HYDRAULIC ASSESSMENT REPORT
514 South Service Road First Gulf Corporation 3751 Victoria Park Avenue Toronto, ON M1W 3Z4
1814292-000-W01
August 2014
Hydraulic Assessment Report | 514 South Service Road
MMM Group Limited | August 2014 | 18-14292-000-W01
i
TABLE OF CONTENTS
1.0 INTRODUCTION ............................................................................................ 1
2.0 SCOPE OF WORK ......................................................................................... 1
3.0 EXISTING HYDRAULIC MODELLING ........................................................... 3
4.0 PROPOSED HYDRAULIC MODELLING ....................................................... 7
5.0 CONCLUSIONS ............................................................................................. 9
LIST OF FIGURES
Figure 1: Study Area ................................................................................................................................. 2
Figure 2: Existing Regulatory Floodline .................................................................................................... 5
Figure 3: Proposed Regulatory Floodline ................................................................................................. 8
LIST OF TABLES
Table 1: Comparison of HEC-2 and HEC-RAS Regulatory Event Water Surface Elevations ................. 4
Table 2: Existing Hydraulic Assessment Results ..................................................................................... 6
Table 3: Comparison of Existing and Proposed Hydraulic Assessments ................................................ 7
LIST OF APPENDICES
Appendix A – HEC-RAS Results
Hydraulic Assessment Report | 514 South Service Road
MMM Group Limited | August 2014 | 18-14292-000-W01
1
1.0 INTRODUCTION
MMM Group Ltd was retained by First Gulf Corporation to determine the hydraulic implications
of the proposed development at 514 South Service Road on the Lower Morrison Creek adjacent
to the project site. The proposed development works at 514 South Service Road includes a
proposed 4-storey Office Building and a proposed parking lot. The study area is shown in Figure
1. The Lower Morrison Creek is located west of the study area, which is under the jurisdiction of
Conservation Halton (CH). The hydraulic assessment is to be conducted for the Lower Morrison
Creek adjacent to the project site.
2.0 SCOPE OF WORK
The objective of this study is to conduct a hydraulic assessment of the Lower Morrison Creek
adjacent to the project site for determining the hydraulic impact resulting from the proposed
developments at 514 South Service Road.
Hydraulic Assessment Report | 514 South Service Road
MMM Group Limited | August 2014 | 18-14292-000-W01
3
3.0 EXISTING HYDRAULIC MODELLING
The study area is located south of South Service Road and the QEW, west of Chartwell Road,
east of Lower Morrison Creek. The CNR tracks are located approximately 260 m south of the
project site. The Lower Morrison Creek flows southerly through QEW and the South Service
Road culverts, and remains as an open channel adjacent to the project site. However,
immediately south of the project site the Lower Morrison Creek is conveyed by a CSP arched
culvert (approximately 25 m in length). Afterwards the Lower Morrison Creek remains as an
open channel for approximately 200 m. Thereafter, the Lower Morrison Creek remains
completely confined and channelized, as it is conveyed by culverts under the CNR tracks,
private properties and Cornwall Road. Finally it confluences with Wedgewood Creek east of
Chartwell Road before discharging to Lake Ontario.
A hydraulic model in the form of HEC-2 was obtained from CH for the Lower Morrison Creek
and Wedgwood Creeks. These hydraulic models were developed as a part of the Flood, Erosion
and Master Drainage Plan Study, prepared by R. V. Anderson and Associates (1993). It should
be noted that the HEC-2 hydraulic model extends from the south of the CNR tracks, but does
not simulate the channelized and confined sections of the Lower Morrison Creek south of the
CNR tracks and does not extend up to the project site, hence should be considered outdated.
The HEC-2 model obtained from CH was initially converted to HEC-RAS. The converted HEC-
RAS model was updated with a box culvert located between the CNR tracks and the Cornwall
Road, and Cornwall Road double culvert.
The model was then rerun to establish a baseline performance based solely on the updated
hydraulic subroutines present in the HEC-RAS software. Table 1 presents the updated results
and compares them to the original floodplain elevations obtained from CH’s floodplain mapping.
Hydraulic Assessment Report | 514 South Service Road
MMM Group Limited | August 2014 | 18-14292-000-W01
4
Table 1: Comparison of HEC-2 and HEC-RAS Regulatory Event Water Surface Elevations
Model Cross-Section
Original CH HEC-2
Water Surface Elevation (as shown on
floodplain mapping)
MMM Converted HEC-RAS
Water Surface Elevation
2.82 n/a 100.71
2.805 (U/S inlet of site
culvert)
n/a 100.71
2.74 (D/S outlet of
site culvert)
n/a 99.09
2.73 98.96 98.96
2.68 98.37 98.37
2.64 97.78 97.79
2.59 97.17 96.94
2.54 96.54 96.54
2.49 96.06 96.09
2.43 95.67 95.71
Table 1 shows excellent agreement between the values reported on the floodplain mapping and
the results from the converted HEC-RAS model (referred to as the MMM converted HEC-RAS
model). Therefore, the results of the HEC-RAS mapping may be interpreted as reasonable
approximations of floodplain behaviour utilizing the out-dated assumptions and therefore as a
baseline simulation for comparison. The MMM converted HEC-RAS model was modified even
further by extending the model north of the CNR tracks up to the project site. New sections were
created from up-to-date contour mapping adjacent to the project site and the arched culvert (1.4
m span and 1.1 m rise) located south of the project site were inserted in the MMM converted
HEC-RAS model. The results for the existing MMM converted HEC-RAS model are shown in
Table 2 (shown in Appendix A). Table 2 shows the Regulatory water surface elevations. Figure
2 shows the Regulatory flood lines in the Lower Morrison Creek adjacent to the project site.
Hydraulic Assessment Report | 514 South Service Road
MMM Group Limited | August 2014 | 18-14292-000-W01
6
Table 2: Existing Hydraulic Assessment Results
Reach River Sta Profile Q Total
Min Ch
El
W.S.
Elev Crit W.S. E.G. Elev
E.G.
Slope Vel Chnl
Flow
Area
Top
Width
Froude #
Chl
(m3/s) (m) (m) (m) (m) (m/m) (m/s) (m2) (m)
Reach-1 3.5 PF 4 16.8 103.89 105.51 105.24 105.78 0.004978 2.59 9.35 10.31 0.67
Reach-1 3.49 PF 4 16.8 103.75 105.47 105.68 0.003616 2.31 11.08 15.01 0.58
Reach-1 3.48 PF 4 16.8 103.97 105.43 105.08 105.63 0.003772 2.25 11.31 13.39 0.6
Reach-1 3.47 PF 4 16.8 103.89 105.07 105.07 105.51 0.0111 3.22 6.94 9.44 0.98
Reach-1 3.46 PF 4 16.8 103.29 104.67 104.12 104.75 0.001605 1.36 16.27 17.44 0.38
Reach-1 3.45 PF 4 16.8 103 104.3 104.3 104.68 0.010545 3.35 8.35 12.14 0.97
Reach-1 3.44 PF 4 16.8 102.54 103.65 103.74 104.2 0.018772 3.94 6.2 8.07 1.24
Reach-1 3.43 PF 4 16.8 102 103.27 103.16 103.61 0.00713 2.8 8.44 12.09 0.8
Reach-1 3.42 PF 4 16.8 101.3 103.33 102.89 103.46 0.002081 1.99 15.39 16.61 0.45
Reach-1 3.41 PF 4 16.8 101.3 103.3 102.89 103.44 0.002237 2.04 14.92 16.38 0.47
Hydraulic Assessment Report | 514 South Service Road
MMM Group Limited | August 2014 | 18-14292-000-W01
7
4.0 PROPOSED HYDRAULIC MODELLING
Under the proposed condition, to reflect the changes due to the proposed site grading plan and
proposed developments, new cross-sections were generated for determining the proposed
hydraulic assessment. These cross-sections were inserted in the proposed MMM converted HEC-
RAS model. The results from the proposed MMM converted HEC-RAS model are shown in
Table 3 (shown in Appendix A). Figure 3 shows the Regulatory flood lines in the Lower Morrison
Creek adjacent to the project site.
Table 3: Comparison of Existing and Proposed Hydraulic Assessments
Existing
W.S.
Elev
Proposed
W.S. Elev
Existing
Vel Chnl
Proposed
Vel Chnl
Reach
River
Sta Profile Q Total Diff Diff
(m3/s) (m) (m) (m) (m/s) (m/s) (m/s)
Reach-1 3.5 PF 4 16.8 105.42 105.51 0.09 2.79 2.59 -0.2
Reach-1 3.49 PF 4 16.8 105.35 105.47 0.12 2.6 2.31 -0.29
Reach-1 3.48 PF 4 16.8 105.28 105.43 0.15 2.59 2.25 -0.34
Reach-1 3.47 PF 4 16.8 105.21 105.07 -0.14 2.46 3.22 0.76
Reach-1 3.46 PF 4 16.8 104.67 104.67 0 1.37 1.36 -0.01
Reach-1 3.45 PF 4 16.8 104.29 104.3 0.01 3.35 3.35 0
Reach-1 3.44 PF 4 16.8 103.65 103.65 0 3.9 3.94 0.04
Reach-1 3.43 PF 4 16.8 103.27 103.27 0 2.8 2.8 0
Reach-1 3.42 PF 4 16.8 103.33 103.33 0 1.99 1.99 0
Reach-1 3.41 PF 4 16.8 103.3 103.3 0 2.04 2.04 0
Table 3 shows that under the proposed condition the Regulatory water surface elevation
increases by a maximum of 0.15 m adjacent to the project site. However, under the proposed
condition changes in the site grading plan ensures that the Regulatory water surface elevations
remain within the channel corridor. Table 3 also shows that the increase in the water surface
elevations at specific sections also causes the average channel velocities to reduce adjacent to
the project site compared to the existing condition. It should be noted that no hydraulic impact
was observed in terms of the water surface elevations downstream of the project site.
Hydraulic Assessment Report | 514 South Service Road
MMM Group Limited | August 2014 | 18-14292-000-W01
9
5.0 CONCLUSIONS
The following conclusions can be reached from the preceding assessment:
1. The existing outdated HEC-2 model was modified, updated and extended to reflect certain
downstream culverts and the existing project site.
2. Regulatory flood lines were plotted for both existing and proposed conditions adjacent to
the project site.
3. Under the proposed condition the minor increase in Regulatory water surface elevation
remains within the watercourse corridor.
4. Under the proposed condition the average channel velocities decrease compared to the
existing condition.
5. Under the proposed condition, there was no hydraulic impact downstream of the project
site.
Respectfully submitted by MMM Group Limited
Asif Quader, P. Eng., Ph.D. Project Engineer Water Resources
Stamped by Maggie Ding on behalf of Asif Quader upon his absence
AP
PE
ND
IX A
– H
EC
-RA
S R
ES
UL
TS
1814292: 514 South Service Road
Existing Condition Hydraulic Assessment
Reach River Sta Profile Q Total Min Ch El W.S. Elev Crit W.S. E.G. Elev E.G. Slope Vel Chnl Flow Area Top Width Froude # Chl
(m3/s) (m) (m) (m) (m) (m/m) (m/s) (m2) (m)
Reach-1 3.5 PF 4 16.8 103.89 105.42 105.25 105.74 0.00626 2.79 8.44 9.66 0.75
Reach-1 3.49 PF 4 16.8 103.75 105.35 104.99 105.62 0.005131 2.6 10.51 17.81 0.69
Reach-1 3.48 PF 4 16.8 103.97 105.28 105.13 105.54 0.005845 2.59 10.78 19.92 0.73
Reach-1 3.47 PF 4 16.8 103.89 105.21 105.21 105.44 0.005514 2.46 13.15 34.12 0.7
Reach-1 3.46 PF 4 16.8 103.29 104.67 104.13 104.75 0.00162 1.37 16.81 21.85 0.38
Reach-1 3.45 PF 4 16.8 103 104.29 104.29 104.68 0.010577 3.35 8.34 12.13 0.97
Reach-1 3.44 PF 4 16.8 102.54 103.65 103.73 104.19 0.018288 3.9 6.26 8.1 1.22
Reach-1 3.43 PF 4 16.8 102 103.27 103.15 103.61 0.007159 2.8 8.42 12.07 0.8
Reach-1 3.42 PF 4 16.8 101.3 103.33 102.89 103.46 0.002087 1.99 15.37 16.6 0.45
Reach-1 3.41 PF 4 16.8 101.3 103.3 102.89 103.44 0.002245 2.04 14.9 16.37 0.47
Reach-1 3.4 Culvert
Reach-1 2.93 PF 4 16.8 101.12 102.26 102.25 102.27 0.000678 0.57 29.28 42.9 0.22
Reach-1 2.92 PF 4 16.8 101.02 102.25 102.25 102.27 0.000443 0.5 33.33 42.9 0.18
Reach-1 2.91 PF 4 16.8 100.68 101.03 101.27 102.08 0.199906 4.54 3.7 17.43 3.15
Reach-1 2.9 PF 4 16.8 100.34 101.08 100.93 101.16 0.006185 1.24 13.5 32.71 0.62
Reach-1 2.858 PF 4 16.8 100 100.97 101 0.001659 0.76 22.08 41.73 0.33
Reach-1 2.84 PF 4 16.8 99 100.64 100.64 100.92 0.008416 2.68 10.21 21.39 0.79
Reach-1 2.83 PF 4 16.8 98.59 100.12 100.32 100.74 0.030313 3.49 4.99 10.85 1.38
Reach-1 2.829 PF 4 16.8 98.37 100.54 99.11 100.54 0.000104 0.49 78.58 83.83 0.11
1814292: 514 South Service Road
Porposed Condition Hydraulic Assessment
Reach River Sta Profile Q Total Min Ch El W.S. Elev Crit W.S. E.G. Elev E.G. Slope Vel Chnl Flow Area Top Width Froude # Chl
(m3/s) (m) (m) (m) (m) (m/m) (m/s) (m2) (m)
Reach-1 3.5 PF 4 16.8 103.89 105.51 105.24 105.78 0.004978 2.59 9.35 10.31 0.67
Reach-1 3.49 PF 4 16.8 103.75 105.47 105.68 0.003616 2.31 11.08 15.01 0.58
Reach-1 3.48 PF 4 16.8 103.97 105.43 105.08 105.63 0.003772 2.25 11.31 13.39 0.6
Reach-1 3.47 PF 4 16.8 103.89 105.07 105.07 105.51 0.0111 3.22 6.94 9.44 0.98
Reach-1 3.46 PF 4 16.8 103.29 104.67 104.12 104.75 0.001605 1.36 16.27 17.44 0.38
Reach-1 3.45 PF 4 16.8 103 104.3 104.3 104.68 0.010545 3.35 8.35 12.14 0.97
Reach-1 3.44 PF 4 16.8 102.54 103.65 103.74 104.2 0.018772 3.94 6.2 8.07 1.24
Reach-1 3.43 PF 4 16.8 102 103.27 103.16 103.61 0.00713 2.8 8.44 12.09 0.8
Reach-1 3.42 PF 4 16.8 101.3 103.33 102.89 103.46 0.002081 1.99 15.39 16.61 0.45
Reach-1 3.41 PF 4 16.8 101.3 103.3 102.89 103.44 0.002237 2.04 14.92 16.38 0.47
Reach-1 3.4 Culvert
Reach-1 2.93 PF 4 16.8 101.12 102.26 102.25 102.27 0.000678 0.57 29.28 42.9 0.22
Reach-1 2.92 PF 4 16.8 101.02 102.25 102.25 102.27 0.000443 0.5 33.33 42.9 0.18
Reach-1 2.91 PF 4 16.8 100.68 101.03 101.27 102.08 0.199906 4.54 3.7 17.43 3.15
Reach-1 2.9 PF 4 16.8 100.34 101.08 100.93 101.16 0.006185 1.24 13.5 32.71 0.62
Reach-1 2.858 PF 4 16.8 100 100.97 101 0.001659 0.76 22.08 41.73 0.33
Reach-1 2.84 PF 4 16.8 99 100.64 100.64 100.92 0.008416 2.68 10.21 21.39 0.79
Reach-1 2.83 PF 4 16.8 98.59 100.12 100.32 100.74 0.030313 3.49 4.99 10.85 1.38
Reach-1 2.829 PF 4 16.8 98.37 100.54 99.11 100.54 0.000104 0.49 78.58 83.83 0.11