i-70 over sr 121 contractor meeting - indiana...mar 04, 2016 · pre-bid meeting march 4, 2016...
TRANSCRIPT
I-70 over SR 121Pre-Bid Meeting
March 4, 2016
Slide 1
Meeting Objectives
Solicit feedback from General Contractors and
Specialty Contractors
Share Preliminary Construction Details (60%
Plans)
Solidify Design Concept for Final Plan
Development
Slide 2
Project Objectives
Safe Project
During Construction
In Service
Successful Project
Completed on time, according to plan and within budget
Learn from a “conventional” (non-Milton Madison) ABC
project for future implementation
Positive experience for Owner, User and Contractor
Slide 3
Project Objectives
Accelerated Construction Schedule
Minimize User Cost
Minimize MOT Cost
Other states are focusing on this type of work as the
primary interstate replacement method
Slide 4
Current Plan Set
Finalized Details
Limits of Construction along I-70
Limits of Construction along SR 121
Interstate Lane Closure Exception – 13 days per MOT
Phase
Maintenance of Traffic (mostly)
Superstructure Geometry
Superstructure Type
Slide 5
Current Plan Set
Dual Design (Bid Option)
Superstructure Installation Method
UDOT 4500 South over I-215 ODOT OR 213 over Washington St.
SPMT(Self-Propelled Modular Transporters) Slide-In
Slide 6
Current Plan Set
Details Under Development
Foundation Type
Substructure Configuration
Bridge will be in service during construction of
substructure
Slide 7
Contract Structure
Design Bid Build
A + B
A = Construction Cost
B = User Cost for I-70 daytime closures (per hour)
B = User Cost for SR 121 when 1 lane is not provided
(per day)
Monetary amounts still under development
Slide 8
Project Site
I-70 over SR 121 just outside of Richmond
Slide 9
Project Site
High bedrock 3’ – 9’ below surface
Bridge staging area
(BSA) in SE corner
Overhead Utilities on
west edge of project
Slide 10
Project Site
High bedrock 3’ – 9’ below surface
Bridge staging area
(BSA) in SE corner
Overhead Utilities on
west edge of project
Slide 11
Existing Structure
Simple Span Steel Beam with RC Girder Approach
Spans
Built in 1959
27.15 Deg. Skew
End Bent on Piles
Pier on Spread
Footing
Slide 12
Existing Structure
Built Horizontally in Wrong Location
41’-3” instead of 45’-8”
Slide 13
Constructability Discussion
Maintenance of Traffic/Duration
Construction Staging
Substructure
Foundation
Wingwalls
Closure Pours
Slide 14
Maintenance of Traffic
Finalized (mostly)
Pavement Design under development
Lane Closure Exception for 13 days per closure
Begins Friday after 9 p.m.
Ends Second Friday at 6 a.m.
For example
Close 9:00 p.m. Friday 10/6/17
Open 5:59 a.m. Friday 10/20/17
Slide 15
Maintenance of Traffic
Phase I & Phase II – Shoulder Strengthening
Slide 16
Maintenance of Traffic
Adjacent Bridges Cause Complications
Slide 17
Maintenance of Traffic
Shoulder Strengthening – 3000 ft. (3600 ft. barrier)
Temporary Traffic Barrier (currently shown)?
Two lanes of traffic open
Can work during day
Length of barrier required
Barrel Drop with Lane Closure?
Must be in conformance with Lane Closure Policy
Not a “Critical Path” item
Slide 18
Maintenance of Traffic
Phase III – Not Allowed in June, July or August
Maximum Duration of 13 Days
Slide 19
Project Site
Phase IV – Reset to Normal
Slide 20
Maintenance of Traffic
Phase V – Not Allowed in June, July or August
Maximum Duration of 13 Days
Slide 21
Maintenance of Traffic
Coordination
Anticipate Back-ups
Fluid Maintenance of Traffic Alerts
Coordination with Ohio
Public Outreach
Slide 22
Construction Staging - SPMT
BSA in southeast corner - 0.6 acres
Slide 23
Construction Staging - SPMT
BSA
On an approximate 5.5% slope south
Rock 3’-4’ below the surface
All temporary supports must be removed completely
after project completion
Area must be restored to original condition
Slide 24
Construction Staging - SPMT
Contract Document Requirements - Submittal
Provisions based on templates from FHWA and other
States
Heavy Lift System Details
Contingency Plan
Temporary Supports (BSA)
Monitoring System and Tolerances
Schedule
Slide 25
Construction Staging - SPMT
Installation - After existing structure removed,
install Precast Bent Cap
Grouted Couplers
Corrugated Metal Pipe (CMP) Pocket (Preferable)
Slide 26
Construction Staging - SPMT
CMP Pocket
Slide 27
Construction Staging - SPMT
WB Installation – Fairly “Conventional” for SPMT
Slide 28
Construction Staging - SPMT
Backfill behind Wings and Cap (flowable fill)
Precast Approach Slabs
Full approach slab with concrete transitions 209 k
Currently shown as three pieces with Transitions (75 k,
45 k, 45 k)
Each concrete transition 8 k
Closure pours between sections and between abutment
and approach slab
Roadwork and Appurtenances
Slide 29
Construction Staging - SPMT
EB Installation – More Complicated
Slide 30
Construction Staging - SPMT
EB Installation – More Complicated
Slide 31
Construction Staging - SPMT
EB Installation – More Complicated
Bridge Rail may be left off during move, but other
precautions must be made
Other than the actual installation, remainder of
the activities same as WB
Each installation needs to be completed in less
than the allowable closure time
Slide 32
Construction Staging - Slide
Contract Document Requirements - Submittal
Provisions based on templates from FHWA and other
States
Contingency Plan
Monitoring System and Tolerances
Schedule
Slide 33
Construction Staging - Slide
Existing Bridges Built too Close Together
Causes 1 lane in each direction to be closed in Phase III (A+B)
Slide 34
Construction Staging - Slide
1’-7 ½” Clearance between Existing and Proposed
Slide 35
Construction Staging - Slide
End Diaphragm set up to allow for 3 Slide Methods
Temporary Slide Shoe with Track
Slide on Teflon Bearings
Slide on Rollers
Slide 36
Construction Staging - Slide
End Diaphragm set up to allow for 3 Slide Methods
Temporary Slide Shoe
Slide on Teflon Bearings Slide on Rollers
Slide 37
Construction Staging - Slide
Installation
Once Existing Bridge is removed, slide new WB
superstructure into place
It is important to have a system that is capable of
pushing and pulling in case complications arise during
installation
Install Temporary Shoring as required
Backfill behind diaphragm
Slide 38
Construction Staging - Slide
Install Temporary Shoring and Wings
Slide 39
Construction Staging - Slide
Install Temporary Shoring and Wings
Currently shown as MSE Wall
Precast
Concrete?
Slide 40
Construction Staging - Slide
Precast Approach Slabs
Roadwork and Appurtenances
Repeat for EB Bridge
Each installation needs to be completed in less
than the allowable closure time
Slide 41
Foundation
Planned to be built while existing bridge is in
service
To minimize foundation size, looking at ways of
limiting horizontal force on abutments
MSE with straps attached to abutment
Expanded Polystyrene Blocks (Geofoam)
Cellular Concrete Fill
Constructability concerns (access)?
Slide 42
Foundation
Currently two options shown
Spread Footings
Main concern is depth of excavation under bridge and
backslope into existing end bent
Temporary shoring feasible under bridge
Slide 43
Foundation
Excavation
Slide 44
Foundation
Micropiles
Logical Choice
Current Provision is as a “Design Build” Item
Provide two configurations with loads and Contractor
designs final configuration
Max Pile Load = 400 kMin Pile Load = -50 k
Max Pile Load = 200 kMin Pile Load = 0 k
Slide 45
Foundation
Micropiles - Testing
Two Verification Tests
Proof Test on 5% of piles
Testing applies actual loads to installed piles to test
grout strength and capacity
Micropile Casing
Buy America Clause needs to be satisfied
Mill Certification is required
Slide 46
Foundation
Third Option – Drilled Shaft with Straddle Bent
Conventionally Reinforced Straddle Bent
Still need to determine if viable option due to concrete
shrinkage between shafts
May require Straddle Bent to be built first and then
connected to drilled shafts
Slide 47
Foundation
Third Option – Drilled Shaft with Straddle Bent
Slide 48
Foundation
For Spread Footing and Drilled Shaft Option,
abutment would go full width (SPMT and Slide)
For Micropile option with SPMT, median may use
MSE walls with pile sleeves for future widening
Slide 49
Wingwalls and Closures
Main concern is time within the closure period
All options are proposing MSE Walls for the outer
wings
Precast concrete or MSE for Median wall closure?
Precast concrete or MSE for Wing Closure?
Slide 50
Wingwalls and Closures
MSE or Precast Concrete
Wing angle cause access concern?
Slide 51
Specialty Item Payment
Goal is to get usable information for future
projects
SPMT – Payment separated
Engineering
Temporary Substructure and BSA
Installation and other items
50% payment after first move. Remainder after second
Slide 52
Specialty Item Payment
Goal is to get usable information for future
projects
Slide – Payment separated
Engineering
Installation and other items
50% payment after first move. Remainder after second
Slide 53
Specialty Item Payment
Goal is to get usable information for future
projects
Micropile
Testing
Installation
All payment made after work completed
Slide 54
Contractor Information
Prequalification is required for this Project
http://www.in.gov/indot/2740.htm
Slide 55
Closing Comments
Current Design Plan Status approximately 60%
Complete
Plan Development Scheduled for Completion
October 17, 2016
Anticipated Letting Date February 8, 2017
WE APPRECIATE ANY FEEDBACK TO HELP MAKE
THIS A BETTER PROJECT!!
Slide 56
Closing Comments
QUESTIONS/COMMENTS?
Topics
Barrel Drop versus TTB during Phase I & II
Slide Option – 1’-7 ½” clearance between bridges
Precast Concrete Closures or MSE
Excavation/backfill for new abutment (shoring)
Slide 57
Future Questions/Comments
Additional Questions/Comments can be sent to the
INDOT Project Manager until 5:00 p.m. 3/18/2016.
Comments and Responses will be compiled and put
on the website for the project
http://www.in.gov/dot/div/contracts/abc/i70/i70.htm
Slide 58