County of Fairfax, VirginiaCounty of Fairfax, Virginia

Department of Transportation

Huntington Area Transportation Study (HATS)

Project Update

Presented to:

Fairfax County Board

Transportation Committee

January 20, 2015

County of Fairfax, Virginia

Department of Transportation

2

Study Purpose

• Address transportation deficiencies identified during prior

comprehensive planning efforts (Huntington Club, North Gateway

APRs)

• Confirm and verify existing and future (projected) transportation

issues and concerns within the HATS study area

• Develop transportation improvement strategies and mitigation

measures with stakeholder and BOS input

• Evaluate the effectiveness of potential transportation solutions

• Assess potential at-grade solutions, in addition to grade-separated,

at Route 1/Huntington Avenue/Fort Hunt Road

• Evaluate proposed higher land use intensity at North Gateway

• Determine recommendations and conclusions

County of Fairfax, Virginia

Department of Transportation

3

County of Fairfax, Virginia

4

County of Fairfax, Virginia

Key Issues• Several large-scale, high-intensity Transit Oriented Development

(TOD) sites recently approved that may negatively impact the

feasibility of further TOD within the Huntington Transit Station Area

(TSA)

• Desire for an at-grade solution for the intersections of Route 1 and

Huntington Avenue and Fort Hunt Road, rather than the grade-

separated interchange currently in the Comprehensive Plan

• Proposal for higher land use intensity at the North Gateway site with a

need for expedited results to respond to evolving market conditions

and support on-going revitalization efforts

• Traffic issues within the Penn Daw CBC – Note that a separate effort

to identify improvements along North Kings Highway is nearly

complete and results will be incorporated

5

County of Fairfax, Virginia

Department of Transportation

6

Study Overview

• Multimodal Existing Conditions Analysis & Assessment

• Multimodal Model Development & Future Conditions Analysis & Assessment

• Detailed Analysis of Route 1/Huntington Ave/Fort Hunt Rd Intersections

o Evaluation of At-Grade & Grade-Separated Concepts

• Identification of Congestion Reduction Strategies and Mitigation Measures

• Evaluation of Alternative Land Use for North Gateway Site

• Conclusions & Recommendations

*** Stakeholder input will be obtained throughout study ***

County of Fairfax, Virginia

Department of Transportation

7

Measures of Effectiveness (MOEs)• Evaluation criteria to gauge existing and future performance

o Average delay per vehicle by intersection and for individual

approach movements

o Queue length and storage for critical individual approach

movements

o Level of Service by intersection and for individual approach

movements

o Average delay per vehicle within the network

o Average speed within the network

o Average travel time within the network

o System-wide delay

*** AM and PM peak hours ***

County of Fairfax, Virginia

North Gateway Site• The North Gateway Site was recently approved by the board for a 1.65

Floor Area Ratio (FAR), with further desire for a 2.0 FAR

• Located adjacent to the intersections of Route 1 and Huntington

Avenue and Fort Hunt Road, it is unlikely that site can develop to its full

potential if a grade-separated interchange is constructed

• Several BRAC and South County Area Plan Review (APR) nominations

have been approved by the County in the Huntington core area

• Certain APRs were analyzed and approved contingent on a planned

interchange at the Route 1 intersections with Huntington Avenue and

Fort Hunt Road

• Citizens and community have concerns about development of an

interchange

• Study will analyze at-grade and grade-separated concepts

• Study will meet VDOT traffic impact analysis requirements

8

County of Fairfax, Virginia

Draft At-Grade & Grade-Separated Concepts

9

• At-grade and grade-separated concepts to be evaluated for the

intersections of Route 1 at Huntington Avenue and Fort Hunt Road

• Multiple concepts under development

• None of these concepts have been tested

• Staff is not making a recommendation at this time

• Two at-grade and two grade-separated concepts will be selected for

more detailed analysis

• Looking for initial feedback on elements associated with current set of

draft concepts

Replace left turn lanes with median and exclusive right

(for Huntington Ave rights/lefts/U-turns)

No Right Turns (1 left,

2 thru)Install signs:

NB Route 1 = straight. SB Route 1 = left.

All U/left turns from SB

Route 1

Remove left turn concrete barrier.

Shift lanes if possible/necessary

to add dual right turn lanes.

No left/right turns Closed roadway

Existing traffic signal

Install Yield Signs for I-495

Off Ramp

At-Grade Option A: Route 1 Left Turn Movements Prohibited

Optional right-in/right-out access to

Route 1

xxx10

At-Grade Option B: “Superstreet” with Side Street Left Turn & Through Movements Prohibited

Optional New Median

Break & Signal

3 thru, 1 shared

thru/right

Or New Signal at Existing Break

Right turn on red prohibitions are recommended during peak hours to reduce the speed differentials on Route 1, unless add lanes can be used.

New traffic signal Closed roadway

Existing traffic signal

Provide access to North Gateway

development here

Provide left out signalized

movement here

I-495 Ramps

Install signs: NB Route 1 = straight.

SB Route 1 = left.

xxx 11

At-Grade Option B: “Superstreet” with Side Street Left Turn & Through Movements Prohibited

Right turn on red prohibitions are recommended during peak hours to reduce the speed differentials on Route 1, unless add lanes can be used.

New traffic signal Closed roadway

Existing traffic signal

Optional new median break & signal or new signal at an existing

median break

Provide left out signalized

movement here

xxx 12

At-Grade Option B: “Superstreet” with Side Street Left Turn & Through Movements Prohibited

Right turn on red prohibitions are recommended during peak hours to reduce the speed differentials on Route 1, unless add lanes can be used.

New traffic signal Closed roadway

Existing traffic signal

3 thru, 1 shared thru/right

Provide access to North Gateway

development here

Provide left out signalized

movement here

xxx 13

At-Grade Hybrid (A-B) Option: Route 1 to Fort Hunt Left Turns Shifted to Huntington

Install signs: NB Route 1 = straight.

SB Route 1 = left.

Existing traffic signal Closed roadway

Widen roadway/decrease median width to provide dual left;

may extend storage to Fort Hunt

Provide access to North Gateway

development

1 left, 1 thru, 1 shared thru/right,

1 receiving lane

Right-In/ Right-Out

For this Hybrid Option, Route 1/Fort Hunt Rd operates better. The other two intersections operate slightly worse. Overall, there is a small 3-5% increase in the CLV & v/c ratios when compared to the No Build.

Provide access to North Gateway

development

Realign Old Richmond Hwy to provide block-like jughandle access

I-495 Ramps

14

County of Fairfax, Virginia

Displaced Left Turn (DLT) Intersections

15

County of Fairfax, Virginia

Displaced Left Turn (DLT) Intersections

16

At-Grade Option C: Partial Displaced Left Turn Intersection

1 shared thru/right, 2 exclusive right

turn lanes

1 left, 2 thru, 1 right,

1 receiving lane

New traffic signal Existing traffic signal

Optional access to North Gateway

Install signs: NB Route 1 = straight.

SB Route 1 = left.

17

At-Grade Option C: Partial Displaced Left Turn Intersection

New traffic signal Existing traffic signal 18

At-Grade Option C: Partial Displaced Left Turn Intersection

New traffic signal Existing traffic signal No left turn Optional no left turn 19

Grade-Separated Option D: Woodrow Wilson Bridge Project – Alternate 1

Route 1 (Richmond Highway)

20

Grade-Separated Option E: Huntington Avenue Interchange

Route 1 lowered. Bridge over Huntington Rd raised. NB Fort Hunt to SB Route 1 prohibited. (24 veh in AM, 30 veh in PM)

Left turns to Fort Hunt, exit right

All left turns to Fort Hunt Road

Provide a thru lane & dual right

lanes.

Provide two receiving

lanes.

Provide two thru lanes & an exclusive right

turn lane

Two phase signal

Left turns to Huntington,

exit left

Configure westbound

to allow left/thru/right

movements

Route 1 (Richmond Highway)

21

Grade-Separated Option F: Single Point Urban Interchange (SPUI)

Provide access to North Gateway:

right-in/right-out onto ramp

New traffic signal Existing traffic signal Closed roadway

Connect Huntington Rd

to Cameron Run Terrace

Route 1 lowered. SPUI raised. Through movements on Route 1 are uncontrolled. xxx 22

County of Fairfax, Virginia

Project Schedule – 2014/2015

23

Jun-Sep 2014

• Existing Conditions Assessment (Complete)

• Travel Demand Model Development (Complete)

Oct-Feb 2014/15

• Model Assessment (Complete)

• Detailed Route 1/Huntington/Fort Hunt Analysis

Feb-May 2015

• Identification & Evaluation of Mitigation Measures

• Identification of Interchange Solution

• North Gateway Land Use Assessment

• Recommendations & Conclusions

County of Fairfax, Virginia

Questions / Comments

Arpita Chatterjee & Thomas Burke