I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy State Project No.: 0064-054-703, P101, R201 & C501 Federal Project No.: IM-064-2(155) Contract ID No.: C00086453DB48 February 3, 2012 Submitted by: February 3, 2012

Upload: others

Post on 12-Jul-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501

I-64/Route 15 (Zion Crossroads) Interchange Improvement

CD Copy

g p

State Project No.: 0064-054-703, P101, R201 & C501Federal Project No.: IM-064-2(155)Contract ID No.: C00086453DB48

February 3, 2012Submitted by: February 3, 2012Sub tted by

Page 2: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501

I-64/ROUTE 15 INTERCHANGE IMPROVEMENT DESIGN-BUILD PROJECT  

HOWARD BROTHERS CONTRACTOR, INC. | A. MORTON THOMAS AND ASSOCIATES, INC.

Section 3.2

Letter of Submittal

Page 3: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 4: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 5: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 6: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 7: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 8: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501

I-64/ROUTE 15 INTERCHANGE IMPROVEMENT DESIGN-BUILD PROJECT  

HOWARD BROTHERS CONTRACTOR, INC. | A. MORTON THOMAS AND ASSOCIATES, INC.

Section 3.3

Team Structure Analysis

Page 9: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 10: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 11: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 12: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 13: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 14: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 15: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 16: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501

I-64/ROUTE 15 INTERCHANGE IMPROVEMENT DESIGN-BUILD PROJECT  

HOWARD BROTHERS CONTRACTOR, INC. | A. MORTON THOMAS AND ASSOCIATES, INC.

Section 3.4

Offeror’s Team Structure

Page 17: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 18: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 19: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 20: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 21: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501

I-64/ROUTE 15 INTERCHANGE IMPROVEMENT DESIGN-BUILD PROJECT  

HOWARD BROTHERS CONTRACTOR, INC. | A. MORTON THOMAS AND ASSOCIATES, INC.

Section 3.5

Project Risk

Page 22: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 23: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 24: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 25: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 26: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501

I-64/ROUTE 15 INTERCHANGE IMPROVEMENT DESIGN-BUILD PROJECT  

HOWARD BROTHERS CONTRACTOR, INC. | A. MORTON THOMAS AND ASSOCIATES, INC.

Appendix A

Page 27: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 28: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 29: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 30: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 31: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 32: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501

I-64/ROUTE 15 INTERCHANGE IMPROVEMENT DESIGN-BUILD PROJECT  

HOWARD BROTHERS CONTRACTOR, INC. | A. MORTON THOMAS AND ASSOCIATES, INC.

Appendix B

Page 33: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 34: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 35: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 36: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 37: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 38: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 39: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 40: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 41: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 42: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 43: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 44: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 45: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 46: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 47: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 48: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501

I-64/ROUTE 15 INTERCHANGE IMPROVEMENT DESIGN-BUILD PROJECT  

HOWARD BROTHERS CONTRACTOR, INC. | A. MORTON THOMAS AND ASSOCIATES, INC.

Appendix C

Page 49: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501

HOWARD BROTHERS CONTRACTOR, INC. | A. MORTON THOMAS AND ASSOCIATES, INC.

ATTACHMENT 3.5.1(a)

LEAD CONTRACTOR – WORK HISTORY FORM

(LIMIT 1 PAGE PER CONTRACT)

Work by Lead Contractor – Three (3) projects which best illustrates current qualifications relevant to this Project. a. Project Name & Location

b. Narrative Describing Nature of Firm's Responsibilities

c. Client/Owner/Project Manager who can verify Firm’s responsibilities. Include address and current phone number

d. Contract Completion Date (Original)

e. Contract Completion Date (Actual or Estimated)

f. Estimated Value (in Thousands)

Original Contract

Value

Final or Estimated Contract

Value

Dollar Value of Work for Which

Firm Was/Is Responsible

(1) Bridge and Approaches to Mattaponi River (NFO)0033-063- 103,C502 D41 Town of West Point (2) Bridge and Approaches to Pamunkey River (FO)0033-966-102,C501,B602 D98 Town of West Point

HBC, Inc. acted as subcontractor to Skanska and McLean prime contractors to construct 2 bridges spaning the Mattaponi and the Pamunkey Rivers. HBC, Inc. supplied coordination and construction of all components of project not associated with actual bridges. Wetland mitigation, Southern Railroad utility crossing, demolition of buildings, subgrade improvements, surcharge with monitoring, and all components associated with town utility and landsacpe aesthetic improvements were required. Lessons Learned: Acting as subcontractor for two bridge contractors required coordination and skilled partnering in dealing with the private sector construction, public sector owners and VDOT. Importance of regular planned communications and partnering.

OWNER: (1) VDOT/Skanska

VDOT- Marcie Parker, Resident Engineer 87 Deacon Road Fredericksburg, VA 22405 540-899-4288 Skanska- Pat Moore 295 Bendix Dr., Suite 400 Virginia Beach, VA 23452 804 829-9044

(2) VDOT/Bryant Contracting, Inc. VDOT- Marcie Parker, Resident Engineer

87 Deacon Road Fredericksburg, VA 22405 540-899-4288

Bryant Contracting - Barry Bryant P.O. Box 1000 Toano, VA 23168 757-566-0400

2007 2007

2007 2007

$5,251 $2,672

$6,075* $2,737*

$6,075 $2,737

Scope and Complexity Similarities

VDOT Project Approaches to bridges over Pamunkey

& Mattaponi Rivers New Kent Co./ King William Co./Town of West Point

Construction size $8.7 million Impact to local commuters Unknown subsurface conditions

Evidence of Good Performance

Project completed on time and on budget

Contractors Performance Rating was 98.5% out of a possible 100%

Lessons Learned

Communication skills of diplomacy in construction, public and private sectors

Partnership of two separate jobs coordinated as one

*increases due to Owner requested change orders

Page 50: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501

HOWARD BROTHERS CONTRACTOR, INC. | A. MORTON THOMAS AND ASSOCIATES, INC.

ATTACHMENT 3.5.1(a)

LEAD CONTRACTOR – WORK HISTORY FORM

(LIMIT 1 PAGE PER CONTRACT)

Work by Lead Contractor – Three (3) projects which best illustrates current qualifications relevant to this Project. a. Project Name & Location

b. Narrative Describing Nature of Firm's Responsibilities

c. Client/Owner/Project Manager who can verify Firm’s responsibilities. Include address and current phone number

d. Contract Completion Date (Original)

e. Contract Completion Date (Actual or Estimated)

f. Estimated Value (in Thousands)

Original Contract

Value

Final or Estimated Contract

Value

Dollar Value of Work for Which

Firm Was/Is Responsible

(4) Interstate 64 Interchange Ramp (NFO)0064-114-115,C501 City of Hampton Hampton Roads District Settlers Landing Road and Tyler Street

Project involved Interstate 64, VDOT interstate interchange improvements in a high traffic/pedestrian area, Hampton University. Project exit/entrance ramps off east bound I-64 in very close proximity to university intersection, required widening of entrance exit ramps, enhance pedestrian flow, safety intersection signalization and traffic flow deliniation. Lessons Learned: The project presented two valuable learning events. (1) The exit ramp off interstate I-64 was short

which would result in a backup of traffic on the interstate quickly. HBC, Inc. and VDOT stream lined the M.O.T. to allow for correction during construction when required.

(2) Working in close proximity to Hampton University and large volumes of unpredictable pedestrian traffic, HBC, Inc. coordinated with VDOT and university personnel to make allowances and adjustments to construction activities and traffic control to enhance flow and safety.

OWNER: Virginia Department of Transportation VDOT Engineer: Quintin Elliott, PE, Resident Engineer 1700 North Main St. Suffolk, VA 23434 540-889-4200

2001

2001

$508

$508

$508

Scope and Complexity Similarities

Entrance/exit ramp reconstruction and interchange improvements

Grade, drain, asphalt paving and signals

Interstate traffic conditions Public awareness – impact to local

commuters

Evidence of Good Performance

Completion on time and on budget Attained 35% DBE participation Contractors Performance Rating

was 98% out of a possible 100% Lessons Learned

Utilize partnering opportunities to overcome potential traffic/pedestrian encounters

Page 51: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501

HOWARD BROTHERS CONTRACTOR, INC. | A. MORTON THOMAS AND ASSOCIATES, INC.

ATTACHMENT 3.5.1(a)

LEAD CONTRACTOR – WORK HISTORY FORM

(LIMIT 1 PAGE PER CONTRACT)

Work by Lead Contractor – Three (3) projects which best illustrates current qualifications relevant to this Project. a. Project Name & Location

b. Narrative Describing Nature of Firm's Responsibilities

c. Client/Owner/Project Manager who can verify Firm’s responsibilities. Include address and current phone number

d. Contract Completion Date (Original)

e. Contract Completion Date (Actual or Estimated)

f. Estimated Value (in Thousands)

Original Contract

Value

Final or Estimated Contract

Value

Dollar Value of Work for Which Firm

Was/Is Responsible

(5) 4 Interstate 95 Interchange Ramps

(FO)0095-042-753,C501 Hanover County Richmond District 0.061 Mi. W. Int. Rte 743 to 0.367 Mi. E. Int. Rte 743

VDOT project classification rural major collector project scope involved: reconstruction and expansion of (4) entrance/exit ramps, I-95 bridge approach improvements, reconstruction modification of (2) industrial intersections, signalization, utility upgrades, and extensive M.O.T. coordination and implementation. Lessons Learned: The project had some unique construction challenges associated with M.O.T. With 2 major industrial interchange rebuilds separated by I-95 the M.O.T. coordination with VDOT was a daily partnering for planning implementation. Scheduling of construction, traffic switching, phasing, and coordinating with multiple on-site utility owners revealed the importance of ongoing partnering, scheduling, and communication to assure safety and on time quality construction practice.

OWNER: Virginia Department of Transportation VDOT Engineer: Keith Rider, PE, Area Construction Engineer 2430 Pine Forest Dr. Colonial Heights, VA 23834 804-328-3099

2011

2011

$2,246

$2,262

$2,262

Scope and Complexity Similarities

VDOT Project Significant roadway and ramp

construction Interstate traffic conditions Challenging M.O.T. $2.7 Million

Evidence of Good Performance

Contractors Performance Rating is 99.2% out of a possible 100%

Completed under budget

Lessons Learned

Proactive approach to interstate interchange M.O.T.

Page 52: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501

HOWARD BROTHERS CONTRACTOR, INC. | A. MORTON THOMAS AND ASSOCIATES, INC.

ATTACHMENT 3.5.1(b)

LEAD DESIGNER – WORK HISTORY FORM

(LIMIT 1 PAGE PER CONTRACT)

Work by Lead Contractor – Three (3) projects which best illustrates current qualifications relevant to this Project.

a. Project Name & Location

b. Narrative Describing Nature of Firm's

Responsibilities

c. Client/Owner/Project

Manager who can verify Firm’s responsibilities. Include address and current phone number

d. Contract Completion Date (Original)

e. Contract Completion Date (Actual or Estimated)

f. Estimated Value (in Thousands)

Original Contract

Value

Final or Estimated Contract

Value

Dollar Value of Work for Which Firm

Was/Is Responsible

(1) Eisenhower Avenue

Improvements

City of Alexandria, Virginia

AMT is providing design services for the widening of Eisenhower Avenue from a variable lane facility to a six lane divided facility with wide raised median and Gateway Project features such as extensive landscaping, open public spaces, wide sidewalks with integral bicycle paths, continuous planter boxes, and decorative street lighting. The project includes a wide outside lane on each side of the roadway that will serve as off-peak parking as well as a through travel lane and bus lane during peak volume hours. The project includes extensive right-of-way constraints including existing Metro bridge piers, existing high-elevation buildings, and concurrent development along the corridor. The extensive traffic engineering study encompassed multi-modal transportation such as pedestrian, bicycle, bus, and metro-rail, as well as the overwhelming amount of vehicular traffic entering the corridor from the two new Beltway ramps entering Eisenhower Avenue. Lessons Learned: AMT designers have quickly learned to adapt to ever changing design parameters through their work on the Eisenhower project. AMT designers and the project manager have honed their people skills as they have been required to facilitate meetings where compromises are brokered between competing interests. The project has created multiple challenges posed by a heavily developed urban setting, including specific problems associated with uncertain as-builts for existing utilities, evolving traffic projections, and the interaction with multi-modal transportation types such as pedestrian, bicycle, and public transit.

OWNER: VDOT 2901 Eisenhower Ave. Alexandria, Virginia 22314 Lisa Jaatinen Project Manager 703.746.4053

2012

2012

$1,400 (fee)

$1,400 (fee)

$1,400 (fee)

Scope and Complexity Similarities

Significant ROW and utility constraints

Multi-model transportation considerations

Located in City of Alexandria (urban) Complex MOT planning required Stakeholder coordination at all stages VDOT funded project

Evidence of Good Performance

AMT received multiple letters of recommendation and appreciation from City Project Managers for design work

Lessons Learned

Learned lessons regarding balance of stakeholder wants, owner needs, and project financing

Page 53: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501

HOWARD BROTHERS CONTRACTOR, INC. | A. MORTON THOMAS AND ASSOCIATES, INC.

Work by Lead Contractor – Three (3) projects which best illustrates current qualifications relevant to this Project.

a. Project Name & Location

b. Narrative Describing Nature of Firm's

Responsibilities

c. Client/Owner/Project

Manager who can verify Firm’s responsibilities. Include address and current phone number

d. Contract Completion Date (Original)

e. Contract Completion Date (Actual or Estimated)

f. Estimated Value (in Thousands)

Original Contract

Value

Final or Estimated Contract

Value

Dollar Value of Work for Which Firm

Was/Is Responsible

(2) US Route 460 Phase I

Design-Build

Buchanan County, Virginia

AMT provided highway design of a four lane Rural Principal Arterial on new alignment with connections to local routes and local roadway improvements. The design-build project includes three bridges: twin 1,733 foot long cast-in-place hollow box concrete structures crossing Grassy Creek and Route 610 at a maximum height of 267 feet, and a 300 foot long bulb-T girder bridge crossing Hunts Creek. The roadway is cut into steep terrain with benched sideslopes engineered to minimize earthwork and disturbance to the environment. Due to the nature of the project, approximately 2.6 million cubic yards of excavated material is planned to be placed in an engineered waste area on the project site. Stormwater management facilities and erosion control features are being designed in order to minimize impacts to sensitive local streams and to control increases in stormwater runoff as a result of the large footprint of the project. AMT is providing roadway design and coordinating closely with members of the structural engineering team throughout the project. Lessons Learned:

AMT has gained valuable experience working on VDOT’s largest active design-build contract. AMT quickly restructured its electronic filing system to improve internal file sharing, access, and review to facilitate extensive QC and QA reviews. AMT designers also learned to extract information from the construction team members who may not normally be fluent in design terminology. AMT also learned to work in a fast paced design environment where multiple designers were advancing concepts concurrently, requiring regular communication and cross-discipline reviews.

OWNER: VDOT 870 Bonham Road Bristol, Virginia 24201 Amanda Cox, PMP Project Manager 276.669.6151 CLIENT and CONTRACTOR: Bizzack Construction, LLC 2257 Executive Drive Lexington, Kentucky 40505 Stewart Gaither, PE 859.299.8001

2014

2014

$1,200 (fee)

$1,200 (fee)

$1,200 (fee)

Scope and Complexity Similarities

Close coordination between roadway and bridge designers required

Design-build delivery method Significant size project - $90 million VDOT project

Evidence of Good Performance

AMT received letter of recognition from VDOT PM for work on roadway design

Lessons Learned

Learned lessons regarding multi-discipline design coordination working closely with structural engineering team on a daily basis

Page 54: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501

HOWARD BROTHERS CONTRACTOR, INC. | A. MORTON THOMAS AND ASSOCIATES, INC.

Work by Lead Contractor – Three (3) projects which best illustrates current qualifications relevant to this Project.

a. Project Name & Location

b. Narrative Describing Nature of Firm's

Responsibilities

c. Client/Owner/Project

Manager who can verify Firm’s responsibilities. Include address and current phone number

d. Contract Completion Date (Original)

e. Contract Completion Date (Actual or Estimated)

f. Estimated Value (in Thousands)

Original Contract

Value

Final or Estimated Contract

Value

Dollar Value of Work for

Which Firm Was/Is

Responsible (3) MD 4/Suitland Parkway

Interchange Project

Prince George’s County, Maryland

AMT provided interchange design and traffic analysis for the MD 4 corridor and Suitland Parkway Interchange. The scope of services included a Value Engineering study of interchange design developed during the planning process, evaluation of initial traffic volumes including modification for change in forecast year, analysis of the Suitland Parkway Interchange under several different scenarios, including roundabout diamond interchange, flyover ramp and single point urban interchange. AMT developed concept plans for two interchange designs, which included horizontal and vertical alignments, limits of disturbance, proposed right of way, braided ramps, roadway widening and access for industrial district. Additional services included capacity analysis, access studies, roadway geometrics, ROW determination, MOT planning, and project cost estimation.

Lessons Learned: AMT has gained valuable experience providing roadway planning, design, traffic analysis and value engineering services to ultimately produce final advertised bid documents for this complex Interchange project. Construction phasing required extensive analysis of MOT alternatives. Each alternative required a Synchro analysis of the entire corridor. Temporary detours were determined after extensive coordination with the County and AAFB. Impacts to rare vegetation required a shift in the entire interchange design. The design was further constrained by AAFB air clearance requirements; NPS roadway and aesthetic design requirements; drainage challenges given depression of MD 4 under Suitland Parkway; timing of developer’s construction funding for Westphalia Interchange; and maintaining fire/rescue and transit routes during construction.

OWNER: Maryland State Highway Administration 707 North Calvert Street Baltimore, Maryland 21202 Teri Soos Project Manager 410-545-8845

2014

2014

$3,200 (Fee)

$3,200 (Fee)

$3,200 (Fee)

Scope and Complexity Similarities

Major urban interchange design Interchange concept studies

completed Extensive MOT and traffic

engineering MD SHA project (state DOT)

Evidence of Good Performance

AMT, at the request of SHA, presented our approach to the development of the TMP at the annual MDOT Quality Initiative Conference. The TMP for the MD4 project is the largest, most complex plan prepared for a SHA project to date.

Lessons Learned

Lessons include stakeholder coordination – regulatory agencies, AAFB, and MOT plans

Page 55: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501

I-64/ROUTE 15 INTERCHANGE IMPROVEMENT DESIGN-BUILD PROJECT  

HOWARD BROTHERS CONTRACTOR, INC. | A. MORTON THOMAS AND ASSOCIATES, INC.

Appendix D

Page 56: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 57: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 58: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 59: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 60: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 61: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 62: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 63: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 64: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 65: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 66: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 67: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 68: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 69: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 70: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 71: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 72: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 73: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 74: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 75: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 76: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 77: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 78: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 79: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 80: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 81: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 82: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 83: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 84: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 85: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 86: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501

I-64/ROUTE 15 INTERCHANGE IMPROVEMENT DESIGN-BUILD PROJECT

HOWARD BROTHERS CONTRACTOR, INC. | A. MORTON THOMAS AND ASSOCIATES, INC.

Appendix E  

Page 87: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 88: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 89: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 90: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 91: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 92: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501
Page 93: I-64/Route 15 (Zion Crossroads) Interchange Improvement gp · I-64/Route 15 (Zion Crossroads) Interchange Improvement CD Copy gp State Project No.: 0064-054-703, P101, R201 & C501