Public Hearing Format
Purpose of the Public Hearing: To solicit feedback from the community regarding proposed improvements
Public Hearing Procedures and Protocols: – Sign up to speak at the registration table
– Provide your name and organization (if applicable)
– Limit comments to three minutes
– To ensure the court reporter correctly documents your comments, please address comments to TxDOT and the court reporter, not the audience
2
I-10 from Loop 1604 to SH 130 – Public Hearing January 31, 2019
Project Location
Approximately 27 miles long
Project begins at Loop 1604 (San Antonio)
Project ends at SH 130 (Seguin)
4
Proposed Project
I-10 from Loop 1604 to SH 130 – Public Hearing January 31, 2019
Project Overview
Address Congestion
– Traffic along I-10 is projected to increase approximately 40% by the year 2040
Facilitate Freight Movement
– The percentage of trucks continues to increase
– Bridge clearances do not meet today’s design standards for trucks
Improve Operations
– Existing I-10/SH 46 intersection will not meet projected traffic demand
– Ramps back up onto mainlanes in some locations
– Existing interchanges lack turnarounds and will not meet projected traffic
demand
– Existing two-way frontage roads do not meet current design standards
5
Why is the Project Needed?
I-10 from Loop 1604 to SH 130 – Public Hearing January 31, 2019
0
20,000
40,000
60,000
80,000
100,000
120,000
SL 1604 US 90(west ofSeguin)
FM 464 SH 46 SH 123 SH 130
VE
HIC
LE
S P
ER
DA
Y
2016 Avg. Daily Traffic 2040 Avg. Daily Traffic
Project Overview - Projected Growth in Traffic on I-10 at Key Interchanges
6
I-10 from Loop 1604 to SH 130 – Public Hearing January 31, 2019
Project Overview
Adding one mainlane in each direction
Adding I-10 direct connector lanes between I-10 and SH 46
Converting frontage roads from two-way to one-way operation
Changing the location of numerous entrance/exit ramps
Reconstructing several overpasses/underpasses to increase
bridge clearances
Adding turnarounds at some intersections
Adding new frontage roads in some areas where none exist
7
What are the Proposed Improvements?
I-10 from Loop 1604 to SH 130 – Public Hearing January 31, 2019
Project Overview – Typical Sections
8
I-10 from Loop 1604 to SH 130 – Public Hearing January 31, 2019
Crash History
9
0
20
40
60
80
100
120
140
2012 2013 2014 2015 2016
CR
AS
HE
S
YEAR
Crashes on Frontage
Roads/Ramps
Crashes along the I-10 frontage
roads/ramps within the project area
have doubled between 2012 and 2016
34% of crashes in the study area
occurred on the frontage roads/ramps
Source: TxDOT Crash reports January 1, 2012 through September 5, 2016
I-10 from Loop 1604 to SH 130 – Public Hearing January 31, 2019
Frontage Road Conversion – Safety Improvements
A study by the Texas A&M Transportation
Institute showed that one-way frontage
roads improved safety by:
10
Source: “Safety and Economic Impacts of Converting Two-way Frontage Roads to One-way: Methodology
and Findings.” Eisele et.al. Texas Transportation Institute, 2011
– Reducing fatal and injury crashes by 57%
– Reducing serious head-on and angle crashes 80-96%
– Reducing intersection crashes 77-85%
I-10 from Loop 1604 to SH 130 – Public Hearing January 31, 2019
Frontage Road Conversion – Traffic Congestion and Delay Improvements
Another study found that one-way frontage roads reduce
traffic congestion and delays because:
– The conversion adds travel lanes in a specific direction
– There is one less direction of traffic moving so waiting
time at traffic signals is reduced
– U-turn lanes improve traffic flow at intersections and
can be used on one-way frontage roads, but not on
two-way frontage roads
11
Source: “A Study to Develop Warrants for Conversion to One-Way Frontage Roads.” Messer, Stover, and
Gattis. Texas Transportation Institute, 1988
I-10 from Loop 1604 to SH 130 – Public Hearing January 31, 2019
Environmental Overview
Archeological Resources
Biological Resources
Community Impacts Assessment
Hazardous Materials Initial Site Assessment
Historic Resources
Traffic Noise
Water Resources
12
Environmental Studies
Environmental reports are available tonight for public review.
I-10 from Loop 1604 to SH 130 – Public Hearing January 31, 2019
Environmental Overview
Right of Way
– Proposed: 14.19 acres
– Temporary Construction Easements: 1.78 acres
No displacements of residential or commercial properties would occur
No noise abatement is proposed
Wetlands and Other Waters of the U.S.
– Potential impacts to waters of the U.S. would primarily occur from the
replacement of bridges and extension of culverts in the project area
13
Environmental Summary
I-10 from Loop 1604 to SH 130 – Public Hearing January 31, 2019
Environmental Overview
Historic Resources
– Consultation under Section 106 is ongoing.
– The project would require 0.006 acres of right of way from a historic
property determined to be eligible for the National Register of Historic
Places (NRHP).
– TxDOT is pursuing a de minimis impact determination. TxDOT will consider
comments received during the public hearing before making a final
Section 4(f) determination.
The public boat ramp under the bridge at the Guadalupe River would remain,
although temporary closures would occur during construction.
14
Environmental Summary Continued
I-10 from Loop 1604 to SH 130 – Public Hearing January 31, 2019
Project Timeline
* Date subject to change.
15
Preparation of
Environmental
Documents &
Schematic
Design
Host Open
House Public
Meetings
Host Public
Hearing
Environmental
Clearance
JANUARY 2017
– DECEMBER
2018
OCTOBER 24 &
NOVEMBER 6,
2017
JANUARY 31,
2019 SPRING 2019
Construction
2021*
Obtain ROW &
Relocate
Utilities
2019 - 2021
I-10 from Loop 1604 to SH 130 – Public Hearing January 31, 2019
Project Funding
I-10 from Loop 1604 to SH 130
– Construction Cost: Approximately $1.2 B
–Funding Available: Approximately $354 M
•Graytown Road to Bexar/Guadalupe County Line = $154 M
•US 90A to SH 130 = $200 M
16
I-10 from Loop 1604 to SH 130 – Public Hearing January 31, 2019
Public Hearing Format - Public Comment Opportunities
17
– Present verbal comments during the hearing
– Give a verbal comment to the court reporter tonight
– Leave a comment form in the comment box
Michael Baker International
ATTN: I-10 from Loop 1604 to SH 130
17721 Rogers Ranch Parkway, #250
San Antonio, TX 78258
* For more information visit txdot.gov and
search “I-10 from Loop 1604”.
Comments must be
postmarked or received
by February, 15, 2019 to
be a part of the official
hearing record
Public Hearing
I-10 from Loop 1604 to SH 130 – Public Hearing January 31, 2019
3:00 2:59 2:58 2:57 2:56 2:55 2:54 2:53 2:52 2:51 2:50 2:49 2:48 2:47 2:46 2:45 2:44 2:43 2:42 2:41 2:40 2:39 2:38 2:37 2:36 2:35 2:34 2:33 2:32 2:31 2:30 2:29 2:28 2:27 2:26 2:25 2:24 2:23 2:22 2:21 2:20 2:19 2:18 2:17 2:16 2:15 2:14 2:13 2:12 2:11 2:10 2:09 2:08 2:07 2:06 2:05 2:04 2:03 2:02 2:01 2:00 1:59 1:58 1:57 1:56 1:55 1:54 1:53 1:52 1:51 1:50 1:49 1:48 1:47 1:46 1:45 1:44 1:43 1:42 1:41 1:40 1:39 1:38 1:37 1:36 1:35 1:34 1:33 1:32 1:31 1:30 1:29 1:28 1:27 1:26 1:25 1:24 1:23 1:22 1:21 1:20 1:19 1:18 1:17 1:16 1:15 1:14 1:13 1:12 1:11 1:10 1:09 1:08 1:07 1:06 1:05 1:04 1:03 1:02 1:01 1:00 0:59 0:58 0:57 0:56 0:55 0:54 0:53 0:52 0:51 0:50 0:49 0:48 0:47 0:46 0:45 0:44 0:43 0:42 0:41 0:40 0:39 0:38 0:37 0:36 0:35 0:34 0:33 0:32 0:31 0:30 0:29 0:28 0:27 0:26 0:25 0:24 0:23 0:22 0:21 0:20 0:19 0:18 0:17 0:16 0:15 0:14 0:13 0:12 0:11 0:10 0:09 0:08 0:07 0:06 0:05 0:04 0:03 0:02 0:01 0:00
• Submit Speaker Registration Card
• Limited to 3 minutes
• Use microphone and face court
reporter
• State your name and whom you
represent (if applicable)
• Unused time may not be given to
another speaker
Verbal Comments
Public Comment Section