20conference%20presentation_sf_p

22
1 Distributed PV is the low cost, high value answer for meeting California’s 33% by 2020 target Feed-In Tariff Workshop, San Francisco Bill Powers, P.E., Powers Engineering July 12, 2010

Upload: shannon-kellman

Post on 13-Mar-2016

214 views

Category:

Documents


0 download

DESCRIPTION

http://www.pacificenvironment.org/downloads/FIT_Conf_12-july-10_FiT%20conference%20presentation_SF_Powers1_clean.pdf

TRANSCRIPT

Page 1: 20conference%20presentation_SF_P

1

Distributed PV is the low cost, high value answer for meeting California’s 33% by 2020 target

Feed-In Tariff Workshop, San FranciscoBill Powers, P.E., Powers EngineeringJuly 12, 2010

Page 2: 20conference%20presentation_SF_P

In-Basin solar PV feed-in tariff for Los Angeles: composite initial tariff ~$220/MWhsource: UCLA & LABC, Bringing Solar Energy to Los Angeles – Assessment of Feed-In Tariff, July 2010, p. 32.

2

Page 3: 20conference%20presentation_SF_P

CEC “levelized cost-of-energy” (LCOE) for new merchant peaker turbines is $800 to $1,000/MWhsource: CEC, Comparative Cost of Electric Generation Technologies, January 2010, Table 4 and Table 5. Note – the dates shown in the table, 2009 and 2018, are commercial start dates.

Combustion turbine (MW)

Capacity factor (%)

LCOE 2009($/MWh)

LCOE 2018($/MWh)

50 5 844 1,009100 5 795 951

3

Page 4: 20conference%20presentation_SF_P

CEC LCOE for new merchant combined cycle -$186/MWh at 65% capacity factor in 2018 source: CEC, Comparative Costs of California Central Station Electricity Generation , January 2010, Table 1, Table 5, Figure A-8.Note – the dates shown in the table, 2009 and 2018, are commercial start dates.

Combined cycle plant (MW)

Capacity factor (%)

LCOE 2009($/MWh)

LCOE 2018($/MWh)

500 92 118 161500 90 119 162500 75 124 169500 65 136 186500 55 149 203

4

Page 5: 20conference%20presentation_SF_P

CEC, DOE: Solar PV cost will drop in half by 2020 sources: 1) CEC, Comparative Costs of California Central Station Electricity Generation , January 2010, Figure 8, 2) DOE, Solar Vision Study – Draft, Chapter 4: Photovoltaics: Technologies, Cost, and Performance, May 28, 2010, Table 4-2, p. 17.

5

Page 6: 20conference%20presentation_SF_P

No operational combined cycle plant could meet “market price referent” (MPR) capacity factorsource: CEC, Comparative Costs of California Central Station Electricity Generation , January 2010, Table C-5.

The MPR calculation assumes combined cycle baseloadpotential capacity factor (CF) of 92% is achieved.

This results in least-cost combined cycle power and a nearly unachievable price point for renewable power.

In reality, no combined cycle in California actually achieves 92% CF, and only two are at 75% or above.

Average in 2008-2009 for combined cycle fleet was 65%. CEC assumes 70-75% combined cycle CF in its January

2010 comparative electricity generation cost analysis. CARB assumes 65% CF in June 2010 draft report on cost to

achieve 33% Renewable Electricity Standard by 2020.

6

Page 7: 20conference%20presentation_SF_P

Residential tiered rates: ~20,000 GWh at rates from $0.24/kWh to $0.40/kWh ($240 to $400/MWh)sources: 1) PG&E A. 10-03-014 General Rate Case Phase 2 filing, Chapter 3, 2) CEC 2009 Integrated Energy Policy Report (IEPR), Figure 4, p. 52. Assumption – residential IOU customer consumption is 2/3 of total statewide residential consumption.

California’s investor-owned utilities (IOUs) bill residential customers using tiered rates: Tier 1 and 2 in $0.12 to $0.15/kWhrange, Tiers 3, 4, and 5 from $0.24 to $0.40/kWh.

In PG&E territory, about a third of residential usage is billed at Tier 3 or above.

California IOU residential customers used ~60,000 GWh in 2008. Assuming the PG&E ratio for the other two California IOUs, about

20,000 GWh was billed at Tier 3 or higher rates. 20,000 GWh represents the production of 10,000 to 12,000 MW

of distributed PV capacity.

7

Page 8: 20conference%20presentation_SF_P

LCOE for solar PV and solar thermal – RETI Phase 2B Reportsource: Renewable Energy Transmission Initiative (RETI) Phase 2B Final Report, May 2010, Tables 4-5, 4-7, 4-8.

Technology Capacity (MW)

Capacity factor (%)

LCOE ($/MWh)

Solar thermal, dry-cooled 200 20-28 195 - 226Fixed thin-film PV 20 20-27 138 - 206

Tracking polysilicon PV 20 23-31 135 - 214

8

Page 9: 20conference%20presentation_SF_P

RETI - Range of renewable energy LCOE valuessource: RETI Phase 2B Final Report, May 2010, Figure 4-1. Dark green bars are May 2010 costs. Light green bars are superseded 2008 costs.

9

Page 10: 20conference%20presentation_SF_P

Cost of new transmission – Achilles heel of remote central station generationsources: 1) RPS Calculator, 2) J. Firooz, P.E., CAISO: How its transmission planning process has lost sight of the public’s interest, prepared for UCAN, April 15, 2010.

CPUC calculated $34/MWh transmission adder in June 2009 for remote renewable generation.

CPUC assumed renewable generation financed over 20 yr, transmission over 40 yr.

Adder is $46/MWh if generation and transmission financed over same 20 yr period (apples-to-apples).

CPUC adder assumes total new transmission requirement of $12 billion to reach 33% by 2020.

Combined RETI new transmission (> $15 billion) + CAISO reinforcement of existing transmission grid ($12 billion) exceeded $27 billion as of September 2009.

Total transmission + upgrades adder: $100/MWh or more?

10

Page 11: 20conference%20presentation_SF_P

Interest in high distributed PV casesource: E3/B&V - ReDEC working group meeting, Summary of PV Potential Assessment in RETI and the 33% Implementation Analysis, December 2009, p. 11.

"If it is conservatively assumed that only 10,000 MW of new high voltage transmission will be built by 2020 to realize the RETI net short target of 68,000 GWh, the estimated cost of this transmission will be in the range of $20 billion in 2008 dollars based on SDG&E’s projections for the Sunrise Powerlink. How much thin-film PV located at IOU substations or at the point-of-use on commercial buildings or parking lots could the IOUs purchase for this same $20 billion? ... This equals an installed thin-film PV capacity of 14,000 to 18,000 MW for a $20 billion investment."

Bill Powers, PE, testimony in SDG&E’s Sunrise PowerlinkCPCN case

11

Page 12: 20conference%20presentation_SF_P

Summer peak availability - sun and wind are not the same

Resource Reference Capacity factor (%)Tracking PV CPUC/E3, June 2009 77

Fixed rooftop PV Itron, Jan 2010 analysis of 2008 CAISO peak hr

59

Fixed rooftop PV Itron, July 2010 analysis of 2009 CAISO peak hr

59

Onshore wind CARB/E3 June 2010 33% RES draft report

11

Onshore wind NERC 2010 study of 20% national RPS

17

12

Page 13: 20conference%20presentation_SF_P

Utilities – wind power must be backed-up by combustion turbines

World without RPS requirements – utilities build combustion turbines to meet rising peak load.

World with RPS requirements – utilities build combustion turbines, and wind turbines, and new transmission to meet rising peak load.

Or central station solar thermal or solar PV, and new transmission.

Or distributed solar PV (ideally with limited 2 to 3 hr energy storage), and no new transmission.

13

Page 14: 20conference%20presentation_SF_P

How much distributed PV could we tie to grid without substantive substation upgrades? source: CPUC Rulemaking R.08-08-009 – California RPS Program, Administrative Law Judge’s Ruling on AdditionalCommission Consideration of a Feed-In Tariff, Attachment A - Energy Division FIT Staff Proposal, March 27, 2009.

14

Page 15: 20conference%20presentation_SF_P

About 13,000 MW at IOU distribution substations, ~20,000 MW statewideNote: IOUs supply about 2/3 of electricity in state, public utilities and others supply remaining 1/3.

15

Page 16: 20conference%20presentation_SF_P

The 21st century smart grid, with full bidirectional flow at every substationsource: CEC 2007 Integrated Energy Policy Report, December 2009, p. 155.

16

Page 17: 20conference%20presentation_SF_P

Utilities spend ¾ of total budgets on distribution system, but not yet building for 21st century source: CEC 2007 IEPR, December 2009, pp. 155.-156

“Utilities spend approximately three-fourths of their total capital budgets on distribution assets, with about two-thirds spent on upgrades/new infrastructure in most years.”

“Investments will remain for 20 to 30 or more years.”

“Magnitude of these investments suggests need to require utilities, before undertaking investments in non-advanced grid technologies, to demonstrate that alternative investments in advanced grid technologies that will support grid flexibility have been considered, including from a standpoint of cost-effectiveness.”

17

Page 18: 20conference%20presentation_SF_P

18

RETI’s “highly technical question” – is not a substantive impedimentsource: RETI Net Short Update – Discussion Draft, February 22, 2010, p. 7.

Potential for substantial development of distributed PV:“When the advent of lower cost PV projects of 20 MW or smaller and occupying sites of about 100 acres or less, the potential exists for substantial development of distributed solar generation located close to urban loads and connected to the grid at lower voltage substations in the electric distribution system.”

Highly technical question – how much distributed PV without compromising safety and reliability of grid?“The distribution system, however, is designed to enable energy from the high voltage transmission system to reach consumers, not to transmit energy in the opposite direction. The highly technical question of how much distributed generation can be connected without compromising safety and reliability has not been fully investigated and resolved.”

Page 19: 20conference%20presentation_SF_P

DOE on current cost of distributed utility-scale PV source: DOE, Solar Vision Study – Draft, Chapter 4: Photovoltaics: Technologies, Cost, and Performance, May 28, 2010, Figure 4-4, p. 7.

19

Page 20: 20conference%20presentation_SF_P

DOE on current cost of commercial rooftop PVsource: DOE, Solar Vision Study – Draft, Chapter 4: Photovoltaics: Technologies, Cost, and Performance, May 28, 2010, Figure 4-4, p. 7.

20

Page 21: 20conference%20presentation_SF_P

B&V/E3: Off-the-mark with PV cost estimates for CPUC LTPP process – inexplicably highsource: Black & Veatch, LTPP Solar PV Performance and Cost Estimates, June 18, 2010, p. 14.

21

Page 22: 20conference%20presentation_SF_P

Conclusiones

A 33% RPS portfolio will be more cost-effective in 2020 than a business-as-usual natural gas portfolio.

The most cost-effective 33% RPS portfolio will consist predominantly of distributed PV resources.

22