hydraulic & hydrology study report peshawar tortham
TRANSCRIPT
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
CONSULTANCY SERVICES
PERTAINING TO FEASIBILITY STUDY
AND PRELIMINARY DESIGN OF
PESHAWAR - KABUL MOTORWAY
HYDRAULIC & HYDROLOGY STUDY REPORT
Peshawar Tortham Motorway- Section I
Submitted to: National Highway Authority
July2017
Submitted by:
Associated Consultancy Centre (Pvt.) Ltd. (ACC) in association
with SAMBO Engineering Co. Ltd. (South Korea),
ACE-TES Lahore & Assign International
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
ii
TABLE OF CONTENTS
Summary ................................................................................................................... v
CHAPTER-1 ................................................................................................................ 1
BACKGROUND .......................................................................................................... 1
1.1 Peshawer Tortham- Section I ........................................................................... 2
CHAPTER-2 ............................................................................................................... 3
OBJECTIVE AND SCOPE OF STUDY ............................................................................ 3
CHAPTER-3 ............................................................................................................... 4
DESCRIPTION OF STUDY AREA ................................................................................ 4
CHAPTER-4 ............................................................................................................... 7
HYDROLOGICAL INVESTIGATION ............................................................................. 7
4.1 General ........................................................................................................... 7
4.2 Climatic Characteristic Analysis ...................................................................... 7
4.3 Rainfall Frequency Analysis .......................................................................... 10
4.4 Rainfall-Runoff Method ................................................................................ 14
CHAPTER-5 .............................................................................................................. 15
HYDRAULIC INVESTIGATION .................................................................................. 15
5.1 Hydraulic Analysis for Major Streams and Nullahs ....................................... 15
5.2 Hydraulic Analysis for Cross-Drainage Structures/ Culverts ......................... 20
5.3 Hydraulic Design Analysis for Side Channels ................................................. 29
CHAPTER-6 ............................................................................................................. 32
FINDINGS & RECOMMENDATIONS .......................................................................... 32
References ................................................................................................................ 33
ANNEXURES............................................................................................................. 34
Annexure A: Historical Climatic Data for Peshawar ................................................ 35
Annexure-B: Catchments Delineation of Major Streams/ Nullahs ............................ 39
Annexure-C: Hydrologic and Hydraulic Parameters relating Bridges over Major Streams/ Nullahs ..................................................................................................... 50
Annexure-D: Hydraulic Outputs of Major Streams/ Nullahs .................................... 53
Annexure-E: Scour Depth Estimation by Lacey Regime Theory .............................. 64
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
iii
LIST OF FIGURES
Figure 1: Location of Peshawar-Torkhum Road ........... Error! Bookmark not defined.
Figure 2: Geo-referenced location of proposed alignment under study ..................... 3
Figure 3: Peshawar-Torkhum Proposed Alignment Location Map ........................... 4
Figure 4: Average Temperature Pattern ................................................................... 8
Figure 5: Average Rainfall Patter .............................................................................. 8
Figure 6: Long Term Maximum Temperature Pattern in Study Area ........................ 9
Figure 7: Long Term Minimum Temperature Pattern in Study Area ......................... 9
Figure 8: Long Term Annual Rainfall Pattern in Study Area ................................... 10
Figure 9: Hydrology of Study Alignment .................................................................. 11
Figure 10: HEC-SSP Computer Modei ....................................................................... 12
Figure 11: Rainfall Frequency Curve for Study Alignment (Gumbel) ........................ 12
Figure 12: Rainfall Frequency Curve for Study Alignment (GEV) ..............................13
Figure 13: Computer Model HEC-HMS ...................................................................... 14
Figure 14: Scheme of runoff generation due to rainfall ............................................ 29
Figure 15: Scheme of protective measures for the road ............................................ 30
Figure 16: Schematic of Drop Structure along embankment .....................................31
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
iv
LIST OF TABLES
Table 1: Rainfall Estimates of Standard Return Periods (in mm) ..............................13
Table 2: Flood Characteristics through the proposed bridges along alignment ......... 17
Table 3: Proposed X- Drainage Structures ................................................................ 21
Table 4: Schedule of Proposed X-Drainage Structures .............................................. 22
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
v
Summary
The trade via Afghanistan towards Central Asian countries and from Arabian sea has been centuries old activity through road connectivity. With the passage of time, the traffic has increased tremendously, exerting pressure on existing road infrastructure, arising need for an improved road infrastructure from Peshwar to Torkham to meet the expanding communication needs, especially after CPEC (China-Pakistan Economic Corridor) initiative. The current hydrological investigation is carried out to study the hydrological regime and allied impacts for safe development and operation of Peshawar-Torkham Expressway (approx 47 km) in the northern part of the Khyber Pakhtunkhwa province of Pakistan.
The Peshawar-Torkham proposed alignment falls in the areas mainly in terrains with barren and rugged mountains where several small streams and nullahs cross the alignment. The area falls in the climate mostly under semiarid Mediterranean influence and less monsoon effects with annual total around 400 mm. The average temperature in summer varies from 18 to 40 oC whereas the winter average temperatures range from 2 to 25 oC. However, the extreme temperatures could be below 0 oC in winters and more than 40 oC in summers. The long term temperature analysis (1974 to 2015) does not present any major deviation in the temperatures both in summer and winters. Whereas long term rainfall pattern shows an increasing trend in annual totals due to the fact that monsoon rains are moving upward towards northern parts of the country. However, the study alignment moves further upward, where such impact would not be that significant as Mediterranean disturbances having more influence in upper parts of the alignment.
Based on the rainfall and runoff analysis in connection with the topography of the area, there have been proposed 22 bridges to safely pass the runoff generated from the upstream and adjoining areas. The design parameters for the bridges have been provided based on hydraulic analysis under the study in order to pass the standard floods safely (100-year). For bridges over major streams and nullahs, scour depth analysis have also been provided. Similarly, for overland flow and minor natural channels, 132 culverts have been proposed (including modification of 11 existing ones) for which design parameters are also provided to safely pass standard flood of 50-year recurrence interval.
The road is located in the range where topography varies from mild to steep. The road may come mostly under the effect of direct flow from the hills in the form of torrents as flash flood; also carrying mud/boulders on its way. To avoid this, drainage channels along the road on hill sides connected to the nearest x-culverts may be provided to protect the road, for which design has also been proposed. The overland flow from the road itself may be passed through road-side drop structure and connected to corresponding culvert or existing conveyance system (watercourse or drain). In the design of culverts, there has been kept cushion for such overland flow from the road itself, giving 20% (0.2 to 0.3 m) freeboard for all culverts.
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
1
CHAPTER-1 BACKGROUND The subject road is connecting Peshawar with Kabul through Torkham and Jalalabad.
Peshawar is the capital of Khyber Pakhtunkhwa and the administrative centre and
economic hub for the Federally Administered Tribal Areas of Pakistan. Peshawar is
situated in a large valley near the eastern end of the Khyber Pass, close to the Pak
Afghan border. Known as “City on the Frontier”, Peshawar’s strategic location on the
cross roads of Central Asia and South Asia has made it one of the most culturally vibrant
and lively cities in the greater region. Peshawar is connected to Motorway system of
Pakistan through Motorway M-1.
Peshawar Northern Bypass having a definition of 4-lane dived Expressway provides link between Motorway M-1 and Start Point of Peshawar – Kabul Motorway. Total Length of the existing road from Peshawar (Hayatabad) to Kabul (Abdul Haq Square) is approximately 281 KM (Project alignment between Peshawar and Kabul is shown in Figure 1). The project is divided into following three sections:
Table 1: Project Sections
Sr. No. Section Name of Section Length (KM)
1 Section - I Peshawar – Torkham (Pakistan) 50
2 Section – II Torkham – Jalalabad (Afghanistan) 76
3 Section - III Jalalabad –Kabul (Afghanistan) 155
Figure 1: Existing Alignment of Peshawar-Kabul Project
From Peshawar to Torkham, the terrain is very difficult in some reaches where the alignment mostly follows valleys and hill slopes. Although the design is completed by
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
2
NHA for the section between Peshawar and Torkham but it is envisaged that the consultant shall provide further value addition and improvement. From Torkham to Jalalabad the existing 2-lane is being upgraded to 4-lane by FWO. The work is held up due to various reasons, it shall now be redesigned/upgraded to Motorway Standard. The distance from Torkham to Jalalabad is 76 Km. From Jalalabad to Kabul using Kabul – Nangarhar Highway the existing road measures 139 km. The terrain is mountainous with hard rock and steep vertical slopes. Especially about 50 km section after Sarobi. It is envisaged that total Motorway length shall be around 265 Km1. Tunnels exist in Afghanistan section of the Highway.
1.1 Peshawar- Torkham, Section I
In the first phase, the Consultant has been advised to carry out feasibility study and
preliminary design of Peshawar-Torkham Section. The Consultant have studied various
alignment alternates in order to achieve stipulated motorway standards. Options of
provision of tunnels in mountainous reach was also investigated. Final proposed
Motorway alignment from Peshawar-Torkham is shown in Figure 2.
Figure 2: Project Alignment of Peshawar-Torkham (Section-I)
On completion of alignment study, requirement of cross drainage structures has been
investigated and preliminary design of structures has been carried out. The subject
report has been prepared as the "Hydrology & Hydraulic Study Report" for Peshawar-
Torkham Section as required by the deliverables of the TOR of the project.
1As per TOR the length is 281 km.
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
3
CHAPTER-2 OBJECTIVE AND SCOPE OF STUDY
The main objective of the study is to carry out hydrological investigations with
reference to the proposed alignment from Peshawar to Torkham in Khyber
Pakhtunkhwa province of Pakistan, expanding over a length of about 47 km. The
specific scope of the study however is:
1. To carry out hydrological investigation with the analysis of rainfall and
flood records supplemented by detailed field investigations for
development of new road alignment and providing required
2. Analyze and propose required cross-drainage structures for the safe
development and operation of the proposed alignment such as bridges,
culverts, support structures etc. against standard flood conditions (100
years for bridges and 50 years for culverts)
3. Submit recommendations based upon concise analysis supported by field
data for embankment, crossing/ drainage bridges, culverts etc. along the
proposed alignment.
The flyovers and other road crossing bridges are not discussed being not scope
of study. The geo-referenced location of the subject road is shown in Figure 2.
Figure 3: Geo-referenced location of proposed alignment under study
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
4
CHAPTER-3 DESCRIPTION OF STUDY AREA
The proposed alignment from
Peshawar to Torkham would be a
major road of about 47 km. This
existing single carriageway (N-5)
provides access from Peshawar to
Torkham. However, the expanding
traffic load demands an expressway
for smooth transportation of goods to
and from Afghanistan and onwards.
The proposed 4-lanes dual alignment
starts from Peshawar near Jamrud and
approx 4 km from Peshawar Ring Road (Figure 3). It runs parallel to the existing
N-5 whereas the distance apart varies from 0.5 to 2 km with terrain varying in
elevation. The proposed alignment crosses several small and medium streams
and nullahs (perennial/ non-perennial) where crossing bridges and drainage
structures would be required. Such considerations would be of importance to be
taken care for the safety of the road.
Figure 4: Peshawar-Torkham Proposed Alignment Location Map
Proposed Alignment
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
5
The climate of the area in which the new alignment falls is semiarid subtropical
continental highland type. The mean annual rainfall is approximately 450 mm, of
which 200 mm falls in March and April, with warm summers and cool winters. The
area falls out of the monsoon belt where the major portion of rainfalls occurs due
to western disturbances. The average daily maximum temperature of the hottest
month is 36°C and the average daily minimum of the coldest is -0.5°C.
The study alignment mainly falls in the Khyber Agency – Federally Administered
Tribal Areas. This the geological region of Pre-aravallis, metamorphic in general
including Precambrian and younger intrusions. The massive grey limestone with
sand and clay beds that makes up the Carboniferous Khyber Formation and the
slate, phyllites and schists with minor limestone and quartzite beds of the
Ordovician-Silurian Landi Kotal Formation in the eastern part of the Khyber
Agency. Mesozoic sediments occur in the western part of the Khyber Agency
(Kruseman and Naqvi, 1988). Near Warsak on the boundary with the Peshawar
Vale is a granite intrusion (Shah et al., 1980). In the western part Jurassic
limestone has been found (Meissner at al.,1975).
The Khyber Agency is mountainous without any well developed alluvial plain.
According to the available information, approximately 20 test-and tube wells have
been drilled in different valleys. The lithological data on two boreholes in the
Jamrud – Landi Kotal area indicate an ill-sorted mixture of clay and gravels,
probably with low transmissivity values. The depth to water level is quite large
(more than 30 m). If these boreholes are representative of the whole area, then
the groundwater development is not viable (Kruseman and Naqvi, 1988).
The land use is generally mild hilly terrain with barren and rugged mountains,
without a well-developed alluvial plain. However, the green valleys are also seen.
But it also has some beautiful valleys with plain cultivable lands. The elevation
varies from about 396 to 1050 along the alignment however, the hills are higher
than these. The soils are derived mainly from the local weathering of bedrock,
deposited by streams and rivers, though loess also occurs to some extent.
Landforms in the area are varied and include piedmont, plains, valleys, gravel
fans, rough broken land and gullied land. Level areas are loamy, while lowlands
are slightly to strongly calcareous. The content of organic matter and available
phosphorus is very low.
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
6
The population is scattered in the area with minimal road and other civil facilities.
Due to recent insurgencies in the FATA areas, it is also badly affected due to
refugees affecting the natural land use/ land cover of the area. The development
of new highway will play a major role in the development of this under-privileged
area as well as help further developing the trade.
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
7
CHAPTER-4 HYDROLOGICAL INVESTIGATION
4.1 General
The hydrological investigation under the current study has been carried out to
analyze the climate cum flow regime in connection with the development of
Peshawar to Torkham highway extending over a stretch of 46 about. For such
development it is necessary to take all necessary deign and protection measures
for safe operation of the road after its development for its service life. The design
considerations and measures could be: appropriate embankment/ alignment,
cross drainage structures including bridges, culverts and drops structures to
safeguard against possible rainfall/ flooding or surface runoff, and inundation
impacts. For such type of structures, the recurrence interval is generally adopted
as 100 year for large bridges and 50 year for small structures and culverts
(Mutreja, 1990).
The land use layout of proposed alignment is such that it mainly passes through
mountainous terrains where the runoff flux due to rainfalls could be either from
the hills along the road or the natural steams or nullahs crossing the alignment.
This section therefore focuses to estimate the runoff flux to the road alignment so
that the protective measures and cross-drainage structures could be proposed to
safeguard the alignment. For this purpose, there could be two different
approaches or sometimes the combination of both to estimate the runoff
magnitude of standard return periods viz. i) Discharge frequency analysis using
observed data, and ii) well practiced and acceptable rainfall-runoff methods
making use of observed rainfall which is mostly available along with physical
characteristics of the catchment areas from where the runoff is generated. Such
hydrological analyses have been presented hereafter.
4.2 Climatic Characteristic Analysis
The study alignment falls in the arid to semi-arid region. In order to analyze the
climatic characteristics of area, it was explored to find weather data source or
climatic station in the area exit in such area. The Peshawar is the only climatic
station where Pakistan Meteorological Department has long term rainfall and
temperature record which has been obtained accordingly and analyzed under the
current study from 1974 to 2015 (41 years). The average temperature pattern
shows that the summer temperatures vary from 18 to 40 oC whereas the winter
average temperatures range from 2 to 25 oC (Figure 4). However, the extreme
temperatures could be below 0 oC in winters and more than 40 oC in summers.
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
8
The rainfall is due to more Mediterranean influence and less monsoon effects
with annual total around 400 mm (Figure 5).
Figure 5: Average Temperature Pattern
Figure 6: Average Rainfall Pattern
The temperature extremes were analyzed for study area as it plays significant
role in the material selection. For this purpose, long term annual maximum and
minimum temperatures were analyzed from the observed temperature data and
the results are shown in Figure 6. The general trend shows that during summer
the maximum temperature is higher than 45 oC with extremes of 48 oC. However,
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
9
looking at long term averages, no significant rise in maximum temperature is
observed (1974 to 2015). However, for winter temperatures, if we ignore the
outlier of year 2012 (15 oC), the average trend almost remains the same over the
period of 1974 to 2015.
Figure 7: Long Term Maximum Temperature Pattern in Study Area
Figure 8: Long Term Minimum Temperature Pattern in Study Area
Whereas long term rainfall pattern shows an increasing trend in annual totals
(Figure 8). This is due to the fact that monsoon rains are moving upward towards
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
10
northern parts of the country – the unprecedented flood of 2010 and thereafter.
However, the study alignment moves further upward, where such impact would
not be that significant as Mediterranean disturbances having more influence in
upper parts of the alignment.
Figure 9: Long Term Annual Rainfall Pattern in Study Area
4.3 Rainfall Frequency Analysis
The alignment falls in the area where there are several small and medium
streams crossing the proposed alignment (Figure 9). The frequency analysis of
historical floods records if available plays significant role in hydrological studies to
analyze the flooding threat from nearby or crossing rivers/ streams to a point of
interest in terms of flood magnitude, its inundation effects and flood elevation.
This also allows deciding viable protection measures and suggesting x-drainage
structures. There are 22 locations where x- drainage bridges are proposed and
132 sites where culverts are identified. However, there is neither possible
gauging for discharge measurement nor any long term discharge record exists in
the area.
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
11
Figure 10: Hydrology of Study Alignment
Alternatively, long term rainfall extreme events play significant role to estimate
the standard rainfalls (100, 50, or 25 years). These standard rainfalls would be
then used to convert into runoff using standard rainfall-runoff methods, such as
SCS Synthetic Unit Hydrograph method. Therefore, under the current study, such
approach was followed. For the estimation of rainfall of standard recurrence
intervals, Generalized Extreme Value Distribution (GEV) is mostly used. In this
case, it is Type-I i.e. Gumbel Distribution for extreme events (a two parametric
distribution) which is well suited for most Pakistani catchments especially relating
frequency analysis. The frequency analysis of observed annual maximum
rainfalls (1974 to 2015) was carried out using widely accepted HEC-SSP
software developed by US Army Corps of Engineers (Figure 10). This ensures
more rigorous analysis for better decision making. The estimated rainfall
frequency curves are shown in Figure 11 (Gumbel) and Figure 12 (GEV).
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
12
Figure 11: HEC-SSP Computer Model
Figure 12: Rainfall Frequency Curve for Study Alignment (Gumbel)
Probability
0.9999 0.999 0.99 0.9 0.5 0.2 0.1 0.02 0.005 0.001 0.0001
Return Period
1.0 1.1 2 5 10 50 200 1000 10000
An
nu
all
Ma
xim
um
Ra
infa
ll (1
97
4-2
01
5)
in m
m
10.0
100.0
1000.0
General Frequency Analytical Plot for Rainfall at Peshawar
Computed Curve Expected Probability Curve
5 Percent Confidence Limit 95 Percent Confidence Limit
Observed Events (Weibull plotting positions) High Outlier
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
13
Figure 13: Rainfall Frequency Curve for Study Alignment (GEV)
The rainfall estimates for standard return periods of 50-year and 100-year are
drawn in Table 1, which indicate difference in standard rainfall estimates as 14%
to 21% between Gumbel and GEV distributions. However, for rainfall frequency
analysis relating major events, a recent global survey on the distribution of annual
maxima of daily rainfall by Apalexiou and Koutsoyiannis (2012) have provided
that GEV (Log Pearson Type III) distribution is most suitable for large return
periods. Therefore, the maximum estimates were adopted under the current
study and also in the light of increasing rainfall trends in Figure 4.
Table 1: Rainfall Estimates of Standard Return Periods (in mm)
S.No. Distribution 50-Year 100-Year
1 Gumbel 177 204
2 GEV 201 248
Difference 14% 22%
Probability
0.9999 0.999 0.99 0.9 0.5 0.2 0.1 0.02 0.005 0.001 0.0001
Return Period
1.0 1.1 2 5 10 50 200 1000 10000
An
nu
all
Ma
xim
um
Ra
infa
ll (1
97
4-2
01
5)
in m
m
10.0
100.0
1000.0
General Frequency Analytical Plot for Rainfall at Peshawar
Computed Curve Expected Probability Curve
5 Percent Confidence Limit 95 Percent Confidence Limit
Observed Events (Weibull plotting positions) High Outlier
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
14
4.4 Rainfall-Runoff Method
The standard rainfall estimates made in Section 4.3 were converted into runoff of
standard return periods (100 and 50 years) to analyze the behavior of floods in
relation to the alignment either through crossing steams for determining
clearance and size of bridges or suggesting structures like culverts for drainage
purposes. For this, SCS Synthetic Unit Hydrograph method was used to carry out
rainfall-runoff analysis using HEC-HMS Computer Model (Figure 13) to simulate
floods of desired return periods at points of interest along the proposed
alignment. For this purpose, GIS applications were made for estimating the
catchments characteristics (watershed area, main stream length, average slope,
land use etc.) used as input in the model (Annexure-B).
Figure 14: Computer Model HEC-HMS
All such discharge estimates from each identified crossing stream and small
catchments overland flow to the alignment, were studied through hydraulic
analysis presented in the coming sections. This was done in order to see the
impact to the alignment and suggest accordingly the protective measures and
design parameters for necessary drainage structures.
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
15
CHAPTER-5 HYDRAULIC INVESTIGATION
5.1 Hydraulic Analysis for Major Streams and Nullahs
The main objective of this investigation was to analyze the behavior of potential
flood from major streams and nullahs passing the subject Peshawar-Torkham
proposed alignment in order to see the impact of flooding on the alignment and
assess the capacity of required bridges and drainage structures. This would help
suggesting the bridge design, embankment height and/or allied protection
measures. Using the detailed topographic, cross sectional and longitudinal profile
data, it is possible to study the flood behavior/ inundation extent and suggest
measures under given potential flood conditions.
In order to carry out the
hydraulic study, the analysis
was carried out using HEC-
RAS Hydraulic Model
because of its wide range
applicability. The US Army
Corps of Engineers’ River
System (HEC-RAS 5.01)
model allows performing
multi-purpose one and two-
dimensional steady and
unsteady flow river
hydraulics analysis. The
model was applied in the
current study to analyze the
flow profiles of potential
flood (100-year in this case)
along the alignment..
In order to model the potential floods behavior through the proposed 22 bridges
and crossing streams, the following data were provided as input to HEC-RAS
model;
Observed X-sectional data at 100 m intervals from upstream (1.0 km) and
downstream (0.5 km) of the alignment
Existing structures and protections
Average slope of reach
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
16
Magnitude of flood/ discharge (100-year) at the starting point of each study
reach
Manning’s roughness coefficient for natural streams taken as n= 0.025
Known highest flood marks from the physical field conditions for
calibration/validation purposes.
The existing alignment and ground NSL
The model was run simultaneously in calibration/ validation process and the final
outcomes of the modeling results were drawn in Table 2, wherein the finish levels
of the road have been proposed in contrast to the highest flood levels through the
proposed bridges, keeping in view the safety of the proposed highway. The
hydraulic parameters for the bridges over these streams and nullahs are also
given in Annexure-C, whereas the hydraulic model outputs are given in
Annexure-D for further elaboration.
All the bridges have been so proposed to have sufficient capacity as the floods in
these areas also bring lot more mud and boulders along due to bare mountains
and steep slopes. For this purpose, the scour depth calculations have also been
made using Lacey Regime Theory (Lacey, 1946). The conditions of Lacey’s
regime are very rarely achieved and are very difficult to maintain in practice.
However, in rivers and streams only in bank full stage or high flood conditions, it
may be considered to achieve temporary or quasi-regime. The recognition of this
fact can be utilized to deal with the issues concerning scour and floods. The total
scour depth for each proposed bridge is therefore given in Table 2, whereas the
estimations are also provided in Annexure-E. As per general rule, the piling depth
for bridges is taken as double the scour depth.
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
17
Table 2: Flood Characteristics through the proposed bridges along alignment
S.#.
RD/ Location on
Pesh-Torkhum
Road
Structure Type
Location/ Name of stream
Bridge Size
Catchment Area
100-year discharge/ design capacity
Deck Level (top of road)
Highest Flood Level
Total Scour Depth
km Cell x
Span (m) km
2 cumecs cusecs m m m
1 7+060 Bridge Chaura Khwar near
Jamrud 7 x 40 425.31 2356 83119 497.225
481.00 (481.00)
8.02
2 8+650 Bridge Nullah 1 x 30 0.53 12.72 449 542.500 532.780
(532.790) 1.26
3 8+890 Bridge Nullah 1 x 40 0.73 17.50 617 542.500 537.060
(537.060) 1.33
4 9+580 Bridge Nullah 1 x 40 1.41 34 1197 543.86 538.110
(538.110) 1.96
5 21+920 Bridge Khyber Khwar at Ali
Masjid 2 x 40 70.00 341 12016 758.966
753.670
(753.670) 4.21
6 22+560 Bridge Khyber Khwar (RD22+560)
2 x 30 69.80 340 11995 785.351 772.00
(772.00) 3.11
7 22+765 Bridge Khyber Khwar (RD22+765)
2 x 25 69.60 339 11960 785.63 779.100
(779.10) 3.42
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
18
S.#.
RD/ Location on
Pesh-Torkhum
Road
Structure Type
Location/ Name of stream
Bridge Size
Catchment Area
100-year discharge/ design capacity
Deck Level (top of road)
Highest Flood Level
Total Scour Depth
km Cell x
Span (m) km
2 cumecs cusecs m m m
8 23+950 Bridge Khyber Khwar (RD23+950)
4 x 30 63.00 307 10831 810.38 803.910
(803.900) 4.07
9 24+700 Bridge Nullah 2 x 35 7.70 92.3 3257 828.000 824.50
(824.50) 1.85
10 25+615 Bridge Khyber Khwar (RD25+615)
1 x 40 56.00 273 9613 840.540 836.170
(836.17) 3.12
11 25+810 Bridge Chingai Khwar 2 x 20 3.29 79 2780 870.000 867.030
(867.000) 2.59
12 28+700 Bridge Kagga Khwar at
Wali Khel 2 x 30 8.45 145 5113 956.000
953.100
(953.190) 3.17
13 30+460 Bridge Dand Khwar 1 x 25 9.00 154 5449 962.000 958.630
(958.630) 2.98
14 33+000 Bridge Bori Khwar 1 x 20 6.80 117 4117 1006.000 1003.660
(103.660) 2.87
15 33+587 Bridge Sawal Khwar 1 x 20 9.00 154 5449 1017.000 1013.66
(1013.660) 3.05
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
19
S.#.
RD/ Location on
Pesh-Torkhum
Road
Structure Type
Location/ Name of stream
Bridge Size
Catchment Area
100-year discharge/ design capacity
Deck Level (top of road)
Highest Flood Level
Total Scour Depth
km Cell x
Span (m) km
2 cumecs cusecs m m m
16 35+002 Bridge Nullah 1 x 25 1.36 32.8 1158 1024.000 1019.750
(1019.760) 1.93
17 36+410 Bridge Nullah 1 x 40 5.60 96 3390 1041.675 1024.870
(1024.870) 2.60
18 39+680 Bridge Nullah 3 x 30 0.80 19.2 677 958.000 949.130
(949.110) 1.62
19 40+545 Bridge Wuch Tangi 1 x 40 9.75 117 4124 922.9 898.550
(898.560) 2.71
20 43+230 Bridge Nullah 1 x 30 3.20 55 1939 808.000 804.16
(804.160) 2.29
21 45+215 Bridge Nullah 1 x 40 15.00 181 6373 749.726 738.540
(738.570) 2.73
22 46+300 Bridge Giani at Torkham 4 x 25 29.20 350 12349 711.000 708.290 4.25
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
20
5.2 Hydraulic Analysis for Cross-Drainage Structures/ Culverts
On the basis of inundation analysis and cross-drainage needs at the point of
interests along the proposed alignment, it was analyzed to assess the required
design capacity of proposed culverts at 132 locations to safely pass flow of
certain magnitude (50 years return period) to withstand the embankment as well
as smooth operation of the alignment under such standard flood conditions.
All such analysis was carried out using a well established computer model HY-8
Culvert Analysis to determine the design parameters of culvert at each point of
interest. The software has been structured to be self-contained and is mostly
used by roadway design engineers.
HY-8 Culvert Analysis Model
For this purpose, GIS applications were also made for estimating the catchments
characteristics (watershed area, main stream length, average slope, land use
etc.). This was done first estimating the standard runoff from standard rainfalls
(50 years) using HEC-HMS Computer Mode. The standard flow at respective
point of interest was estimated for using as input in the HY-8 Culvert Analysis
Computer Model to estimate viable culvert parameters (shape, number of cells,
width, height, freeboard).
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
21
On the basis of analysis, total 132 box culverts have been proposed including
improvement of 11 existing ones (Table 3). The design parameters are given in
Table 4 providing sufficient design capacity to safely pass the runoff generated
especially from the steep slopes along the road which also bring sediment/
boulders along with due to generally bare mountains. For such purposes, the
sufficient viable capacity of the culverts has been proposed.
Table 3: Proposed X- Drainage Structures
S.No. Structures Nos.
1 New Box culverts 121
2 Modification/ rehabilitation of existing into
Box culverts 11
Total 132
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
22
Table 4: Schedule of Proposed X-Drainage Structures
(Manning’s n=0.020 for concrete culverts; Curve Number for SCS Runoff Estimation CN=75 )
S.# Station Remarks
Culvert Parameters Associated Catchment
Area
Runoff Generated (Qobs)
Design Capacity of Culverts (Q
design)
No. of Cells Span (L)
m Height (H) m
km2 cumecs cumecs
1 0+229 Provide new box culvert 2 3 3 0.115 1.94 11.82
2 0+920 Provide new box culvert 1 2 2 0.096 1.63 2.00
3 1+000 Provide new box culvert 1 2 2.5 0.100 1.69 2.64
4 1+400 Provide new box culvert 1 2 3 0.160 2.70 3.30
5 2+590 Provide new box culvert 5 4 4 0.160 2.70 63.66
6 2+880 Provide new box culvert 1 2 2 0.099 1.67 2.00
7 3+250 Provide new box culvert 1 2 1.5 0.075 1.27 1.39
8 3+650 Provide new box culvert 1 2 2.5 0.072 1.22 2.64
9 4+180 Provide new box culvert 1 2 1.5 0.072 1.21 1.39
10 4+550 Provide new box culvert 1 2 1.5 0.072 1.22 1.39
11 5+140 Provide new box culvert 1 2 2 0.100 1.69 2.00
12 5+800 Provide new box culvert 1 2 4 0.224 3.78 4.62
13 7+410 Provide new box culvert 4 4 4 0.320 5.40 50.93
14 7+980 Provide new box culvert 3 4 1.5 0.350 4.34 10.29
15 8+800 Provide new box culvert 1 2 2 0.096 1.19 2.00
16 9+080 Provide new box culvert 1 2 2 0.094 1.60 2.00
17 9+160 Provide new box culvert 1 2 3 0.150 2.53 3.30
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
23
S.# Station Remarks
Culvert Parameters Associated Catchment
Area
Runoff Generated (Qobs)
Design Capacity of Culverts (Q
design)
No. of Cells Span (L)
m Height (H) m
km2 cumecs cumecs
18 9+220 Provide new box culvert 1 3 2.5 0.125 2.11 4.69
19 9+810 Provide new box culvert 1 3 4 0.260 3.22 8.43
20 9+980 Provide new box culvert 1 2 3 0.060 1.01 3.30
21 10+040 Provide new box culvert 1 2 4 0.080 1.35 4.62
22 10+196 Provide new box culvert 1 2 4 0.095 1.60 4.62
23 10+671 Provide new box culvert 5 4 4 0.270 4.56 63.66
24 11+100 Provide new box culvert 1 3 4 0.112 1.90 8.43
25 11+420 Provide new box culvert 1 3 4 0.091 1.53 8.43
26 11+705 Provide new box culvert 1 2 4 0.066 1.11 4.62
27 11+860 Provide new box culvert 1 3 4 0.060 1.01 8.43
28 12+060 Provide new box culvert 1 3 4 0.150 2.53 8.43
29 12+160 Provide new box culvert 1 3 3 0.144 2.43 5.91
30 13+020 Provide new box culvert 1 3 2 0.150 2.53 3.50
31 13+127 Provide new box culvert 1 3 2 0.100 1.69 3.50
32 13+230 Provide new box culvert 1 2 4 0.091 1.54 4.62
33 13+360 Provide new box culvert 1 2 4 0.094 1.58 4.62
34 13+490 Provide new box culvert 1 2 4 0.131 2.22 4.62
35 13+680 Provide new box culvert 1 2 4 0.100 1.69 4.62
36 13+740 Provide new box culvert 1 2 4 0.158 1.96 4.62
37 13+979 Provide new box culvert 1 3 2 0.097 1.63 3.50
38 14+620 Provide new box culvert 1 2 1 0.036 0.61 0.81
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
24
S.# Station Remarks
Culvert Parameters Associated Catchment
Area
Runoff Generated (Qobs)
Design Capacity of Culverts (Q
design)
No. of Cells Span (L)
m Height (H) m
km2 cumecs cumecs
39 14+840 Provide new box culvert 1 3 4 0.225 3.80 8.43
40 15+160 Provide new box culvert 1 3 4 0.252 4.26 8.43
41 15+240 Provide new box culvert 3 4 4 0.300 5.07 38.20
42 16+000 Provide new box culvert 1 2 2 0.100 1.69 2.00
43 16+200 Provide new box culvert 1 2 3 0.120 2.03 3.30
44 16+277 Provide new box culvert 1 2 2 0.080 1.35 2.00
45 16+360 Provide new box culvert 1 2 4 0.110 1.86 4.62
46 16+500 Provide new box culvert 3 4 4 1.500 25.33 38.20
47 16+640 Provide new box culvert 2 3 4 0.375 6.33 16.86
48 16+733 Provide new box culvert 2 3 4 0.400 6.75 16.86
49 16+800 Provide new box culvert 1 2 4 0.060 1.01 4.62
50 17+060 Provide new box culvert 1 2 4 0.080 1.35 4.62
51 17+140 Provide new box culvert 1 2 4 0.084 1.42 4.62
52 17+240 Provide new box culvert 1 3 4 0.106 1.79 8.43
53 17+360 Provide new box culvert 1 2 3 0.100 1.69 3.30
54 17+485 Provide new box culvert 2 3 4 0.100 1.69 16.86
55 17+520 Provide new box culvert 2 3 4 0.080 1.35 16.86
56 17+618 Provide new box culvert 2 3 4 0.110 1.86 16.86
57 17+690 Provide new box culvert 1 2 4 0.120 2.03 4.62
58 18+278 Provide new box culvert 1 2 2 0.100 1.69 2.00
59 18+695 Provide new box culvert 1 2 4 0.240 4.05 4.62
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
25
S.# Station Remarks
Culvert Parameters Associated Catchment
Area
Runoff Generated (Qobs)
Design Capacity of Culverts (Q
design)
No. of Cells Span (L)
m Height (H) m
km2 cumecs cumecs
60 18+990 Provide new box culvert 1 2 2 0.066 1.11 2.00
61 19+280 Provide new box culvert 1 2 1.5 0.065 1.09 1.39
62 19+420 Provide new box culvert 1 2 4 0.094 1.59 4.62
63 19+750 Provide new box culvert 5 4 4 1.168 19.72 63.66
64 19+920 Provide new box culvert 1 2 4 0.075 1.27 4.62
65 19+960 Provide new box culvert 1 2 4 0.060 1.01 4.62
66 20+070 Provide new box culvert 3 4 4 0.320 5.40 38.20
67 20+654 Provide new box culvert 3 4 4 1.870 23.19 38.20
68 21+500 Provide new box culvert 1 2 4 0.210 3.55 4.62
69 21+730 Provide new box culvert 1 2 4 0.150 2.53 4.62
70 22+425 Provide new box culvert 1 2 4 0.128 2.16 4.62
71 22+700 Provide new box culvert 1 2 4 0.150 2.53 4.62
72 23+150 Provide new box culvert 3 3 3 0.918 15.50 17.73
73 23+245 Dismantle existing structure and provide new box culvert
1 3 4 0.224 3.78 8.43
74 23+572 Dismantle existing structure and provide new box culvert
1 3 4 0.256 4.32 8.43
75 23+655
Dismantle existing structure and provide new box culvert
1 3 4 0.120 2.03 8.43
76 24+405 Provide new box culvert 1 2 1.5 0.064 1.08 1.39
77 24+583 Dismantle existing structure and provide new box culvert
1 2 4 0.070 1.19 4.62
78 24+884
Dismantle existing structure and provide new box culvert
1 3 4 0.144 2.43 8.43
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
26
S.# Station Remarks
Culvert Parameters Associated Catchment
Area
Runoff Generated (Qobs)
Design Capacity of Culverts (Q
design)
No. of Cells Span (L)
m Height (H) m
km2 cumecs cumecs
79 25+172 Dismantle existing structure and provide new box culvert
2 3 2.5 0.158 2.67 9.38
80 25+382 Dismantle existing structure and provide new box culvert
2 3 4 0.523 8.82 16.86
81 25+840 Provide new box culvert 1 2 2 0.070 1.19 2.00
82 26+114 Dismantle existing structure and provide new box culvert
1 3 3 0.120 2.03 5.91
83 26+330 Provide new box culvert 1 3 2 0.065 1.09 3.50
84 26+469 Provide new box culvert 1 3 2 0.190 3.21 3.50
85 26+520 Provide new box culvert 1 3 4 0.103 1.73 8.43
86 25+590 Provide new box culvert 1 2 3 0.160 2.70 3.30
87 26+220 Provide new box culvert 1 2 4 0.120 2.03 4.62
88 26+460 Provide new box culvert 1 2 4 0.092 1.55 4.62
89 26+623 Provide new box culvert 4 4 4 0.240 4.05 50.93
90 26+840 Provide new box culvert 1 2 4 0.105 1.77 4.62
91 26+960 Provide new box culvert 1 2 4 0.096 1.62 4.62
92 27+240 Provide new box culvert 1 2 4 0.091 1.54 4.62
93 27+440 Provide new box culvert 1 2 4 0.078 1.32 4.62
94 27+760 Provide new box culvert 1 2 4 0.151 2.55 4.62
95 28+890 Provide new box culvert 4 4 4 0.600 10.13 50.93
96 29+300 Provide new box culvert 2 4 4 0.480 8.11 25.46
97 29+460 Provide new box culvert 1 2 4 0.177 2.99 4.62
98 29+770 Provide new box culvert 3 4 4 0.600 10.13 38.20
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
27
S.# Station Remarks
Culvert Parameters Associated Catchment
Area
Runoff Generated (Qobs)
Design Capacity of Culverts (Q
design)
No. of Cells Span (L)
m Height (H) m
km2 cumecs cumecs
99 30+780 Provide new box culvert 1 2 4 0.090 1.52 4.62
100 30+920 Provide new box culvert 1 2 3 0.109 1.83 3.30
101 31+400 Provide new box culvert 1 3 3 0.153 2.58 5.91
102 31+940 Provide new box culvert 1 2 2
0.090 1.52 2.00
103 32+400 Provide new box culvert 1 2 4 0.075 1.27 4.62
104 32+760 Provide new box culvert 1 2 3 0.089 1.49 3.30
105 33+940 Provide new box culvert 1 2 4 0.138 2.33 4.62
106 34+140 Provide new box culvert 1 2 1.5 0.075 1.27 1.39
107 34+470 Provide new box culvert 1 3 3 0.142 2.40 5.91
108 35+390 Provide new box culvert 1 2 4 0.158 2.67 4.62
109 36+055 Provide new box culvert 3 4 4 0.306 5.17 38.20
110 37+020 Provide new box culvert 1 2 4 0.120 2.03 4.62
111 37+140 Provide new box culvert 1 2 3 0.060 1.01 3.30
112 37+370 Provide new box culvert 1 2 2 0.076 1.28 2.00
113 38+485 Provide new box culvert 1 3 4 0.296 4.99 8.43
114 39+340 Provide new box culvert 3 4 2 0.800 9.92 15.37
115 39+752 Dismantle existing structure and provide new box culvert
1 2 1.5 0.028 0.47 1.39
116 39+866 Dismantle existing structure and provide new box culvert
1 2 1.5 0.038 0.64 1.39
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
28
S.# Station Remarks
Culvert Parameters Associated Catchment
Area
Runoff Generated (Qobs)
Design Capacity of Culverts (Q
design)
No. of Cells Span (L)
m Height (H) m
km2 cumecs cumecs
117 40+005
Dismantle existing structure and provide new box culvert
1 2 1.5 0.053 0.90 1.39
118 40+220 Provide new box culvert 1 2 3 0.081 1.37 3.30
119 41+430 Provide new box culvert 5 4 4 3.055 37.88 63.66
120 41+943 Provide new box culvert 1 2 1.5 0.070 1.19 1.39
121 42+138 Provide new box culvert 1 4 1.5 0.165 2.79 3.43
122 42+679 Provide new box culvert 1 2 4
123 42+820 Provide new box culvert 1 2 1.5 0.075 1.27 1.39
124 43+690 Provide new box culvert 5 4 4 0.250 4.22 63.66
125 43+840 Provide new box culvert 1 2 4 0.092 1.55 4.62
126 44+380 Provide new box culvert 1 2 4 0.200 3.38 4.62
127 44+760 Provide new box culvert 1 2 4 0.102 1.72 4.62
128 44+890 Provide new box culvert 1 2 4 0.066 1.11 4.62
129 45+4360 Provide new box culvert 1 2 4 0.060 1.01 4.62
130 45+440 Provide new box culvert 1 2 3 0.060 1.01 3.30
131 45+650 Provide new box culvert 1 2 4 0.100 1.68 4.62
132 45+938 Provide new box culvert 1 4 1.5 0.161 2.72 3.43
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
29
5.3 Hydraulic Design Analysis for Side Channels
Storm water management of roads should be integrated with management of
surrounding land and development. However, the drainage of runoff from the
along the road and its surface should be so designed to avoid any damage or
ponding to the road surface for safe operation of the highways.
The road is located in the range where topography varies from mild to steep. The
road may come mostly under the effect of direct flow from the hills in the form of
torrents as flash flood (Figure 14). The main threat to the road would be from
such torrents which are flash floods in the form of sheet flow and may damage
the road if no protective measures are adopted to control and their safe passage.
The case would be more critical as the flood water carry mud/boulders on its way.
Figure 15: Scheme of runoff generation due to rainfall
For example an area of 500 m upto 50 m height of hill with 43 mm critical rainfall
(in 15 minutes) may bring about 0.24 cumecs (8.5 cusecs) to the road using
following Rational formula:
Q = C i A (1)
Where
Q = Discharge in cusecs
Road
Slope along the road
NSL
Rainfall
Runoff
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
30
C = Runoff Coefficient (taken 0.80 in present case)
i = Rainfall intensity (inches per hour)
A = Area in acres
So Q = 0.8 x 1.72 x 6.2
= 8.53 cusecs (0.24 cumecs)
To avoid this, drainage channels along the road on hill sides connected to the
x-culverts may be provided to protect the road. Further, reinforced retaining walls
would also be required especially at steep slopes. The scheme along with design
of side channel is shown in Figure 15.
Figure 16: Scheme of protective measures for the road
Adequate cut-off must be provided such that the maximum length of flow path in
the road drainage channel does not exceed up to a reasonable length, preferably
200 m. The cut-off must discharge to a natural watercourse. In the instant case, it
is proposed that drainage may be provided from the sides connecting through
drop structures with proper riprap arrangements (Figure 16) to avoid any rill
development of the embankment. Under the propose alignment, there is at least
one cross-drainage structure at about 300 m apart so the road overland flow may
be diverted to the nearest one through drop structures. And the given proposed
culverts have suffici9ent capacity with 20% freeboard to accommodate such
overland flows.
Road
Slope along the road
NSL Rainfall
Runoff
Proposed side channels 0.8 m
0.5 m
Retaining walls
2:1
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
31
Figure 17: Schematic of Drop Structure along embankment
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
32
CHAPTER-6 FINDINGS & RECOMMENDATIONS
The major findings and recommendations of the study are:
i. The Peshawar-Torkham proposed alignment falls in the areas mainly in terrains with barren and rugged mountains where several small streams and nullahs cross the alignment.
ii. The area falls in the climate mostly under Mediterranean influence and less monsoon effects with annual total around 400 mm. The average temperature in summer varies from 18 to 40 oC whereas the winter average temperatures range from 2 to 25 oC. However, the extreme temperatures could be below 0 oC in winters and more than 40 oC in summers.
iii. The long term temperature analysis (1974 to 2015) does not present any major deviation in the temperatures both in summer and winters. Whereas long term rainfall pattern shows an increasing trend in annual totals due to the fact that monsoon rains are moving upward towards northern parts of the country. However, the study alignment moves further upward, where such impact would not be that significant as Mediterranean disturbances having more influence in upper parts of the alignment.
iv. Based on the rainfall and runoff analysis in connection with the topography of the area, there have been proposed 22 bridges to safely pass the runoff generated from the upstream and adjoining areas. The design parameters for the bridges have been provided based on hydraulic analysis under the study in order to pass the standard floods safely (100-year), besides scour depth analysis.
v. Similarly, for overland flow and minor natural channels, 132 culverts have been proposed (including modification of 11 existing ones) for which design parameters are also provided to safely pass standard flood of 50-year recurrence interval.
vi. The road is located in the range where topography varies from mild to steep. The road may come mostly under the effect of direct flow from the hills in the form of torrents as flash flood; also carrying mud/boulders on its way. To avoid this, drainage channels along the road on hill sides connected to the nearest x-culverts may be provided to protect the road, for which design has also been proposed.
vii. The overland flow from the road itself may be passed through road-side drop structure and connected to corresponding culvert or existing conveyance system (watercourse or drain). In the design of culverts, there has been kept cushion for such overland flow from the road itself, giving 20% (0.2 to 0.3 m) freeboard for all culverts.
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
33
References
Kruseman, G.P. and Naqvi, S.A.H., (1988), Hydrogeology and Groundwater
Resources of the North-West Frontier Province Pakistan, A joint publication of
WAPDA Pakistan and Institute of Applied Geosciences, Delft Netherlands.
1988
Lacey, G. (1946), A general theory of flow-in alluvium. Journal of the
Institution of Civil engineering. London, Vol.27, 16-47, Vol.28, pp. 425-451.
Meissner, C.R., M. Hussain, M.A. Rashid and U.B. Sethi,1975. Geology of the
Parachinar Quadrangle, West Pakistan. US Geol. Survey; Prof. Paper 716-F;
24 pp.
Mutreja K. N. (1990), Applied Hydrology, Tata McGraw-Hill Publishing
Company, Ltd, New Delhi, 1990.
Papalexiou, S.M., and D. Koutsoyiannis (2012), A global survey on the
distribution of annual maxima of daily rainfall: Gumbel or Fréchet?, European
Geosciences Union General Assembly 2012, Geophysical Research
Abstracts, Vol. 14, Vienna, 10563, European Geosciences Union, 2012.
Shah, S.M.I., R.A. Siddiqi, and J.A. Talent, 1980. Geology of the eastern
Khyber Agency, North Western Frontier Province, Pakistan. Records of the
Geol. Survey Pakistan; Vol. 44.
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
34
ANNEXURES
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
35
Annexure A: Historical Climatic Data for Peshawar
Annual Daily Maximum and Total Annual rainfall
Years Daily Maximum Rainfall
(mm) Annual Total Rainfall
(mm)
1974 19.40 190.20
1975 53.50 434.90
1976 102.00 612.16
1977 113.50 452.07
1978 68.50 497.78
1979 54.40 403.97
1980 45.50 372.37
1981 56.00 393.29
1982 40.70 326.36
1983 84.70 710.24
1984 86.80 521.98
1985 62.00 340.81
1986 47.50 416.05
1987 52.40 342.57
1988 44.30 360.90
1989 35.00 251.03
1990 55.00 453.91
1991 62.00 384.42
1992 56.00 579.93
1993 67.00 466.51
1994 51.00 642.52
1995 55.00 618.73
1996 142.00 667.35
1997 30.00 299.54
1998 47.00 569.73
1999 48.00 407.44
2000 33.00 258.89
2001 27.00 263.22
2002 30.00 299.03
2003 65.00 904.73
2004 68.00 453.04
2005 72.00 625.00
2006 56.00 497.50
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
36
Years Daily Maximum Rainfall
(mm) Annual Total Rainfall
(mm)
2007 84.00 575.40
2008 78.00 719.90
2009 187.00 533.00
2010 274.00 839.00
2011 122.10 568.00
2012 88.00 480.00
2013 80.00 551.00
2014 30.00 326.00
2015 65.00
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
37
Daily Annual Maximum and Minimum Temperature
Years Daily Maximum Temperature
(oC)
Daily Minimum Temperature (oC)
1974 46.00 0.00
1975 47.00 0.00
1976 46.00 0.00
1977 45.00 1.00
1978 47.00 -1.00
1979 45.00 2.00
1980 45.00 0.00
1981 45.00 0.00
1982 45.00 0.00
1983 44.30 -1.60
1984 46.10 -1.30
1985 45.00 2.00
1986 48.00 1.10
1987 45.00 1.70
1988 44.80 2.30
1989 45.50 -0.50
1990 45.00 2.40
1991 44.20 1.00
1992 46.60 1.50
1993 47.30 0.00
1994 48.60 1.00
1995 50.00 -0.50
1996 47.00 -1.00
1997 44.00 0.00
1998 46.50 0.50
1999 49.50 2.00
2000 46.00 1.00
2001 46.00 -1.00
2002 46.00 2.50
2003 48.00 2.00
2004 44.50 2.00
2005 47.00 0.50
2006 44.00 -0.50
2007
2008
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
38
Years Daily Maximum Temperature
(oC)
Daily Minimum Temperature (oC)
2009
2010
2011 46.00 0.00
2012 45.00 -15.00
2013 44.00 0.00
2014 44.00 1.00
2015 43.00 2.00
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
39
Annexure-B: Catchments Delineation of Major Streams/ Nullahs
Chaura Khwar at RD 7+060
Nullah at RD 8+650
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
40
Nullah at RD 8+890
Nullah at RD 9+580
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
41
Khyber Khwar at RD 21+920
Khyber Khwar at RD 22+560
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
42
Khyber Khwar at RD 22+765
Khyber Khwar at RD 23+950
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
43
Nullah at RD 24+700
Khyber Khwar at RD 25+615
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
44
Chigai Khwar at RD 25+810
Kagga Khwar at Wali Khel at RD 28+700
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
45
Dand Khwar at RD 30+460
Bori Khwar at RD 33+000
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
46
Sawal Khwar at RD 33+587
Nullah at RD 35+002
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
47
Nullah at RD 36+410
Nullah at RD 39+680
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
48
Wuch Tangi at RD 40+545
Nullah at RD 43+230
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
49
Nullah at RD 45+215
Giani at Torkham at RD 46+300
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
50
Annexure-C: Hydrologic and Hydraulic Parameters relating Bridges over Major Streams/ Nullahs
S.No. Location Name of Stream/
Nullah
Catchment Area
Main stream Length
Average Slope
Catchment 100-Year
Discharge
(Curve Number CN for SCS
Runoff=75)
Bridge Size
Channel Velocity at
Bridge Location (before bridge)
Channel Velocity
at Bridge
Location (with
bridge)
Flow Area at bridge
location (before bridge)
Flow Area at bridge
location (with
bridge)
HFL (before bridge)
HFL (with
bridge)
km2 Km m/m cumecs
Cell x Span
m/sec m/sec m2 m
2 m m
1 7+060 Chaura Khwar near Jamrud
425.31 38.70 0.0388 2356 7 x 40 2.81 2.86 837.20 824.65 479.22 479.30
2 8+650 Nullah 0.53 0.93 0.0690 12.72 1 x 30 0.49 0.55 26.12 23.05 532.79 532.78
3 8+890 Nullah 0.73 0.96 0.2190 17.5 1 x 40 0.63 0.64 27.60 27.14 537.06 537.06
4 9+580 Nullah 1.41 1.40 0.2764 34 1 x 40 0.92 1.10 36.91 30.90 538.11 538.11
5 21+920 Khyber Khwar at
Ali Masjid 70.00 20.00 0.0070 341 2 x 40 1.76 1.89 193.68 179.97 753.67 753.65
6 22+560 Khyber Khwar (RD22+560)
69.80 19.80 0.0071 340 2 x 30 1.77 2.15 192.48 158.17 771.94 771.91
7 22+765 Khyber Khwar (RD22+765)
69.60 19.60 0.0071 339 2 x 25 2.20 2.47 154.18 137.13 779.14 779.10
8 23+950 Khyber Khwar (RD23+950)
63.00 18.00 0.0361 307 4 x 30 1.48 1.55 207.35 197.46 803.90 803.91
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
51
S.No. Location Name of Stream/
Nullah
Catchment Area
Main stream Length
Average Slope
Catchment 100-Year
Discharge
(Curve Number CN for SCS
Runoff=75)
Bridge Size
Channel Velocity at
Bridge Location (before bridge)
Channel Velocity
at Bridge
Location (with
bridge)
Flow Area at bridge
location (before bridge)
Flow Area at bridge
location (with
bridge)
HFL (before bridge)
HFL (with
bridge)
km2 Km m/m cumecs
Cell x Span
m/sec m/sec m2 m
2 m m
9 24+700 Nullah 7.70 4.53 0.0838 92.3 2 x 35 0.94 1.43 97.89 64.43 823.24 823.28
10 25+615 Khyber Khwar (RD25+615)
56.00 16.00 0.0406 273 1 x 40 1.74 2.50 156.70 109.40 836.24 836.17
11 25+810 Chingai Khwar 3.29 2.33 0.3425 79 2 x 20 0.90 1.53 87.73 51.71 867.00 867.03
12 28+700 Kagga Khwar at
Wali Khel 8.45 3.49 0.2146 145 2 x 30 1.55 1.58 93.32 91.82 953.09 953.10
13 30+460 Dand Khwar 9.00 4.50 0.1756 154 1 x 25 1.75 2.02 87.91 76.33 958.68 958.63
14 33+000 Bori Khwar 6.80 4.00 0.1595 117 1 x 20 0.81 2.74 144.33 42.71 1003.48 1003.84
15 33+587 Sawal Khwar 9.00 4.50 0.1818 154 1 x 20 1.08 2.94 142.30 52.35 1013.74 1015.13
16 35+002 Nullah 1.36 1.60 0.1119 32.8 1 x 25 0.63 0.99 52.46 33.04 1019.76 1019.75
17 36+410 Nullah 5.60 3.20 0.1678 96 1 x 40 2.44 2.44 39.32 39.32 1024.87 1024.87
18 39+680 Nullah 0.80 1.76 0.1403 19.2 3 x 30 1.07 1.12 18.02 17.14 949.10 949.13
19 40+545 Wuch Tangi 9.75 6.50 0.1418 117 1 x 40 1.65 1.73 70.99 67.81 898.56 898.55
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
52
S.No. Location Name of Stream/
Nullah
Catchment Area
Main stream Length
Average Slope
Catchment 100-Year
Discharge
(Curve Number CN for SCS
Runoff=75)
Bridge Size
Channel Velocity at
Bridge Location (before bridge)
Channel Velocity
at Bridge
Location (with
bridge)
Flow Area at bridge
location (before bridge)
Flow Area at bridge
location (with
bridge)
HFL (before bridge)
HFL (with
bridge)
km2 Km m/m cumecs
Cell x Span
m/sec m/sec m2 m
2 m m
20 43+230 Nullah 3.20 5.10 0.2049 55 1 x 30 1.45 1.45 37.89 37.89 802.82 802.82
21 45+215 Nullah 15.00 8.00 0.1373 181 1 x 40 1.61 1.79 112.21 100.99 738.57 738.54
22 46+300 Giani at Torkham 29.20 8.00 0.1415 350 4 x 25 1.88 1.98 186.30 177.07 708.28 708.30
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
53
Annexure-D: Hydraulic Outputs of Major Streams/ Nullahs
0 50 100 150 200 250 300 350470
475
480
485
490
495
500
505
Bridge 7+060 Plan: Bridge 7+060 7/23/2017 Bridge of Chaura Khwar at RD 7+060 (Q=2356 cumecs)
Station (m)
Ele
vatio
n (
m)
Legend
EG PF 1
WS PF 1
Crit PF 1
Ground
Bank Sta
.025
0 50 100 150 200 250530
532
534
536
538
540
542
544
546
548
550
Bridge 8+650 Plan: Bridge 8+650 7/23/2017 Bridge of Nullah at RD 8+650 (Q= 12.72 cumecs)
Station (m)
Ele
vatio
n (
m)
Legend
EG PF 1
WS PF 1
Crit PF 1
Ground
Bank Sta
.025
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
54
0 20 40 60 80 100 120 140536
538
540
542
544
546
548
Bridge 8+890 Plan: Bridge 8+890 7/23/2017 Bridge of Nullah at RD 8+890 (Q= 17.50 cumecs)
Station (m)
Ele
vatio
n (
m)
Legend
EG PF 1
WS PF 1
Crit PF 1
Ground
Bank Sta
.025
0 50 100 150 200 250535
540
545
550
555
560
565
Bridge 9+590 Plan: Bridge 9+590 7/23/2017 Bridge of Nullah at RD 9+590 (Q= 34 cumecs)
Station (m)
Ele
vatio
n (
m)
Legend
EG PF 1
WS PF 1
Crit PF 1
Ground
Bank Sta
.025
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
55
0 20 40 60 80 100 120 140 160750
752
754
756
758
760
762
764
Bridge 21+920 Plan: Bridge 21+920 7/23/2017 Bridge of Khyber Khwar at RD 21+920 (Q=341 cumecs)
Station (m)
Ele
vation
(m
)
Legend
EG PF 1
WS PF 1
Crit PF 1
Ground
Bank Sta
.025
0 20 40 60 80 100 120 140 160765
770
775
780
785
790
Bridge 22+560 Plan: Bridge 22+560 7/23/2017 Bridge of Khyber Khwar at RD 22+560 (Q=340 cumecs)
Station (m)
Ele
vation
(m
)
Legend
EG PF 1
WS PF 1
Crit PF 1
Ground
Bank Sta
.025
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
56
0 20 40 60 80 100770
775
780
785
790
795
Bridge 22+765 Plan: Bridge 22+765 7/23/2017 Bridge of Khyber Khwar at RD 22+765 (Q=339 cumecs)
Station (m)
Ele
vatio
n (
m)
Legend
EG PF 1
WS PF 1
Crit PF 1
Ground
Bank Sta
.025
0 100 200 300 400 500800
802
804
806
808
810
812
814
816
818
Bridge 23+950 Plan: Bridge 23+950 7/23/2017 Bridge ofKhyber Khwar at RD 23+950 (Q= 307 cumecs)
Station (m)
Ele
vatio
n (
m)
Legend
EG PF 1
WS PF 1
Crit PF 1
Ground
Bank Sta
.025
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
57
0 20 40 60 80 100 120 140 160820
822
824
826
828
830
832
Bridge 24+700 Plan: Bridge 24+700 7/23/2017 Bridge of Nullah at RD 24+700 (Q=92.3 cumecs)
Station (m)
Ele
vatio
n (
m)
Legend
EG PF 1
WS PF 1
Crit PF 1
Ground
Bank Sta
.025
0 50 100 150 200 250 300832
834
836
838
840
842
Bridge 25+615 Plan: Bridge 25+615 7/23/2017 Bridge of Khyber Khwar at RD 25+615 (Q=273 cumecs)
Station (m)
Ele
vatio
n (
m)
Legend
EG PF 1
WS PF 1
Crit PF 1
Ground
Bank Sta
.025
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
58
0 20 40 60 80 100 120 140 160864
866
868
870
872
874
876
878
880
882
Bridge 25+810 Plan: Bridge 25+810 7/23/2017 Bridge of Chingai Khwar at RD 25+810 (Q=79 cumecs)
Station (m)
Ele
vatio
n (
m)
Legend
EG PF 1
WS PF 1
Crit PF 1
Ground
Bank Sta
.025
0 50 100 150 200950
952
954
956
958
960
Bridge 28+700 Plan: Bridge 28+700 7/23/2017 Bridge of Kagga Khwar at RD 28+700 (Q=145 cumecs)
Station (m)
Ele
vation
(m
)
Legend
EG PF 1
WS PF 1
Crit PF 1
Ground
Bank Sta
.025
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
59
0 50 100 150 200950
955
960
965
970
975
Bridge 30+460 Plan: Bridge 30+460 7/23/2017 Bridge of Dand Khwar at RD 30+460 (Q=154 cumecs)
Station (m)
Ele
vation
(m
)
Legend
EG PF 1
WS PF 1
Crit PF 1
Ground
Bank Sta
.025
0 50 100 150 200 2501001
1002
1003
1004
1005
1006
Bridge 33+000 Plan: Bridge 33+000 7/23/2017 Bridge of Bori Khwar at RD 33+000 (Q=117 cumecs)
Station (m)
Ele
vatio
n (
m)
Legend
EG PF 1
WS PF 1
Crit PF 1
Ground
Bank Sta
.025
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
60
0 50 100 150 200 250 300 3501010
1015
1020
1025
1030
1035
Bridge 33+590 Plan: Bridge 33+590 7/23/2017 Bridge of Sawal Khwar at RD 33+590 (Q=154 cumecs)
Station (m)
Ele
vatio
n (
m)
Legend
EG PF 1
WS PF 1
Crit PF 1
Ground
Bank Sta
.025
0 50 100 150 200 2501015
1020
1025
1030
1035
1040
1045
Bridge 35+002 Plan: Bridge35+002 7/23/2017 Bridge of Nullah at RD 35+002 (Q= 32.8 cumecs)
Station (m)
Ele
vatio
n (
m)
Legend
EG PF 1
WS PF 1
Crit PF 1
Ground
Bank Sta
.025
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
61
0 20 40 60 80 100 120 1401020
1030
1040
1050
1060
1070
Bridge 36+410 Plan: Bridge36+410 7/23/2017 Bridge of Nullah at RD 36+410 (Q= 96 cumecs)
Station (m)
Ele
vatio
n (
m)
Legend
EG PF 1
WS PF 1
Crit PF 1
Ground
Bank Sta
.025
0 50 100 150 200 250 300945
950
955
960
965
970
975
Bridge 39+680 Plan: Bridge 39+680 7/23/2017 Bridge of Nullah at RD 39+680 (Q=19.2 cumecs)
Station (m)
Ele
vatio
n (
m)
Legend
EG PF 1
WS PF 1
Crit PF 1
Ground
Bank Sta
.025
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
62
0 50 100 150 200 250 300 350 400890
900
910
920
930
940
950
960
Bridge 40+545 Plan: Bridge 40+545 7/23/2017 Bridge of Wuch Tangi at RD 40+545 (Q=117 cumecs)
Station (m)
Ele
vatio
n (
m)
Legend
EG PF 1
WS PF 1
Crit PF 1
Ground
Bank Sta
.025
0 10 20 30 40 50 60 70800
805
810
815
820
825
830
Bridge 43+230 Plan: Bridge43+230 7/23/2017 Bridge of Nullah at RD 43+230 (Q= 55 cumecs)
Station (m)
Ele
vation
(m
)
Legend
EG PF 1
WS PF 1
Crit PF 1
Ground
Bank Sta
.025
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
63
0 50 100 150 200 250 300 350735
740
745
750
755
760
Bridge 45+215 Plan: Bridge45+215 7/23/2017 Bridge of Nullah at RD 45+215 (Q= 181 cumecs)
Station (m)
Ele
vatio
n (
m)
Legend
EG PF 1
WS PF 1
Crit PF 1
Ground
Bank Sta
.025
0 50 100 150 200 250704
706
708
710
712
714
716
718
720
Bridge 46+300 Plan: Bridge46+300 7/23/2017 Bridge of Nullah at RD 46+300 (Q= 350 cumecs)
Station (m)
Ele
vation
(m
)
Legend
EG PF 1
WS PF 1
Crit PF 1
Ground
Bank Sta
.025
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
64
Annexure-E: Scour Depth Estimation by Lacey Regime Theory
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
65
S.# Location
D50
(Soil Type AASHTO
A-1-b)
Design 100-Year
Discharge Q
Lacey silt factor [1.76 SQRT(D50)]
P=4.75*sqrt(Q)
river width relation to select Lacey
Equation
L (actual channel
width)
Sy (scour depth)
mm cumecs f m m m
1 7+060 0.074 2356 0.479 230.559 228.000 8.02
2 8+650 0.074 12.72 0.479 16.941 32.650 1.26
3 8+890 0.074 17.5 0.479 19.871 38.490 1.33
4 9+580 0.074 34 0.479 27.697 26.250 1.96
5 21+920 0.074 341 0.479 87.714 75.890 4.21
6 22+560 0.074 340 0.479 87.586 57.73 3.11
7 22+765 0.074 339 0.479 87.457 43.560 3.42
8 23+950 0.074 307 0.479 83.227 111.750 4.07
9 24+700 0.074 92.3 0.479 45.635 75.010 1.85
10 25+615 0.074 273 0.479 78.483 45.960 3.12
11 25+810 0.074 79 0.479 42.219 42.770 2.59
HYDRAULIC & HYDROLOGY STUDY REPORT
for
Peshawar Torkham Motorway
66
S.# Location
D50
(Soil Type AASHTO
A-1-b)
Design 100-Year
Discharge Q
Lacey silt factor [1.76 SQRT(D50)]
P=4.75*sqrt(Q)
river width relation to select Lacey
Equation
L (actual channel
width)
Sy (scour depth)
mm cumecs f m m m
12 28+700 0.074 145 0.479 57.198 50.320 3.17
13 30+460 0.074 154 0.479 58.946 29.710 2.98
14 33+000 0.074 117 0.479 51.379 25.380 2.87
15 33+587 0.074 154 0.479 58.946 27.710 3.05
16 35+002 0.074 32.8 0.479 27.204 29.870 1.93
17 36+410 0.074 96 0.479 46.540 27.900 2.60
18 39+680 0.074 19.2 0.479 20.813 19.470 1.62
19 40+545 0.074 117 0.479 51.379 30.160 2.71
20 43+230 0.074 55 0.479 35.227 23.580 2.29
21 45+215 0.074 181 0.479 63.905 45.850 2.73
22 46+300 0.074 350 0.479 88.864 79.590 4.25