i 84 waterbury project
TRANSCRIPT
I-84 Waterbury Project
Construction Newsletter
www.i-84waterbury.com
Creating Habitats: A family of
Canadian geese (below) enjoy a swim
in the newly realigned Mad River.
Realigning Beaver Pond Brook
Bridge Construction
Setting Structural Steel
Construction Off the Mainline
Public Involvement
IN THIS ISSUE
Summer, 2016
CONSTRUCTION WITH PRECAST
CONCRETE SECTIONS
REALIGNING BEAVER POND BROOK
The I-84 Waterbury Project includes unique
construction features — extensive in-water
work for the realignment of two rivers: the
Mad River, in the Plank Road/Reidville Drive
vicinity, and the Beaver Pond Brook, in the
Scott Road vicinity. Realignment of the water
bodies supports the successful realignment
of I-84 and its access ramps. Work, which
started in the spring, continues as the Beaver
Pond Brook is realigned along the existing
I-84 WB Exit 25 off ramp and along Plank
Road, to flow through two new culverts that
will carry the waterway under the roads (see
map at right). Once realigned, the Beaver
Pond Brook will flow through Culvert 014,
under Scott Road, and then through Culvert
06622, under the new Plank Road East.
Plank Road East will run parallel to future
I-84, in two directions, both east and west, to
Harpers Ferry Road.
Left: Construction site of Culvert
06622 after initial excavation
and site preparation for new
path of Beaver Pond Brook.
Right: Site during placement of
precast concrete segments,
with 20 of 22 segments in
Above: Culvert backfilled; forms for holding
poured concrete for the headwalls in place.
Right: Culvert with water-proofing on top and
cast concrete headwalls on both ends.
Precast concrete sections (culvert
section being moved by crane below)
can be seen on various construction
sites within the project limits of the I-84
Waterbury Project. Each product is
uniquely designed for its ultimate
usage in retaining walls, culverts, and
drainage.
The series of photos below follow the construction of Culvert 06622, constructed using
22 precast interlocking concrete segments, to form a two-barrel box culvert.
I-84 Waterbury Project
Construction Newsletter
Summer, 2016 ▪ Page 2
Project Office: 64 Avenue of Industry, Waterbury, CT 06705
T 203-725-3089
www.i-84waterbury.com
BRIDGE CONSTRUCTION
I-84 and EB 25 Off Ramp Over Mad River, Western
Crossing (Bridge 1224): Workers set structural steel for
this bridge under construction on the southern side of the
existing/demolished I-84 bridge in the spring, and construction
of the decks continue this summer, with paving scheduled in
July. Once completed, drivers can anticipate traffic shifts onto
this new portion of the I-84 bridge so that demolition and
reconstruction of the north side of the bridge can commence.
The EB 25 off ramp will not be in use until the entire ramp,
that extends for almost a
mile, from west of the
Hamilton Avenue Bridge
overpass, crossing over
the Mad River twice, to
Harpers Ferry Road,
opens in 2017.
Right: Deck of
Bridge 1224 (EB 25
off ramp portion)
with rebar in place
as machine for
finishing concrete
prepares for a dry-
run before concrete
is placed.
Above: Structural
steel in place for
Bridge 1224, shot
from the bank of the
Mad River.
Right: Workers
install diaphragms
between steel
girders.
Left: Steel girders with
cross braces in place for
new bridge deck.
Below: Worker installs
braces for parapet.
Left: Stay-in-place forms
welded in place onto steel
beams for bridge deck.
Below: Stay-in-place forms
with foam covering and shear
stud connectors to join steel
girders to concrete deck.
Right: Deck finishing
machine rolls over
poured concrete to
take it to the proper
grade and cross
slope; 138 yards of
concrete were
poured.
Above: Old bridge
abutment is
demolished after
existing deck and
steel are partially
removed.
Right: Structural
steel girders are
set in place for
new bridge.
I-84 Waterbury Project
Construction Newsletter
Summer, 2016 ▪ Page 3
Project Office: 64 Avenue of Industry, Waterbury, CT 06705
T 203-725-3089
www.i-84waterbury.com
P4
Above: New structural steel spans full expanse of Hamilton Avenue
Bridge, on the western portion, from north to south over I-84.
SETTING STRUCTURAL STEEL
Hamilton Avenue Bridge (Bridge 4321): As the Project will
widen I-84 to three lanes in each direction, the existing bridge
must be lengthened to accommodate not only the additional
lanes, but also the EB 25 off ramp. This requires spanning all
new structural steel across I-84, from the newly constructed
abutment on the north side, over two center piers, to the
abutment on the south side. As the steel girders had to be
placed and secured over travel lanes of I-84, the structural
steel was erected during the night time hours. For safety
purposes, I-84 was closed at Exit 23 in both directions to
prevent travelers from entering the active work zone during
splicing of girder sections. Motorists were guided through the
detour route by construction signage, State, and local Police.
The photo to the right depicts
locations of the two bridges
where the steel decks are
currently under construction,
with Hamilton Ave. overpass;
facing east.
I-84 Bridge Over Mad
River (Bridge 1224)
Hamilton Ave Bridge
(Bridge 4321)
Right: Excavation for
cofferdam, which will
keep water out of the site
during construction of the
abutment for the new I-84
bridge over the Mad
River, eastern crossing.
CONSTRUCTION OFF THE MAINLINE
West of Harpers Ferry Road: Construction of the new I-84
bridge and new EB 25 off ramp over the Mad River (eastern
crossing) continues with abutment construction visible on both
banks of the river (photo of sites below). The new EB 25 off
ramp will rise to meet the new Harpers Ferry Road. These
bridges are currently under construction south of the existing
highway. Once these structures are complete and open to
traffic, the existing section of I-84 will be demolished.
1
2
Left: Crane lifts steel
girder over closed I-84
during night work.
Below: Worker secures
bolts on steel girders.
Harpers Ferry Road Bridge will be realigned, and construction
for the footings for the southern abutment and pier stem for
the new bridge is underway. The new abutment and pier stem
footings run almost parallel to the existing highway on the
easternmost bank of the Mad River, south of I-84.
5 4
3
The photo below shows the locations of structures, discussed
above, with I-84 WB at top and Harpers Ferry Road below the
Mad River; view is facing north.
Future EB 25 off ramp over Mad River
Future I-84 bridge over Mad River, eastern crossing
Footings for Harpers Ferry Road pier and abutment
3
4
5 1
2
I-84 Waterbury Project
Construction Newsletter
Summer, 2016 ▪ Page 4
Project Office: 64 Avenue of Industry, Waterbury, CT 06705
T 203-725-3089
www.i-84waterbury.com
Outreach to Residents
The Public Information Team directly engages with residents
and businesses within areas of potentially unexpected
disruptive construction activities to make them aware of work
that is scheduled to take place. The team was invited by the
Bouley Manor Neighborhood Association to present project
updates during its
monthly meeting
on June 9th
(photo on right).
P4
PUBLIC INVOLVEMENT
Outreach at Local Businesses
The Public Information Team hosted a Public Listening
Session at Blackie’s Hotdog Stand on June 22nd to which the
public was invited to come and offer comments.
Keep Informed! Sign up to receive Weekly Project
Updates via email at: I-84waterbury.com/email
Know Before You Go: Consult our real-time interactive
traffic map (depicted below) before you travel through the
project limits, and see the speed of traffic flow in each
direction. Find the link to the map on the homepage of the
website: i-84waterbury.com
Public Information Meeting
The Connecticut Department of Transportation’s I-84
Waterbury Project Team held a public information meeting at
Crosby High School auditorium on Thursday, May 5, 2016
with a presentation on project updates and highlights of
upcoming work in 2016 and 2017. Project plans were
available and the public was invited to ask questions of the
team concerning current and upcoming work.
The Q & A recap, along with the slides presented depicting
upcoming work can found on the Public Information page on
the project website.
Upcoming Work in 2016 Presented at the May 5th Public
Information Meeting Presentation is as follows:
▪ Hamilton Avenue Bridge (Bridge 4321)
I-84 closure at Exit 23 for setting structural steel.
(completed June 2016)
Open western portion of Hamilton Avenue Bridge; shift
traffic, begin demolition of eastern portion (Fall 2016)
▪ I-84 over Mad River western crossing (Bridge 1224)
Complete EB portion of bridge
Shift I-84 EB traffic (Late Summer 2016)
Shift I-84 WB traffic (Fall 2016)
▪ Scott Road/Plank Road East/WB 25 off ramp
Continue construction of two culverts
Relocation of Beaver Pond Brook to the north
Above and left:
Project team
engineers discuss
plans for the new
I-84 alignment with
meeting attendees.
Left and below: Elected
official and resident
discuss their concerns
with the Public
Information Team.