htr-pm progress and further commercial deployment
TRANSCRIPT
![Page 1: HTR-PM Progress and Further Commercial Deployment](https://reader030.vdocument.in/reader030/viewer/2022012416/6170e5af0e7aa11aba351f7b/html5/thumbnails/1.jpg)
HTR-PM Progress and Further Commercial
Deployment
Frank Wu President of CHINERGY Co.
Sep. 19, 2017, Vienna, IAEA
![Page 2: HTR-PM Progress and Further Commercial Deployment](https://reader030.vdocument.in/reader030/viewer/2022012416/6170e5af0e7aa11aba351f7b/html5/thumbnails/2.jpg)
1, HTR-PM Progress
2
![Page 3: HTR-PM Progress and Further Commercial Deployment](https://reader030.vdocument.in/reader030/viewer/2022012416/6170e5af0e7aa11aba351f7b/html5/thumbnails/3.jpg)
HTR-PM Reactor
building
HTR-PM plant building
Cross section 3D-view
Control
building
Auxiliary
building
Spent fuel
storage building
Steam turbine
building
3
![Page 4: HTR-PM Progress and Further Commercial Deployment](https://reader030.vdocument.in/reader030/viewer/2022012416/6170e5af0e7aa11aba351f7b/html5/thumbnails/4.jpg)
2004: industry investment agreement was signed
2006: decided to use 2×250 MWt reactor modules with a 200 MWe steam turbine, became a key government R&D project
2008: ATP was issued
2012.12.9: FCD the first concrete poured
Project Milestones
HTR-PM in 2008 HTR-PM in 2009 HTR-PM in 2012.12
4
![Page 5: HTR-PM Progress and Further Commercial Deployment](https://reader030.vdocument.in/reader030/viewer/2022012416/6170e5af0e7aa11aba351f7b/html5/thumbnails/5.jpg)
Project progress
2016.8, Manufacture of fuel
elements started
2016.3/9, two RPVs on site
and installed
2015~2016, Metallic internal structure, Water cooling panel, DCS, Simulator, Reverse transmission power, …
2017.6: Reactor 1#, ceramic internals finished
2017.8: 250,000 fuel pebbles produced
2015.6, Civil work of nuclear island
finished
5
![Page 6: HTR-PM Progress and Further Commercial Deployment](https://reader030.vdocument.in/reader030/viewer/2022012416/6170e5af0e7aa11aba351f7b/html5/thumbnails/6.jpg)
2, Commercial Deployment
6
![Page 7: HTR-PM Progress and Further Commercial Deployment](https://reader030.vdocument.in/reader030/viewer/2022012416/6170e5af0e7aa11aba351f7b/html5/thumbnails/7.jpg)
Chinese HTR development
7
Basic research Test reactor
Demonstration plant
1970s 1986, HTR-10
2012, HTR-PM
Commercial plant
2019~
HTR Roles in China
Power generation: supplement to LWR; repowering coal
fired plants
Co-generation to supply steam
Hydrogen production
![Page 8: HTR-PM Progress and Further Commercial Deployment](https://reader030.vdocument.in/reader030/viewer/2022012416/6170e5af0e7aa11aba351f7b/html5/thumbnails/8.jpg)
Commercialization based on HTR-PM experiences
HTR-PM 600MW HTR
Engineering verification tests
Design / Manufacture
Construction / Commissioning
Licensing
Project management
Next Step
Objectives Standardized plant (650MWe) Cogeneration Inherent safety Modularization Economic competitiveness 8
![Page 9: HTR-PM Progress and Further Commercial Deployment](https://reader030.vdocument.in/reader030/viewer/2022012416/6170e5af0e7aa11aba351f7b/html5/thumbnails/9.jpg)
HTR-PM600
6 reactor modules connect to one steam turbine, the same safety features,
the same major components,
the same parameters,
comparing with HTR-PM
the same site area and the same reactor plant building volume comparing with the same size PWRs
9
![Page 10: HTR-PM Progress and Further Commercial Deployment](https://reader030.vdocument.in/reader030/viewer/2022012416/6170e5af0e7aa11aba351f7b/html5/thumbnails/10.jpg)
2×HTR-PM600
10
![Page 11: HTR-PM Progress and Further Commercial Deployment](https://reader030.vdocument.in/reader030/viewer/2022012416/6170e5af0e7aa11aba351f7b/html5/thumbnails/11.jpg)
Cost of HTR-PM600
which is in China, under the condition:
1,reduce the 1st of a kind costs,
2,increase the plant power Generating Efficiency
3,order 12 reactor modules at the same time.
~2600$/kWe
~0.65 ¢/kWh
![Page 12: HTR-PM Progress and Further Commercial Deployment](https://reader030.vdocument.in/reader030/viewer/2022012416/6170e5af0e7aa11aba351f7b/html5/thumbnails/12.jpg)
0%
20%
40%
60%
PWR
HTR-PM
HTR600
High Generating Efficiency
![Page 13: HTR-PM Progress and Further Commercial Deployment](https://reader030.vdocument.in/reader030/viewer/2022012416/6170e5af0e7aa11aba351f7b/html5/thumbnails/13.jpg)
Regulatory R&D Project: “Regulations, guidelines and safety review technology of HTGR
nuclear power plant”, 2014-2020
Members Regulator: Suzhou Nuclear Power Research Institute, SNPI
Regulator: Nuclear and Radiation Safety Center, MEP
Designer: INET, Tsinghua University
References Safety documents developed by NNSA of China for PWRs
State-of-the-art IAEA safety documents
Progress Code on the Safety of Nuclear Power Plant: Design (2016) is generally
applicable to HTGR
Some safety guides need major revision or new development
13
![Page 14: HTR-PM Progress and Further Commercial Deployment](https://reader030.vdocument.in/reader030/viewer/2022012416/6170e5af0e7aa11aba351f7b/html5/thumbnails/14.jpg)
Regulatory for Multi-modular
Standard for high temperature material for HTR(steam generator, Gas-turbine)
Study of off-site emergency response and Planning Restricted Area
Safety Class review for systems and equipments
14
Regulatory R&D
![Page 15: HTR-PM Progress and Further Commercial Deployment](https://reader030.vdocument.in/reader030/viewer/2022012416/6170e5af0e7aa11aba351f7b/html5/thumbnails/15.jpg)
Repowering fossil power plant Inherent safety: no reactor core melt-down; very
limited release of radioactive emission in accidents
Research on simplify off-site emergency response Accident consequences of HTR-PM are evaluated with very limited
radiological effects.
HTR-PM owns the conditions of reducing Exclusion Area, Planning Restricted Area and Emergency Planning Zone.
Technically, HTR-PM can simplify the off-site emergency response, without complicated emergency preparedness and large-scale off-site emergency protection operations.
At present, the National Nuclear Emergency Management Agency is reviewing the feasibility of simplifying the off-site emergency response of HTR-PM.
15
![Page 16: HTR-PM Progress and Further Commercial Deployment](https://reader030.vdocument.in/reader030/viewer/2022012416/6170e5af0e7aa11aba351f7b/html5/thumbnails/16.jpg)
Site study
Company Site Status
China
Huaneng
Group
Xiapu, Fujian Early site study
China Nuclear
E&C Group
(CNEC)
Ruijin, Jiangxi Preliminary feasibility
study reviewed
Wan’an Fujian Preliminary feasibility
study reviewed
Bai’an, Guangdong Preliminary feasibility
study reviewed
16
![Page 17: HTR-PM Progress and Further Commercial Deployment](https://reader030.vdocument.in/reader030/viewer/2022012416/6170e5af0e7aa11aba351f7b/html5/thumbnails/17.jpg)
A series of MOUs on jointly-development of HTGR were signed between CNEC and the following countries & organizations Saudi Arabia
Indonesia
Dubai, United Arab Emirates
South Africa
Amec Foster Wheeler (AMEC), UK
ASEAN Centre for Energy (ACE, hosted by Indonesia)
International cooperation
17
![Page 18: HTR-PM Progress and Further Commercial Deployment](https://reader030.vdocument.in/reader030/viewer/2022012416/6170e5af0e7aa11aba351f7b/html5/thumbnails/18.jpg)
Thanks for your attention