hydraulic l: · 2017. 11. 13. · degree v-notch weir, from which it was conveyed through the...
TRANSCRIPT
![Page 1: HYDRAULIC L: · 2017. 11. 13. · degree V-notch weir, from which it was conveyed through the underground distribution system to the short section of the main canal by way of the](https://reader035.vdocument.in/reader035/viewer/2022071300/6090f8f7a76d3426c32069f2/html5/thumbnails/1.jpg)
·I
• .
..
, 1,.' 'V, .
_;__,
HYDRAULICS BRANCH OFFICIAL FILE COPY
HYDRAULIC L:�·-.
*************************
*
* * -�--�
*
* *
UNITED STATES DEPARTivIBNT OF THE INTERIOR
BUREAU OF RECLAMATION
HYDRAULIC LABORATORY REPORT NO. 184
HYDRAULIC MODEL S7UDIES FOR THE DESIGN OF THE PILOT KHOB liASTEViAY
BOULDER CANYON PROJECT ALL-JJIERICAN CANAL SYSTEM
By
J. ir. Ball
- - �
; s,._-··Donvcr, Colorado October 12, 1945
********** * ***********
-�
-�--�-
![Page 2: HYDRAULIC L: · 2017. 11. 13. · degree V-notch weir, from which it was conveyed through the underground distribution system to the short section of the main canal by way of the](https://reader035.vdocument.in/reader035/viewer/2022071300/6090f8f7a76d3426c32069f2/html5/thumbnails/2.jpg)
PREFACE
The program of h7draulic model studies to develop a satisfactory design tor the Pilot Knob W&st.ew111 on the All-American Canal in California, five miles weet of Yuma, Arizona, wa.e performed in the hydra.ulic laboratoey of the Colorado A. and M. College at Fort Collins, Colorado between September 1936 and Kq 1937. 'lhe investigations concerned the flow conditions at the entrance, 1n the gate section, the chute, the stilling pool and the downstream channel of the wa.steway structure. The
studies were conducted on a l to 36 model of the complete wastew'1, including a short section of the All-American Canal, and a l to 12 model of a single by-pass sluiceway of the gate section of the wa.stewa.;r.
The model tests were conducted by D. M. Lancaster, H. W. Brewer and
M. R. Spindler. Mr. J. M. Buswell was in immediate charge of the con
struction and testing of the models and assisted in preparing the data
for this report. The work was supervised by J. w. Ball under the general
direction of J. E. Warnock. Urgent work in the laboratories prevented
an ear lier completion of the report.
![Page 3: HYDRAULIC L: · 2017. 11. 13. · degree V-notch weir, from which it was conveyed through the underground distribution system to the short section of the main canal by way of the](https://reader035.vdocument.in/reader035/viewer/2022071300/6090f8f7a76d3426c32069f2/html5/thumbnails/3.jpg)
UNITED STATES DEPARTMffiT OF THE INTERIOR
BUREAU OF �LAMA TION
Branch of Design and Construction Engineering and Geological Control and Research Division
Laboratory Report No. 184 Hydraulic Laboratory
Denver, Colorado October 12 ., 191+5
Compiled by: Reviewed by:
J. w. Ball J. E. Warnock
Subject: ff7draulic model stwiies for the design of the Pilot Knob
Waeteway - All-American Canal System - Boulder Canyon Project.
INTRCDUCTION
1. Location and Oescription.-The Pilot Knob wasteway is located on
the All-American Canal in California, approximately five miles west of
Yuma., Arizona (figure l). It conaiata of an intake section ., gate sec
tion, chute, and stilling pool. The structure (figures 2 and 3) will
waste water into the Colorado River continually to supply the Alamo Canal
until the Pilot Knob Power Plant is constructed and will be used after
wards to regulate the water surface in the All-American Canal and waste
surplus water when units in the power plant are not operating.
A concrete-lined channel normal to the center line of the All-Americon
Canal, forms the intake of the waeteway. This channel, joined to the
side of the canal by transitions, leads to a gate section consisting of
four large and two small radial gates, which assist 1n controlling the
water level in the main canal by regulating the flow through the wasteway.
It is estimated that the discharge through the gates will vary from 2,000
and 13,155 second-feet, until the power plant is in operation. The flow
will pass from the All-American Canal through the entrance channel and
the gate structure into a concrete-lined chute under the Southern Pacific
Railroad to the stilling pool, thence into the Ala.mo Canal or the Colorado
River, by way of the Rockwood heading. With water flowing through the
wasteway, the Rockwood heading will control the minimum depth of tailwater
to 16.5 feet for all discharges. With the Colorado River in flood stage,
![Page 4: HYDRAULIC L: · 2017. 11. 13. · degree V-notch weir, from which it was conveyed through the underground distribution system to the short section of the main canal by way of the](https://reader035.vdocument.in/reader035/viewer/2022071300/6090f8f7a76d3426c32069f2/html5/thumbnails/4.jpg)
it is possible for the tailwater to reach a depth of 29.5 feet. With no
water in the Colorado River, the Alamo Canal, or the wasteway, the esti
mated minimum depth is 9.5 feet. Normally the total drop from the water
in the canal to that in the �tilling pool will be 57 feet.
Models of the wasteway on a scale of 1 to 36 and of one by-pass
sluiceway to a scale of 1 to 12 were constructed in the Fort Collins lab
oratory for the pw-pose of checking the adequacy of the hydraulic features
of the wasteway structure.
2. Scope of Tests.--Smooth entrance conditions are essential to the
satisfactory operation of a chute or spillway, thus detailed investigations
were made concerning the right-angle entrance from the main canal to the
wasteway channel.
It is important that the Pilot Knob wasteway have sufficient capac
ity to discharge the entire flow from the main canal in an emer8ency. As
the capacity of a structure depends on the efficiency of the control sec
tion, and the efficiency is lowered by any unnecessary hea.d loss, the
investigations concerning this part of the structure involved the stream
lining of parts of the gate section.
Features of any structure operating as continuously as it is expected
the by-pass sluiceways of the Pilot Knob Wasteway will be operated, should
give flow conditions with as little disturbance as possible. Extensive
tests were conducted on the l to 36 wasteway model and a 1 to 12 model of
a single by-pass to study flow conditions in the channel below the gate
section and within the sluice conduit. The by-pass capacity was obtained
during the investigation.
The material, underlying and adjacent to the full-sized structure
being ot an easily erodible nature, made it of vital importance to dissi
pate, as completely as possible, the energy in the high-velocity water
entering the pool. Instability ot excavation slopes due to shallow water
table and seepage, governed the pool depth. The shallow pool thus deter
mined was necessarily of greater width than the channel immediately below
2
![Page 5: HYDRAULIC L: · 2017. 11. 13. · degree V-notch weir, from which it was conveyed through the underground distribution system to the short section of the main canal by way of the](https://reader035.vdocument.in/reader035/viewer/2022071300/6090f8f7a76d3426c32069f2/html5/thumbnails/5.jpg)
the gate section of the wasteway. Thie greater width introduced the problem of spreading the flow uniformly over the entire width of the
pool entrance so as to obtain the proper relation between the upetream
and downstream depths tor formiJ!lg the hydra•lic jwap. A!ter detailed
st\ldy, the spreading was accomplished by introducing a superelevation or
spreader at the junction of the slopes in the channel connecting the gate
section with the stilling pool. The problem en the stilling pool involved the design of tea.turee
directly responsible for dissipating the energy contained in the influent
water and tor protecting the stilling pool etr�cture. Length of pool,
size of sill, aize and effectiveness of the toothed apron at the pool
entrance, shape ot exit transitions, and extent of downstream riprap were
important factors considered.
J. Summary of R•umlts.--Entrance transition designs eliminating
excessive turbulence, were evolved from the model tests.
By altering and streamlining t.he control section slightly, it••
possible to increase the eapacitT s�fficient.ly to handle the flow of the·
main canal. Improvement in the action of the by-pass sluicewa.ys was obtained by
making the exit angle into the wasteway chute leas abrupt and by placing
a beam in the roof of each conduit. A eatiefaetor, means was found tor spreading the wasteway flow from
the channel width to that. of tbe s\illing pool. This was accomplished by
euperelevating the vertical curve s;ymmetricall.T about the wasteway center
line between stations 5+50.3 and 6�10.J.
A pool 60 feet long, with a ioothed apron 2¼ feet high at the en
trance and a 5-foot dentated sill at the downstream ead, wa.s found best
suited to the operating eonditiona ot the wasteway. A shorter pool gave
rough surface conditions and a· longer one was never utilized. completei,.
It was found that the paving in the tailrace below the apron was not
easential to the satisfactory n,draulie action o! the stilling pool.
3
![Page 6: HYDRAULIC L: · 2017. 11. 13. · degree V-notch weir, from which it was conveyed through the underground distribution system to the short section of the main canal by way of the](https://reader035.vdocument.in/reader035/viewer/2022071300/6090f8f7a76d3426c32069f2/html5/thumbnails/6.jpg)
The model with all the improved features incorporated is shown on
figure 4 and plate 1. THE INVESTIGATION
4. Description of Models. --A metal-lined timber bead tank, repre
senting the short length of the All-American Canal adjoining the wasteway,
was attached to a 2-foot riser of the underground distribution system of
the laboratory (figure 4). The 1:36 model wasteway intake, containing
the left entrance transition formed of concrete, was a metal-lined flume
attached to the tank representing the portion of the main canal. The flume led to the control section, which was constructed of redwood. The piers were made of the same material and the radial gates were fabricated
of heavy galvanized iron. A wooden chute lined with lightweight sheet
iron was used for conveying the discharge to the stilling pool. The
stilling pool, constructed of wood, was placed in a metal-lined tank
which contained sand to represent the tailrace. An adjustable weir at
the end of the sand box, hinged at the bottom, was Qsed to regulate the
tailwater elevation, which was measured by a float gage attached by a
pipe to a piezometric opening in the tailrace.
The model discharge or l. 69 second-fe�t, which represented the design
capacity of the prototype, or 13,155 second-feet, was measured b� a 90-
degree V-notch weir, from which it was conveyed through the underground
distribution system to the short section of the main canal by way of the
two-foot riser. The water then nowed into the intake, normal to the
center line of the canal, through the gate section, chute, and stilling
pool to a channel which returned it to the laboratory circw.ating system.
The elevation of the water surface in the main canal was measured by a
point gage fastened to the side of the intake tank.
A metal-lined wooden box attached to the laboratory supply system
represented the entrance channel of the wasteway in the 1:12 model of the by-pass sluiceway (figure 7). Piers of redwood were extended into
the box to supply the proper entrance conditions to the model. '!be well
4
![Page 7: HYDRAULIC L: · 2017. 11. 13. · degree V-notch weir, from which it was conveyed through the underground distribution system to the short section of the main canal by way of the](https://reader035.vdocument.in/reader035/viewer/2022071300/6090f8f7a76d3426c32069f2/html5/thumbnails/7.jpg)
structure containing the gate and the downstream conduit of the sluiceway
were constructed of redwood. The radial gate was of sheet metal and the
conduit downstream from the gate was provided with a covering of trans
parent plastic sheet to permit viewing the flow within.
5. Preliminary Tests.--The initial test, in which the model was
operated throughout the discharge range, indicated that it would be desir
able to make changes in the design of several features of the wasteway.
These included the transition of the left intake wall, the gate section,
the b7-paas sluicewqe, the chute, and the etilling pool.
6. Study of the Left Entrance Transition.--Flow conditions in the
entrance channel were very good when the gates were operating to maintain
a constant level in the canal and small quantities were being discharged.
However, rough now existed at the original left entrance transition
(design 1, figure 5), when the gates were completely raised and various - -
discharges passed through the wasteway. In view of this action, a satis
factory design for the maximum discharge was considered the criterion and
subsequent tests were made accordingly. The disturbance at the transition
was caused by the contraction and loss of head resulting from the abrupt
change in direction of the flow from the canal to the wasteway (plate 2B).
This sharp angle caused the flow to be deflected toward the right wall of
the intake, producing a high water surface at the right end of the gate
section.
The design of this transition was altered to improve these conditions.
The second design (design 2, figure 5) consisting of a warped surface
between a straight line at the top and an arc at the base, gave improved
flow (plate 2D) but the disturbance at me.ximwn discharge indicated that
the transition was still too abrupt. A new design, introducing a more
gradual transition consisting of a curved surface between two horizontal
circular arcs of equal radii, or a segment of an inclined elliptical
cylinder, wa& tried (design 3, figure 5). Practically all surface dis
turbances were eliminated with this design. It performed similarly for
5
![Page 8: HYDRAULIC L: · 2017. 11. 13. · degree V-notch weir, from which it was conveyed through the underground distribution system to the short section of the main canal by way of the](https://reader035.vdocument.in/reader035/viewer/2022071300/6090f8f7a76d3426c32069f2/html5/thumbnails/8.jpg)
all discharges and was the most desirable of the shapes so far as hydrau
lic conditions were concerned (plate 2F). However, it was objectionable
because of complex construction. A third design, a combination of this
and the previous shape, and of simpler construction, was installed (design
4, figure 5). The turbulence increased but since operation at the maxi
mum discharge was expected to be infrequent, this action was not considered
critical and the shape was approved for the final design.
7. Study of the Gate, or Control Section.--The submerged condition
which existed for the design discharge on the original control section
(plate 3B), was,next investigated. Observations indicated that the sub
mergence was due to excessive head loss resulting from the contractions
at the ends of the gate structure. The condition was present whether the
sluices were open or closed.
Several transitions with openings for the by-pass discharge were
placed in the corners immediately upstream from the gates but none worked
satisfactorily unless they were extended an appreciable distance upstream.
The gate section was free of submergence when temporary extensions to the
piers between the main channel and by-pass gates were held in place, thus
lengthening the piers seemed the most feasible solution. The two outside
piers next to the sluiceways were extended to correspond in length to the
center pier, which was to be used as a support for the highway bridge,
and all semicircular noses except those on the sloping portion at the up
stream end of the short piers were replaced by sharp ones for the purpose
of minimizing the pier contractions (recommended design, design 2, figure
6). With this design, the submergence we.s entirely eliminated, and the
water flowed smoothly through the gate openings (plate 3D). This design
was later revised to shorten the spans and permit more economical bridge
construction. In thie case the center pier was shortened, the two adja
cent piers were extended 21 feet to support the bridge, and the outside
piers were extended a minimum distance to give free !low conditions under
the wa.steway gates (final design, design 3, figure 6). Although waves
6
![Page 9: HYDRAULIC L: · 2017. 11. 13. · degree V-notch weir, from which it was conveyed through the underground distribution system to the short section of the main canal by way of the](https://reader035.vdocument.in/reader035/viewer/2022071300/6090f8f7a76d3426c32069f2/html5/thumbnails/9.jpg)
reached the top of the gate openings occe.sionall.y, the design was considered acceptable and was adopted !or the protot7Pe.
8. Study of the !31-pass Sluicewa.zs.-When the two by-pass sluices located on each side o! the gate section of the wasteway were operated alone, their jete came together abruptly at the center of the channel below the gate section. A concentration of now, with considerable splash resulted (plate 4A). This condition, which was attributed to the
impact of the jets upon one another as they flowed tr0111 the 45-degree outlets, was undesirable and the outlet angle was changed to 30 degrees. Considerable improvement was noted (plate 4B) and this design was accepted,
subject to tests on a 1 to 12 model of a single sluice, when it was be
lieved illlpractical to further decrease the outlet angle. The excessive
spray from these outlets at partial gate openings and the pulsating !low,
which seemed to occur in the sluice immediately downstream when the gate
was raised completely, made it desirable to stud7 the now conditions in
more detail. A model of the right sluice on a scale of l to 12 was con
structed for this purpose, (figure 7). The construction of a sloping
downstream wall in the gate well 1n the larger model eliminated the pul
sating action. The spray at partial gate openings was more noticeable
than at full gate (plate 4) and the cause was obvious when the conditions
were viewed through the transparent top of the model. The high-velocit7
water impinged on the JO-degree outside wall of the tunnel and was turned
upward to the roof, thence back upstream toward the wasteway channel where it covered the top of the opening as it left the tunnel exit. This thin jet produced spray and closed the conduit exit completely !or all except
very small flows. These objectionable characteristics were reduced to a
minimum by placing a protruding beam in the root of the conduit (figure
7 and plate 4). Moreover, the beam served to aerate the tunnel at all
flows. The sluice was calibrated !or various water surface elevations in
the canal with the gate raised completely and a head-discharge curve pre
pared (figure 7). After the final design had been determined, the sluices
were installed on the l to 36 model where testing was resumed on th•
7
![Page 10: HYDRAULIC L: · 2017. 11. 13. · degree V-notch weir, from which it was conveyed through the underground distribution system to the short section of the main canal by way of the](https://reader035.vdocument.in/reader035/viewer/2022071300/6090f8f7a76d3426c32069f2/html5/thumbnails/10.jpg)
hydraillc features downstream from the control section.
9. Study of the Chute and the Stilling Pool.-The chute leading from the control section to the stilling pool consisted of two sectione of eloping channel connected by a vertical curve. The upper part on a
slope of 0.006 had a constant width, while the lower part on a J to l
slope had its walls nared symmetrically, increasing the width from 62 to
140 feet {design 1, figure 8). The conditions in the upstream portion of
the chute were satisfactory for all gate combinations and it was not necessary to alter this pa.rt of the wasteway. The flow through the vertical curv& and down the 3 to 1 slope tailed to spread sufficiently to follow
the diverging walle, thus the water was conoentrated 1n the center of the
chute as it entered the stilling pool. The concentration interfered with
the formation of the hydraulic jwnp and gave objectionable turbulence in
the stilling pool. The action indicated that better results would be
obtained with a narrow and deeper pool but this design was prohibited
geologically, thus a means was sought for spreading the jet uniformly
across the width of the pool.
Consideration was given to flaring the channel immediately below the
gate section, but due to the increase in construction coat this plan was
abandoned in favor of a auperelevation of the vertical curve. Several
shapes of this t;ype of diffuser, with the superelevation symmetrical about
the center-line of the waste1¥8Y, were investigated (designs 2 to 10, fig
ure 8). Because the size, shape, and position of the superelevation were
important factors influencing its efficiency, these characteristics were
varied until the most efficient design for the range of discharge was obtained. The diffusers became more effective when placed on the more gradual slope where the velocity of the water was less. This was attrib
uted to the greater spreading action produced by gravity on the more gradual slope. The superelevation was, therefore, placed as far upstream
as feasible without reducing the wasteway discharge, preventing draining of the channel, or producing undesirable waves in the channel at low dis
charges. The spreading was not complete for all discharges in any case,
8
![Page 11: HYDRAULIC L: · 2017. 11. 13. · degree V-notch weir, from which it was conveyed through the underground distribution system to the short section of the main canal by way of the](https://reader035.vdocument.in/reader035/viewer/2022071300/6090f8f7a76d3426c32069f2/html5/thumbnails/11.jpg)
but was more uniform over a wider range on the final than on aey of the other designs ldesign 7, figure 8). The design selected proved very effective in spreading the uneven now when the gates were.operated wi�
symmetrically (plate 7). With satisfactory entrance conditions for the
pool assured, tests concerning the adequacy of the pool were conducted. 10. Study of the Stilling Pool Design.--The pavement downstream from
the sill of the original design of the stilling pool was omitted in the model because it was desired to study the effectiveness of various designs
in minimizing the erosion of a pool bottom of silt and fine sand. Jforeover, it did not seem essential so far as the operation of the pool was
concerned to pave such a large area downstream from the apron.
Since under certain conditions of operation it was possible for all
the gates in the control section to be opened suddenly, allowing 13,155
second-feet of water to flow into the stilling pool with the tailwater at
its minimum elevation, it was imperative that the structure be designed
for this contingency. With these conditions the hydraulic jump was completel.Jr swept from t.he original apron (design 1, figure 8). Streaming now carried beyond the square sill where a standing wave .formed and rather
severe erosion occurrede It was noted that a substantial increase in
tailwater depth was necessary to retw-n the b,1draulic jwap t.o the apron
wbe-n this condition was present, and that a slight increase in tailwater
depth would move the jump upstream only if the jwnp were formed partially, with the streaming .flow passing under the surface layer of tailwater. In
view of this observation, it was essential for the hydraulic jump to form
with its upstream edge in front of the sill, such that streaming flow
ceased to carry be7ond it into the tailrace at the minimum tailwater ele
vation. With this condition, the jump would move back rapidly on the
apron as the tailwater increased t.o its normal elevation. It was esti
mated that normal tailwater on the prototype would be established in about
15 minutes, so the fa.ct that the jump formed near tbe end of the pool for
the minim.um elevation was not critical.
9
![Page 12: HYDRAULIC L: · 2017. 11. 13. · degree V-notch weir, from which it was conveyed through the underground distribution system to the short section of the main canal by way of the](https://reader035.vdocument.in/reader035/viewer/2022071300/6090f8f7a76d3426c32069f2/html5/thumbnails/12.jpg)
The original deeign apron (design 1, figure 8) was too short when
the streams leaving the tops ot the high steps o! the toothed apron at
the upstream end of the pool floor arched over the downstream sill and
struck the sand portion of the tailrace. Smaller steps and a longer
apron were installed to eliminate this condition (design 2, figure 8).
'!'he square sill was replaced b7 a 21-toot Rehbock sill. The jump did
not sweep off the apron at maximum discharge with a tailwater elevation of 104,0, but the pool seemed to have more than sufficient length and
the sill too 8118ll. Accordingly, the height ot the sill was increased
to 5 feet and the pool shortened to its original length (designs 2 and 3,
figure 8). The jump still formed on the apron but a high roll appeared
over the sill, indicating that the apron needed more length. Before it
was lengthened,bowever, tests were made to determine the essentiality of
the upstream steps (toothed apron). They assisted materially in keeping
the hydraulic jump on the apron and were indispensable for operating at
the low tallwater elevations. The pool length was increased to 60 feet and the appearance was much improved. The steps were as essential as
with the ahorter apron and were recommended tor the prototype. Tests on
this arrangement indicated that the pavement downstream from the end ot
the pool could be replaced by a 50-foot band or riprap and that the
warped wing walls could be shortened considerably. Also, that the warped
walls were essential in preventing erosion near the downstream corners o!
the apron. When an acceptable design had been evolved (figure 9) perform
ance tests were made and the model was demonstrated to the design section.
The arrangement proved satisfactory for all conditions under which it was
expected to o�erate, including gate combinations (plates 5, 6, and 7)o
Slight changes in the pool to take care of structural features, which
included pavement downstream from the sill and increased warp length,
were inatalled and checked by model tests. The results remained unchanged
and the plan was adopted.
10
![Page 13: HYDRAULIC L: · 2017. 11. 13. · degree V-notch weir, from which it was conveyed through the underground distribution system to the short section of the main canal by way of the](https://reader035.vdocument.in/reader035/viewer/2022071300/6090f8f7a76d3426c32069f2/html5/thumbnails/13.jpg)
CONCLUSIONS
11. Waetmy StNoture.--The·waateway design, as evolved. from the
hydraulic model stwiiee (r-igure 4) will, under all conditions ., adequately
and efficiently control flows up to and including the maximum design dis
charge of 13,155 second-feet.
12. Entrance Trans1tions.-There will be smooth flow conditions at
the wasteway entrance transition for all discharges except those near the
maximum. It is anticipated that the wasteway will seldom operate at these
discharges, so the rough surface conditions, which did not appear objec
tionable on the .model, should not prove critiea.l.
Smooth flow conditions· will always be present at the original design
transition on tbe upstream end of the right wall ot the approach section
when the operation is the same as that of the model.
13. Gate or Control Section.--A rearrangement and lengthening of the
end piers of the gate structure decreased the head loss due to contractions
at the ends of this section and eliminated submerged now through it.
Better results were obtained when longer piers were used, but further ex
tena1on was not considered justified when these piers were not needed for
supporting the highway- bridge1 which crossed upstream from the gate section.
14. Bz-pass Slu.icewys.-The waves and splash resulting from the
impingement on each other of the sluiceway jets were materially reduced
by changing the angle of the outside exit wall from 45 to .30 degrees and
by placing a protruding beam in the roof of each cond'llit.
15. Chute to Stilling Pool.--The railroad bridge crossing the chute
belew tbe gate section should receive little or no splash for any method
of wasteway operation. The flow through the wastew&y would not spread to the width ot the
stilling pool without the superelevation of the floor of the chute at the·
vertical curve. Superelevating below .the curve was ineffective, while
above the curve it became too effective, dividina the flow into two streams
at low discharges, and forming a standing wave in the channel immediatel,y
upstream. 11
![Page 14: HYDRAULIC L: · 2017. 11. 13. · degree V-notch weir, from which it was conveyed through the underground distribution system to the short section of the main canal by way of the](https://reader035.vdocument.in/reader035/viewer/2022071300/6090f8f7a76d3426c32069f2/html5/thumbnails/14.jpg)
The recommended superelevated spread.er, which is symmetrical about
the center line at the vertical curve, will spread the wasteway flow ver7
uniformly from a width of 62 feet at the upper erid of the ehute te 140
feet at t.he stilling pool entrance tor practically all discharges, thereby
causing an efficient hydraulic jump to fona in the pool . All but very low
flows, which will be divided, forming two streams, one along each wall of
t.he wasteway, will be favorably affected by this superelevation. In arrr case, the conditions for the small discharges are not too objectionable,
especially when it is considered that a change to improve the now for
these discharges resulted in undesirable and possibly critical conditions
for the maximum discharge. The design evolved from the model studies
will give optimum flow conditions throughout the discharge rangeo
16. §tillllyg Pool.--The waateway stilling pool will be very effective
in dissipating the energy of the inflowing water when the t.ailwater becomea
nonaal or above. The JWllp should no\ sweep completely off t.he apron at the maximum
discharge when the t.a.ilwater is abnormally low, but should move downstream
oTer the sill. In event the wasteway should be set into operation sud
denly at_ the maximum discharge, the tailwater will reach the normal ele
vation within a few mimltes and the jump will move upstream into the pool,
thus this condition cannot be considered serious.
The warped walls at tbe end. of the stilling pool a.re eseent.ial in
preventing the formation of return eddies which would scour the banks
below the poC>l. The paved floor downstream .from the apron was not essen
tial to the satistact.ory performance of the wasteway stilling pool.
The riprap at the end of the warped walls is essential in �ing
the wave action on the edges of the pool 1n this vicinity and preventing
scour of tbe channel near the downstream edge of the warp and pavement..
![Page 15: HYDRAULIC L: · 2017. 11. 13. · degree V-notch weir, from which it was conveyed through the underground distribution system to the short section of the main canal by way of the](https://reader035.vdocument.in/reader035/viewer/2022071300/6090f8f7a76d3426c32069f2/html5/thumbnails/15.jpg)
�___:_' ___:_· __ _...:.____:___ __ �--::J·n� N
' · ·o;�id1r
' LOS AHGELl5· · � . . ·. ·. ""t�a H,o,.-r.1 d·r"
.....
r:: f...
,.
K E Y M A P
<0
'-;, ,;, ,,
•..,
···:\ :::
,,,, , , \ ,�� : ._ _ .... .... ,1 , . ,,,
NOT£:
QC' � R 2 1 E R 2 2 E . o � ',,,;·,tf�-<;"tf"� R.2h r4i ,
;,S\
, . ,L I /, ,',
Bo:-row J" t area for compacted f
i
ll shown
thus : fj
. , Knob P I LOT KNOB CHECK AND WASTE WAY
STA. 109 3 •91,: - ,,
T.IG S.
6 C, . p ,. ...... .. -��?:.�'!"' O Ba � •. :
PI LOT �NOB �
-��'l
Cantu (A ndrade
!'iOO
'·, , 1 1 1
t -� ·::!,,'
�[_ �"�
.I
CL .. ,./ _,I i._ --, .-
..,
0
-1-,"-,('• -' .:!
T. l s.
�-� <,[·· ........ .._ .. .. ;
--,J
---..:::· :;. ""'.; '�<;; --� ; ... ,
..../ , , 1,,,, . ., ., ' 11 1 1 , ',, \ \
R.22 W.
::: ," •'' ,,: .. ,;1 , " 1 ' / 1 1 1h\' I I \ \
7.
SCALE OF M I LE S
O E PA A. T M E N T O F T H E I N T E A I O A
B U R E A U OF R E CLAMAT ION
, , ,,, , .. ,,,,,' T 8 5.
?,
8 0 U L D E A CA N Y O N PA O J E C T
ALL-AMERICAN CANAL SYSTEM- CALIFORNIA
A LL - AMER I C A N CANA L - S TA . 1093 + 9 2 PI L O T KNOB CHECK ANoWA S TEWAY
L O CA T I O N MAP
.,... C') )> .... 0 z u,
z 0
--.j (>I --.j
,, Gl t-------------,.,-_--_ -------tc
DRAWN: Kt'� .
R.24W. R.'23W
TJfACCD: .... !i'.MI;, .. .. ..
CHECKED: .H.(?_ . . .. . . . . APPflOV£D : • . . . .
;o ['1
![Page 16: HYDRAULIC L: · 2017. 11. 13. · degree V-notch weir, from which it was conveyed through the underground distribution system to the short section of the main canal by way of the](https://reader035.vdocument.in/reader035/viewer/2022071300/6090f8f7a76d3426c32069f2/html5/thumbnails/16.jpg)
' E C I F I C AT I O N S N o . 7 3 7
G E N E R A L P L A N
100 0 100 ?00
S C A L E OF FE E T
· ·; . . . . ·Avo1/able area for disposal ..._ ·· of excavated materials
'
/ · · · ·::>,.
(
For oddit1onol topoqrophy see Dwq. 212 ·0-2623
r I
.,.... 11 -V- J 180 --< ' ' I I ' \ --- I --
'l> .'l> �
I ' I
0
n 'l> z l> r
\
F l G U K C.. .c.
• [I /00. 0 ·. : . - - - - - · ->' :
r<··- · · · · · · · ·- -·· · 150'·0'
� S£'i X )iifP.J; : �""
£/. � � .
b .t ' ·�
j . A
n 0 t"
\ 0
'<,•·
f E/. 94.50 ,, I ,, ' ·� r .... 24"-Min. riprap • ..... . . . . . . ...... . .. .. as : ,i " . . . . .
SE C TI ON C·C
24• Min. riprap·,
S£CTION B·S
· ·· ·JZ'Dry rock pavinq
SE C TI ON A·A
.. ·· · ·-aockf,11 to fop · of structure · · · ·-.
'-X.<mtrrm'"""--nr--=--::-:-'m-m _,;..,,,.fflf"1e,r,,------:�·
; I · · · · · · · · · · ·· Vories . . . . . . . . .
.. . . . . . .
.. . ,J�/2'
Structure excavation ) below £1. of top of slob.
SECTION OF WAST£ WAY \l. I '!' ' ' 510
SCALE OF ,.£ET
_ ;at:!rol qround surface�- _ _ _ L.------- �����-q�:��������
e
-i ·>: ,. ... . . . . . . ··t'24'·0'··· · · ·· · · · · · + ·�-W�
ste�iro • . . . . . . . .. ,.; . <�;,'
f/. /00. 0-
S£CTI O N D · D
0 10 100
SCALE OF F E ET
O f P A A T M E N T OF T H E / N T E A J O A. 6 U � E AU O F i'\ E C L A M A T / O N
6 0 U L .'.l E R C A N Y O N P R O J E C T
A L L · A M f A I C A IJ C A N A L S YS T E M · C A L / F O A N I A
A L L • A M E A / C A N CANA L · S T A . 1 0 9 3 • 9 2
Pl L O T K N O B CHECK ANO WAS TE WAY
GENERAL PLAN A N D TO P O G R A P H Y
DRAWN H C C
2 9 1 7 1
![Page 17: HYDRAULIC L: · 2017. 11. 13. · degree V-notch weir, from which it was conveyed through the underground distribution system to the short section of the main canal by way of the](https://reader035.vdocument.in/reader035/viewer/2022071300/6090f8f7a76d3426c32069f2/html5/thumbnails/17.jpg)
)
SPEC I F I C A T I ONS No. 7 7
0 ...;
� � 1'-lz".;_ • 5'·0" �
... ... ti !::: � ---
D
, c: I 0 \J
<t C: ..:. �
A -� I . ··Sta. 1092+ 92.79
. · Additional lininq, see _.: Dwq. 2l2·0- 3725
- - - - - - - - - - -- - - - - - - - - - - - - - - -- - - - - - - - - - - - 7 D
I ·Sfa. I093 , I 2. 79
;! · · · · ··•· · ·75'·o· ... . . . . . . . . . . . . . . . . . . 15·. o· "'
I------+ -·· .. t
� � �
. .l§v · I i
. ( I .. ·Sfo. I093 ,92.00 i ====���� � �-=-�·4===·J=::::_..,_..,_ ===========�..,_..,_..,_��=====�====-�= ==-. '-Wasteway I ···Sta. I , 29.11
E i
' . i_ Wastewoy
t . �, Sfo. 2 .�./J···�_,·· '!1--�Hl=:::a:llh-
PLAH M·M
�
t 7 Sta. s,sa
NOTC:Fordetailofpipeinstal/ation see 0wq. ZIZ·D·l64a
[x fend reverse filters to (L IZQOO.
-11,--------+ �
F I G U R E. 3
;.
�,-.,r
8
4'.8'
Sta. o,oo • J· I * · IS 5 _ _;_� � .... ········-/00'-0"·�··-··· ... . ..
. . . . . . -'· · · 60 '. 0" . . .... . . .. ; .... ...... so·. o· . . . . . .. · - ·�·- -..... . "'
;;. : . ·-- .. 5z:a.· . . .
;j
0 .. ... ..; .. � ::? i::i �
l '··
... 0 0 ...
...... ; : : ..:: : t.ii : � ·.., =-=.=.illol
!ii . 0 c,; �
�
.� �
li .. � .. � 0 .!:!,� � Q. "' " � E 111
� � ... --�
..
ln__er, . t<iJ.<lfe. ;_ enter unit _,;___lnterm�diote unit •
1 unit
'*--.-...--w.�r�--�-------"l ' ..,
· 55'.y
Sta. 1096+60.:2.J
... .f/. /48./4
Sta. 1095 ,20.92 �
r' . . - -i A.·A. Canal
°""' �;�" �., "· . • /.� - - - -- · -z. · t
. . .
• 0. �- - -- · -- 69'· o· ·+ . - 69'· 0' . . : ., . •
El. /70. 26 ··,
4· - - ·� �-4 · 0 E L E VATION C · C
· · ·If A -A Canal
� . . . . ..... . . . 59·. o·- . 59 '.0! £ L E. VAT/ON D · D
NOTE: Slope 6"C. l.pipt uniformly btfwttn elevations shown.
.... { Wasftwoy
. '"': . ., . . j:l l IZ-�1° ... JI ·�, r· · Jl ·0- -
6"C. 1 .pipt) �
El. 173. 21,
S £ C TION F· F
S ·�0012· ·'··.
1 0 l t J � � I ul I I I I I
SCAL£ Of f H T
.. : .· . { 6"C. l. pipt·····
'f6"C. l. pipt // \l .,J P L. A N EJ. 144.9� / .!§·c: (FlOO1' />ANt:l/NIS NOT SHOWN)
Sto.J,JJ.11··· .J :,
f/. 173. 04···
[l. /61.3'·--
i :1r·· • . • • • • . . , • . -rf-JJ .. ·· .. ···-r/ZO·O _of' ��r p_� dratn ·· ···· -·ZJ ·O ·• { Pipt·· in �rst filttr
SECTI ON I< · I<
,-Crown · EJ. 173.01 i
S EC TI O N a - a
J F
f Wasft woy· · - - ...
�
. ..... ---fl. /18.31 --� ·£/. /73.04
fl 120.00·.
Reverse filter:.-,
, ... : i
[L /Zi)J)(). El. 127.00·
Mr
E L E VA T I O N G - G
Provide /"layer of cement mortar rwer surrtx:. of reverse filf'ers.·\
•/:/ . ··tto 1fqrovel. · ·f tot"qravel.
·· ·-,f to fqrovel. ··· · ·Sand.
S E:C TI O H L • L
for details of reverse--··,. filter; see Dwq. Zll·D·lGS4
. '<> • :0 � s> � "'
__ El. 94.so·,
. . . . . . . · f./. /27.00
El. 911-SO ··
O f �A Jl T M � N T 01' He IH l flll OA 8Ul'-EAU 0� "I CLAMAT/ 0
8 0 U l.O E A C A NYON P ,._ O .J E CT ALL·AMEAICAN CANAL SYSTEM·CA ll'MNIA
I N
ALL-AM E " I C A N CAN AL · STA. IOIJ • II
PILOT KNOB CHECK ANoWASTEWAY
PLAN AND SECTPONS
![Page 18: HYDRAULIC L: · 2017. 11. 13. · degree V-notch weir, from which it was conveyed through the underground distribution system to the short section of the main canal by way of the](https://reader035.vdocument.in/reader035/viewer/2022071300/6090f8f7a76d3426c32069f2/html5/thumbnails/18.jpg)
1 ¼ : 1
y _ _
;,, -�· - ·
SAND
F I G U R E
,< - - - - - - - - - - - - - 4'-aj· - - - - - - - - - - - - ->: A----------------------,
' �- - - - - -2·-1·-- - - -�
'< - - - - - - - - - - - - - 5'. 4" - - - - - - - - - - - - - - - - - - - - - 20· - - - - ,.; :
I :
' '
- - - - - - - - - - - - - - - - ,· -4a· - - - - - - - - - - - - - - - - - - ->:<- - - - - - - - - - - - s·- ,H·- - - - - - - - - - - - - - - -� :;.�·
�- -
�= • <:" - · N '
_y : �. :_)· · - - CONCRETE LINIIIG · -rr·•
�- - - - - 2 3• - - - - : �- - - - - - - - - - - 45• _ _ _ _ _ _ _ _; _ _ __ ::.,!
,,:s
. ' · . '·t--- -, __ ......
. u . · , ·� ·- . · , . [.. . . ··_ · ;;
___ .)
' ' ' ' . ... ... ' . �
S• .001 2
P L A N
. - E l . 1 4 6 .88
l-
0
36 18 0
F I N E S A N D A N D SI LT
I j I i t . I ·:
I � I 1 1 I i i
... <Z .. .. Q z <Z ...
... a ,,. _, ... ... .. ... <Z
j
-<· - - - - - - - - - - - - - - - 1 2 '- 1 1' - - - - - - - - - - - - - - - - - - - - - - - - - - - · - - - � - - - - - - - - -+ - - - - - - - - - - - - - - - - - - - - 7'- D"· - - - - - - - - - - - - - - - - - -
E l . 1 4 5.68 - . .. S • .006
S E C T ION ON C E N T E R L I N E OF WAST E WAY
50
S C A L E O F F E E T - M O D E L 3 4
100 1 50 200
6
S C A L E O F F E E T - P R O T OT Y P E
8
250 300
9 10
350
O E P A R T II E � T OF' T H E l llf T E: R t O R B U R E A U OF RECLAM A T I ON
B O U L D E R C A N Y O N P R O J E C T
A LL- AM E RICAN CANAL SY STEM · CA L I FO R N I A
PI LOT .K N O B WAST E WAY HYDRAULIC MODEL STU D I ES
M O D E L S C A L E 1 : 5 6 GENERAL MODEL LAYOUT - R ECOMME NDED DESIGN
DAA"'frill "· • e .
T A A C l O . A _W ._� - -� ._L . A A I C0• 1t Ulfl O I D
C M I C • I O APPltOV i D DI NVl•. OOLOa&OO·CIICl•MR 11, 1911
![Page 19: HYDRAULIC L: · 2017. 11. 13. · degree V-notch weir, from which it was conveyed through the underground distribution system to the short section of the main canal by way of the](https://reader035.vdocument.in/reader035/viewer/2022071300/6090f8f7a76d3426c32069f2/html5/thumbnails/19.jpg)
,c- - t f� I - - - -
L E F T I N TA K E W A L L " .
y E L 1 7 3 2 7
--C- - r f I
F I G U R E 5
' • S C R E E D L I N E S .L TO P O F W A L L
P L A N
{ - E L 1 7 3 2 7
, . - F L O O 'l O F W A S T E W A Y �. '"" " t -.W,WJ.;J.1.1...W....l....J.-.....!.I'_. ·_·_;E_L_l 4_B_l_4�t::;'_'...J
I N T A K E . 5 , 00 1 2
E L E V A T I O N
D E S I G N
..c - - , f: I - - - - _ ,, , · I'\,
,_.'"'--___ __...._ • • �- S'-i
P L A N
��:'} E L E V A T I O N
D E S I G N 3
1 r'I 0 5 0
E L E V A T I O N
D E S I G N 2
· · · S C R E E D L I N E S .L T O P OF W A LL
P L A N
� ,:,�:�:� "} , oo
E L E V A T I O N D E S I G N 4
S C A L E I N F E E T - P R OT O T Y P E
P l L O T K N O B W A S T E W A Y
E N T R A N C E T R A N S I T I O N M O D E L S T U D I E S
D E T A I L S O F T R A N S I T I O N S H A P E S
![Page 20: HYDRAULIC L: · 2017. 11. 13. · degree V-notch weir, from which it was conveyed through the underground distribution system to the short section of the main canal by way of the](https://reader035.vdocument.in/reader035/viewer/2022071300/6090f8f7a76d3426c32069f2/html5/thumbnails/20.jpg)
A -t_
A 1._
J M 8
12" R
'-<- 2 3'-6" -
: - 2 4"
- � 2'-9'
- - - - - - ->- FLOW
H A L F P L A N
6"-3" R
0 -<-- -2 3'-6"
0
6'- 3"R
,.._ 10'-9"
6' -3 "p
H A L F P L A N
111 I I ' I
1 : I I I I I I I
I -- ..... --:_:.:::: ...
�-.---::::---�.-
..-- II . . . . SECT I O N A � A
D E S I G N 3
}A
It_
10
.J-'- A
A t_
C,
SCA L E I N
F I G U R E 6
' 6'- 3 R
" 2 3'-6"
6 - 3" R 0
Q
6'- 3" R
_j A
H A L F P L A N
I
. I I
i I I I I
. ----_-::-:::• --- --,,.-__:_:.::---
---S EC T I O N A - A
D E S I G N 2
,o 20 3r
I F E E T - PROTO T Y P E
P I L O T K N O B W A S T E W A Y C O N T R O L S E C T I O N M O D E L S T U D I E S
D E TA I L S O F P I E R A R R A N G E M E N T
![Page 21: HYDRAULIC L: · 2017. 11. 13. · degree V-notch weir, from which it was conveyed through the underground distribution system to the short section of the main canal by way of the](https://reader035.vdocument.in/reader035/viewer/2022071300/6090f8f7a76d3426c32069f2/html5/thumbnails/21.jpg)
F I G U RE 7
WALL OF HEAD TANK
l'------1
�iN ...
, . "' 0 0 0 -- ! " -
i : 1
0 lo II:: 20 Q. 1-1&1 ILi I&. I 1 9
0:: 0 0 ...J
&\"ll
e,
2 4"
- � r � ' / ·-: �- �-, � : : 1 :
4
30 \¼"
P L A N
,---- -4' - � - ,if ll
- ' -
1 1 f
S E C T I O N A LO N G C E N T ER L I N E
M O D E L S C A L E I N I NCHES 0 I 2 3 4 5 6 7 8 9 10 �-+--+---+----+--+--+--+-+---<
0 I 2 3 4 5 6 7 8 9 1 0
P R O T O _ S C A L E I N F E E T
i ·-
I [ I I i I i ! / ' I I ,
�
I i I I I / �+�- 1' ! +- --t -t-- - - - --- + :-....-------
./
�-t--+---t---t I I I I .A""
i I ' v.� I I&. ILi 1 8 0
� -1-- -� --+ I -t� -- - -- t------:c,0$� t I
--� --
1
1 I ��,., i I i
p�--t---+----1"---t--
ii----;---t----t---+----1
<(
1-
ILi 1 7
ILi 0
Ill 1 6 ILi
m <(
O 1 5 <( ILi J:
- - I ! i v� _..;
i-- - - -� I /' i
I 1 � '/
- � -- - -
NOTE
I / SLUICEWAY G ATES WERE
COMPLETELY RAISED
I/ 1 -
1 900 2000 2 100 2200
P R OTOTY P E D I S C H ARGE IN S E CO N D - FE E T - BOTH SLU I C E S
P I LOT K NOB WASTE WAY
D I S C HARGE CURVE - BYPA S S SLU ICES
- ft 0PYRAL I N TOP
"- ' "- Jo• '-----.___
-
�'-,
D E PA R T M E N T OF TH E I N T E R I O R B U R E A U O F R E C L A M A T I O N
B O U L D E R C A N Y O N P R O J E C T
�'
-..,
ALL A M E R I C A N C A N A L S Y S T E M - C A L I FO R N I A
P I LOT KN O B WA S T E W AY H Y D R AU L I C M O D E L S T U D I E S
BY- PASS S LU I C E - S C A L E I : 1 2 M OD E L LAY O UT A N D D I S C H A R G E C U R VE �
D R A W N . . , . �: � -.Ill . . . . . . . . . SU B M I TT E D • . . . . . . . . . . . . . . . , . . . . • . . . . C T R A C ED. _E; �; �-.-. '? -.1 : � · . . . . . RECOMM E N DE D . . . . . . . . . . . . . . . . . . . . . . . . . . . iO CHEC K E D . . . . . . . . . . . . . . . . . APPROVED.-. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . f'1
- -- · · · - - - - - -- - -- --DENVE R , COLORADO - DEC. Z7, 19::MI ..J
![Page 22: HYDRAULIC L: · 2017. 11. 13. · degree V-notch weir, from which it was conveyed through the underground distribution system to the short section of the main canal by way of the](https://reader035.vdocument.in/reader035/viewer/2022071300/6090f8f7a76d3426c32069f2/html5/thumbnails/22.jpg)
i---
! i � -+--+-- ------ -+-+:
L_ __ , ___ _ -
S• .006 · · ·E l . 145.7
�
�;;38.5
l- - ·
' '
FLOOR ELEVAT ION
DES IGN I
·::: -+--+--- --n--
L _____ _
�·3 _£1138 5
l · • "' . \? •. 0. "' SEC. ON t
DE S IGN 6
.... -.. t " ::rj
""l �
·., N
r1t-3· .. I I i ---n··)
� -tf-1'1 3--
! !
F I G U R E. 8
. ' "' ' J
�El. 138.5
�
-l 1 2' i N
-_.E 1. 138.5
. · • V D �
·r D El 138 5
· . ..... 30 __ ,., � . .
� �o:: ' 0 � ?�, 138 5 -. ·,v· .� : - �r� ...
S E CT ION ON t SECT ION ON t
D E S I GN 3
S EC. ON l ..,Jl !'>
SEC. ON t :
D E S IGN 2 D E S I G N 4 DES IGN 5
VERT ICAL CURVE :· BEGINS ENOS ··.
P L A N
�� .
�- -· 30' .. :,;.: �� t;.� --� El . 138.5
�El. 138.5 ..
':., ,c- - - - - 30'- · - - -... -�
� · El. 138.5 ·; r - .· · T> - 1_ -_ . ., _�
;..,
�: ! El I �8 5 _,.; 1 2' �--- 30' - - .,.: �
c:i .,
SEC. ON t �- S EC. ON t -.,, � SEC. ON t SECT ION ON t
DES I GN 7 D E S I G N 8 DES I GN 9 DES I GN 10
D I F F U S E R FOR S P R E AD I N G FLOW AT V E RT ICAL C U R VE
10 0 50 · L111L11d , · 1 · r I I
SCALE IN F E E T - PROTOTYPE
· Ei. 125.0
•• -TOOTH SPACING s·-o· O.C.
100
,· El . 1 25.0
E l. 94_5 :�-�t-9l� . 1 . .
.E:
.· 97.5·,J-
; � t RE H BOCK SILL
El . 94_ 5_� �_1 917_0 E l . 99.S·
K! · • - t · REH BOCK S I L L
.
· _c, • �. :;_:�:�;= --80:-0�- -�� -:_:_�_j t;; · · ·t:'.·- -��-?-�-eo�o· � -!- - - �- -J ,. DES IGN 2 DESIGN 3
t I c::::J - ---- �---
----44�---->1�18"
P L A N
·· E l . 125.0
DESIGN I
l•
· Ei. 1 25.0 · El . 125.0
···•- RE HBOCK S ILL J· E l . 99 5�w El. 94.5 -�i C ,, .o . . •. _ . :,r,�-··;.J.· REHBOCK SILL
DESIGN 4
·· El. 125.0
El. 94.5�� , El. 99.5-,
. 'E?S:;:2:���; DESIGN 6
ST I L L I N G POOL
P l L O T
. ·. ! • . : .(>_ � -;1 . : -.. f\,'. . '<· · · - 44'-6"- - - .,_,;
DESIGN 5
·· E l . 125.0
J:, .- El. 97.0 t E l . 94.5 -�i--�
,--. -�<� �:J·.:·.'.- ·:�:�T:·
�- - - � :. . � 60°· 0 · - - - ......
DESIGN 7
R I P RAP - - 3' O E E P
K N O B W A S T E W A Y CH U T E A N D STI LL I N G POO L MODEL STU D I ES
D ETAI LS O F POO L A N D D I FFUSER DES I G NS
'Tl (j) C ';o 1('1
0,
![Page 23: HYDRAULIC L: · 2017. 11. 13. · degree V-notch weir, from which it was conveyed through the underground distribution system to the short section of the main canal by way of the](https://reader035.vdocument.in/reader035/viewer/2022071300/6090f8f7a76d3426c32069f2/html5/thumbnails/23.jpg)
J M 8 .
F I G U R E 9
� ' 'o
, � - '
y
l
I 'o _ ,
'<0 'o
·N E L . 94 . 5 . ·I() ·- y E L . 1 00
H A L F P L A N
CONCRETE WARP
'
-:r-- l -�L S Y M M E T R I C A L A BOUT T '-' 1 S <t · ·
E L 1 2 5
� E L . 94 . E L . 1 00
'o _ ,
y _
E!,. .§il <- - 50·- o ·� - - >
S E C T I O N R E C O M M E N D E D S T I L L I N G P O O L
1 0 0 5 0 1 00 l, 1 ii I I I I I I ! I I I S C A L E I N F E E T - P R O T O T Y P E
-----� ! -' :� Y E L 94 .5
-< - 6 '- 3 " - - - - - �
D E TA I LS OF S I L L DE TA I L S O F TOOTH E D A P RON
1 0 1 2 3 4 5 I, , , ) I I I I I
SCALE I N F E E T - P R O T O T Y P E
P I L O T K N O B WA S T E W A Y S T I L L I N G P O O L M O D E L S T U D I E S
D E TA I L S O F R E C O M M E N D E D P O O L
![Page 24: HYDRAULIC L: · 2017. 11. 13. · degree V-notch weir, from which it was conveyed through the underground distribution system to the short section of the main canal by way of the](https://reader035.vdocument.in/reader035/viewer/2022071300/6090f8f7a76d3426c32069f2/html5/thumbnails/24.jpg)
PLATE l
CHANNEL AND STILLING POOL .
ENTRANCE AND CONTROL SECTION.
RlOClOMMENDED WASTE-NAY DESIGN - NO FLOW.
![Page 25: HYDRAULIC L: · 2017. 11. 13. · degree V-notch weir, from which it was conveyed through the underground distribution system to the short section of the main canal by way of the](https://reader035.vdocument.in/reader035/viewer/2022071300/6090f8f7a76d3426c32069f2/html5/thumbnails/25.jpg)
PLATE 2
SET-UP. ORIGINAL DESIGN . DISCHARGE 13, 155 Sl!X: OND-FEE'.I: .
SET-UP .
ALTERNATE DESIGN NO . 1 . DISC:LARGE 13, 155 S:EX:OND-FliST .
SET-UP . ALTERNATE DE�I GN NO . 2 .
DISCHARGE 13, 155 SECOND-FEET
SET-UP. .FINAL DES_IGN. DISCHJJWE 13, 155 Sl!X: OND-FEET .
FLOW C ONDITIONS AT LEFT ENTRANCE - VARIOUS TRANSITION DESIGNS .
![Page 26: HYDRAULIC L: · 2017. 11. 13. · degree V-notch weir, from which it was conveyed through the underground distribution system to the short section of the main canal by way of the](https://reader035.vdocument.in/reader035/viewer/2022071300/6090f8f7a76d3426c32069f2/html5/thumbnails/26.jpg)
SET-UP. ORIGINAL PIER DESIGN .
DISCHARGE 13, 155 SECOND-FEET .
SET-UP . RECOMMENDED PIER DESIGN .
DISCHARGE 13, 155 Sl!X:OND-FEET
SET-UP . FINAL PIER DESIGN.
DISCF.ARGE 13 , 155 SECOND-FEET . � C>
FLOW C ONDIT IONS THROUGH C ONTROL SECTION - VARIOUS PIER DESIGNS .
![Page 27: HYDRAULIC L: · 2017. 11. 13. · degree V-notch weir, from which it was conveyed through the underground distribution system to the short section of the main canal by way of the](https://reader035.vdocument.in/reader035/viewer/2022071300/6090f8f7a76d3426c32069f2/html5/thumbnails/27.jpg)
450 SLUIC E EXIT 1,/ITHOUT DEFLECTOR
30u SLUICE EXI'.r
WITHOUT DEFLECTOR DISCHARGE i,080 SEXJOND-FEET
WITH DEFLECTOR
WITHOUT DEFLECTOR DISCHARGE 686 SECOND-FEET
\'/ITH DEFLECTOR
WITHOUT DEFLECTOR WITH DEFLECTOR
DISCHARGE 280 SECOND-FEET
FLOW THROUGH BY-PASS SLUICES WITH AND WITHOUT DEFLECT OR IN
ROOF OF SLUICE CONDUIT . 19-FOOT HEAD ON SLUICE.
![Page 28: HYDRAULIC L: · 2017. 11. 13. · degree V-notch weir, from which it was conveyed through the underground distribution system to the short section of the main canal by way of the](https://reader035.vdocument.in/reader035/viewer/2022071300/6090f8f7a76d3426c32069f2/html5/thumbnails/28.jpg)
DISCHARGE 2 , 500 SJ;X; OiiD-FEET DISCHARGE 5 , 000 SECOND-FJ�E1' .
NOR!.!AL TAI1'.'/ATER E1EHTIOU 111 , 0
DISCHARGE 10 , 000 SIDOND-FEET , DISCHAiWE 13 , 155 SECOND-FEET .
NORMAL TAILWATER ELEVATION 111 , 0
ST ILLING POOL AC T ION - VARIOUS DISCHAIWES WITH NORMAL TAILWATER .
REC OMMENDED POOL DESI GN .
![Page 29: HYDRAULIC L: · 2017. 11. 13. · degree V-notch weir, from which it was conveyed through the underground distribution system to the short section of the main canal by way of the](https://reader035.vdocument.in/reader035/viewer/2022071300/6090f8f7a76d3426c32069f2/html5/thumbnails/29.jpg)
:.IINL.IT.n,i TAILW,.'l'ER (J<:L . 104 . 0 ) . . iAXH!UL! TAILVl!\TER ( EL . 124 . 0 )
DISCHARGE 13, 155 SECOND-FEET .
BEFORE TEST .ACCUMULATIVE SCOUR FOR TEST .
.NO FLOW
ST ILLING POOL C ONDITIONS - VARIOUS TAILWATER ELEVAT IONS . R:EX: OMMENDED POOL DESI GN .
� II> 1-3 t?-:l
O>
![Page 30: HYDRAULIC L: · 2017. 11. 13. · degree V-notch weir, from which it was conveyed through the underground distribution system to the short section of the main canal by way of the](https://reader035.vdocument.in/reader035/viewer/2022071300/6090f8f7a76d3426c32069f2/html5/thumbnails/30.jpg)
PLATE 7
GA'i'E 4 ONLY OPEN GATE 3 ONLY OPEN
IJ1SCHA.11GE 3 , 250 SEC OND-FEET
GATES 1 AND 2 OPEN GATES 1 AUD 3 OPEii
DISCI·IARm� 6 , 500 S}::COJ 'D-FE}::'l'
Gi.'i'ES 2 . ,i-D 3 OI'EI: G, TES 1 A..l'fD 4 OPEN
DI SCH. RGE G , 500 SEC O�'D-J,"U;'l' .
GATES 1, 2 AND 3 OPEN GA'.PES 1, 2 !TD 4 OPEN
DISCHARGE 9 , 750 SECOND-FEET .
ST ILLING POOL AC TION FOR VARIOUS GATE C OMBINAT IONS
![Page 31: HYDRAULIC L: · 2017. 11. 13. · degree V-notch weir, from which it was conveyed through the underground distribution system to the short section of the main canal by way of the](https://reader035.vdocument.in/reader035/viewer/2022071300/6090f8f7a76d3426c32069f2/html5/thumbnails/31.jpg)
I.