hse practice no 6 - simops procedure
TRANSCRIPT
GUPCO
HSE Practice No. 6 GOS OFFSHORE SIMULTANEOUS
GOS
Rev # 2
Date: 20/07/01Authorized By: GOS D.D. Gen. Mgr. (Operation) Page 1 of 18
GOSOffshore
SimultaneousOperations Procedure
C:\Hytham\Procedures\New Safety Manual\GOS OFFSHORE SIMULTINES.doc (6)
GUPCO
HSE Practice No. 6 GOS OFFSHORE SIMULTANEOUS
GOS
Rev # 2
Date: 20/07/01Authorized By: GOS D.D. Gen. Mgr. (Operation) Page 2 of 18
ObjectiveThe objective of this document is to state the limitations under which different operations can be carriedout simultaneously on the GOS platforms
Simultaneous Operations Procedure
The procedures have been structured under headings as follows:OperationGeneral background information concerning the operation.Specific HazardsHazards liable to arise as a result of the operations concerned.Procedures & RestrictionsRestrictions applying to the operation, and specific procedures relating to the interaction of the twooperations being carried out simultaneously.The ‘Simultaneous Activities Matrix’ summarizes the activities associated with simultaneous operations.For each procedure that follows, the appropriate part of the matrix is reproduced.
1 2 3 4 5 6 7 8 9 1 1 1 1 1 1 1 1 1 1 2 2 2
C:\Hytham\Procedures\New Safety Manual\GOS OFFSHORE SIMULTINES.doc (6)
GUPCO
HSE Practice No. 6 GOS OFFSHORE SIMULTANEOUS
GOS
Rev # 2
Date: 20/07/01Authorized By: GOS D.D. Gen. Mgr. (Operation) Page 3 of 18
0 1 2 3 4 5 6 7 8 9 0 1 2 1 Drilling Rig Positioning
- x - x x x o x x - - - x x x x x x x o x x
2 Lifts affecting wells
x - o x x o o x o x o o o o o o o o o o o
3 Drilling Ops. - o - o o o o o o o o - o o o o o o x o 4 Flowline Installation
x o o - o o o o o x o o x o o o o o o
5 Pressure & leak testing
x o o o - o o o x o o o o o o x o
6 Instr. El. Work x o o o o - o o o o o o o o o o o 7 Well Prod/Injec. o o o o - 8 Wellhead Maintenance
x o o o o o - o o o o o o o o o o
9 Chemical Injection
x o o o o o o - x o o o o o o o o
10 Explosives Op. - - o x x o o x - o o x o o o x x x x o11 Wireline Op. - - o o o o o o o - - o o o o o o o12 Coil Tubing Op - - - - o o o o o - - o o o o o o o13 Hot Work x x o x o o x o o - o o 0 x14 Scaffolding x o o o o o o o o o o - o15 Painting x o o o o o o o o o o o - o o o16 Grit Blasting x o o o o o o o o o o o - o o x17 Radiography x o o o o o o o x o o o o o o - o o x18 Vessel Operation x o x o o - o o19 Diving x o o o x o o o o -20 Gas Lift o o -21 Emergency Eq. Maint./Repair
x o x x o o x o o o o o o - x
22 Purging x o o o o o x x x o x -
C:\Hytham\Procedures\New Safety Manual\GOS OFFSHORE SIMULTINES.doc (6)
GUPCO
HSE Practice No. 6 GOS OFFSHORE SIMULTANEOUS
GOS
Rev # 2
Date: 20/07/01Authorized By: GOS D.D. Gen. Mgr. (Operation) Page 4 of 18
The terms used in the matrix are as follows:Not Applicable (-)Two operations that cannot physically be carried out simultaneously due to the configuration of the platform.Allowed Subject to Permit Restrictions (�)This is to be treated as normal work on the platform and will require a permit to work to be raised andsubject to normal observances and precautions.Restricted (o)Operations that may only take place simultaneously provided certain conditions have been met. Risk Assessment might be the tool to identify the required precautions.Not Permitted (x)Operations not to be undertaken simultaneously.
Drilling Rig InstallationOperation
This operation involves the movement of a drilling rig approaching a satellite or Complex drilling platform. This is required to drill a new well or perform workover on a platform. Specific Hazards
The positioning of a drilling rig above a satellite or Complex platform is a critical operation. The drilling rig is much heavier and bigger than a satellite and the possibility of objects falling or bumping into each other is high.
Rig move Risk Assessment to be completed before Rig approach or begging work with, O/P, Marian, Drilling and any other Dept. involved.Procedures & Restrictions
If on a drilling platform the area has to be barriered off from unauthorized personnel.
No operation shall take place on the satellite or drilling platform during this operation.
No other operation than production may continue. The drilling platform must be barriered off.
Skidding Derrick
C:\Hytham\Procedures\New Safety Manual\GOS OFFSHORE SIMULTINES.doc (6)
GUPCO
HSE Practice No. 6 GOS OFFSHORE SIMULTANEOUS
GOS
Rev # 2
Date: 20/07/01Authorized By: GOS D.D. Gen. Mgr. (Operation) Page 5 of 18
Operation This operation involves the movement of the drilling derrick
over the satellite helideck deck or drilling platform. This is required when work requiring the derrick on one well is complete and when work on another well, requiring the derrick, is to be started, or for maintenance or access purposes.Specific Hazards
The moving of heavy equipment above hydrocarbon filled facilities, and the possibility of objects
falling onto the decks below, and/or into the sea.Procedures & Restrictions
If on a drilling platform the area has to be barriered off from unauthorized personnel.
No operation shall take place on or above the deck under the path of the skidding rig.
No operations other than production may continue
Lifts Affecting WellsOperation
This procedure covers the moving of a heavy piece of equipment, for example a Xmas tree, the wellhead or conductor, below or through the wellbay deck. Specific Hazards
Damage to flowlines or pipework under pressure or containing well fluids during equipment handling.
Endangering diving operations by dropped objects. Injury to personnel. Damage to gas lift flowlines under pressure.
Procedures & Restrictions All work on affected wells is to cease. All wells considered to be at risk to be shut in as and the
relevant flowlinesdepressurized. Cold work permit for heavy lift operation will only be issued after the Production Supervisor has confirmed that the wells have been shut in and the flowlines depressurized as required.
If risk is apparent, ensure diving operations have been completed and the divers returned to the bell.
C:\Hytham\Procedures\New Safety Manual\GOS OFFSHORE SIMULTINES.doc (6)
GUPCO
HSE Practice No. 6 GOS OFFSHORE SIMULTANEOUS
GOS
Rev # 2
Date: 20/07/01Authorized By: GOS D.D. Gen. Mgr. (Operation) Page 6 of 18
Drilling OperationsOperation
Drilling Operation covers all modes of drilling, during well control, drilling in the reservoir and normal drilling.Specific Hazards
Shallow gas encounter risk. Release of hydrocarbons. Drilling in the reservoir. Injury to personnel.
Procedures & Restrictions No Hot Work operations will be allowed during abnormal
drilling operations (as listed under specific hazards above). Wells considered to be at risk of collision are to be made
secure. Should the drilling phase reach the point where primary well
control has been lost, then the production and all other work on the platform must stop.
Flowline InstallationOperation
Once a well is ready to be connected to the platform system, the flowline spool must be fitted, making
the final connection from the tree to the production manifold.Specific Hazards
Hot Work may be required in the well area.Procedures & Restrictions
No operation allowed on adjacent wells. If drilling is in the critical phase, Hot Work restrictions are
imposed. Suspend the following operations that may be ongoing on any
wells for the duration of the HotWork required for the flowline installations:
- Wellhead maintenance- Scale inhibitor squeeze operation Withdraw all Hot Work permits in force on the Platform other
than those required for flowline installation.
C:\Hytham\Procedures\New Safety Manual\GOS OFFSHORE SIMULTINES.doc (6)
GUPCO
HSE Practice No. 6 GOS OFFSHORE SIMULTANEOUS
GOS
Rev # 2
Date: 20/07/01Authorized By: GOS D.D. Gen. Mgr. (Operation) Page 7 of 18
Scaffold erection/striking, painting, grit blasting and radiography may continue provided access to
or egress from their worksite is not affected by the area affected by the flowline installation.
The DHSV on the affected well to be closed and tested for PBU, and the well prepared for flowline
installation as per the detailed procedures. No diving operation to be undertaken below the area deemed
by the Area Authority to be at riskfrom falling objects.
Pressure & Leak TestingOperation
Pressure and leak testing, where possible, will be limited to hydraulic testing.Specific Hazards
Injury to personnel following failure of equipment under test.Procedures & Restrictions
Before allowing a pressure or leak test to be undertaken, the Area Authority must ensure that all
work in the vicinity of the test is stopped and the permits withdrawn.
Erect barriers at a safe distance from the pressure test. If these barriers affect the access to or egress
from another work site, or the extent of the barriers encompass another job site then that job must
be suspended until after the completion of the pressure or leak test.
Ensure that responsible persons patrol the barriers at regular intervals to stop unauthorized access.
Make regular PA announcements warning unauthorized personnel to stay clear of the pressure test area.
Instrument Electrical WorkOperation
This procedure applies only to ‘dead’ electrical work and exclude those works
C:\Hytham\Procedures\New Safety Manual\GOS OFFSHORE SIMULTINES.doc (6)
GUPCO
HSE Practice No. 6 GOS OFFSHORE SIMULTANEOUS
GOS
Rev # 2
Date: 20/07/01Authorized By: GOS D.D. Gen. Mgr. (Operation) Page 8 of 18
requiring a Hot Work (Spark Potential) Permit.Specific Hazards
Injury to personnel due to failure of equipment under test.Procedures & Restrictions
Prior to allowing instrument/electrical work on pressure vessels, the Area Authority is to ensure
that the pressure/leak testing has been completed and system or equipment has been depressurized.
Instrument/electrical work will be restricted in terms of being performed simultaneously with any
other work when access to or egress from the site of the instrument/electrical work is affected by
the extent of the other work.
Well Production/InjectionOperation
Production via the Xmas trees and flowlines to the production manifold of formation fluids, and injection from the water injection manifold through flowlines to the injection Xmas trees of treated seawater.Specific Hazards
Uncontrolled release of hydrocarbons may result if a well being drilled intersects an on line
producing well. Failure of lifting gear when making heavy lifts over live plant
could result in injury to personneland uncontrolled release of hydrocarbons. Specifically affecting
production will be heavy lifts overlive flowlines and trees.
Procedures & Restrictions Wells considered to be at risk of collision are to be made
secure. Wells at risk due to overhead heavy lifts are to be shut in and
isolated.
C:\Hytham\Procedures\New Safety Manual\GOS OFFSHORE SIMULTINES.doc (6)
GUPCO
HSE Practice No. 6 GOS OFFSHORE SIMULTANEOUS
GOS
Rev # 2
Date: 20/07/01Authorized By: GOS D.D. Gen. Mgr. (Operation) Page 9 of 18
Wellhead MaintenanceOperation
This procedure refers to any operation involving work on the wellhead.Specific Hazards
Any release of hydrocarbons presents a risk of fire/explosion if a source of ignition exists.
Any release of well fluids presents an additional hazard to personnel in the area of the leak due to
its H 2 S content. Injury to personnel from failure of equipment under test.
Procedures & Restrictions All pressure testing in the area of the affected wellhead must
have been completed and the systemor equipment depressurized before the wellhead maintenance is
allowed to commence or continue. No Hot Work in the wellbay area will be allowed. No heavy lift will be allowed in the area of the wellhead being
worked on. No other operation (for example wireline operations) will be
permitted on the well at the same timeas the well head maintenance is being performed.
If access to or egress from the wellhead being maintained is affected by any other operation, one of
either of the operations will be suspended.
Scale Inhibitor SqueezeOperation
At regular intervals, each production well will be treated with chemicals to avoid, as far as
possible, the formation of scale. This treatment is referred to as ‘Squeeze’ treatment and consists
primarily of injecting a mixture of scale inhibitor and sea water into the production wells. Specific Hazards
Injury to personnel following failure of equipment under pressure.
Hazard to personnel involved in the handling of chemicals.
C:\Hytham\Procedures\New Safety Manual\GOS OFFSHORE SIMULTINES.doc (6)
GUPCO
HSE Practice No. 6 GOS OFFSHORE SIMULTANEOUS
GOS
Rev # 2
Date: 20/07/01Authorized By: GOS D.D. Gen. Mgr. (Operation) Page 10 of 18
Procedures & Restriction If access to or egress from the wellhead is restricted in any
way by any other operation, the squeezeshould be suspended until such times as safe and clear access
is available. The area encompassing the adjacent wells is to be barriered
off for the duration of the squeeze, andno other operation is to be permitted within these barriers.
Inhibitor squeezes may be restricted during drilling.
Explosives OperationsOperation
The operation that require the use of explosives is related to well perforations. In all cases, the explosives are run into the hole on electric line. Detonation will be electrical, initiated at the surface.
Either conventional explosives or explosives using Schlumberger’s SAFE equipment may be utilized.Specific Hazards
Premature detonation of explosive charge whilst using conventional explosives. Procedure &
Restrictions (Conventional Explosives). Radio silence to be imposed. Operations relying on radio communication to be suspended
or postponed. Work involving the use of explosives must not be carried out
under conditions of thunder orlightning and may be restricted during high winds.
Withdraw all Hot Works. Procedures & Restrictions (SAFE Equipment)
Use of equipment featuring SAFE will only be permitted subject to the following restrictions:
Work involving the use of explosives may be restricted during high winds.
The area in which there may be a risk to persons or plant from premature detonation of theexplosive device shall be clearly marked out. Only persons authorized by the platform Supervisor shall enter or remain in the
C:\Hytham\Procedures\New Safety Manual\GOS OFFSHORE SIMULTINES.doc (6)
GUPCO
HSE Practice No. 6 GOS OFFSHORE SIMULTANEOUS
GOS
Rev # 2
Date: 20/07/01Authorized By: GOS D.D. Gen. Mgr. (Operation) Page 11 of 18
defined danger area. This area must remain clearly demarcated until the explosives operations are complete.
Withdraw all Hot Work.
Wireline OperationsOperation
Wireline operations, as described in this procedure, refer to any operation which involves the lowering of a tool or device into a well on either slickline or electric line.
Electric line and slickline work can take place through the Helideck on Satellites and weather deck on drilling platforms. On drilling rigs it is performed from the drill floor.
All wireline work on a live well will take place using pressure control equipment to enable entry of the
tool or device into the well without release of well fluids.Specific Hazards
Potential for release of well fluids and subsequent fire hazard should failure of pressure control
equipment occur. Injury to personnel from wireline breakage under tension. Damage to well/completion integrity should wireline part. Injury to personnel from failure of equipment under test.
Procedures & Restrictions All Hot Work liable to present a source of ignition to a leak of
hydrocarbons as a result of failureof or damage to any part of the equipment associated with the
wireline work to be withdrawn. All work within an area judged by the Area Authority to be at
risk due to its proximity to thewireline operation to be suspended.
No lifts of any kind to be made above the wireline once it is under tension.
When lifting the wireline hatch covers, and installing the lubricator and riser, specific precautions
to be taken. Barriers and signs to be erected warning personnel of the
wireline operations. If these barriers affect
C:\Hytham\Procedures\New Safety Manual\GOS OFFSHORE SIMULTINES.doc (6)
GUPCO
HSE Practice No. 6 GOS OFFSHORE SIMULTANEOUS
GOS
Rev # 2
Date: 20/07/01Authorized By: GOS D.D. Gen. Mgr. (Operation) Page 12 of 18
the access to or egress from another work site, or the extent of the barriers encompass another job
site then that job must be suspended until after the completion of the pressure or leak test.
No diving operation to be undertaken below the area deemed by the Area Authority to be at risk
from falling objects.
Coiled Tubing OperationsOperation
The types of operations performed with coiled tubing. Each operation involves passing small bore tubing through an injector head attached to a lubricator which is attached to the wellhead. The rig up of this equipment involves heavy lifting operations.
Specific Hazards Inadvertent release of hydrocarbons. Injury to personnel following failure of equipment under
pressure. Hazard to personnel involved in the handling of chemicals. Hazard to personnel or equipment underneath the coiled
tubing operation due to failure of equipment causing a spillage of chemical.
Risk of damage to equipment or injury to personnel during rig up operations.
Release of chemicals/hydrocarbons should damage occur to the tubing whilst it is in service.Procedures & Restriction
Restrictions will be imposed on Hot Work as advised by the Area Authority.
No operation to be undertaken beneath the coiled tubing operation that could be at risk should a
spillage of chemical or nitrogen occur. All wells considered to be at risk due to the heavy lifts
involved during rig up to be shut in andmade safe.
Diving operations to be restricted below the area deemed by the Area Authority to be at risk from
falling objects.
C:\Hytham\Procedures\New Safety Manual\GOS OFFSHORE SIMULTINES.doc (6)
GUPCO
HSE Practice No. 6 GOS OFFSHORE SIMULTANEOUS
GOS
Rev # 2
Date: 20/07/01Authorized By: GOS D.D. Gen. Mgr. (Operation) Page 13 of 18
No lifts of any kind to be made above the coiled tubing spread once it is in service.
Hot Work Operation
Hot Works are defined as those requiring a Hot Works, Naked Flame and Spark Potential Permit.
In this section, Hot Work in that area of the platform that will directly affect well related is addressed.Specific Hazards
On a production platform any source of ignition presents a potential explosion/fire hazard.Procedures & Restrictions
Before allowing Hot Work to commence, ensure that the area where the work is being undertaken
is gas-free, and stop all operations liable to give rise to a hydrocarbon release. If necessary, the area
should be washed down to remove traces of oil or grease. Due to the increased risk of hydrocarbon release associated
with the following operations,consideration will have to be given to restricting them for the
duration of the Hot Work:- Coiled tubing operations- Wireline operations- Wellhead maintenance Due to the flammable nature of the solvents associated with
painting, painting in proximity to HotWork must be restricted.
ScaffoldingOperation
A scaffold is defined as a temporary structure on which persons work and which provides support for the materials used in construction, maintenance, repair or demolition work. It can also be used to obtain access to certain areas or equipment.
C:\Hytham\Procedures\New Safety Manual\GOS OFFSHORE SIMULTINES.doc (6)
GUPCO
HSE Practice No. 6 GOS OFFSHORE SIMULTANEOUS
GOS
Rev # 2
Date: 20/07/01Authorized By: GOS D.D. Gen. Mgr. (Operation) Page 14 of 18
Specific Hazards Endangering diving operations when constructing or
dismantling scaffolding over the side of the platform Injuries
Procedures & Restrictions Diving operations must cease during the period of
construction or destruction of scaffold extendingover the side of the platform.
Scaffolding operations can generally be restricted by their proximity to other ongoing work. For
example, scaffold operations are not permitted on any well adjacent to one being worked on.
PaintingOperation
Application of paint to all surfaces throughout the entire platform.Specific Hazards
The flammable nature of the solvents used during the painting process give rise to a potential
fire hazard. The toxicity of some paints or solvents can affect personnel in
the vicinity of the worksite.Procedures & Restriction
Painting in proximity to Hot Work must be restricted. Painting will be restricted by the physical encroachment of
other operations which affectaccess/egress or site hygiene.
Painting in confined spaces requires special precautions and the provision of adequate ventilation or
personal protective equipment.
Grit BlastingOperation
Grit blasting is carried out for the purpose of surface preparation for painting.
C:\Hytham\Procedures\New Safety Manual\GOS OFFSHORE SIMULTINES.doc (6)
GUPCO
HSE Practice No. 6 GOS OFFSHORE SIMULTANEOUS
GOS
Rev # 2
Date: 20/07/01Authorized By: GOS D.D. Gen. Mgr. (Operation) Page 15 of 18
Specific Hazards Grit blasting is a possible source of ignition. The materials used during grit blasting are abrasive and will
cause damage to systems or machineryif ingress is allowed to occur.
Injury to personnel due to flying grit.Procedures & Restrictions
When reviewing an application for grit blasting operations, the Area Authority must consider
restricting the following activities or restricting grit blasting in their vicinity:
- Wireline operations- Coiled tubing operations- Flowline installation- Wellhead maintenance- Painting
RadiographyOperation
Radiography is a method used to evaluate the integrity of material welds, and involves the exposure of a radioactive source. As a result restrictions are imposed on all operations that are being performed within the field of exposure of the source.Specific Hazards
Exposure of personnel to radiation doses above a safe level.Procedures & Restrictions
Before allowing radiography to be undertaken, the Area Authority must ensure that all work in the
vicinity of the radiography is stopped and permits withdrawn. The HSE advisor in conjunction with the Performing Authority
will barrier off the area affected bythe radiography. If these barriers encompass or ingress into
another worksite, then that job or theradiography must be suspended.
Responsible persons must patrol the barriers at regular intervals to stop unauthorized access.
C:\Hytham\Procedures\New Safety Manual\GOS OFFSHORE SIMULTINES.doc (6)
GUPCO
HSE Practice No. 6 GOS OFFSHORE SIMULTANEOUS
GOS
Rev # 2
Date: 20/07/01Authorized By: GOS D.D. Gen. Mgr. (Operation) Page 16 of 18
Vessel OperationsOperation
All vessel operations within the 500 meter safety zone will only be conducted on the authority of theProduction Supervisor. The master of the vessel remains responsible for the safety of his crew and the vessel.
The Production Supervisor will co-ordinate all vessel operationsSpecific Hazards
Vessel operations can present a hazard to diving operations.Procedures & Restrictions
Vessels entering the 500 meter safety zone while divers are in the water should be notified
regarding the location of the diving operation and areas of prohibited vessel operation.
Once a vessel enters the 500 meter safety zone, smoking is to be prohibited on the open deck of the
vessel, and any work liable to give rise to a source of ignition to hydrocarbon gas is to cease.
DivingOperation
Diving operations will be required at regular intervals for inspection purposes, for the platform structure and the gas export line sub-sea isolation valve.Specific Hazards
Divers in the water are at risk from falling objects, discharges or vessel movements.Procedures & Restrictions
Scaffold work over the side of the platform to be suspended while diving operations are in progress.
Diving operations must not coincide with drilling or well activities that involve lifting of objects
which may be dropped into the water. Outboard crane operations are restricted during diving.
C:\Hytham\Procedures\New Safety Manual\GOS OFFSHORE SIMULTINES.doc (6)
GUPCO
HSE Practice No. 6 GOS OFFSHORE SIMULTANEOUS
GOS
Rev # 2
Date: 20/07/01Authorized By: GOS D.D. Gen. Mgr. (Operation) Page 17 of 18
- Clearance is to be obtained from the Diving Supervisor prior to any outboard lifts
Commencing.
Gas LiftOperation
Production wells will be considered for gas lift as their production rate decreases and water out increases.Specific Hazards
Uncontrolled release of hydrocarbons may result if a well being drilled intersects an online gas
lift well. Failure of lifting gear when making heavy lifts in vicinity of gas
lift piping. Rigging of wireline/coil tubing equipment on wells adjacent to
gas lift manifold. Potential dropped objects during drilling rig positioning
operations.Procedures & Restrictions
ط Heavy lifting above Gas Lift piping must be restricted.
Emergency Equipment Maintenance/RepairOperation
ط Any emergency equipment like the Fire Water pumps out of operation due to maintenance or repair etc.Specific Hazards
ط High risk jobs creating a fire without fire pumps in operation.Procedures & Restrictions
ط No hot work open flame (welding) jobs to take place.ط No other critical job that can initiate sparks etc to take place.
Purging Operation
ط Using nitrogen to gas free hydrocarbon pipes.Specific Hazards
ط Hydro carbon gas is intentionally released to atmosphere.Procedures & Restrictions
ط No hot work to take place during purging operations.
C:\Hytham\Procedures\New Safety Manual\GOS OFFSHORE SIMULTINES.doc (6)
GUPCO
HSE Practice No. 6 GOS OFFSHORE SIMULTANEOUS
GOS
Rev # 2
Date: 20/07/01Authorized By: GOS D.D. Gen. Mgr. (Operation) Page 18 of 18
ط All emergency equipment to be operationalط No grit blasting or painting
C:\Hytham\Procedures\New Safety Manual\GOS OFFSHORE SIMULTINES.doc (6)