i 84 waterbury project

4
I-84 Waterbury Project Construction Newsletter www.i-84waterbury.com [email protected] Creating Habitats: A family of Canadian geese (below) enjoy a swim in the newly realigned Mad River. Realigning Beaver Pond Brook Bridge Construction Setting Structural Steel Construction Off the Mainline Public Involvement IN THIS ISSUE Summer, 2016 CONSTRUCTION WITH PRECAST CONCRETE SECTIONS REALIGNING BEAVER POND BROOK The I-84 Waterbury Project includes unique construction features — extensive in-water work for the realignment of two rivers: the Mad River, in the Plank Road/Reidville Drive vicinity, and the Beaver Pond Brook, in the Scott Road vicinity. Realignment of the water bodies supports the successful realignment of I-84 and its access ramps. Work, which started in the spring, continues as the Beaver Pond Brook is realigned along the existing I-84 WB Exit 25 off ramp and along Plank Road, to flow through two new culverts that will carry the waterway under the roads (see map at right). Once realigned, the Beaver Pond Brook will flow through Culvert 014, under Scott Road, and then through Culvert 06622, under the new Plank Road East. Plank Road East will run parallel to future I-84, in two directions, both east and west, to Harpers Ferry Road. Left: Construction site of Culvert 06622 after initial excavation and site preparation for new path of Beaver Pond Brook. Right: Site during placement of precast concrete segments, with 20 of 22 segments in Above: Culvert backfilled; forms for holding poured concrete for the headwalls in place. Right: Culvert with water-proofing on top and cast concrete headwalls on both ends. Precast concrete sections (culvert section being moved by crane below) can be seen on various construction sites within the project limits of the I-84 Waterbury Project. Each product is uniquely designed for its ultimate usage in retaining walls, culverts, and drainage. The series of photos below follow the construction of Culvert 06622, constructed using 22 precast interlocking concrete segments, to form a two-barrel box culvert.

Upload: others

Post on 04-Oct-2021

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: I 84 Waterbury Project

I-84 Waterbury Project

Construction Newsletter

www.i-84waterbury.com

[email protected]

Creating Habitats: A family of

Canadian geese (below) enjoy a swim

in the newly realigned Mad River.

Realigning Beaver Pond Brook

Bridge Construction

Setting Structural Steel

Construction Off the Mainline

Public Involvement

IN THIS ISSUE

Summer, 2016

CONSTRUCTION WITH PRECAST

CONCRETE SECTIONS

REALIGNING BEAVER POND BROOK

The I-84 Waterbury Project includes unique

construction features — extensive in-water

work for the realignment of two rivers: the

Mad River, in the Plank Road/Reidville Drive

vicinity, and the Beaver Pond Brook, in the

Scott Road vicinity. Realignment of the water

bodies supports the successful realignment

of I-84 and its access ramps. Work, which

started in the spring, continues as the Beaver

Pond Brook is realigned along the existing

I-84 WB Exit 25 off ramp and along Plank

Road, to flow through two new culverts that

will carry the waterway under the roads (see

map at right). Once realigned, the Beaver

Pond Brook will flow through Culvert 014,

under Scott Road, and then through Culvert

06622, under the new Plank Road East.

Plank Road East will run parallel to future

I-84, in two directions, both east and west, to

Harpers Ferry Road.

Left: Construction site of Culvert

06622 after initial excavation

and site preparation for new

path of Beaver Pond Brook.

Right: Site during placement of

precast concrete segments,

with 20 of 22 segments in

Above: Culvert backfilled; forms for holding

poured concrete for the headwalls in place.

Right: Culvert with water-proofing on top and

cast concrete headwalls on both ends.

Precast concrete sections (culvert

section being moved by crane below)

can be seen on various construction

sites within the project limits of the I-84

Waterbury Project. Each product is

uniquely designed for its ultimate

usage in retaining walls, culverts, and

drainage.

The series of photos below follow the construction of Culvert 06622, constructed using

22 precast interlocking concrete segments, to form a two-barrel box culvert.

Page 2: I 84 Waterbury Project

I-84 Waterbury Project

Construction Newsletter

Summer, 2016 ▪ Page 2

Project Office: 64 Avenue of Industry, Waterbury, CT 06705

T 203-725-3089

www.i-84waterbury.com

[email protected]

BRIDGE CONSTRUCTION

I-84 and EB 25 Off Ramp Over Mad River, Western

Crossing (Bridge 1224): Workers set structural steel for

this bridge under construction on the southern side of the

existing/demolished I-84 bridge in the spring, and construction

of the decks continue this summer, with paving scheduled in

July. Once completed, drivers can anticipate traffic shifts onto

this new portion of the I-84 bridge so that demolition and

reconstruction of the north side of the bridge can commence.

The EB 25 off ramp will not be in use until the entire ramp,

that extends for almost a

mile, from west of the

Hamilton Avenue Bridge

overpass, crossing over

the Mad River twice, to

Harpers Ferry Road,

opens in 2017.

Right: Deck of

Bridge 1224 (EB 25

off ramp portion)

with rebar in place

as machine for

finishing concrete

prepares for a dry-

run before concrete

is placed.

Above: Structural

steel in place for

Bridge 1224, shot

from the bank of the

Mad River.

Right: Workers

install diaphragms

between steel

girders.

Left: Steel girders with

cross braces in place for

new bridge deck.

Below: Worker installs

braces for parapet.

Left: Stay-in-place forms

welded in place onto steel

beams for bridge deck.

Below: Stay-in-place forms

with foam covering and shear

stud connectors to join steel

girders to concrete deck.

Right: Deck finishing

machine rolls over

poured concrete to

take it to the proper

grade and cross

slope; 138 yards of

concrete were

poured.

Above: Old bridge

abutment is

demolished after

existing deck and

steel are partially

removed.

Right: Structural

steel girders are

set in place for

new bridge.

Page 3: I 84 Waterbury Project

I-84 Waterbury Project

Construction Newsletter

Summer, 2016 ▪ Page 3

Project Office: 64 Avenue of Industry, Waterbury, CT 06705

T 203-725-3089

www.i-84waterbury.com

[email protected]

P4

Above: New structural steel spans full expanse of Hamilton Avenue

Bridge, on the western portion, from north to south over I-84.

SETTING STRUCTURAL STEEL

Hamilton Avenue Bridge (Bridge 4321): As the Project will

widen I-84 to three lanes in each direction, the existing bridge

must be lengthened to accommodate not only the additional

lanes, but also the EB 25 off ramp. This requires spanning all

new structural steel across I-84, from the newly constructed

abutment on the north side, over two center piers, to the

abutment on the south side. As the steel girders had to be

placed and secured over travel lanes of I-84, the structural

steel was erected during the night time hours. For safety

purposes, I-84 was closed at Exit 23 in both directions to

prevent travelers from entering the active work zone during

splicing of girder sections. Motorists were guided through the

detour route by construction signage, State, and local Police.

The photo to the right depicts

locations of the two bridges

where the steel decks are

currently under construction,

with Hamilton Ave. overpass;

facing east.

I-84 Bridge Over Mad

River (Bridge 1224)

Hamilton Ave Bridge

(Bridge 4321)

Right: Excavation for

cofferdam, which will

keep water out of the site

during construction of the

abutment for the new I-84

bridge over the Mad

River, eastern crossing.

CONSTRUCTION OFF THE MAINLINE

West of Harpers Ferry Road: Construction of the new I-84

bridge and new EB 25 off ramp over the Mad River (eastern

crossing) continues with abutment construction visible on both

banks of the river (photo of sites below). The new EB 25 off

ramp will rise to meet the new Harpers Ferry Road. These

bridges are currently under construction south of the existing

highway. Once these structures are complete and open to

traffic, the existing section of I-84 will be demolished.

1

2

Left: Crane lifts steel

girder over closed I-84

during night work.

Below: Worker secures

bolts on steel girders.

Harpers Ferry Road Bridge will be realigned, and construction

for the footings for the southern abutment and pier stem for

the new bridge is underway. The new abutment and pier stem

footings run almost parallel to the existing highway on the

easternmost bank of the Mad River, south of I-84.

5 4

3

The photo below shows the locations of structures, discussed

above, with I-84 WB at top and Harpers Ferry Road below the

Mad River; view is facing north.

Future EB 25 off ramp over Mad River

Future I-84 bridge over Mad River, eastern crossing

Footings for Harpers Ferry Road pier and abutment

3

4

5 1

2

Page 4: I 84 Waterbury Project

I-84 Waterbury Project

Construction Newsletter

Summer, 2016 ▪ Page 4

Project Office: 64 Avenue of Industry, Waterbury, CT 06705

T 203-725-3089

www.i-84waterbury.com

[email protected]

Outreach to Residents

The Public Information Team directly engages with residents

and businesses within areas of potentially unexpected

disruptive construction activities to make them aware of work

that is scheduled to take place. The team was invited by the

Bouley Manor Neighborhood Association to present project

updates during its

monthly meeting

on June 9th

(photo on right).

P4

PUBLIC INVOLVEMENT

Outreach at Local Businesses

The Public Information Team hosted a Public Listening

Session at Blackie’s Hotdog Stand on June 22nd to which the

public was invited to come and offer comments.

Keep Informed! Sign up to receive Weekly Project

Updates via email at: I-84waterbury.com/email

Know Before You Go: Consult our real-time interactive

traffic map (depicted below) before you travel through the

project limits, and see the speed of traffic flow in each

direction. Find the link to the map on the homepage of the

website: i-84waterbury.com

Public Information Meeting

The Connecticut Department of Transportation’s I-84

Waterbury Project Team held a public information meeting at

Crosby High School auditorium on Thursday, May 5, 2016

with a presentation on project updates and highlights of

upcoming work in 2016 and 2017. Project plans were

available and the public was invited to ask questions of the

team concerning current and upcoming work.

The Q & A recap, along with the slides presented depicting

upcoming work can found on the Public Information page on

the project website.

Upcoming Work in 2016 Presented at the May 5th Public

Information Meeting Presentation is as follows:

▪ Hamilton Avenue Bridge (Bridge 4321)

I-84 closure at Exit 23 for setting structural steel.

(completed June 2016)

Open western portion of Hamilton Avenue Bridge; shift

traffic, begin demolition of eastern portion (Fall 2016)

▪ I-84 over Mad River western crossing (Bridge 1224)

Complete EB portion of bridge

Shift I-84 EB traffic (Late Summer 2016)

Shift I-84 WB traffic (Fall 2016)

▪ Scott Road/Plank Road East/WB 25 off ramp

Continue construction of two culverts

Relocation of Beaver Pond Brook to the north

Above and left:

Project team

engineers discuss

plans for the new

I-84 alignment with

meeting attendees.

Left and below: Elected

official and resident

discuss their concerns

with the Public

Information Team.