Alstom Environmental Control Systems: Global
Applications Manager
− Program Director aligning 10 offices for global
execution.
15 years industry experience
− Previous:
• Intel technology development manager
• Intel project controls group
New Mexico State University, BBA
Arizona State University, MBA
Scott Warnke
ECS –Partnering Industry Leaders Worldwide
Air Pollution Control systems for
− Power Generation Business
− Industry Sectors
− Incineration Plants
− C02 Removal
Built to customer requirements
NOx Control
Flue Gas
Desulfurization
– Wet FGD
– Dry FGD
– FDA
Particulate
Control
– Fabric Filter
– Electrostatic
Precipitator
Ash
Handling
Pulverizer
Boiler
Steam Turbine
and Generator
-SCR Systems
-SCONOx
Burner Systems
- LNCFS
- TFS 2000TM
- Fuel Switching
Burner NOx Retrofits
- RSFC™
- P2™
Electrical & Control Systems
- ALSPA P320
- Optiplant +
– Power Distribution Systems
Research and
Development
- Air Modeling
Capabilities
- CFD Modeling
Construction
Substation
Systems
Air Preheater
Isolated Phase Bus
Fossil Fueled Power Plant
P3DM - Alstom
Project EngineeringP1
Design, implement, deploy
and maintain project
management solutions
Plant EngineeringP2
Design, implement,
deploy and maintain
plant engineering
solutions (e.g.,
PDMS,Comos,) in ALSTOM
Power
Product EngineeringP3
Design, implement,
deploy and maintain
product engineering
solutions
Production Systems Operations
Provide stable, reliable end-to-end service, training and support for all P3DM
solutions
To make integrated engineering lifecycle information available globally
across ALSTOM Power’s value chain – Efficiently, Economically, Easily
Value
Added
Solutions(Data Centric Integration)
Remove
Duplication, complexity
Standardize processes and tools
Business as it is: Complex,
regionalized and segmented
Growth
Operational
Compliance
Nuisance
Value Category
Info
rma
tio
n
Fra
me
wo
rk
Type Category
Policies Tools
Processes
Conver
gence
KnoxvilleMilan
VaxjoOslo
Kolkata
Beijing
Sao
Paulo BucharestMoscow
Kobe
Main Entities
Changing the ECS Business Model
ECS Landscape
Knoxville
Sao Paulo
Oslo Vâxjo
Kolkata
Beijing
Milan
Knoxville
Sao Paulo
OsloOslo VâxjoVâxjo
KolkataKolkata
Beijing
Milan
Multiple
Suppliers/
Multiple
Databases
Plant IntegrationECS Product
Portfolio
ECS Multi-Site
Operations
• Program Objective:
RE-INVENT THE GLOBAL DESIGN ENGINEERING PROCESS
• Program Scope:
• Global Process Definitions
• Tool application• Integration with Sector plant integration initiatives (P3DM / Plant)• Tool methodologies and templates (configuration)• Multisite project governance and processes• Cats & Specs
− Global Administration of all applications• Hardware / Database Architecture• Connectivity / bandwidth• User support• Training• Ongoing development, support and maintenance
− Database Integration− Group 1 Offices: Knoxville, Milano, Oslo, Vaxjo, Kolkata− Group 2 Offices: Moscow, Beijing, Kobe, Sao Paulo.
EP3DM Program Overview
EP3DM: The Game Plan
Three Phases – Overlapping Activities
Balance the needs of the business
Phase 1
Design 3D 2D
Document, Data mgt.
Std. Licensing
Admin and Support
FEED
Enhanced Data Base
SAP integration
Structural Analysis
Phase 2
Phase 3
Engineering Database with
Full change management
And Supplier interfacesCurrent Scope
Functional delivery – support global
design
You are
here
SITE 3
SITE 1
SITE 2
WEB User
Desk Top Client
LAN
LAN
LAN
WEB Portal Server
+ Web Vault
External WEB User
Desktop Clients
ECS Units
Third party WEB
access
Cross sites Work
Sharing
capabilities
enabled by a
multi site
architecture
Current issues
Multiple software platforms internally and multiple systems required by
customers and suppliers in collaboration.
Joint venture development on C02 removal technology. No system or
standard alignment.
Must support sharing between the engineering Offices and
Subcontractors on multiple platforms.
ECS will never refuse contracts for CAD reasons
No standard WBS, data standards or master documents are defined.
ECS approach starts at tender stage to identify the potential
discrepancy between internal standards and customer expectation
Interoperability
Many systems, many deliverables
NoPDMS EDFPlan-CDrawings extractions
YesPDMS AvevaPDMSEqp, piping, piping
supports, light steel structure Modeling
Installation – 3D
YesROHR2SIGMAROHR2Piping stress calculation
Pipe calculation
NoSECADIntergraphPDSPiping classes
NoSECADAvevaParagon
and SpeconPiping classes
Pipe specification
Yes2D Pipe / SP
PIDAsuni CAD2D PipeP&ID
Yes2D Pipe / SP
PIDIntergraphSP PIDP&ID
Not applicableNot applicableEDFAXSYS2DSMF/SMD
Processschematic
According to P3DM standard
P3DM Standard
Software editors
SotwareName
Activities
NoPDMS EDFPlan-CDrawings extractions
YesPDMS AvevaPDMSEqp, piping, piping
supports, light steel structure Modeling
Installation – 3D
YesROHR2SIGMAROHR2Piping stress calculation
Pipe calculation
NoSECADIntergraphPDSPiping classes
NoSECADAvevaParagon
and SpeconPiping classes
Pipe specification
Yes2D Pipe / SP
PIDAsuni CAD2D PipeP&ID
Yes2D Pipe / SP
PIDIntergraphSP PIDP&ID
Not applicableNot applicableEDFAXSYS2DSMF/SMD
Processschematic
According to P3DM standard
P3DM Standard
Software editors
SotwareName
Activities
Equipment
Schematic
Alst
om
Turbine
PI&D
process
engineering
Installation
engineering
Mechanical
engineering
Cable trays
TNU
Electrical
engineering
Purc
Alternateur
Heat Exchanger
Pumps
Purchase
Equipment
3D Model PTP
Instrumentation
engineering
Detailed
Design
Project
Reviews
Schematic
Schematic
Equipment
Equipment
Schematic
Basic Design
Handovers
Designed
Alstom
Purchase
3rd Party
Engineering Example
Issues Faced by ECS
Legacy: Every office has the best standard.
The pressure from customers to use their data/naming coding, has
been high.
Alstom has had to adapt its own systems and procedures to this
requirement.
The KKS System is mainly a material / maintenance oriented System
and does not lend itself to project delivery. Require a more open
standard.
The ECS System is mainly a functional process oriented System.
Deliverables include model transfers on various formats but still must
protect Alstom ECS IP
The Future
• Dedicated tool for the EPCs organisations (Changes management & Workflow features).
− Many tools require data exchange and notification− Standardise on ISO 15936 internally
• CAD neutral solution (ISO 15 926) to support customers and suppliers.
• Flexible regarding the codification of the projects ECS, KKS and leverage Fiatech standards.
• Stable, reliable and well-known IT solutions. Ride the technology curve and move away from custom developed systems.
− Moore’s Law− Grove’s Law− Vendor sponsored development
Future standards
Standard ISO 15926
The ISO 15926 is titled: "Industrial automation systems and
integration—Integration of life-cycle data for process plants
including oil and gas production facilities“
This standard developed a generic data model and Reference Data
Library for process plants
Data Exchanges should be based on the standard ISO 15926
dedicated for data integration, sharing, exchange, and hand-over
between computer systems
Future Based on Data and standards
Change Management, Configuration Management
Access Control, Revision Management, Baselining
Workflow, Data and Document Management
Input-Output Management (Reporting & Interfaces)
Catalogue & Specification Management / MTO
ElectricalElectrical
ALSTOM Standard
I&C
ALSTOM Standard
Engineering
Database
(EDB)
New EDB
Powermax
P&ID
ALSTOM Standard
External
Suppliers /
Partners
Customer tools /
standards
SECAD Archive
Product Mgmt
APC-RPDM
3D Design
PDMS
Stress calculation Cost calculation
Simulation
Project Mgmt
Project Tool Suite
Primavera
Improvements
A standard compass to sail to
Support of the entire life cycle.
Improved plant information management
CAD neutral position maintained with
customers and suppliers
Reduction of geography specific issues and
software