessment of Operational Noise Impacts  

Chelmsford Avenues  1  The location is not expected to be impacted as there are many 

roads, residences and industrial sites between this location and the 

SICTL Terminal. This location is also close to Sydney Airport. 

Dent Street  2  This location is expected to be the most impacted because it is the 

closest residential receiver to the SICTL Terminal. This area is the 

most suitable for operational noise monitoring and will be treated 

as representative of other locations. 

Jennings Street  3  This location is not expected to be impacted as there are many 

roads, residences and industrial sites between this location and the 

SICTL Terminal. 

Botany Road (North 

of Golf Club) 

4  This location is expected to be impacted due to the proximity to the 

SICTL Terminal. 

Australia Avenue  5  This location is not expected to be impacted as there are many 

roads, residences and industrial sites between this location and the 

SICTL Terminal. 

Military Road  6  This area is not expected to be impacted as there are two other 

stevedores and various industrial sites between this location and 

the SICTL Terminal. 

5.1.8 Procedures for Notifying Residents 

In the event that SICTL anticipates operational activities likely to affect the noise amenity of nearby residents a 

suitable notification will be selected from the following methods: 

Messages communicated to passing motorists on VMS boards located on Foreshore Rd and/ or near 

Botany shops on Botany Rd 

Broadcasting notification emails to the addresses on the SICTL community mailing list (visitors to the 

company website can register their email address) 

Letterbox drops through the surrounding areas of Banksmeadow and Botany 

Attaching a notification to the Community notice boards at Botany Shops 

Advertising notifications on the company website 

Advertising notifications in the local newspapers 

Door knocks for the residents likely to be most affected 

 

 

 

 

Health Safety Enviroment and Quality Management System 

Noise Management Sub‐Plan ‐ SICTL 

Document Reference:   HSEQ5.1.7d  Document Title:  Noise Management Sub‐Plan ‐ SICTL  Version: 2

Document Owner:  HSEQ Department  Approved Date:  30 August 2013  Page 21 of 33

Printed Version is uncontrolled ‐ controlled version available on Sharepoint 

5.2 Training of personnel 

The training of personnel on the requirements of this sub‐plan occurs during the general terminal induction 

where an outline of noise management is delivered to all new workers. This training will be completed online 

prior to the new worker arriving at the terminal. Further detailed training on the noise impacts on nearby 

residents may be delivered to workers undertaking the level 2 and level 4 environmental training under 

section 2.3 of the HSEQ5.1.7 Operational Environmental Management Plan (OEMP) – SICTL. 

5.3 Monitoring and Response 

5.3.1 Background Noise Monitoring Strategy 

The strategy adopted by SICTL is to undertake continuous noise monitoring for two weeks prior to operational 

commencement and record a pre‐operational background noise level at selected receivers, namely: 

Chelmsford Avenues, Botany 

Dent Street, Botany 

Jennings Street, Matraville 

Botany Road, Banksmeadow (North of Golf Club) 

Australia Avenue, Matraville 

Military Road, Matraville 

This noise monitoring will generally be unattended however attended noise monitoring may be included 

where appropriate. The background noise levels measured prior to operations would be used as a baseline for 

comparison against future results during operation of the terminal. 

5.3.2 Operational Noise Monitoring Strategy 

The six locations identified in the Development Consent, figure 5 and table 4 will be also used in the 

operational background noise monitoring program. The noise levels measured during operations will be 

compared to the baseline in order to establish the contribution emanating from the SICTL Terminal. 

During operations, SICTL will undertake periodic attended and unattended noise monitoring to develop a 

representation of the terminal noise received by residential receivers. The operational noise monitoring 

program will: 

Continuously record for a duration of two weeks at a time; 

Take place at a frequency of every six months; 

Additionally take place at the commencement of a new phase of operations or at appropriate 

operational milestones; 

Take place in support of any application made by NSW Ports to increase the throughput at the 

terminal; 

Take place at any other additional time as determined by SICTL for example, in relation to noise 

complaints or the introduction of different equipment, and 

Be used to verify the noise contribution of the terminal against the noise modelling predictions stated 

in the EIS and investigate and explain differences. 

SICTL will engage noise consultants accredited by the Association of Australian Acoustical Consultants (AAAC) 

for the monitoring of noise from the SICTL Terminal. In order to isolate the noise contribution by SICTL as 

much as is possible and to measure in accordance with the Consent Conditions, additional noise monitoring 

Health Safety Enviroment and Quality Management System 

Noise Management Sub‐Plan ‐ SICTL 

Document Reference:   HSEQ5.1.7d  Document Title:  Noise Management Sub‐Plan ‐ SICTL  Version: 2

Document Owner:  HSEQ Department  Approved Date:  30 August 2013  Page 22 of 33

Printed Version is uncontrolled ‐ controlled version available on Sharepoint 

locations may be included or residential receiver locations adjusted in consultation with the noise consultant 

(but still in compliance with conditions C2.7 and C2.8). 

5.3.3 Proactive and Reactive Strategies for Dealing with Complaints 

The reactive strategy for dealing with complaints is triggered by a noise complaint received by SICTL. Upon 

receipt of the complaint SICTL will follow the complaints management process (including verbal and written 

responses to complainants – refer to Step 1 of the complaints management process) shown in section 6.2 and 

investigate. 

The proactive strategy for dealing with complaints is an investigation initiated during noise monitoring if an 

exceedance of the noise limits in Consent Condition C2.6 that would normally cause a complaint to be lodged. 

This investigation is undertaken without a complaint being received. Both of these processes are described in 

the diagram below: 

Noise Complaint

Investigation

Periodic monitoring

AND/ OR

Check or reviewoperations underway

Complaint logged in register or software

Exceedance logged by monitoring 

station

Noisecaused bySICTL?

Advise SICTL Management and 

implement controls

Yes No

Advise complainant and 

close outFollow up

Advise complainant and 

close out

(REACTIVE) (PROACTIVE)

  

Figure 6 Proactive and reactive strategies for dealing with complaints. 

Through analysis and review of noise data and comparison to operations underway at the terminal, SICTL can 

understand and pre‐empt the noise impacts experienced at the residential receivers. In order to comply with 

the noise limits in the Development Consent SICTL can implement: 

Changes to operations; 

Training and education of Operators and other personnel; 

The fitting, repair or adjustment of noise control devices, where needed. 

 These noise controls will be specified on a case by case basis depending on the noise impact but may include: 

Using methods or devices to cushion containers landing; 

Using an alternative berth farther away, if available and practicable; 

Stacking containers for use as shielding; 

Educating operators about noise impacts and SICTL’s mitigation measures, and 

Health Safety Enviroment and Quality Management System 

Noise Management Sub‐Plan ‐ SICTL 

Document Reference:   HSEQ5.1.7d  Document Title:  Noise Management Sub‐Plan ‐ SICTL  Version: 2

Document Owner:  HSEQ Department  Approved Date:  30 August 2013  Page 23 of 33

Printed Version is uncontrolled ‐ controlled version available on Sharepoint 

Standing down plant identified as having faulty noise control equipment. 

SICTL will analyse and graph all noise monitoring data. These graphs will show trends and any exceedances of 

noise criteria. This graph will be reviewed regularly by the HSEQ department and will be distributed in 

accordance with the below diagram:  

 

Figure 7 Illustration showing the how the monitoring results are used. 

 

SICTL will undertake an annual review of the monitoring and discuss justification in each Annual Environmental 

Management Report (AEMR). Section 6.2.1 provides more information on reporting obligations. 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Health Safety Enviroment and Quality Management System 

Noise Management Sub‐Plan ‐ SICTL 

Document Reference:   HSEQ5.1.7d  Document Title:  Noise Management Sub‐Plan ‐ SICTL  Version: 2

Document Owner:  HSEQ Department  Approved Date:  30 August 2013  Page 24 of 33

Printed Version is uncontrolled ‐ controlled version available on Sharepoint 

6 Performance Expectations In addition to monitoring the noise emanating from SICTL against the Development Consent noise limits, two 

complimentary measures of how well this sub‐plan is implemented and the effectiveness of the control 

measures described in section 5.1 is the number of noise complaints returned by residents or the number of 

exceedances of the noise limits in the Development Consent during monitoring. This ‘cover‐all’ approach is 

deemed the most suitable for quantifying this Key Performance Indicator (KPI). The KPI is described in the 

table below. 

Table 5: Management of Key Performance Areas 

Key Performance Areas  Key Performance Indicators  Goal 

Noise and Complaints  Noise disturbance, expressed as the number of 

community complaints or exceedances of the noise 

limits specified in Development Consent Condition 

C 2.6 during monitoring per 100,000 TEU 

Zero per 100,000 TEU 

 

Note: The noise limits specified in condition C 2.6 of the Development Consent are managed through section 

3.2. 

SICTL aims to meet this KPI goal through proactive management of its operations. The goal adopted by SICTL 

under this sub‐plan is for no noise complaints attributed to the operation of the SICTL Terminal. 

SICTL may use the noise disturbance KPI in order to determine where additional noise monitoring and 

potential adjustment to operations is required. The results of this targeted noise monitoring strategy (in 

addition to the periodic noise monitoring) allows SICTL to assess and ensure it’s Statutory Compliance. 

6.1 Opportunities for Improvement 

Under this sub‐plan opportunities for improvement of operational practices and noise controls will be 

identified by the HSEQ Officer and Environmental and Safety Compliance Engineer during general inspections 

of the terminal, inspections of the control measures, analysis of monitoring data and consultation with the 

workforce. Additionally the community or the Operational Community Consultative Committee (OCCC) can 

raise issues directly with SICTL that affect or interfere with the noise amenity of nearby residents. These will be 

treated as opportunities for improvement by the HSEQ Officer or the Environmental and Safety Compliance 

Engineer and be rectified within agreed timeframes. All such opportunities for improvement will be reported 

in accordance with the HSEQ2.2.1 Hazard and Improvement Opportunity Reporting Procedure using the 

HSEQ2.2.1.1 Hazard and Improvement Report Form and registered on the HSEQ Information Management 

System. 

 

 

 

 

 

Health Safety Enviroment and Quality Management System 

Noise Management Sub‐Plan ‐ SICTL 

Document Reference:   HSEQ5.1.7d  Document Title:  Noise Management Sub‐Plan ‐ SICTL  Version: 2

Document Owner:  HSEQ Department  Approved Date:  30 August 2013  Page 25 of 33

Printed Version is uncontrolled ‐ controlled version available on Sharepoint 

6.2 Management of Noise Complaints 

This section describes the approved process of complaint management by SICTL. An overview of the 

complaints management and investigation process is outlined below: 

   

Figure 8 The process of complaint management. 

Health Safety Enviroment and Quality Management System 

Noise Management Sub‐Plan ‐ SICTL 

Document Reference:   HSEQ5.1.7d  Document Title:  Noise Management Sub‐Plan ‐ SICTL  Version: 2

Document Owner:  HSEQ Department  Approved Date:  30 August 2013  Page 26 of 33

Printed Version is uncontrolled ‐ controlled version available on Sharepoint 

The complaints management process is comprised of six steps which aim to ensure beneficial resolution 

following a complaint lodged with SICTL. Other stakeholders can also lodge complaints with SICTL, the process 

followed will be the same: 

Step 1: SICTL will receive the complaint and provide initial feedback and acknowledgement to the 

Complainant. This initial feedback will be within the following timeframes: 

(verbal) immediately for complaints lodged by phone or in person with a written follow‐up within 2 

hours (email or fax); 

(in writing) within 24 hours for complaints received by other means, and 

In the event of a complaint about an environmental issue or pollution, SICTL will verbally notify NSW 

Ports within 2 hours of receiving the complaint and then in writing within 24 hours. 

Step 2: SICTL will log the complaint in the complaints register (or database software) and will capture the 

following information; 

the date and time of the comment, enquiry or complaint; 

the means by which the comment, inquiry or complaint was made (telephone, fax, mail, email or in 

person); 

any personal details of the commenter, enquirer or complainant that were provided, if no details were 

provided a note to that effect; 

the nature of the complaint; 

any actions taken by SICTL in relation to the comment, inquiry or complaint; 

If no action was taken by SICTL in relation to the comment, inquiry or complaint, the reasons why no 

action was taken, and 

any follow up actions with the date and time of follow up communications to the commenter, 

enquirer or complainant. 

Step 3: SICTL will arrange an investigation to determine the cause of the complaint and if this cause is a 

product of SICTL’s actions or under SICTL’s responsibility. The HSEQ Officer or the Environmental & Safety 

Compliance Engineer will conduct an investigation in conjunction with the Terminal Manager and/ or National 

HSEQ Manager. The operations underway at the time of the complaint will be reviewed in order to identify the 

cause. The investigation may collect information through the following sources: 

Speaking with the workforce, plant operators, shift managers and yard managers about the activities 

underway at the time of the complaint; 

Review of shift manager’s diary entries or prestart forms for information; 

Review of operations against the documented and approved work methods to be followed: 

Review of work records/ logged entries within the Terminal Operating System which controls the 

movement of freight within the terminal; 

Review of records of when trucks or ships were being serviced at the time of the complaint; 

Review of any relevant maintenance records for plant; 

Review of environmental conditions at the time of the complaint from weather records online; 

Review of monitoring data, if available, and 

Advice from independent consultants, if required 

The findings of the investigation will contain the above cause data and then include a proposed resolution 

which will satisfy the complainant and SICTL’s operational needs and alternative resolution options which may 

Health Safety Enviroment and Quality Management System 

Noise Management Sub‐Plan ‐ SICTL 

Document Reference:   HSEQ5.1.7d  Document Title:  Noise Management Sub‐Plan ‐ SICTL  Version: 2

Document Owner:  HSEQ Department  Approved Date:  30 August 2013  Page 27 of 33

Printed Version is uncontrolled ‐ controlled version available on Sharepoint 

be implemented if the preferred option is not practicable. The findings, proposals and the resolution (including 

any resolutions already implemented) will be communicated to the complainant in writing. 

Recurring complaints from a localised area will be offered specific noise monitoring to provide further 

information on noise impacts that can be used to develop mitigation measures. 

 In other situations where the complaint was caused by:  

Actions not attributable to any operational actions or ongoing activities by SICTL; 

Actions not otherwise under the responsibility or control of SICTL, or 

A combined effect of the actions by SICTL and another Port Botany lessee such as Patricks Stevedores 

Refer to section 4.4.5. 

Step 4: SICTL will arrange for follow up with the complainant within an agreed timeframe (relative to the 

complaint and the resolution) to collect feedback on the effectiveness of the resolution.  

Step 5: If the resolution is not acceptable to the complainant, SICTL will escalate the matter internally whereby 

a senior‐level manager (Terminal Manager, Operations Manager or National HSEQ Manager) will contact the 

complainant and discuss the issue including existing or further resolution options. At this stage: 

a negotiated resolution which will satisfy the complainant and SICTL’s operational needs can be 

implemented; 

if the senior manager and the complainant do not agree on a negotiated resolution, the senior 

manager will offer the Complainant the opportunity for external mediation, and 

if the Complainant elects mediation, SICTL will respond to the Complainant in writing advising them of 

the details of the mediation venue and appointment. 

Step 6: SICTL will arrange mediation by an impartial external party. SICTL will fund the mediation process and 

accept the mediated solution. The outcome of the mediation will be communicated to the Complainant in 

writing by SICTL. The mediation will be documented and all documents from this and the previous five steps 

will be included in the record of the complaint. 

A Quarterly Complaints Report will be prepared by the HSEQ department outlining each complaint received 

within the previous three‐month period. The relevant portion of the complaints register will be attached to 

each report, in addition to the circumstances of each complaint, any actions HPA undertook to resolve each 

complaint, follow up actions and trends over time. Each Quarterly Complaints Report will be submitted to the 

OCCC, DP&I and the EPA where relevant and published on the HPA website (with personal information 

omitted). 

6.2.1 Management of Complaints or Common Issues involving Neighbouring Stevedores 

The SICTL HSEQ Officer or the Environmental and Safety Compliance Engineer will investigate the complaint or 

the noise disturbance issue in accordance with the process outlined in section 4.6.4 of the OEMP (reproduced 

in section 6.2 of this sub‐plan). However, in cases where the findings of the investigation (Step 3) prove that 

the complaint was caused by a combined effect of the actions by SICTL and another Port Botany lessee (for 

example, activities carried out near the boundary between SICTL and Patricks Stevedores on the Southern end 

of the Terminal known as ‘The Knuckle’) then SICTL will formally notify the complainant with these findings 

and interface with the other lessee via the Terminal Manager using the below process: 

Health Safety Enviroment and Quality Management System 

Noise Management Sub‐Plan ‐ SICTL 

Document Reference:   HSEQ5.1.7d  Document Title:  Noise Management Sub‐Plan ‐ SICTL  Version: 2

Document Owner:  HSEQ Department  Approved Date:  30 August 2013  Page 28 of 33

Printed Version is uncontrolled ‐ controlled version available on Sharepoint 

 

Figure 9 The process of managing complaints involving organisations other than or in addition to SICTL. 

 

SICTL will formally notify the complainant if the findings of the investigation show that SICTL was not 

responsible. In the event that a shared responsibility exists, SICTL will call a meeting or a teleconference 

between NSW Ports and Patricks Stevedores where a collaborative solution can be achieved that satisfies the 

complainant and the operational needs of both stevedores. The SICTL Terminal Manager will be the primary 

interface with the Operations Manager for Patricks Stevedores in this situation. 

6.3 Documentation and Record Keeping 

SICTL will retain all records of noise measurement for traceability. Additionally, the Tier 4 documents that 

come under this sub‐plan are: 

HSEQ2.2.1.1 Hazard and Improvement Report Form 

the complaints register generated by the stakeholder management software 

These documents will be retained for traceability and will be included in the OCCC Quarterly Complaints 

Report and the Annual Environmental Management Report (AEMR). They will be administered by the HSEQ 

Officer/ Environmental & Safety Compliance Engineer and will be uploaded into SICTL’s internal document 

management system, Sharepoint. In line with HPA’s reporting requirements, the complaints, incidents and 

monitoring data will be collated and entered into a database graphing trends over time. Sections of these 

graphs depicting different time periods will be included in the reports as relevant. 

Health Safety Enviroment and Quality Management System 

Noise Management Sub‐Plan ‐ SICTL 

Document Reference:   HSEQ5.1.7d  Document Title:  Noise Management Sub‐Plan ‐ SICTL  Version: 2

Document Owner:  HSEQ Department  Approved Date:  30 August 2013  Page 29 of 33

Printed Version is uncontrolled ‐ controlled version available on Sharepoint 

6.3.1 Reporting Obligations 

Further to section 5.1.8 the monitoring, mitigation, complaints and response information arising from this sub‐

plan will be reported by SICTL in the following: 

The internal reporting documents provided to the six‐monthly operational review by the HPA 

Executive Management Team 

The Annual Environmental Management Report 

Environmental Protection Licence Annual Return Documents 

Operational Community Consultative Committee Quarterly Complaints Report 

Hutchison Ports Website 

The raw data that is captured on the complaints register will go directly into the AEMR together with copies of 

the complaint reports including times, dates, photos and follow up. 

The Noise Disturbance KPI will be reviewed monthly by the HSEQ department so that trends and statistics can 

be included in the 6‐monthly internal reports and the AEMR. The source of this information is the monitoring 

data and the complaints register or database software employed by SICTL. 

Monitoring data must be uploaded to the HPA website within 14 days of receipt as per SICTL’s environmental 

protection licence conditions. 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Health Safety Enviroment and Quality Management System 

Noise Management Sub‐Plan ‐ SICTL 

Document Reference:   HSEQ5.1.7d  Document Title:  Noise Management Sub‐Plan ‐ SICTL  Version: 2

Document Owner:  HSEQ Department  Approved Date:  30 August 2013  Page 30 of 33

Printed Version is uncontrolled ‐ controlled version available on Sharepoint 

7 Responsibility, Accountability and Authority 

7.1 SICTL as Tenant 

SICTL retains ultimate responsibility for implementing this sub‐plan. SICTL has adopted a shared responsibility 

approach where all members of the SICTL Terminal workforce are expected to meet the requirements of this 

sub‐plan and be aware of the potential effects of their work on nearby residents. All staff are made aware of 

this responsibility during the SICTL induction and in the regular toolbox meetings and prestart talks. The HSEQ 

team provides the necessary expertise, guidance and support. 

7.1.1 HSEQ Officer 

The HSEQ Officer is part of the HSEQ Management team and is the primary point of contact at the Terminal 

who advises the management team and the operations staff about compliance with this sub‐plan.  Other 

responsibilities include: 

general surveillance of operations to detect the potential for impacts on nearby residents; 

advise on control measures required to mitigate impacts on nearby residents, and 

interface with the OCCC to manage any impacts originating from the Terminal which affect nearby 

residents as they arise. 

The SICTL Environmental Representative can also undertake these functions. 

7.1.2 Environmental and Safety Compliance Engineer 

The Environmental and Safety Compliance Engineer is also a part of the HSEQ Management Team who 

supports the HSEQ Officer by advising on the legislative and Development Consent requirements applicable to 

operations.  Other responsibilities include: 

measuring operational data, assessing trends and facilitating review; 

setting KPI’s and generating reports outlined in section 2.2 of the OEMP 

authoring and amending the OEMP and sub‐plans, and 

liaising with SICTL management and external stakeholders to determine compliance requirements. 

7.1.3 National HSEQ Manager (Environmental Representative) 

The National HSEQ Manager is responsible for giving overall guidance to the operational staff, HSEQ 

Management team and SICTL management on the HSEQ Management System which includes the OEMP and 

its sub‐plans. The National HSEQ Manager is also responsible for ensuring adequate HSEQ resources are 

available to SICTL. Currently, the National HSEQ Manager is the approved Environmental Representative. 

7.1.4 Terminal Manager 

The Terminal Manager is the central point of co‐ordination between the HSEQ Officer and the general 

operational staff such as Shift Managers, Plant Operators and also the shipping lines.  The Terminal Manager 

controls all operations of the SICTL Terminal and ensures that the HSEQ resources are being used effectively. 

7.1.5 Work Crews and Plant Operators 

The SICTL workforce is responsible for understanding the purpose of this sub‐plan and the controls specified in 

it. Working together with the HSEQ Officer, the workforce will implement this sub‐plan in their daily work 

activities. 

 

 

Health Safety Enviroment and Quality Management System 

Noise Management Sub‐Plan ‐ SICTL 

Document Reference:   HSEQ5.1.7d  Document Title:  Noise Management Sub‐Plan ‐ SICTL  Version: 2

Document Owner:  HSEQ Department  Approved Date:  30 August 2013  Page 31 of 33

Printed Version is uncontrolled ‐ controlled version available on Sharepoint 

8 Identification of Stakeholders 

8.1.1 Internal Stakeholders 

Internal stakeholders are involved with the operation of the Terminal in some way and have an interest in the 

successful implementation of the controls listed in section 5.1. Most internal stakeholders are under the 

direction of Hutchison Ports Australia, a list is given below: 

HPA Corporate (the Executive Management Team); 

HSEQ Department; 

SICTL Management at the Terminal; 

SICTL Maintenance Department; 

Operations Personnel ; 

Contractors, and 

Customers (Shipping Lines). 

8.1.2 External Stakeholders 

External stakeholders are groups or organisations who are affected by or involved with the operation of the 

Terminal through consultation, communication or approval. Most external stakeholders are government 

organisations, a list is given below: 

The local community; 

The Operational Community Consultative Committee; 

The Rail Noise Working Group; 

Randwick City Council; 

Botany Bay City Council; 

NSW Ports; 

Sydney Ports Corporation; 

NSW Roads and Maritime Services; 

NSW Department of Planning and Infrastructure, and 

NSW Office of Environment and Heritage/ EPA. 

 

 

 

 

 

 

 

 

 

Health Safety Enviroment and Quality Management System 

Noise Management Sub‐Plan ‐ SICTL 

Document Reference:   HSEQ5.1.7d  Document Title:  Noise Management Sub‐Plan ‐ SICTL  Version: 2

Document Owner:  HSEQ Department  Approved Date:  30 August 2013  Page 32 of 33

Printed Version is uncontrolled ‐ controlled version available on Sharepoint 

8.2 Consultation with Stakeholders 

8.2.1 Ongoing consultation 

SICTL will consult with the various stakeholders in different situations where their involvement is appropriate 

and will cultivate a pro‐active and reactive relationship for dealing with complaints. Complaints from 

stakeholders will be handled in accordance with section 4.6.4 and 4.6.5 of HSEQ5.1.7 Operational 

Environmental Management Plan. Under this sub‐plan, the primary external stakeholder is the Operational 

Community Consultative Committee which includes representatives from the local community and Botany Bay 

City Council.  

8.2.2 Key Personnel Contact Details ‐ SICTL 

Name  Position  Contact number 

Toll Free Hotline  SICTL Community Information Line  1800 472 888 

George Stinson  HSEQ Officer, SICTL  0448 343 963 

John Ieroklis  Environmental and Safety Compliance 

Engineer 

0458 009 650 

Trevor Ballantyne  National HSEQ Manager, HPA and 

Environmental Representative 

0420 961 877 

Keith Glass  Terminal Manager, SICTL  0477 004 262 

8.2.3 Key Personnel Contact Details – Operational Community Consultative Committee 

Name  Position  Contact number 

Roberta Ryan  OCCC Chairperson  0402 209 896 

Steven Poulton  Botany Bay City Council representative 

to the OCCC 

9366 3659 

 

 

 

 

 

 

 

 

 

 

 

Health Safety Enviroment and Quality Management System 

Noise Management Sub‐Plan ‐ SICTL 

Document Reference:   HSEQ5.1.7d  Document Title:  Noise Management Sub‐Plan ‐ SICTL  Version: 2

Document Owner:  HSEQ Department  Approved Date:  30 August 2013  Page 33 of 33

Printed Version is uncontrolled ‐ controlled version available on Sharepoint 

9 Referenced Documents  Instrument of Development Consent DA‐494‐11‐2003‐i‐ Schedule C Terminal Operations (NSW 

Department of Planning) 

Port Botany Expansion Environmental Impact Statement, URS Australia, 2003 

HSEQ1.1 HSEQ Policy Statement 

HSEQ2.2.1 Hazard and Improvement Opportunity Reporting Procedure 

HSEQ5.1.7 Operational Environmental Management Plan (OEMP) – SICTL 

HSEQ11.4 Compliance Auditing Policy 

HSEQ11.4.1 Compliance Auditing Procedure 

10 Review and Auditing of this Sub‐Plan The review and amendment of this sub‐plan will be in accordance with sections 5.2 and 5.4 of the OEMP which 

emphasises the Environmental Risk Assessment as the ‘driver’ of the review process. Drawing upon the 

Environmental Risk Assessment for guidance on the depth of the review will help SICTL achieve the following: 

fulfilment of SICTL’s commitment to continuous improvement as noted in the HSEQ1.1 HSEQ Policy 

Statement; 

Rectification of operational or system deficiencies identified during workplace inspections through a 

holistic and thorough approach; 

Transparent and straightforward auditing of HPA’s systems and processes; 

changes to operations directed by management upon review of activities, incidents, monitoring data, 

AEMRs and KPIs can be reflected in this sub‐plan, and 

Supporting SICTL and HPA’s competitive market position by implementing beneficial industry trends in 

environmental best practice. 

Detailed provisions for auditing SICTL’s environmental management system such as audit scope, depth, 

frequency and distribution of findings are explained in section 5.2 of the OEMP. Auditing of this Sub‐Plan shall 

be in accordance with: 

condition C 4.5 of the Development Consent; 

section 5.2 of the OEMP; 

HSEQ11.4 Compliance Auditing Policy, and 

HSEQ11.4.1 Compliance Auditing Procedure 

This sub‐plan will be included in the scope of OEMP Tier 3 audits and all Annual Independent Environmental 

Audits.