  • AS ON 31.01.2015

  • PERFORMA P-47A

    STATUS OF MAJOR DEVELOPMENT WORKS HAVING BUDGET PROVISION OF RS.1.00 CRORE AND ABOVE

    (WHICH ARE LIKELY TO BE COMPLETED DURING THE YEAR 2014-2015) UPTO 31.01.2015

    HUDA CIRCLE FARIDABAD

    Sr.

    No.

    Name of work Estimated cost / Approval

    No. & Date

    ( Rs. In lacs)

    Budget

    for the

    year

    2014-15

    ( Rs. In

    lacs)

    Likely

    date/

    date of

    start

    Upto

    date

    Expd.

    (Rs. in

    lacs)

    Likely

    date of

    completion

    Action

    Plan

    Remarks

    1 2 3 4 5 6 7 8 9

    Divn.1, Faridabad.

    1. ROB on bye pass road between

    sector 59 & 61, near Malerna

    Railway crossing, Faridabad.

    Detail of amount deposited to

    Railway Deptt.

    i) 08.10.07 Rs. 5.54 crores

    ii) 17.10.07 Rs. 2.68 crores

    iii) 04.03.08 Rs. 2.04 crores

    iv) 31.03.11 Rs. 1.50 crores

    v) 31.05.11 Rs. 0.75 crores

    vi) 30.06.11 Rs. 0.75 crores

    vii)06.01.11 Rs 0.02 crores

    viii)29.07.11 Rs. 1.15 crores

    Total Rs.14.43 crores

    i) For approaches

    Revised estimate appvd.

    vide CA letter no.6045-48

    dt.10.02.11 for Rs.1917.50

    lacs. Original estimate

    Rs.1220.00 lacs C.A.

    No.19745 dt.11.08.2005

    ii)For railway portion, revised

    estimate apprd. Vide CA

    No.628 dt.05.01.2011 for

    Rs.1989.42 lacs. Original

    estimate Rs.826.12 lacs-

    37093 dt. 23.10.07.

    iii)Estimate for Rs.1.1768

    crores (shifting of

    transmission line) appd. vide

    CA No.24714-19

    dt.19.07.2011 Total =

    Rs.4024.60

    300.00 10.03.08

    3867.57 31.01.2015

    Work completed

    --

    The work of construction of approaches has been allotted with

    restricted amount of Rs.932.72 lacs which has been further

    increased Rs.2329.00 lacs.

    The work for Railway portion completed.

    The work in HUDA portion has been completed on

    31.01.2015.

    Reasons of delay:-

    i) Due to increase in height of Railway portion. From 6.5 mtr. to

    8.05mtr. GAD approved by Railway Department-27.11.2009.

    ii) 132 KVA Transmission line of railway deptt. shifted -

    31.01.2013.

    iii) Shifting of casted RCC girders by railway (lying in the

    alignment of approaches) 30.08.2013.

    iv) GAD rechecked and cleared by Railway Department-

    16.04.2014.

    ContdP/2

  • -:2:-

    Sr.

    No.

    Name of work Estimated cost /

    Approval

    No. & Date

    ( Rs. In lacs)

    Budget for

    the year

    2014-15

    ( Rs. In

    lacs)

    Likely

    date/ date

    of start

    Upto date

    Expd.

    (Rs. in

    lacs)

    Likely date

    of

    completion

    Action Plan Remarks

    1 2 3 4 5 6 7 8 9

    2 Constn. of Polyclinic

    building Sec-55, Fbd.

    394.30-CA 14771-

    75 dt. 19.04.2012

    100.00 19.10.12 468.54 31.03.2015 G.F. slab laid. Brick work on F.F. completed

    Revised Estimate approved Rs.580.48 by CA HUDA Pkl. letter

    No.17328 dt.11.07.14. Work will be completed upto 31.03.2015.

    3 S/R of road Ankhir

    Chowk to Surajkund

    Road and Guraon Mor

    to Ankhir Chowk.

    8505 .00

    11865-68/

    11.03.13

    2300.00 11.04.13

    05.08.13

    3958.00 31.03.2015

    31.10.14

    Bituminous work :-

    Total length = 7.50 Km, 6.50 Km completed & balance work is in

    progress.

    RMC work has been completed.

    Divn.-2, Fbd.

    4 Re-constn. of dividing

    road Sec-12-15A,12-

    15&13-14, Fbd.

    746.49/

    49779/ 28.12.12.

    300.00 05.08.13 561.15 30.11.2014 - Total length - 2.25 Km - Work completed

    on both the carriage way and both

    the carriage way are made functional

    Divn.-3, Fbd.

    5 Construction of dual

    carriage way on

    periphery road of NH-

    3, Faridabad.

    14.70 Crore CA

    20866-69 / 19.8. 14

    500.00 09/2014 1410.54 28.02.2015

    The DNIT approved for Rs. 13.12 Crore on 28.7.2014 in anticipation of

    administrative approval of estimate. Tender approved on 28.8.2014 and

    work allotted on 3.9.2014. Approx 95% work completed at site.

    Target Achievement

    Construction of 3400 Mtr.

    x2 x 8.5mtr. each

    carriageway

    3400 Mtr. road portion

    completed.

    ContdP/3

  • -:3:-

    Sr.

    No.

    Name of

    work

    Estimated cost /

    Approval

    No. & Date

    ( Rs. In lacs)

    Budget for

    the year

    2014-15

    ( Rs. In lacs)

    Likely

    date/ date

    of start

    Upto date

    Expd.

    (Rs. in

    lacs)

    Likely

    date of

    completion

    Action Plan Remarks

    6 Consn. of

    Master

    road Sec-

    75 to 89,

    Faridabad.

    R/C/E for master

    road 75-89, Fbd.

    approved vide

    CA HUDA No.

    41719 dated

    16.12.2011 for

    Rs.391.77

    crores.

    3500.00 01/04/12 22292.12 30.09.2014

    31.03.2015

    The work was allotted for restricted amount of Rs.225.98 Crore for 29.50 km of Master roads. At present work is going on in 38.495 km.

    Date of start : 01.04.2012

    Likely date of completion : 31.03.2015

    The total length of Master road Sector 75 to 89, Fbd. is 44.925 km out of which

    possession of 38.895 km road length has been given by Estate Office, HUDA Fbd.

    The work is held up on 6.03 km & detail is as under :- a) Section -6 notified on 31.12.2013 and award likely

    to be announced- - 0.41 km

    b) Possession held up as CWP disposed Off with the direction of Honble High Court to provide alternate plot to land Owners - 0.465 km

    c) Possession held up due to protect from the Farmers regarding pending CWPS (10514/2009, 10491/2009,

    11143/2008, 8243/2009, 16318/2009, 8483/2009,

    11165/2008, 8396/2009, 8525/2009, 6782/2009,

    13631/2012,13302/2012,20830/2013) in High Court - 1.175 km

    d) Possession held up due to protect of farmers regarding land rates. Estate Officer is making efforts to get possession

    at an early date - 3.750 km

    e) Possession due to dispute between farmers & colonizers. - 0.230 km - 6.03 km

    The balance work in 6.03km will be completed in six months from the date of handing over of possession by LAO/EO/STP, Faridabad.

    The work in 38.895 Km is likely to be completed upto 31.03.2015 & physical progress is as under:-

    Physical Target Revised physical target Achievement

    29.50 km road to

    be completed in

    all respect.

    38.895 Km road to be

    completed by 31.03.2015

    a) Earth work -38.895 km

    b) GSB 38.00 km

    c) WMM 37.00 km

    d) DBM 35.50 km

    e) BC - 33.50 Km

    ContdP/4

  • -:4:-

    Sr.

    No.

    Name of work Estimated cost

    / Approval

    No. & Date

    ( Rs. In lacs)

    Budget for

    the year

    2014-15

    ( Rs. In lacs)

    Likely date/

    date of start

    Upto date

    Expd.

    (Rs. in lacs)

    Likely date

    of

    completion

    Action

    Plan

    Remarks

    Divn. Palwal

    7 Widening of 18 wide road, Ph-I,

    Rojkameo

    260.60

    2098

    dt.11.01.13

    50.00 08.04.13 22.38 30.09.2014

    31.03.2015

    Work in progress & status as under:-

    Target Achievement

    i)Widening from

    (3.66 m to 7 m) = 4.6Km 2 WBM layer completed in

    4.00 Km length

    ii)S/R with BM &

    25mm DBC = 4.6 Km ---

    Divn. Elect.

    8 Prov. & fixing of HT line with

    AB cable 50sqmmx3core on 11

    mtr. long PCC pole and T/F for

    street light in Sec-75 to 89, Fbd.

    2011.00 C.A.

    No.40317

    dt.11.10.2012

    200.00 05.11.2012 216.77 30.09.2014 22.57 Km Work completed.

  • PERFORMA P-48A

    STATUS OF MAJOR DEVELOPMENT WORKS HAVING BUDGET PROVISION OF RS.1.00 CRORE AND ABOVE

    (WHICH ARE LIKELY TO BE STARTED IN THE YEAR 2014-2015 AND TO BE COMPLETED IN SUBSEQUENT YEAR(S)) UPTO 31.01.2015

    HUDA CIRCLE FARIDABAD

    Sr.

    No.

    Name of work Estimated

    cost /

    Approval No.

    & Date

    (Rs. In lacs)

    Budget for

    the year

    2014-15

    (Rs. In lacs)

    Likely

    date/ date

    of start

    Upto date

    Expd.

    (Rs. in

    lacs)

    Likely date of

    completion

    Action

    Plan

    Remarks.

    1 2 3 4 5 6 7 8 9

    Divn.-1

    1

    Const. of Master

    Storm Water

    Drainage Scheme

    Sec-75 to 89, Fbd.

    144.40 crores

    apprd. vide

    CA letter

    No.40980-84

    dt.18.10.12

    5220.00 30.10.13

    7378.52 30.06.2015 24.00 Km RCC box drain completed & balance in progress.

    Divn.-2

    2 Dev. of new sectors

    Agra Canal. ( Ext.

    Sewer).

    5475.00

    3781/

    30.01.12

    1200.00 09/2012 3700.01 15.08. 14

    (For completion

    of enhanced

    work 30.06.15)

    The work was allotted for restricted amounts of Rs.32.71 crores for 31.865 Km

    of sewerline. At present work is going on in 38.495 Km. length.

    Date of start : 30.09.2012

    Likely date of completion : 30.06.2015 for 38.495 km complete in all respect.

    Total land length of roads for Sec-75 to 89 is 44.56 Km out of which

    possession of 38.495 Km has been given by E.O.HUDA Faridabad.

    The detail of work is as under:-

    Phy.Target Rev.Phy. Target Achievement

    31.865 38.495 (clear land) 34.500

    Manholes - 813 Nos. 561 Nos.

    Revised length 38.495 Km (clear land) sewerline to be completed by

    30.06.2015.

    Total revised target 45.020 Km to be completed according to clearance of land

    ContdP/2

  • -:2:-

    Sr.

    No.

    Name of work Estimated cost /

    Approval No. &

    Date

    (Rs. In lacs)

    Budget for

    the year

    2014-15

    (Rs. In lacs)

    Likely

    date/ date

    of start

    Upto date

    Expd.

    (Rs. in

    lacs)

    Likely

    date of

    comple-

    tion

    Action

    Plan

    Remarks.

    1 2 3 4 5 6 7 8 9

    Divn. -3, Fbd.

    3 Constn. of RUB

    Near Old Fbd.

    Revised R/C/E

    approved vide

    C.A. letter

    No.6025

    dt.10.02.11 for

    Rs.1548.00 lacs

    300.0 0 9/11/2011 1315.03 30.04.2015 The work was allotted with a restricted amount Rs. 1293.00 lacs. The RUB approaches towards Mathura road , railway station / NIT site and sector -21B &

    village Fatehpur Chandila has been completed.

    The work on approaches towards village Fatehpur Chandila has been completed recently. Approval received for demolisation of existing school room & reconstruction of the same

    within the school premises convey vide Director Secondary Education Haryana memo

    No.6/21/14 dt.30.04.2014.

    The work has been delayed due to :-

    The resentment raised by villagers of Fatehpur Chandila & Sector -21B for change in GAD & Design at various locations i.e. opening of approaches toward village Fatehpur Chandela &

    Sector -21B.

    The site of sump well is yet to be given by railway department. Efforts are being carried out to get the site of sumpwell.

    The case of sump well for transfer of land (Way leave charges) is pending with Sr. Divisional Engineer in the O/o DRM office, New Delhi. A meeting was held up in his office on

    20.06.2014 & on 20.09.2014 and it was decided to make a combined scheme for disposal of

    storm water of railway yard alongwith RUB. The survey has been carried out & combined

    scheme sent to Railway deptt. vide E.E.-3,HUDA Faridabad letter No. 6739 dated 03.07.2014.

    Reminder & drawings again submitted personally vide E.E. 3,HUDA Faridabad No. 13155-58

    dated 05.12.2014. He ensured that necessary approval will be accorded very soon.

    The physical progress of work is as follows : -

    Physical Target Achievement

    Retaining wall 860 mtr. Completed

    RMC approaches 580 mtr. Completed

    Service road 550 M Completed

    Approach roads from Mathura

    road to RUB 120 M

    Completed

    Shifting of electrical , sewer,

    water supply line

    Services towards Mathura road already shifted. 900 mm W/S

    line of Ranney Well scheme has been dismantled & made

    functional.

    Const. of sump well, machinery

    and drain.

    The approval from Railway Authority is awaited.

    ContdP/3

    -:3:-

  • Sr.

    No.

    Name of

    work

    Estimated

    cost /

    Approval No.

    & Date

    (Rs. In lacs)

    Budget for

    the year

    2014-15

    (Rs. In

    lacs)

    Likely

    date/ date

    of start

    Upto

    date

    Expd.

    (Rs. in

    lacs)

    Likely

    date of

    comple-

    tion

    Action

    Plan

    Remarks.

    1 2 3 4 5 6 7 8 9

    4 Const. of

    Indoor

    Stadium

    Sector -12,

    Fbd.

    CE No. 11777-

    80 dt.11.03.13

    for Rs.

    1704.00 Lacs.

    800.00

    Lacs

    01/07/2013 739.97 30.09.2015 The vetted drawing has been given to the contractual agency. The work has been started. Fabrication

    of structural steel has been started at site. The physical progress is as under:- Physical Target Achievement

    Footing 72 Completed upto plinth beam

    Fabrication of Major truss 8 Nos. of

    size 167 feet span

    Completed

    Fabrication of Minor truss 4 Nos.

    100 feet span

    Completed

    Fabrication of truss 4 Nos. 105 feet

    span

    4 Completed

    Fabrication of Minor truss 6 Nos.

    75 feet span

    Completed

    Column 72 Completed

    Stands (4 Nos.) 3 Nos. stands completed

    Brick work 96% work upto ground floor completed &60% at 1st floor.

    Entry 4 Nos. 4 Nos. completed upto slab level & 3 No. entry basement slab casted.

    Beam at First Floor Height 90% Completed

    5 R/C/E for

    augmentation

    of master

    water supply

    scheme Zone

    I (For

    Sectors 33,

    34, 39, 41,

    42, 45, 91 &

    Green Field

    colony) Fbd.

    55.30 Crores

    Secy. HUDA

    Pkl. Letter No.

    38872-75 dt.

    29.9.2013

    1000.00 29.11.13

    830.37 30.06.2015

    2Nos.

    Ranney

    wells for

    Rs.25.26

    Crores.

    A) The Ranney Well construction status is as under:-

    Ranney Well No. Casting ( inmtrs.) Well sinking ( in mtrs.)

    1. 21.0 mtr. 16.00 Mtr.

    2. 7.3 Mtr. 0.00 Mtr.

    Work in progress is as under:- Target Achievement

    2 Nos. Ranney Wells work The site for 2 Nos. Ranney wells identified and work is in progress.

    400mm DI pipes 3.0 Km D.I. Pipe received

    8 VT pump 8 Nos. received at site

    8 motors 8 Nos. received at site.

    70 Sluice valve 70 Nos. received at site.

    10 Non return valves 10Nos. received at site.

    Cutting edge 2 Nos.

    Reasons of delay:-

    Arrangement of land/ selection of site for Ranney Wells.

    ContdP/4

  • -:4:-

    Sr.

    No.

    Name of

    work

    Estimated

    cost /

    Approval

    No. & Date

    (Rs. In lacs)

    Budget for

    the year

    2014-15

    (Rs. In

    lacs)

    Likely

    date/

    date of

    start

    Upto

    date

    Expd.

    (Rs. in

    lacs)

    Likely date

    of comple-

    tion

    Action

    Plan

    Remarks.

    1 2 3 4 5 6 7 8 9

    05.09.14 04.03.16

    B) Consisting of 1 Boosting Stations (BS) and 1 UGT, Providing & Stringing of DI Rising Mains

    upto Sectors 19,29,33-34 & 91, Faridabad on EPC Basis amounting to Rs.1428.70 lacs. Rs. 1428.70 lacs allotted to M/s Subhash Infraengineers Pvt. Ltd. on 05.09.2014

    Target Achievement

    1 UGT (4540 KL) Excavation completed, PCC work in

    progress

    DI. PIPE

    DIA QTY. RECEIVED

    250 mm 4500

    300 mm 500

    350 mm 50

    400 mm 50

    450 mm 50

    500 mm 2500

    600 mm 4000

    1 Nos. Pump house

    2 Nos. Staff Qtr.

    (1 BHK 815 Sft.

    each

    11 KV VCB Panel

    630 KV

    Transformer

    500 KVA DG Set

    ContdP/5

  • -:5:-

    Sr.

    No.

    Name of

    work

    Estimated

    cost /

    Approval

    No. & Date

    (Rs. In lacs)

    Budget for

    the year

    2014-15

    (Rs. In lacs)

    Likely

    date/

    date of

    start

    Upto

    date

    Expd.

    (Rs. in

    lacs)

    Likely date

    of comple-

    tion

    Action

    Plan

    Remarks.

    1 2 3 4 5 6 7 8 9

    6 Augmentat

    ion of

    Master

    water

    supply

    scheme

    (Constructi

    on of

    Ranney

    Well &

    Tube Well

    & Tube

    Wells)

    Sec-75 to

    89,

    Faridabad

    Rs. 198.50

    Crores appd.

    vide CA

    HUDA

    Panchkula

    letter No.

    40461 dt.

    12.10.2012.

    3500.00

    Lacs.

    04/2013

    14/08/14

    5706.76 30.06.2015

    13.11.2015

    A)Work of Rs. 63.48 Crores allot vide EE-3, HUDA Faridabad letter No. 2850-57 dated 25.03.2013.

    Work in progress.

    Target Achievement

    Land

    procuremen

    t

    The land for 6 Nos. Ranney Well have been purchased

    by the agency and transferred in the name of E.O.

    HUDA Fbd.

    DI pipe The DNIT quantity 9000 mtr. of 400 mm DI pipes

    received at site & 7500 M pipe laid at site.

    VT Pump All 24 Nos. VT pumps received

    Motors All 24 Nos. Motors received

    Sluice valve All 180 Sluice valves received

    R/Wells construction status as under:-

    R/Wells

    Sr. Nos.

    Casting

    (in mtrs.)

    Well sinking

    (in mtrs.)

    Pushing of laterals

    5 30.575 28.50 --

    6 19.325 15.00 --

    7 32.00 28.0 200 Mtr.

    8 36.00 32.50 Ready for pushing

    9 28.900 27.00 Platform casted

    10 28.90 28.80 Platform work started

    B) DNIT approved vide C.E. HUDA Pkl. letter No.6628 dt.04.06.14 for Rs.4835.00 lacs and tender

    approved in favour of M/s. Tirupati Cement Products for main boosting station and rising main on

    dt.14.08.2014, work allotted and started.

    ContdP/6

    -:6:-

  • Sr.

    No.

    Name

    of

    work

    Estimated

    cost /

    Approval

    No. & Date

    (Rs. In lacs)

    Budget

    for the

    year

    2014-15

    (Rs. In

    lacs)

    Likely

    date/

    date of

    start

    Upto date

    Expd.

    (Rs. in

    lacs)

    Likely

    date of

    comple-

    tion

    Action

    Plan

    Remarks.

    1 2 3 4 5 6 7 8 9

    15.10.13

    31.03.15

    C) The work for Rs.58.96 Lacs for providing and installation of 10 Nos. Tubewells allotted on

    15.10.2013.

    The work status as under:-

    Physical Target Achievement

    Drilling of Tubewell

    10 Nos.

    8 Nos. completed

    other 2Nos. are in

    progress.

    Physical Target Achievement

    Purchase of land 7 Acre Land has been purchased.

    Const. of Main boosting station with

    electrical , mechanical installation and

    boundary wall.

    i) Pump house -1 No

    ii) UGT 4500 KL-2 Nos.

    iii) Staff Qtr. 1 BHK -2 Nos.

    iv) Staff Qtr. 2 BHK -1 Nos.

    v) Office cum lab 1 No.

    vi) Guest House-1 No.

    D.I. rising main

    i) 800mm-6000M 2000 mtr. received and 894 mtr. laid.

    ii) 1000mm-9250M 6954 mtr. D.I. pipe received & 3000mtr. laid.

    Centrifugal horizontal pumps - 5 Nos.

    Independent Feeder 9.0 km

    ContdP/7

    -:7:-

  • Sr.

    No.

    Name of work Estimated

    cost /

    Approval

    No. & Date

    (Rs. In

    lacs)

    Budget

    for the

    year 2014-

    15

    (Rs. In

    lacs)

    Likely

    date/

    date of

    start

    Upto date

    Expd.

    (Rs. in

    lacs)

    Likely

    date of

    comple-

    tion

    Action

    Plan

    Remarks.

    1 2 3 4 5 6 7 8 9

    03.03.14

    06.08.14

    06.08.14

    21.08.14

    30.06.15

    31.03.15

    31.03.15

    31.01.15

    D) The Work for Rs.101.00 lacs for the construction of 10 Nos. Pump chambers (16x16) at

    sector-75 to 89 Fbd. with boundary wall & 3 Nos. of staff quarters along the green belt of 75M

    wide master road Fbd. complete in all respect and all other works contingent thereto allotted on

    03.03.14

    Physical Target Achievement

    Pump chamber 10

    Nos.

    4 Nos. completed upto slab

    4 Nos. ready upto slab level

    2 Nos work in progress.

    3 Nos. staff qtr. 2 Nos. Under progress

    Additional 5 Pump

    Chamber & staff

    qtrs.

    Increased from 10 Nos. to 15 Nos. has been approved vide C.E.-

    I HUDA, Pkl. memo No.10293 dt.25.08.2014 and work is in

    progress.

    E) DNIT approved by C.E-I. HUDA Panchkula vide memo No.5183 dated 15.05.2014 for

    Rs.147.22 lacs. Tender approved by CE-I on 1.8.2014 & allotted to M/s. Ajit Singh & Baljit

    Singh vide E.E.-3, HUDA Fbd. letter No.8131-38 dt.06.08.2014.

    Physical Target Achievement

    Approach road 6.0 km Earth work completed in 4500 mtr., GSB work started

    F) DNIT for 15 Nos. tubewell machinery approved by C.E-I. HUDA Panchkula vide memo

    No.4601 dated 15.04.2014 for Rs.26.46 lacs. Tender approved by CE-I on 26.06.2014 & work

    allotted to the agency M/s. Vishwakarma Engg. On dt.06.08.2014.

    Physical Target Achievement

    Providing and installation of

    Machinery for tubewells 15 Nos.

    Machinery for

    15Nos. tube wells

    received at site.

    G) Tender for other 5 Nos. T.W. approved on 14.8.2014 & allotted to the agency M/s. B&R

    Tubewell Drilling Corporation.

    Physical Target Achievement

    5 Nos. Tubewells drilling. 5 Nos. tubewell drilled

    Work completed

    ContdP/8

    -:8:-

  • Sr.

    No.

    Name of work Estimated

    cost /

    Approval

    No. & Date

    (Rs. In lacs)

    Budget for

    the year

    2014-15

    (Rs. In

    lacs)

    Likely

    date/

    date of

    start

    Upto

    date

    Expd.

    (Rs. in

    lacs)

    Likely

    date of

    comple-

    tion

    Action

    Plan

    Remarks.

    1 2 3 4 5 6 7 8 9

    7 Master water supply

    Scheme Sector -75 to

    89, Fbd.

    4785 Lacs.

    CA No.

    40476 dt.

    12.10.2012

    1700.00

    Lacs.

    04/2013 1250.10 30.09.2015 The work amounting to Rs.25.35 crores allotted and status as under:-

    The 60180 mtr. DI pipes have been inspected at factory premises in Calcutta by M/s. RITES

    Ltd.

    The Detail of DI pipe dispatched from factory & received at site is as follows : -

    Dia DNIT Qty. Received Laid

    200 10725 7673

    16000 mtr.

    laid

    250 2990 2970

    300 23300 12609

    350 2200 2021

    400 3585 3217

    450 2370 2119

    500 5990 6028

    600 4155 4278.50

    700 1450 1524

    800 1180 1160.50

    900 2235 1800

    TOTAL 60180 45400

    Divn. Palwal

    8 Augmentation of

    water supply scheme

    Rozka Meo & Sohna

    (Deposit work of

    HUDA- by PHE).

    Project Cost.

    6430.00 lacs

    3267.15

    22043-46

    18.06.09

    5.00 03/2013 3265.00 30.06.2015 Deposit work by PHE Department Rs.3265.00 lacs paid by HUDA to PHE Deptt. And work is in progress.

    Remarks:- Canal based scheme for = 27 MLD

    Water supply demand for Rojkameo Industrial Area = 8.7 MLD

    ContdP/9

    -:9:-

  • Sr.

    No.

    Name of work Estimated

    cost /

    Approval

    No. & Date

    (Rs. In lacs)

    Budget for

    the year

    2014-15

    (Rs. In

    lacs)

    Likely

    date/

    date of

    start

    Upto

    date

    Expd.

    (Rs. in

    lacs)

    Likely

    date of

    comple-

    tion

    Action

    Plan

    Remarks.

    1 2 3 4 5 6 7 8 9

    1. Water works at Ghamroj Target Achievement .

    a) Staff quarter 4 Nos. Complete

    b) S/S tank 2 Nos. Complete

    c) CWT 4 Nos. Complete

    d) Pump chamber 1 No. Complete

    e) WTP 1 No. Complete

    f) Boundary wall 1 No. Complete

    g) Clarifloculator 1 No. Complete

    h) Pumping machinery & Generation set Complete

    i) D/I pipe rising main 12 Km laid

    2. Water works at Budhera a) S/S tank 2 Nos. 1 Complete & 1 90% complete

    b) Pump chamber 1 No. Complete

    c) Staff quarter 4 Nos. Complete

    d) Pumping machinery & Generation set Fixing in Progress

    e) PSC Pipe line 27 Km 25 Km supplied & 21 Km laid

    3. Boosting station at Sohna a) UGT 2 Nos. Complete

    b) Pump chamber 2 Nos. Complete

    c) DI pipe distribution system In progress

    600 mm i/d 10100 mtr.

    450 mm i/d 800 mtr.

    300 mm i/d 950 mtr.

    NOTE :

    i) Overall civil works = 90% completed

    ii) Overall Pipe line laid = 70% completed

    * A supplementary estimate received from E.E. PHED Sohna for balance cost for Rs.1212.75

    lacs is under process of approval.

    Contd..P/10

    -:10:-

  • Sr.

    No.

    Name of work Estimated

    cost /

    Approval

    No. & Date

    (Rs. In lacs)

    Budget for

    the year

    2014-15

    (Rs. In

    lacs)

    Likely

    date/

    date of

    start

    Upto

    date

    Expd.

    (Rs. in

    lacs)

    Likely

    date of

    comple-

    tion

    Action Plan Remarks.

    1 2 3 4 5 6 7 8 9

    9 Construction of Road,

    Sector-12, Palwal.

    769.79

    29549

    27.07.2012

    Dev. 716.82

    Mtc. 52.97

    90.00 24.12.12 426.74 30.09.2014

    30.06.2015

    Work in progress & status as under:-

    Target Achievement

    Sub Grade -12.64Km

    GSB -12.64Km

    WMM - 12.64 Km

    DBM - 1.91Km

    SDBC - 1.91 Km

    Premix - 10.73Km

    Road SWD - 1.00 Km

    Kerb stone -15.20 Km

    11.50 Km

    11.25 Km

    10.66 Km

    1.91 Km

    1.91 Km

    8.75 Km

    0.91Km

    11.20 Km

    Road of 2.00 km road is under encroachment/stay but land for road not made clear,

    E.O. HUDA Faridabad has to provide clear land for execution of held up road work.

    The case for increase in scope of work has been approved vide C.E. HUDA Pkl.

    letter No.12406 dt.16.10.2014.

    10 Construction of 45 mtr. Wide

    master road in Sec-12,

    Palwal

    524.80 CA

    No.21449-53

    dt.26.03.2014

    5.00 29.10.14 67.09 28.04.2015 Work of earth work including GSB & WMM in 45 mtr. wide road is in progress.

    Divn. Elect.

    11 Prov. of fixing of street light

    on octagonal pole 9/10 mtr.

    long with HPSV fitting 250

    watt with underground cable

    and high mast Fbd. (EDC)

    2011.00

    C.A.

    No.40317

    dt.11.10.2012

    200.00 05.11.12 569.27 30.06.2015 29.63 Km.

    Increased to

    39.63 Km

    Street light work has been completed and energized on 29.63 Km road length &

    additional work of 3.9 Km out of 10 Km. has been completed & balance work is in

    progress.

    12. Special repair of Surajkund

    road from Gurgaon mode

    Ankhir Chowk to Pehladpur

    Border, Fbd. (Civil work)

    200.00 10.07.14 142.43 30.04.2015 12.0 Km Street light work of 7.5 km completed & energized and balance work is in progress

  • 16

    PERFORMA P-47A

    STATUS OF MAJOR DEVELOPMENT WORKS HAVING BUDGET PROVISION OF Rs.1.00 CRORE AND ABOVE

    (WHICH ARE LIKELY TO BE COMPLETED DURING THE YEAR 2014-15)

    HUDA CIRCLE-I, GURGAON [01/2015]

    Sr.

    No.

    Name of Work Estimated

    Cost /App. No.

    & Dt.

    (Rs. in Lacs)

    Budget for

    the year

    2014 -15

    (Rs. in Lacs)

    Likely date/

    date of start

    Upto date

    Expenditure

    (01/2015)

    (Rs. in Lacs)

    Likely date of

    completion

    Action Plan Remarks.

    1 2 3 4 6 5 7 8 9

    HUDA DIVISION No. II

    1. Prov. Distribution mains for Recycle water for Zone-I, II & III, U/E, Gurgaon.

    2465.00

    CA 3786

    30.01.2012

    200.00

    a Prov. stringing out, jointing, cutting and testing of D.I. pipes of 200mm to

    600mm i/d sizes for recycled water,

    prov. and laying M.S. pipe of size

    600mm through trenchless method etc.

    and all other works contingent thereto.

    A/c Rs.8.45Crores (Work enhanced from

    Rs.8,08,59,757/- to Rs.11.99Crores)

    (Original Time limit 12 Months from

    07.01.2013 to 06.01.2014)

    07.01.2013 854.52 30.06.2015 -- a) Physical Status i) Total DNIT scope 21.48K.M. & completed

    19.00K.M. i.e. 90% work completed.

    ii) The work in balance 2.48 K.M. is in progress

    and affected by various hindrances such as, Court

    Stay, NHAI / IOCL permission, Crossing at

    Badshahpur Nallah, Pipe line in Tau Devi Lal

    Stadium etc.

    iii) 0.92 K.M. crossing by trenchless method is in

    progress in thickly populated area & 730 M

    completed at site.

    b) Bottlenecks / Reasons for Delay

    Permission from NHAI / IOCL is under approval.

    b Prov. stringing out, jointing, cutting and testing of D.I. pipes of balance 100mm

    to 450mm i/d sizes for recycled water,

    prov. and laying M.S. pipe of size

    300mm to 600mm i/d through trenchless

    method, prov. and fixing of sluice valves

    haudies and all other works contingent

    thereto. A/c Rs.13.00Crores /

    Rs.12.25Crores. (Original Time limit 12

    Months from 12.09.2014 to 11.09.2015)

    12.09.2014 231.40 11.09.2015 -- a) Physical Status Total DNIT scope 41.78 K.M. and 18.32 K.M.

    pipes inspected at Kolkata.

    Work completed 04 Km. and balance work is in progress

  • 17

    Sr.

    No.

    Name of Work Estimated

    Cost /App. No.

    & Dt.

    (Rs. in Lacs)

    Budget for

    the year

    2014 -15

    (Rs. in Lacs)

    Likely date/

    date of start

    Upto date

    Expenditure

    (01/2015)

    (Rs. in Lacs)

    Likely date of

    completion

    Action Plan Remarks.

    2. Const. of Northern Peripheral Road from Kherki Dula to Dwarka,

    Gurgaon

    13178.00

    CA 20851

    24.05.2010

    200.00

    a) Const. of road in 14 K.M length of available land

    A/c Rs.57.00Crores (Work enhanced

    from Rs.44,08,14,640/- to

    Rs.50,01,99,531/-)

    01.04.2011

    4554.28 30.06.2015 -- a) Physical Status Work completed in 14.33 K.M. available land and

    balance work 300 Mtr held up due to non

    availability of land.

    b) Bottlenecks / Reasons for Delay

    Site Physical possession not given by E.O.-I HUDA GGN in a length of 280 Mtr due to agitation of local

    affected residents lead by Rishi Raj Rana.

    Removal of 66 K.V. gantry poles by HVPNL in 20 Mtr length.

    1.31 K.M. under litigation / Court stay and not clear for want of alternate plots policy by E.O. I,

    HUDA, Gurgaon. The next date in Honble High

    Court is 18.02.2015.

    Auction of malba by E.O.-I, HUDA, Gurgaon for the removal of existing structures in 168Mtr length.

    b) Const. of 4 Nos Culverts on NPR Road A/c Rs.5.28Crores. / Rs.5,66,20,537/-

    (Original Time limit 09 Months from

    28.03.2013 to 27.12.2013)

    28.03.2013

    401.39 28.02.2015 -- a) Physical Status 04 Nos. culvert completed at R.D. 3373 / 9933 /

    13739 / 16403.

    c) Const. of SWD in 2 x 14 K.M available land. A/c Rs.20.61Crores (Work

    enhanced from Rs.18,62,60,082/- to

    Rs.26,91,77,436/-)

    (Original Time limit 12 Months from

    01.04.2013 to 31.03.2014)

    22.03.2013

    2083.39 31.03.2015 -- a) Physical Status The original scope 31.50 K.M. and 26.64 K.M.

    completed.

    b) Bottlenecks / Reasons for Delay

    2.00 K.M. SWD work will be completed after completion of road work by M/s Atlas Construction

    Co. which cant be taken up due to local hindrances.

    2.30 K.M. SWD work held up due to ongoing ROB work at site

    560 Mtr SWD work held up due to local hindrance / stay / possession not given by E.O. I, HUDA,

    Gurgaon.

    d) Const. of Road (2 x 12.5m) of Balance Portion & Cross Drainage etc. (1.0Km

    Length)

    A/c Rs.980.00Lacs / Rs.783.90Lacs.

    01.03.2014 0.00 6 Months after

    physical

    possession is

    -- a) Physical Status Total scope in DNIT 1.00 K.M.Work could not be

    started due to site hindrances.

    b) Bottlenecks / Reasons for Delay

  • 18

    (Original Time limit 06 Months from

    01.03.2014 to 31.08.2014) made available. Site Physical possession not given by E.O. I

    HUDA, Gurgaon in a length of 1.00 K.M. due to

    agitation of local affected residents lead by Rishi

    Raj Rana (900 M) and Jhanda Singh (100 M).

    Sr.

    No.

    Name of Work Estimated

    Cost /App. No.

    & Dt.

    (Rs. in Lacs)

    Budget for

    the year

    2014 -15

    (Rs. in Lacs)

    Likely date/

    date of start

    Upto date

    Expenditure

    (01/2015)

    (Rs. in Lacs)

    Likely date of

    completion

    Action Plan Remarks.

    3. Const. Of 120 MLD 2nd. STP & MPS at Behrampur, Gurgaon. Tender Amt. E/m

    Rs.90.00Lacs / Rs.98.10Crores.

    Const. Cost = Rs.73.58Crores.

    10% Commissioning = Rs.9.81Crores

    15% O & M Charges = Rs.14.71Crores

    Total Cost = Rs.98.10Crores

    (Original Time limit 18 Months from

    22.03.2012 to 21.09.2013 + 03 Months trial

    run)

    10078.00

    CA 6040

    10.02.2011

    1000.00 22.03.2012 7923.51 31.03.2015 -- a) Physical Status STP work completed upto tertiary treatment &

    under commissioning

    b) Bottlenecks / Reasons for Delay

    The work was allotted subject to decision of Honble High Court & court decision was

    conveyed after 6 months and subsequently

    work also delayed by 6 months

    4. Const. Of 100 MLD 2nd. STP & MPS at Dhanwapur, Gurgaon Tender Amt. E/m

    Rs.80.00Lacs / Rs.79.43Crores

    Const. Cost = Rs.59.58Crores.

    10% Commissioning = Rs.7.94Crores

    15% O & M Charges = Rs.11.91Crores

    Total Cost = Rs.79.43Crores

    (Original Time limit 18 Months from

    22.03.2012 to 21.09.2013 + 03 Months trial

    run)

    9440.00

    CA 5992

    Dt.10.02.2011

    1000.00 23.03.2012 5855.00 31.03.2015 -- a) Physical Status STP work completed upto tertiary treatment &

    under commissioning

    b) Bottlenecks / Reasons for Delay

    The work was allotted subject to decision of Honble High Court & court decision was

    conveyed after 6 months and subsequently

    work also delayed by 6 months

    5. Providing Distribution mains for recycle water from Sector 58 to 80, Gurgaon.

    Providing Distribution mains for recycle

    water from Sector 81 to 115 (Zone

    VII & VIII), Gurgaon ( M/s L & T Ltd.)

    A/c Rs.115.60Crores / Rs.11404.20Lacs.

    (Original Time limit 12 Months from

    01.05.2013 to 30.04.2014)

    7420.00

    CA 3068

    Dt.23.01.2012

    16160.00

    CA 3771

    Dt.30.01.2012

    500.00 01.05.2013 8941.46 30.06.2015 -- a) Physical Status DNIT Scope

    (In Mtr)

    Pipe Received

    (In Mtr)

    Pipe laid

    (In Mtr)

    58400 58241 40200

    4.64Km clear site but taken in hand after construction of box drain and manhole.

    The overall work progress 93% in clear available site.

    b) Bottlenecks / Reasons for Delay

    The site unavailable in 13.40 K.M. due to various hindrances such as, road not

    constructed at site due to non acquisition of

    land / change in alignment (9.54 K.M.), Court

    stay (2.50K.M.), encroachment at site (1.23

    K.M.), Railway crossing permission (0.13

    K.M.).

  • 19

    Sr.

    No.

    Name of Work Estimated

    Cost /App. No.

    & Dt.

    (Rs. in Lacs)

    Budget for

    the year

    2014 -15

    (Rs. in Lacs)

    Likely date/

    date of start

    Upto date

    Expenditure

    (01/2015)

    (Rs. in Lacs)

    Likely date of

    completion

    Action Plan Remarks.

    6. Providing master sewerage scheme of Sector -77 -115 Urban Estate Gurgaon

    A/c Rs.124.70Crores /Rs.12002.25Lacs.

    (Original Time limit 18 Months from

    16.01.2013 to 15.07.2014)

    38148.00

    CA3776 -80

    Dt.30.01.2012

    2500.00 21.01.2013 2356.84 01.07.2015 Size - Qty

    (i/d) - (in Mtr)

    600mm-21625

    800mm-20235

    900mm-11050

    1000mm-36350

    1200mm-9000

    1600mm-10850

    1800mm-3200

    2000mm-19400

    2400mm-1000

    Total 132710

    S.W. Pipe

    500mm-21475

    GTotal-154185

    Say-154.19Km.

    a) Physical Status

    DNIT Scope, only

    HUDA, Division No. II,

    Gurgaon

    (In K.M.)

    (RCC Np3 pipe 600mm

    to 2000mm i/d, and

    500mm S.W. pipes)

    Pipe

    Received

    (In K.M.)

    Pipe laid

    (In K.M)

    47.56 21.00 19.20

    Work in progress on clear available site 35.80 K.M. and likely to be completed by 01.07.2015.

    The overall work progress 37% in clear available site.

    b) Bottlenecks / Reasons for Delay

    The sewer line in 11.76 K.M. length is affected due to various hindrances such as, congested

    portion on Pataudi Road (4.275 K.M.), Stay

    portion (4.855K.M.), land under acquisition and

    change of alignment (2.63 K.M.).

    The scheme revised due to interference of levels by Master SWD Scheme and

    TPI engaged for testing of material after allotment of 6 months by approval from the Chief

    Engineer I, HUDA, Panchkula

    The above status is for HUDA Division No. II, Gurgaon and total scope is 62.70 K.M., including

    the scope of 15.14 K.M. of HUDA Division No.

    V, Gurgaon

  • 20

    HUDA DIVISION No. III

    7. Providing master water supply

    scheme. Construction of 22MGD

    Treatment Plant at Village Chandu

    Budhera.

    Rs.13200.00Lacs / Rs.12900.00Lacs

    Revised

    14092.00,

    CA20830-33

    Dt.24.05.10

    800.00 04.12.2009 13191.37 Work

    Completed

    -- The civil works completed and 22 MGD WTP is commissioned and functional.

    Sr.

    No.

    Name of Work Estimated

    Cost /App. No.

    & Dt.

    (Rs. in Lacs)

    Budget for

    the year

    2014 -15

    (Rs. in Lacs)

    Likely date/

    date of start

    Upto date

    Expenditure

    (01/2015)

    (Rs. in Lacs)

    Likely date of

    completion

    Action Plan Remarks.

    8. Construction of Master Roads in

    New Sector 81 to 95, Gurgaon.

    (Different following Seven Nos.

    works allotted to different agencies)

    27974.00

    CA23416

    Dt.09.06.2010

    500.00 10249.00 As per estimate 75Mtr = 11.33 Km

    60Mtr = 31.70 Km

    Total = 43.03 Km

    As per Allotment 75Mtr = 11.78 Km

    60Mtr = 26.83 Km

    Total = 38.61 Km

    Work Completed 75Mtr = 11.71 Km

    60Mtr = 18.67 Km

    Total = 30.38 Km

    Length under changes of

    alignment /

    litigation / stay

    75Mtr = 0.35 Km 60Mtr = 7.88 Km

    Total = 8.23 Km

    Work completed in available land.

    a D/Road 81A/82A & 81/82 Rs.8.88Cr./Rs.6.95Cr. (21.81% Below)

    (M/s Bestech India Pvt. Ltd.)

    24.03.2011

    Work completed except stay portion.

    The stay portion will

    be completed within 2 Months after clearance

    of litigation/ Stay

    b D/Road 90/91, 91/92, 85/89 & 86/90 Rs.23.27Cr./Rs.18.22Cr.(21.70%Below)

    (M/s DLF Ltd.)

    24.03.2011

    Work completed except stay portion.

    The stay portion will

    be completed within 4 Months after clearance

    of litigation/ Stay

    c D/Road Rs.75.80Cr./Rs.65.45Cr.(13.55%Below).

    (M/s K.C.C. Buildcon)

    17.01.2012

    30.04.2014

    Stay portion will be completed within 4

    Months after clearance

    of litigation/ Stay

    d D/Road 92/95 Rs.11.65Cr./Rs.8.66Cr. (25.60% Below).

    (M/s Ram Prastha)

    25.01.2012

    30.04.2014

    Stay portion will be

    completed within 4

    Months after clearance

    of litigation/ Stay

    e D/Road 89/93 & 89/94 Rs.10.09Cr./Rs.6.88Cr. (37.45% Below).

    (M/s Orries Infrastructure)

    12.04.2012

    Work completed except stay portion.

    The stay portion will

    be completed within 4 Months after clearance

    of litigation/ Stay

    f D/Road 91/92 & 93 and 85/86 07.07.2011 Work completed

  • 21

    Rs.14.17Cr./Rs.10.76Cr.(24.01%Below)

    (M/s DLF Ltd.) except stay portion.

    The stay portion 360 M which is under

    encroachment/litigation

    & work will be completed within 4

    Months after clearance

    of litigation/ Stay

    g D/Road 82/83, 82/85, 84/85, 83/84 and 82/82A

    Rs.27.65Cr./Rs.21.62Cr.(21.80%Below)

    (M/s Vatika Ltd.)

    25.03.2011 Work completed except stay portion.

    Stay portion will be

    completed within 6 Months after clearance

    of litigation/ Stay

    Sr.

    No.

    Name of Work Estimated

    Cost /App. No.

    & Dt.

    (Rs. in Lacs)

    Budget for

    the year

    2014 -15

    (Rs. in Lacs)

    Likely date/

    date of start

    Upto date

    Expenditure

    (01/2015)

    (Rs. in Lacs)

    Likely date of

    completion

    Action Plan Remarks.

    10. Construction of 2 No. S & S tanks of W.T.P., Basai.

    3865.00

    C.A. 5987

    Dt.10.02.2011

    200.00 4134.78 Total scope of work Tank no. 5 = 195 X 400 X 5.00M

    Capacity = 335900 KL Tank no. 6 = 650 X

    450 X 3.85M

    Capacity = 361900 KL Constn of CC road =

    3300M

    Brick B.Wall = 2600 M

    RCC inlet channel =

    700M RCC outlet channel =

    1150 M

    RCC culvert = 7 Nos Provision of CWT =

    02Nos

    RCC channel for filling of tank by

    gravity = 350 M

    a) Construction of 2 Nos. RCC Clear Water Tank of 9100 KL capacity each of one

    compartments / 20.00Lacs gallons capacity of

    size 55x55x3.0 Mtr. (working depth)

    Including providing and laying of MS pipe,

    specials and sluice valve for connection for

    inlet, outlet and overflow pipe etc at site of

    WTP Vill. Basai, Gurgaon and all other

    works contingent thereto. (Including one

    year defect liability period and mtc. free of

    15.04.2013 31.12.2014 2 Nos. tank 9100KL capacity

    each

    Work completed.

  • 22

    cost) A/C Rs.5.00Crores / Rs.6.80Crores

    11. Designing, Construction, Testing, Commissioning, Operation and Maintenance

    for 5 years after 12 months defect liability

    period of Second Water Works comprising of

    Raw Water pumping Machinery, 22MGD

    Automated Water Treatment Plant, Clear

    Water pumping machinery, Pre & Post

    chlorination, lowering of sub soil water,

    1000 mm dia. MS Rising Main for Clear

    Water up to Basai Water Works, Transformer,

    SCADA and all other works contingent there

    to complete in all respects on Turn Key basis

    for HUDA at Village Chandu Bhudhera,

    District Gurgaon, Haryana.(2nd Unit)

    Rs.3000.00Lacs / Rs.2693.90Lacs

    3840.00

    CA - 5982

    Dt.10.02.2011

    600.00 17.01.2012 3070.53 Work

    Completed

    i) 22 MGD WTP.

    ii) 01No. CWT

    9100KL

    iii)Raw water

    pumping

    machinery

    iv)Clear water

    pumping

    machinery

    v)Scada System

    The civil work completed and 22 MGD WTP is

    functional since 31.12.2013

    Sr.

    No.

    Name of Work Estimated

    Cost /App. No.

    & Dt.

    (Rs. in Lacs)

    Budget for

    the year

    2014 -15

    (Rs. in Lacs)

    Likely date/

    date of start

    Upto date

    Expenditure

    (01/2015)

    (Rs. in Lacs)

    Likely date of

    completion

    Action Plan Remarks.

    13. Dismantling of Raw water pump house No. I with allied and construction of new

    Raw water pump house at WTP Basai,

    Gurgaon. Construction of Clear Water

    Pump House of size 55 X 10 M, Sump

    well 40 X 5 X 5.5 M, RCC GWS

    Channel, Gen Set Room, C.I. pipes &

    specials and all other works contingent

    thereto

    A/C Rs.348.05Lacs / Rs.382.82Lacs

    678.40

    CA.37556

    Dt.25.09.2012

    300.00 25.10.2014 476.25 Work

    Completed

    i)Pump chamber 55

    x 10 M = 01 Nos.

    ii)RCC channel

    covered 2.75 x

    2.45M = 1.60 M

    iii) RCC channel

    without slab 2.75 x

    2.45M = 100 M

    iv) Pump 710 LPS

    15M head = 07

    Nos.

    v) V.T. pump 35

    cusecs 7.5M head =

    03 Nos.

    Work completed

    14 Providing, cutting & jointing of 450mm i/d pipe line from boosting station Sector-

    72 to Gwal Pahari on Faridabad road

    815.00

    CA. 9244-45 200.00

    411.47

    i) 450mm DI pipe = 9.00 KM

    ii) 250mm DI pipe =

    2.15 KM

  • 23

    a) Providing master water supply scheme (distribution mains) for new sector-58

    to 115 (Zone-IV to VIII), U/E, Gurgaon.

    Providing, stringing out, jointing,

    cutting and testing of 450mm i/d DI pipe,

    providing & fixing of sluice valves

    construction of sluice valves haudies and

    all other works contingent thereto.

    (Including A/Mtc. for 3 years) from

    sector-51/57 to Gwal Pahari.

    A/C Rs.6.36Crores / Rs.5.75Crores

    Dt.22.02.2013 07.11.2012 31.03.2015 -- 72% work completed at site (6.00Km 450mm line laid & 3213 Mtr. pipe received at site). Water

    supply pipe line laid upto village Baliyawas. For

    250mm dia DI pipe = 2.00Km in place of 450mm

    i/d is under process for approval and will be laid

    simultaneously along with 450mm i/d pipe after

    approval of N.S. item.

    Action under clause II have been taken for slow

    progress. Work is likely to be completed upto

    31.03.2015.

    HUDA DIVISION No. V

    15. a) Master Sewer Leg No. V (58 to 76) Rs.3540.00Lacs

    b) Master Sewer Sector 99 to 115,

    Gurgaon.

    Part of A/C Rs.124.70Crores

    11650.00

    CA.41727-31

    Dt.16.12.2011

    1200.00 01.04.2012 2292.63 31.03.2015 As per estimate 66.45Km work

    allotted 23.44Km

    completed

    19.53Km. Balance

    2.31 Km. sewer

    line laid by MCG

    and to be

    completed by

    31.03.2015

    Status of Work

    Total Length : 23.44 Km.

    Length of sewer work : 19.53 Km. completed (Work completed

    on the available land)

    Length of sewer line laid : 2.31 Km. by MCG

    Bottleneck : 1.60 km a) 0.70 km due to change in alignment of road at

    dividing sector 63/64 approved by Director

    Town Country Planning. Land is under

    acquisition.

    b) 0.90 km land litigation

    Sr.

    No.

    Name of Work Estimated

    Cost /App. No.

    & Dt.

    (Rs. in Lacs)

    Budget for

    the year

    2014 -15

    (Rs. in Lacs)

    Likely date/

    date of start

    Upto date

    Expenditure

    (01/2015)

    (Rs. in Lacs)

    Likely date of

    completion

    Action Plan Remarks.

    16. Construction of Master Roads in New Sector 99 to 115, Gurgaon.

    21255.00

    CA.23387

    Dt.09.06.2010

    2000.00

    8696.17

    Total Road length against approved estimate = 30.88Km.

    Work allotted against approved

    estimate = Rs.8270.00Lacs

    Work completed = 18.00Km

    Detail of balance work of 12.88 K.M.

    Land not acquired as yet = 8.945K.m. Encroachment of land to be = 2.730K.m. cleared after removing

    structures ______________

    Total =11.730Km

    DNIT amounting to Rs.13.00Crores for sector road between 101/104

    involving 1.15 K.M. length

    approved recently = 1.15K.m.

    a) A/C Rs.82.70Crores, Const. of 60Mtr. & 75 Mtr. Road

    20.11.2011 Work completed

    except un-

    acquired /

    litigation area

    200Mtr. yet to be

    Acquired

    Litigation and

    encroachments =

    85Mtr. b) A/C Rs.856.30Lacs, Const. of 60Mtr. Road recently acquired road.

    29.03.2013 Work completed

    c) A/C Rs.5.30Crores, Const. of 2 Nos. bridges / culvert

    16.04.2013 Work completed

  • 24

    Tenders are being invited___________ G. Total = 12.88K.m.

    17. Construction of Govt. College of

    Commerce Balance Sector 51,

    Gurgaon.

    Rs.2958.00Lacs / Rs.2723.00Lacs

    4003.30

    CA.24523-27

    Dt.17.05.2013

    Education

    Deptt. =

    3450.50Lacs

    HUDA =

    522.80Lacs

    1800.00 15.12.2013 2209.13 31.07.2015 -- The status of Commerce College in Sector-51 Gurgaon is as under.

    Main Building: - Structure of main building (Basement + Ground + 4 Floors)

    completed up to plaster. Flooring completed of

    02 Nos. floors i.e. 3rd

    & 4th floor, outer face

    plaster 50% completed.

    Boys Hostel: - Structure (Ground + 3 Floors) completed up to plaster work.

    Girls Hostel: - Structure (Ground + 3 Floors) completed up to plaster work.

    Auditorium: - Foundation work (RCC) completed. Roof slab of Balcony, Canteen and

    Stage portion laid & columns of double height

    roof completed and plaster works in Canteen area

    completed. Auditorium roof laid.

    Staff Quarters: - 5 Nos. Staff Quarters roof laid, 100% brick work completed. Principal residence

    roof laid.

    Boundary Wall: - 75% Boundary wall completed.

    Superintending Engineer,

    HUDA Circle I, Gurgaon.

  • 25

    PERFORMA P-48A

    STATUS OF MAJOR DEVELOPMENT WORKS HAVING BUDGET PROVISION OF RS.1.00 CRORE AND ABOVE

    (WHICH ARE LIKELY TO BE STARTED IN THE YEAR 2014-15 AND TO BE COMPLETED IN SUBSEQUENT YEAR(S) HUDA CIRCLE-I, GURGAON

    Sr.

    No.

    Name of Work Estimated

    Cost /App. No.

    & Dt.

    (Rs. in Lacs)

    Budget for

    the year

    2014 -15

    (Rs. in Lacs)

    Likely date/

    date of start

    Upto date

    Expenditure

    (01/2015)

    (Rs. in Lacs)

    Likely date of

    completion

    Action Plan Remarks.

    1 2 3 4 6 5 7 8 9

    HUDA DIVISION No. II

    1. Const. of approaches of ROB on Delhi Rewari Railway line.

    A/C Rs.63.20Crores.

    Restricted Amt. Rs.71.24Crores

    (Original Time limit 15 Months from

    18.02.2014 to 17.05.2015)

    7731.00

    CA 39568-71

    Dt.07.10.2013

    3500.00 18.02.2014 4173.84 30.05.2015 -- a) Physical Status 60% work completed at site & as detail under: - Activity DNIT Qty Progress Balance

    Casting of Piles 522 Nos. 522 Nos. 0 No.

    Casting of Pile cap 58 Nos. 57 Nos. 1 Nos.

    Casting of Piers 250 Lifts 220 Lifts 30 Lifts

    Casting of Pier caps

    58 Nos. 40 Nos. 18 Nos.

    Casting of desk

    slabs

    54 Nos. 13 Nos. 41 Nos.

    Wearing coat on stilted portion

    54 Nos. 0 No. 54 No.

    Fixing of

    expansion joint

    54 Nos. 0 No. 54 No.

    Casting of RE wall panels

    10000 Sqm.

    9200 Sqm. 800 Sqm.

    Erection of RE

    wall panels with earth work

    10000

    Sqm.

    5500 Sqm. 4500

    Sqm.

    Casting of Friction

    slab

    2000 Rm 0 Rm 2000

    Rm

    Casting of crash barriers / railings

    3000 Rm 68 Rm 2932 Rm

    2. Const. of Railway portion of ROB on Delhi Reweri Railway line.

    6391.00

    CA 13629

    Dt.18.03.2013

    3195.00 -- -- 02 Years after

    release of funds -- a) Physical Status

    Rs.31.96Crores i.e. 50% amount released & deposited to Railway Deptt. by the XEN-II vide his office memo

    No. 17757 dated 11.09.2013 for inviting tenders in

    C.E. of Railway.

    Tender of RUB Rs.5.50Crores is under allotment process by the Railway Deptt.

    The consent for RUB sump provision and its maintenance to be conveyed by HUDA to Railway

    Department, same under approval.

  • 26

    Sr.

    No.

    Name of Work Estimated

    Cost /App. No.

    & Dt.

    (Rs. in Lacs)

    Budget for

    the year

    2014 -15

    (Rs. in Lacs)

    Likely date/

    date of start

    Upto date

    Expenditure

    (01/2015)

    (Rs. in Lacs)

    Likely date of

    completion

    Action Plan Remarks.

    HUDA DIVISION No. III

    3. Designing constructing testing commissioning operation and

    maintenance for 5 years after 12

    months defect liability period of second

    water works comprising of Raw Water

    pumping Machinery 22 MGD

    Automated Water Treatment plant clear

    water tank clear water pumping

    machinery Pre and post chlorination

    lowering of sub soil water 1000mm

    diameter MS rising main for clear

    water pumps up to Gurgaon water

    supply canal near water works

    transformer SCADA and all other

    works contingent thereto complete in

    all respect on Turnkey basis for HUDA

    at village Chandu Budhera District

    Gurgaon Haryana.(3rd

    unit)

    Rs.3000.00Lacs / Rs.2668.25Lacs

    3830.00

    CA.11802-05

    Dt.11.03.13

    1500.00 15.04.2013 2575.56 28.02.2015 a) Clarifloculator Complete in all respect except tiles on walkway.

    b) Rapid Sand Filler Both side of Raw filter completed.

    c) Annexy Building Completed & finishing work is in progress.

    d) Chemical House Completed and alum tanks are being

    constructed.

    e) Clear water reservoir 1 No. UGT completed.

    f) Machinery being installed. Work is expected to be completed by 28.02.2015.

    4. Augmentation of master water supply scheme (Zone-I), U/E, Gurgaon.

    Providing, stringing out, jointing,

    cutting and testing of DI pipes (K9) of

    200mm to 1200mm i/d sizes,

    providing and fixing of sluice valves,

    zero velocity valve, scour valve,

    double action air valve and

    construction of sluice valve haudies

    and all other works contingent

    thereto." (including A/Mtc. defect

    liability period for 3 years).

    Rs.852.00Lacs / Rs.948.65Lacs

    2649.00

    CA.11807-10

    Dt.11.03.13

    800.00 02.12.2013 1100.06 31.03.2015 Total scope of work

    D.I. Pipe =

    20.54Km.

    Work allotted to M/s Tirupati Cement Product.

    9.45Km. pipe laid and work is in progress.

    Permission for trenchless crossing of Railway line

    is under approval and Nos. of house has come up

    adjoining to alignment.

  • 27

    Sr.

    No.

    Name of Work Estimated

    Cost /App. No.

    & Dt.

    (Rs. in Lacs)

    Budget for

    the year

    2014 -15

    (Rs. in Lacs)

    Likely date/

    date of start

    Upto date

    Expenditure

    (01/2015)

    (Rs. in Lacs)

    Likely date of

    completion

    Action Plan Remarks.

    5. Laying of water supply line for new sectors i.e. 58-115

    49805.00

    CA No. 2655

    Dt.19.01.10

    7000.00

    18296.10

    Total scope of work D.I. pipe = 147.15 KM

    MS Pipe= 48.74 KM

    a) Providing master water supply scheme(distribution mains) for new

    Sector-58 to 115 (Zone IV to VIII),

    U/E, Gurgaon. Providing, stringing

    out, jointing, cutting and testing of

    1600mm i/d, 1500mm i/d & 1400mm

    i/d M.S. pipe, providing and laying of

    sluice valves, construction of sluice

    valve haudies and all other works

    contingent thereto. (including A/Mtc.

    3 years)

    Rs.176.10Crores / Rs.144.40Crores

    15.12.2012 30.06.2015 Length as per

    Agreement

    32.21Km.

    Worthy Chief Administrator, HUDA PKL had

    granted time extension to original agency M/s

    SaiSudhir Infrastructures Pvt. Ltd. upto

    31.12.2014 for completion of work and latest

    progress is as under: -

    1600mm & 1500mm i/d MS pipe received =

    28000 Mtr.

    1600mm & 1500mm i/d MS pipe laid = 20000

    Mtr.

    b) Providing master water supply scheme for new sector 58 - 115 (distribution

    mains) for (Zone-IV to VIII),

    Gurgaon. "Providing, stringing out,

    jointing, cutting and testing of DI

    pipes (K9) of 200mm to 1200mm i/d

    sizes and 1200mm MS pipe, providing

    and fixing of sluice valves, zero

    velocity valve, scour valve, double

    action air valve and construction of

    sluice valve haudies and all other

    works contingent thereto." (including

    A/Mtc. for 3 years).

    Rs.76.10Crores / Rs.79.78Crores

    01.04.2013 30.06.2015 72.925Km. pipe

    of various sizes

    from 200mm i/d

    to 1200mm i/d

    46.00Km pipe received at site.

    24.00Km pipe laid at site & work is in

    progress.

    (80% work completed)

    Reason of delay: -

    Non finalization of slot. Slot finalized recently. Number of hurdles due to

    construction stay.

    Site adjacent to SWD work & execution is delayed due to heaps of earth of master

    SWD.

    c) Providing master water supply scheme for new sector 58 - 115 (distribution

    mains) for (Zone-IV to VIII),

    Gurgaon. "Prov., stringing out,

    jointing, cutting and testing 1600mm

    &1500mm i/d MS pipe, providing and

    29.08.2014 28.08.2015 Total length

    13.80Km.

    Work recently allotted to M/s Tirupati Cement

    Products vide XEN-III memo No. 24160-68

    dated 29.08.2014.

    Pipe received = 6300 Mtr.

    Laid = 1230 Mtr.

  • 28

    fixing of sluice valves, construction of

    sluice valve haudies and all other

    works contingent thereto." (including

    A/Mtc. for 3 years)

    Rs.7630.00Lacs/Rs.7176.84Lacs

    Sr.

    No.

    Name of Work Estimated

    Cost /App. No.

    & Dt.

    (Rs. in Lacs)

    Budget for

    the year

    2014 -15

    (Rs. in Lacs)

    Likely date/

    date of start

    Upto date

    Expenditure

    (01/2015)

    (Rs. in Lacs)

    Likely date of

    completion

    Action Plan Remarks.

    HUDA DIVISION No. V

    6. Internal development of Sector-57

    Part-I & II, Gurgaon.

    Work allotted = Rs.4590.00Lacs

    Work allotted = Rs.5.42Crores

    4960.00

    CA 27427

    Dt.01.08.2007

    500.00 15.07.2007

    15.07.2014

    3753.78 --

    31.03.2015

    Work rescind &

    completed balance

    work re-allotted

    amounting to

    Rs.5.42Crores

    Work started & in

    progress as per

    detail given.

    Detail of works: - 1 Road in terms of

    3.66Km complete upto

    WMM = 5.55Km. Total Road length as per

    DNIT = 6.05Km. 2 Sewer line laid

    = 2.70Km. Total length of sewer line

    as per DNIT = 3.05Km. 3 SWD pipe laid

    = 1.15Km. SWD Drain = 2.65Km.

    Total length of SWD pipe

    line & drain as per DNIT

    2.65 + 3.00 = 5.65Km. (SWD Pipe + SWD Drain)

    4 Water Supply line laid = 1.25Km.

    Kerbs & Channels

    = 2.5Km.

    Supply of DI pipe in

    progress.

    Total Water supply line

    length as per DNIT

    = 4.00Km.

    Bottleneck: -

    All services such as roads, sewer SWD & water

    supply affected due to stay recently awarded by

    court and existing jhuggi and encroachments,

    approximate length effected due to above

    bottlenecks 0.85Km.

    Note: -

    1. The black top of 6.05Km involves an expenditure of 2.94 Crores which shall be taken

    up after the completion of 6.05Km. WMM in

    one go.

    2. The water supply pipe line has been dispatch from Kolkata and is expected to be received in

    3 to 4 Days. (Appx. Rs.75.00Lacs)

    Superintending Engineer,

  • 29

    HUDA Circle I, Gurgaon. PERFORMA P-47A

    STATUS OF MAJOR DEVELOPMENT WORKS HAVING BUDGET PROVISION OF RS. 1.00 CRORE AND ABOVE

    (WHICH ARE LIKELY TO BE COMPLETED DURING THE YEAR 2014-15) (UPTO 01/2015)

    HUDA CIRCLE-II, GURGAON

    Sr.

    No.

    Name of work. Estimate / appd.

    No. & Date. cost

    (Rs in lacs)

    Budget for

    the year

    2014-15 cost

    (Rs in lacs)

    Date of Start Upto date

    expdt upto

    01/2015

    (Rs. In

    lacs)

    Likely date

    of

    Completion

    Action Plan Remarks

    1 2 3 4 5 6 7 8 9

    Div. No. I, GGN

    1 Construction of Southern

    Periphery Master Roads from

    Sohna Road to NH-8 Gurgaon.

    2295.31

    CA No 5976-80

    Dt. 10.02.2011

    300.00 20.09.10 for 0.66 Km

    (2nd

    lane)

    1710.23 Completed

    in clear area

    and balance

    with in 2

    months

    after

    clearance of

    site.

    Road two lane of 12.50 Mtr

    each = 5.28 km

    Completed = 5.03 K.M.

    Balance portion 150mtr is under stay bearing

    CWP No. 2367/2009 (Sh. Rambir Singh Vs.

    state of Haryana.

    The application for vacation of stay was

    listed in Honble High Court on 20.09.2013

    for which next date for hearing is on

    12.02.2015.

    In this case learned Judge Sh. Surya

    Kant has forwarded instruction during hearing

    05.05.2014 that It appears prima-facie that

    the residential house, which is the only social

    shelter for petitioners and their family, cannot

    be allowed to be demolished to facilitate the

    private-builders unless the petitioners are

    suitably rehabilitated by allotting them plots

    along with residential house of A Class

    construction on the equivalent area.

    Let learned state counsel shall have

    instructions whether the private-builders are

    willing to share the responsibility

    30.11.13 for 0.66 km

    (2nd

    lane)

    01.5.11 for 1.991km

    (1st lane)

    22.07.11 for 1.991km

    (2nd

    lane)

    19.09.11 for 1.495km

    (1st lane)

    16.09.13 for 1.495km

    (2nd

    lane)

    04.06.13 for 1.305

    (Two lane)

  • 30

    Sr.

    No.

    Name of work. Estimate / appd.

    No. & Date. cost

    (Rs in lacs)

    Budget for

    the year

    2014-15 cost

    (Rs in lacs)

    Date of Start Upto date

    expdt upto

    01/2015

    (Rs. In

    lacs)

    Likely date

    of

    Completion

    Action Plan Remarks

    1 2 3 4 5 6 7 8 9

    proportionately for the said purpose?

    100 mtr under existing structure coming into

    alignment at entrance near Sohna Chowk.

    2 Up-gradation of 60mtr wide

    master road from NH-8 to Sec-

    55/56, Gurgaon (Joint venture

    of HUDA & DLF )

    DLF Share = 42852.00 lacs

    HUDA Share= 16678.00 lacs

    (Joint venture of

    HUDA & DLF)

    Revised

    Amt = 59500.00

    3500.00 23.05.2012 4830.74 31.03.2016 Shifting of utilities. Shifting of services is in progress at site.

    Under Pass = 6 Nos. 5 Nos. under construction. The right turn of underpass at Shankar Chowk open up for trial

    run of traffic.

    The work for shifting of 66 KV line at under pass 2

    nd U-turn is completed, but work is held

    up due to shifting storm water box drain.

  • 31

    Sr.

    No.

    Name of work. Estimate / appd.

    No. & Date. cost

    (Rs in lacs)

    Budget for

    the year

    2014-15 cost

    (Rs in lacs)

    Date of Start Upto date

    expdt upto

    01/2015

    (Rs. In

    lacs)

    Likely date

    of

    Completion

    Action Plan Remarks

    1 2 3 4 5 6 7 8 9

    lacs Flyover = 1 No.

    Flyover completed. Finishing work is in

    progress & ready to open for traffic except

    some road portion is held up opposite Metro

    Station.

    Bottlenecks

    i) 8 Nos cases existing structure coming into

    alignment

    ii) Left out pockets of land are under

    acquisition.

    iii) STP, GGN has been requested vide SE-II,

    GGN earlier letter No. 14746 dated

    19.12.2013 and latest EE-I, HUDA, No. 950

    dated 12.06.2014, 1730 dt. 05.11.2014 &

    DB-1997 dt. 22.12.2014 to handover the land

    occupied by the colonizers.

    iv) The EO-II, HUDA, GGN has been requested

    vide SE-II, HUDA earlier letter No. 1109

    dated 20.01.2014 and latest EE-I, letter No.

    975 dated 12.06.2014, 1733 dt. 05.11.2014

    & DB-1992 dt. 22.12.2014 to remove the

    encroachments.

    Road = 8.30 Km

    Widening / diversion 5.00 Km.

    43% work completed at site.

    3. Strengthening of Road and

    const. of RCC surface drain

    along 60 Mtr. wide Outer

    Master Road from Sohna Road

    to Village Ghatta, Gurgaon

    2475.40 lacs

    CA No. 40444

    dt. 12.10.2012

    1500.00 03.12.2013 825.19 31.05.2015 Road two lane each of 9.70

    Mtr = 6.70 KM.

    RCC Surface Drain=13.76 km

    11.50 Km drain completed.

    4.00 Km DBM completed on one carriage way and balance work is in progress.

    The Principle approval received from CE-I, HUDA, PKL vide No. 13533 dt 03.10.13 &

  • 32

    Sr.

    No.

    Name of work. Estimate / appd.

    No. & Date. cost

    (Rs in lacs)

    Budget for

    the year

    2014-15 cost

    (Rs in lacs)

    Date of Start Upto date

    expdt upto

    01/2015

    (Rs. In

    lacs)

    Likely date

    of

    Completion

    Action Plan Remarks

    1 2 3 4 5 6 7 8 9

    detailed enhancement case submitted to CE-I,

    PKL vide SE-II, memo No. 15817 dt.

    16.12.14.

    Enhancement case of work returned vide CE-I, HUDA No. 15354 dated 30.12.2014.

    EE-IV, Gurgaon

    4 Construction of 60mtr wide

    development plan road from

    IMT Manesar to Pataudi Road,

    Gurgaon.

    2495 lacs

    CA No. 40477

    Dt-24.12.10.2012

    200.00 30.10.2012 for

    2.85km

    1307.01 Completed

    Road two lane 12.5 mtr each

    with central verge=3.40 Km.

    i) Work Completed

    External SWD is yet to be finalized by

    HSIDC. However the shoots, kerbs &

    channels has been provided to dispose off

    rain water.

    25.02.2014 for

    0.55km

    EE-VI, GURGAON

    5 Up-gradation of master road

    from HUDA City Centre to

    Subhash Chowk, Gurgaon.

    3204.00 Lacs

    C.A. No. 40467-

    71 Dt.12.10.12

    400.00 01.02.2013 1940.26 Completed.

    Widening 2.50m both side,

    strengthening on 10M existing

    road, 2.50M footpath both side

    and 5.50M wide service road

    both side =4.71 Km

    Completed for 4.40 K.M & 0.31 KM comes under flyover Subhash Chowk which is not

    required.

    6 Prov. Master SWD along

    Master Road in new Sectors

    from Sec-58 to 67, Gurgaon.

    6692.00 Lacs

    C.A. No.

    40452-56 Dt.

    12.10.12

    500.00 01.02.2013 2212.16 31.01.2015

    (In clear

    area)

    a) RCC pipe =11.43 km

    b) RCC box drain =6.50 km a) 11.50 K.M. completed.

    b) Completed upto roof slab = 4.50 K.M.

    Bottleneck

    There are 8 No. Stay. The Hon'ble High Court

    has now ordered to reprocess the acquisition..

    The Permission on outer road of Sec-58 not

    yet accorded by Forest Department.

    The I.O.C Pipe line is passing through the

    alignment of Master road of Sec-62/63.

    Permission / Acquisition of revised alignment

    is in progress.

    7 Const. of Master SWD in new

    Sectors from Sec-81 to 98,

    25302.00

    C.A. No. 11786 -

    4000.00 09.04.2013 12172.80 07.04.2015

    (In clear

    a) RCC pipe =27.72 Km

    b) RCC box drain =18.81km

    a) SWD RCC Pipe = 18.09 KM.

    b) RCC box = 7.56 KM

  • 33

    Sr.

    No.

    Name of work. Estimate / appd.

    No. & Date. cost

    (Rs in lacs)

    Budget for

    the year

    2014-15 cost

    (Rs in lacs)

    Date of Start Upto date

    expdt upto

    01/2015

    (Rs. In

    lacs)

    Likely date

    of

    Completion

    Action Plan Remarks

    1 2 3 4 5 6 7 8 9

    Gurgaon. 90 dt. 11.03.2013 area)

    Balance

    within

    6 months

    after

    clearance of

    site.

    Bottlenecks:-

    Under Gas pipe line, encroachments and electric poles.=3.07 K.M.

    Village Aabadi/acquisition of land= 6.30 K.M.

    8 Remodeling of Kost Nallah

    along SPR, Gurgaon.

    8752.00

    C.A. 11811-15

    dt. 11.03.2013

    4000.00 07.06.2013

    But actual as on

    1.10.13 as per decision

    of covered drain

    accorded vide CA No.

    13223 dt. 26.9.13 &

    contr. was asked vide

    EE-VI No. 12566 dated

    01.10.13, reckoned

    from 07.10.13.

    6268.21 07.04.2015

    In clear

    portion and

    balance in 6

    months

    after

    clearance of

    site

    RCC box drain = 7.05 Km

    RCC box = 5.59 KM.

    Bottlenecks:-

    There is a stay granted by Honble High Court CWP No. 11 of 2011 Sh. Prem Singh &

    Others on 30 mtr. wide green belt along Sec-

    62 RD-2850 to 3040.

    9 Remodeling of Badshahpur

    Nallah from Sohna Road to

    NH-8, Gurgaon.

    7723.00

    C.A. No. 11781-

    85 dt. 11.03.2013

    3000.00 09.04.2013 2152.21 30.09.2015 RCC box drain = 5.83 Km RCC box = 2.02 K.M.

    10 Const. of Flyover at Subhash

    Chowk along Road from

    Bhaktawar Chowk to Hero

    Honda Chowk, Gurgaon.

    3460.00

    C.A. No. 11826-

    30

    dt. 11.03.2013

    2000.00 15.04.2013 998.71 04.04.2015 Flyover = 1 No. 2 No. Test Pile laid/Tested.

    Load Bearing Test on Test Pile = 2 Nos.

    52 No. Piles laid.

    Routine Test on working Pile = 4 Nos.

    8 No. Pile cap Completed.

    4 No. Piers Completed.

    Abutment = 4 Nos.

  • 34

    Sr.

    No.

    Name of work. Estimate / appd.

    No. & Date. cost

    (Rs in lacs)

    Budget for

    the year

    2014-15 cost

    (Rs in lacs)

    Date of Start Upto date

    expdt upto

    01/2015

    (Rs. In

    lacs)

    Likely date

    of

    Completion

    Action Plan Remarks

    1 2 3 4 5 6 7 8 9

    Pier Cap = 4 Nos.

    Abutment Cap = 4 Nos

    2 x1.50 Deck Slab completed, 1 x 0.5 Deck

    slab completed & balance is in progress.

    Slope towards Hero Honda completed upto

    sub grade level by providing RE panel etc

    Slip Road upto DBM = 0.70 K.M.

    Retaining Wall = 4600 Sqm casted, 2100

    sqm erected.

    800 M RCC Carrier Drain

    Crush Barrier casted = 50M

    (Total 55% work completed).

    Bottlenecks:-

    The progress of work is hampered due to non

    shifting of 11KVA Independent Feeder of

    various colonizer & STP, Sec-47 Etc. exists

    on road dividing Sec-38/47. The matter has

    been taken up with the various colonizers as

    well as. Underground cable has been got laid

    at the cost of colonizer lowering /removing of

    HT independent feeder line.

    The permission for cutting of trees was

    granted by the Deputy Conservator of Forest

    vide No. 2984 Dt. 06.12.2013. The matter was

    taken up and the deforestation to take place.

    EE-HUDA, REWARI.

  • 35

    Sr.

    No.

    Name of work. Estimate / appd.

    No. & Date. cost

    (Rs in lacs)

    Budget for

    the year

    2014-15 cost

    (Rs in lacs)

    Date of Start Upto date

    expdt upto

    01/2015

    (Rs. In

    lacs)

    Likely date

    of

    Completion

    Action Plan Remarks

    1 2 3 4 5 6 7 8 9

    11 Const. of sector dividing road

    single carriage way between

    Sec-18/24, U/E, Dharuhera.

    40987-90 dt.

    25.10.13

    Const. of sector dividing road single carriage way between

    Sec-23/24, U/E, Dharuhera.

    40997-11000 dt.

    25.10.13

    Const. of sector dividing road single carriage way between

    Sec-1B/1 & 1 B & 2 B, U/E,

    Dharuhera.

    40959-62 dt.

    25.10.13 200.00 01.06.2014 592.95 31.03.2015

    Road 45mtr. wide ( single

    carriage way) = 4.70 km. Work completed for 3.20 KM and balance in

    progress

    Const. of sector dividing road single carriage way between

    Sec-22/23, U/E, Dharuhera.

    40992-95 dt.

    25.10.13

    Const. of sector dividing road single carriage way between

    Sec-5A/5B & 5, Dharuhera.

    40982-85 dt.

    25.10.13

    12 Roads in Sec-6 & 7 Rewari 998.93

    CA No. 17619 dt.

    14.7.2014

    400.00 Lacs -- -- -- Road = 9.50 KM Work allotted to contractual agency. The

    demarcation plan of Sec-6&7, Rewari yet to

    be finalized by DTP, Rewari / EO, HUDA,

    Rewari.

    Executive Engineer, HUDA, Division Rewari

    has requested to DTP Rewari & Estate Officer

    Rewari vide No. 10456 dated 02.12.2014,

    10681-86 dt. 08.12.2014, 10960-64 dt.

    17.12.2014, SE-II, HUDA, Gurgaon No.

    15209 dated 04.12.2014 and SE-II, HUDA,

    GGN endst. No. 15992 dt. 22.12.2014.

  • 36

    (A. K. Maken)

    Superintending Engineer,

    HUDA, Circle-II, Gurgaon

  • 37

    PERFORMA P-48A

    STATUS OF MAJOR DEVELOPMENT WORKS HAVING BUDGET PROVISION OF RS. 1.00 CRORE AND ABOVE

    (WHICH ARE LIKELY TO BE STARTED DURING THE YEAR 2014-15) (UPTO 01/2015) HUDA CIRCLE-II, GURGAON

    Sr.

    No.

    Name of work. Estimate cost (Rs in

    lacs)/ appd. No. &

    Date.

    Budget for

    the year

    2014-15

    likely date /

    date of start.

    Upto date

    expdt. upto

    01/2015

    Likely date of

    completion

    Action Plan Remarks

    1 2 3 4 5 6 7 8 9

    Div. No. IV, Gurgaon.

    1 Master SWD Sec-99 to 115,

    Gurgaon.

    16498.00

    CA No. 19709 dt.

    5.8.2014

    500.00 24.12.2014 0.20 23.06.2016 RCC box drain = 46.26 KM Work allotted recently.

    Structural design & drawing under submission.

    2. Const. of 60Mtr & 75 Mtr. Wide

    road From IMT Manesar to

    Pataudi Road (Service Road),

    Gurgaon

    1167.00 Lacs

    200.00 -- -- -- The estimate is under resubmission with Executive Engineer, HUDA, Div. No. IV,

    Gurgaon.

    3. Const. of dividing road Sector-

    9B & 37C, Gurgaon

    807.00 lacs

    CA No. 21897

    dt. 20.08.2014

    300.00 09.09.2014 93.74 08.03.2015 Road in two lane of 12.50 M &

    surface drain = 1.70 Km 80% earth work completed.

    15% GSB completed.

    Now work is held up due to court case.

    4. Const. of dividing road Sector-

    37C & 37D, Gurgaon

    855.77 lacs

    CA No. 17210-13

    Dt. 10.07.2014

    500.00 21.08.2014 69.89 20.02.2015 Road in two lane 12.50M each

    and surface drain = 1.47 Km 35% earth work completed.

    20% GSB completed.

    20% WMM completed.

    DIV. NO. VI, Gurgaon.

    5 Const. of balance Master Road

    dividing Sector 50/57, Gurgaon.

    155.45

    C. A. No.

    1352 dt 14.01.14

    100.00 11.04.2014 95.04 Work

    completed

    7.50mtr wide road both side,

    central verge & footpath = 0.405

    Km

    Work Completed.

    (A. K. Maken)

    Superintending Engineer,

    HUDA, Circle-II, Gurgaon

  • 38

    P-47A

    STATUS OF MAJOR DEVELOPMENT WORKS HAVING BUDGET PROVISION OF RS. 1.00 CRORE AND ABOVE (WHICH ARE LIKELY TO BE

    COMPLETED IN DURING THE YEAR 2014-2015)

    HUDA CIRCLE, HISAR UPTO 01/2015 Sr. No.

    Name of Work

    Estimated Cost

    (Rs. In

    Lacs) App. No. &

    Date

    Budget for the year 2014

    2015 (Rs. In Lacs)

    Date of start

    Upto date Exp.

    (Rs. In

    Lacs)

    Likely date of completion Action Plan

    Remarks

    Original

    Revised

    1. Construction of 20 MLD capacity MPS

    & 10 MLD capacity STP based on SBR process at Jind. (including five years

    maintenance)

    (Phase - I)

    1382.00 32072-76

    Dt.

    5.10.2011

    300.00 01.11.12 1118.34 30.06.13 30.09.14 31.12.14

    Work completed and functional (Electric connection released on 26.12.2014).

    2. Construction of Sports Complex in

    sector-9, Jind

    1205.00 11855-58

    11.03.2013

    200.00 01.09.13 609.12

    31.03.15 Construction of Various courts and Athletic track:- Construction of Volleyball court, Lawn

    Tennis Court, Basket Ball Court, Handball Court, Kho-Kho Court, Kabbadi Court, Through Ball Court Construction of athletic track

    Work allotted vide Executive Engineer, HUDA Division No.-I, Hisar letter No. 13372 dated

    14.08.2013 and the progress is as under :- Athletic Track = 98% completed. Lawn Tennis Courts (2 No) =

    98% completed. Basket Ball Courts (2 No) = 98%

    completed.

    Volley Ball Courts (2 No) = 98% completed.

    Kabbadi Courts (2 No) = 98% completed.

    Hand Ball Courts (2 No) = 98% completed.

    Throw Ball Court (1 No) = 98% completed.

  • 39

    Kho-kho Court (2 Nos) = 98%

    work completed Overall 98% work completed and in

    progress.

    Construction of athletic pavilion :- Work allotted E.E.-I, HUDA Hisar letter No. 3060 dated 19.2.2014

    The work for construction of

    basement completed and further work is in progress. Overall 35% work completed.

    Completion of work Construction of Road & parking Work allotted on 19.06.2014.

    70% work completed and in progress.

    Providing Water Supply, Sewerage & SWD

    DNIT approved on 11.07.2014. Tender opened on 14.08.2014.

    Work allotted on 13.11.2014 and yet to be started.

    HUDA DIVN. NO. II, HISAR

    1. Providing internal

    water supply scheme sec 11 Fatehabad

    392.12 38525-29

    dt 18.10.12

    200.00 01.8.2014 8.8.2014

    58.28 8.8.14 30.11.14 30.04.15

    * Excavation of earth work * Laying of pipe lines

    Work allotted on 8.8.2014. Pipe arranged.

    Work was held up due to agitation of the farmers whose lands has been acquired. Work has been started in January - 2015. 4.50 KM W/S Line laid.

    2.

    Providing

    internal sewerage scheme Sec 11 Fatehabad

    274.63

    40002-05 dt 10.10.13

    150.00 23.12.13 105.34 22.06.14 26.06.14

    15.04.15

    * Excavation of earth work and

    preparation of bed. * Laying of pipe lines and construction of manholes.

    90% work completed and in

    progress. Reason for delay Work was held up due to agitation of the farmers whose lands has

    been acquired. Work restarted recently.

    3.

    Development of roads in residential area across railway line MT Bhattu.

    339.00 30968-71

    dt 08.07.13

    150.00

    13.01.14 257.61 12.07.14 31.10.14 * Earth work and preparation of sub grade. * Providing and laying of GSB * Providing and laying of WMM * Providing and laying of BM&PC * Providing and fixing of K&C

    Work completed.

  • 40

    4. Development

    of Road and parking in Auto market

    MT Bhattu

    360.00

    30952-55 Dt 08.07.13

    150.00

    4.10.13 320.13 03.07.14 10.6.2014 *Providing and laying of BM&PC

    * Construction of pavements.

    Work completed on 10.6.2014.

    PERFORMA P-48A

  • 41

    STATUS OF MAJOR DEVELOPMENT WORKS HAVING BUDGET PROVISION OF RS. 1.00 CRORE AND ABOVE (WHICH ARE LIKELY TO BE STARTED IN THE YEAR 2014 2015 AND TO BE COMPLETED IN SUBSEQUENT YEAR(S)

    HUDA CIRCLE, HISAR UPTO : 01/2015 Sr. No.

    Name of Work

    Estimated Cost

    (Rs.In Lacs)

    App. No.&

    Date

    Budget for the year

    201415 (Rs.In

    Lacs)

    Likely date/

    date of start

    Upto date Exp. (Rs. In Lacs)

    Likely date of

    completion

    Action Plan

    Remarks

    1 Providing external

    SWD scheme in sector-1,3,4,5,23,

    24&MGA, Hisar

    1352.45

    3465.69 25.01.2012

    40.00 10.12.12 541.68 10.12.13

    (Work RCC pipe sewer

    only) 31.12.15

    (For whole work)

    RCC Pipe Sewer From sector to

    Disposal Work :-

    Work completed.

    Construction of Disposal & Pumping Machinery

    0.5 Acre land is to be got transferred from GLF. The case for which under process with Administrator Hisar/LAO, Hisar (Ref. E.E.-I, No. 7617-20 dated 13.5.2013). The case for transfer of the land stand submitted to CTP HUDA, Pkl. Vide Administrator, HUDA Hisar letter No. 12387 dated 1.10.2013. Case

    referred to Director General, Animal Husbandry and Dairying Department, Haryana vide CA, HUDA, Panchkula D.O. reference No. 16143

    dated 19.11.2013. Reminder to C.A. HUDA Panchkula (T.P. Wing) vide Admn. HUDA Hisar Letter No. 11029 Dt. 21.08.2014.

    Construction of Carrier Channel The work will be taken in Hand after transfer of

    land for construction of disposal. and permission of concerned department which has already been applied to forest department vide EE-I, HUDA, Hisar letter No. 9736 dt. 19.06.2013 and NHAI vide EE-I letter No. 10268 dated 28.06.2013 and resubmitted after

    doing the needful vide EE-I, No. 18600-03 dated 28.10.2013

    2.

    Providing internal water supply

    scheme in sector-7, Safidon

    284.02 C.A. No.

    44711-14 Dt. 10.12.13

    100.00 - Single tender received, to be recalled.

    3. Development of roads in sector-8,

    1873.00 CA No.

    400.00 -

  • 42

    Safidon 39636-39

    Dt. 02.10.13

    Single tender received, to be recalled.

    4. Providing internal water supply scheme in sector-8,

    Safidon

    500.45 CA No.

    2216-19

    Dt. 22.01.14

    120.00 - Single tender received, to be recalled.

    5. Providing internal sewerage scheme in sector-8, Safidon

    259.07 CA No. 44119

    Dt. 02.12.13

    100.00 - Single tender received, to be recalled.

    6. Providing internal SWD scheme in sector-8, Safidon

    372.16 CA No.

    1235-38

    Dt. 13.01.14

    150.00 - Single tender received, to be recalled.

    7. Development of roads in sector-9,

    Safidon

    997.00 Revised to

    Rs. 1288.46 Lacs

    (U/A)

    300.00 - The estimate has been revised amounting to Rs. 1250.20 Lacs as per observations of PWD B&R

    Department and under process.

    8. Providing internal water supply scheme in sector-9, Safidon

    289.26 CA No. 44114

    Dt. 02.12.13

    100.00 - Single tender received, to be recalled.

    HUDA DIVISION NO. II, HISAR

    1. Providing external

    water supply scheme in sector-

    19P, 20 & 21 Sirsa.

    2214.00

    40462

    dt. 12.10.2012

    600.00 15.10.13 250.75

    15.04.15

    31.10.15

    Time = 18 months

    Action plan as per execution schedule given by the agency on 05.06.2014.

    a) Work Upto 31.07.2014. Preparation and approval of hydraulic and structural design

    b) Work Upto 31.12.2014. (i) S & S tank:- 50% Excavation work,

    Work allotted on 10.10.2013. Hydraulic design

    approved structural design approved.

    S&S Tank:- 80% work of excavation of earth work

    com