I-94 MODERNIZATION PROJECTLAC-GAC Meeting
December 5, 2017
MEETING AGENDA
Introductions Public Engagement Activities Update Advance Bridge Construction Update Breakout Discussions Next Steps
PUBLIC ENGAGEMENT : OUR PURPOSE
To collect public input used to refine the proposed I-94 project modifications and meet SEIS* requirements.
*Supplemental Environmental Impact Statement
PUBLIC ENGAGEMENT : HOW WE GOT STARTED
Formed the LAC/GAC and solicited your recommendations.
PUBLIC ENGAGEMENT : HOW WE GOT STARTED
Conferred with Districts 3, 4, 5 and 6
councilpersons and staff from Detroit City
Council and Mayor’s Department of
Neighborhood staff
PUBLIC ENGAGEMENT : HOW WE GOT STARTED
Created “Resident Roundtable” outreach concept including:
Customized presentations
Comprehensive project newsletter
Workforce/SBE development information
Opportunities for one-on-one and group feedback
Media outreach
PUBLIC ENGAGEMENT : IN THE COMMUNITY
Events and Activities DatesProject Briefing – Detroit Greenways Coalition – Todd Scott 7/28/17Project Briefing – Pastor Raymond Scott, New Mt. Carmel Tabernacle Church 8/8/17Project Briefing – Councilman Scott Benson and staff – District 3 8/1/17Project Briefing – Councilman Andre Spivey and staff – District 4 8/3/17Community Fair – New Mt. Carmel Tabernacle Church – Pastor Raymond Scott 8/19/17Project Briefing – Councilwoman Mary Sheffield and staff – District 5 8/28/17Project Briefing – Councilwoman Raquel Castaneda-Lopez staff – District 6 8/29/17LAC-GAC Educational Online Webinar – I-94 Project Team 9/20/17Community Resource Fair – Mayor’s Department of Neighborhoods – District 6 9/26/17I-94 Resident Roundtable Meeting – Councilman Spivey – District 4 9/28/17LAC-GAC I-94 Corridor Bus Tour – I-94 Project Team 10/7/17Community Resource Fair – Councilman Benson – District 3 10/11/17I-94 Resident Roundtable Meeting – Councilman Benson – District 3 10/18/17Project Briefing – Mayor’s Department of Neighborhoods – District 5 10/19/17Workforce Development Taskforce – Councilwoman Brenda Jones – Citywide 10/24/17I-96/I-94 Interchange Community Leaders – District 6 10/26/17The Mildred Gaddis Show – Radio 102.7 – I-94 Project Team 10/30/17Chadsey-Condon Community Organization Safety Committee --District 6 11/8/17Woodbridge Community Council – District 6 11/9/17Wayne State University Student Center – Emily Thompson and WSU staff 11/13/17Midtown Detroit, Inc. – Sue Mosey/Elise Fields 11/14/17Bridging Communities, Inc. – District 6 11/16/17
PUBLIC ENGAGEMENT : WHAT WE HEARD
PUBLIC ENGAGEMENT : 2018/2019 – KEEP IT GOING!
More Public Engagement: Community corridor tour –
spring/summer 2018 Roundtable discussion with: Eastside Coalition Matrix Center University Prep parents Precincts 3, 4 and 9 Council of Communities Fourth Street Neighborhood Henry Ford Hospital employees And others
PUBLIC ENGAGEMENT : 2018/2019 – KEEP IT GOING!
More Public Engagement: Public Hearing – 2019
PUBLIC ENGAGEMENT : 2018/2019 – KEEP IT GOING!
More Media Outreach: Detroit Today with Stephen Henderson (WDET 101.9)
Mason and Coco in the Morning Show (KISS 105.9 FM)
Michigan Chronicle
Latino Press and El Centro
Arab News
Chaldean News
Connect With Us!
Facebook–I94DetroitTwitter–@I94Detroit
Website–www.I94Detroit.orgSave the date: Jan 10, 2018
For all I-94 project news, events and updates.
PUBLIC ENGAGEMENT : 2018/2019 – KEEP IT GOING!
ADVANCED BRIDGE CONSTRUCTION UPDATE
2018 CONSTRUCTION SEASON
Anticipated Letting: December 2017
2018 Construction (1 season)
Scope:– Complete bridge replacement
– Staged construction – Gratiot Avenue Bridge remains open during construction
– Utility relocations
– Traffic & safety improvements
– New lighting
GRATIOT AVENUE BRIDGE CONSTRUCTION (2018)OVERVIEW
GRATIOT AVENUE BRIDGE CONSTRUCTION (2018)PROPOSED DESIGN
GRATIOT AVE. | EXISTING BRIDGE
GRATIOT AVE. | PROPOSED BRIDGE
GRATIOT AVENUE BRIDGE CONSTRUCTION (2018)STAGED CONSTRUCTION – STAGE 1 (<1 Month)
Removing existing sidewalk on the west side of Gratiot.
Gratiot Avenue remains open:– 2-lanes southbound
– 3-lanes northbound
I-94 Ramps:– Eastbound Open
– Westbound Closed (Detoured)
Total duration: <1 Month
N
Remove existing sidewalk to allow vehicle traffic.
LEGEND
Work Zone
Traffic Lane
GRATIOT AVENUE BRIDGE CONSTRUCTION (2018)STAGED CONSTRUCTION – STAGE 2 (4 Months)
N Reconstruct eastern half
of the Gratiot Bridge.
Gratiot Avenue remains open:– 2-lanes southbound
– 2-lanes northbound
I-94 Ramps:– Eastbound Closed
– Westbound Closed
– Ramps detoured
Total duration: 4 Months
Remove and replace eastern half of the bridge.
Access to business maintained during construction.
LEGEND
Work Zone
Traffic Lane
GRATIOT AVENUE BRIDGE CONSTRUCTION (2018)STAGED CONSTRUCTION – STAGE 3 (4 Months)
N Removing western half of
the Gratiot Bridge.
Gratiot Avenue remains open:– 2-lanes southbound
– 2-lanes northbound
I-94 Ramps:– Eastbound Closed
– Westbound Closed
– Ramps detoured
Total duration: 4 Months
Remove and replace western half of the bridge.
Access to business maintained during construction.
LEGEND
Work Zone
Traffic Lane
New bridge.
GRATIOT AVENUE BRIDGE CONSTRUCTION (2018)DETOUR ROUTES – EB & WB I-94 EXIT RAMPS TO GRATIOT AVENUE
Closure of I‐94 ramps at Gratiot Avenue during construction.
EB I‐94 traffic detoured to Van Dyke.
LEGEND
Work Zone
Detour Route
N
VAN DYK
E
WB I‐94 traffic detoured to Conner.
• Full closure of Gratiot Avenue Ramps (8 Months)
GRATIOT AVENUE BRIDGE CONSTRUCTION (2018)DETOUR ROUTES – EB & WB I-94 ENTRANCE RAMPS FROM GRATIOT AVENUE
Gratiot Avenue traffic detoured to Conner to access I‐94.
LEGEND
Work Zone
Detour Route
N
Closure of I‐94 ramps at Gratiot Avenue during construction.
VAN DYK
E• Full closure of Gratiot Avenue Ramps (8 Months)
GRATIOT AVENUE BRIDGE CONSTRUCTION (2018)DETOUR ROUTES – PEDESTRIANS
LEGEND
Work Zone
Pedestrian Detour Route
N
SHOEMAKER
Pedestrian traffic detoured to Cadillac to cross I‐94.No pedestrian access
on the bridge during construction.
• Pedestrian access closed (8‐9 Months)
CHEN
E
Anticipated Letting: December 2017
2018 Construction (1 season)
Scope:
– Complete bridge replacement
– Full closure of the Chene Street Bridge
– Utility relocations
– Traffic & safety improvements
– New lighting
CHENE STREET BRIDGE CONSTRUCTION (2018)OVERVIEW
CHENE STREET BRIDGE CONSTRUCTION (2018)PROPOSED DESIGN
CHENE STREET | PROPOSED BRIDGECHENE STREET | PROPOSED BRIDGE
• Full closure of Chene Street Bridge ( 8 Months)• Full closure of WB I‐94 entrance ramp from Lucky Place (1 Month)
E GRA
ND
ST AUBIN
GRA
NDY
DUBO
IS
LUCK
Y
SAGINAW
MT ELLIOTT
GM M
AIN ENTR
ANCE
GM W
EST EN
TRAN
CE
GM EAS
T EN
TRAN
CEGM TRUCKENTRANCE
CHEN
E
MEDBURY
CHENE STREET BRIDGE CONSTRUCTION (2018)DETOUR ROUTES – WB I-94 ENTRANCE RAMP FROM LUCKY PLACE (PRE-STAGE)
LEGEND
Work Zone
Detour Route
WB I‐94 entrance ramp closure.
Traffic detoured to the WB entrance ramp at Chene Street.
• Full closure of Chene Street Bridge ( 8 Months)
E GRA
ND
ST AUBIN
GRA
NDY
DUBO
IS
LUCK
Y
SAGINAW
MT ELLIOTT
GM M
AIN ENTR
ANCE
GM W
EST EN
TRAN
CE
GM EAS
T EN
TRAN
CEGM TRUCKENTRANCE
CHEN
E
MEDBURY
CHENE STREET BRIDGE CONSTRUCTION (2018)DETOUR ROUTES – NB CHENE STREET
`
LEGEND
Work Zone
Detour Route
Local NB Chene Street traffic detoured along the service drive to the U‐turn bridge west of Mt. Elliott.
No left‐turns permitted at E. Grand Boulevard.
Chene Street bridge closure.
LEGEND
Work Zone
Pedestrian Detour Route
• Full closure of Chene Street Bridge ( 8 Months)
E GRA
ND
ST AUBIN
GRA
NDY
DUBO
IS
LUCK
Y
SAGINAW
MT ELLIOTT
GM M
AIN ENTR
ANCE
GM W
EST EN
TRAN
CE
GM EAS
T EN
TRAN
CEGM TRUCKENTRANCE
CHEN
E
MEDBURY
CHENE STREET BRIDGE CONSTRUCTION (2018)DETOUR ROUTES – PEDESTRIANS
Pedestrian traffic detoured to E. Grand Boulevard to cross I‐94.
Chene Street bridge closure.
LEGEND
Work Zone
Detour Route
• Full closure of Chene Street Bridge ( 8 Months)• Full closure of EB I‐94 exit ramp to Chene Street (8 Months)
EB I‐94 traffic detoured to the Mt. Elliott exit.
CHENE STREET BRIDGE CONSTRUCTION (2018)DETOUR ROUTES – EB I-94 EXIT RAMP TO CHENE STREET
E GRA
ND
ST AUBIN
GRA
NDY
DUBO
IS
LUCK
Y
SAGINAW
MT ELLIOTT
GM M
AIN ENTR
ANCE
GM W
EST EN
TRAN
CE
GM EAS
T EN
TRAN
CEGM TRUCKENTRANCE
CHEN
E
MEDBURY
EB I‐94 exit ramp to Chene Street closure.
OTHER 2018 BRIDGE CONSTRUCTIONOVERVIEW
Concord Avenue – Summer 2018– Full closure of the Concord Avenue Bridge
– Traffic detours
French Road – Summer 2018– Full closure of the French Road Bridge
– Ramp closures
PEDESTRIAN BRIDGE REMOVALS2018 CONSTRUCTION
Helen, Rohns, and Springfield are currently closed due to their condition.
Scheduled for removal in 2018.
These bridges will be replaced during the I-94 corridor construction as either pedestrian bridges (Approved Selected Alternative from the 2004 FEIS) or Complete Streets bridges (2017 Proposed Modifications).
SPRINGFIELD PEDESTRIAN BRIDGEROHNS PEDESTRIAN BRIDGEHELEN PEDESTRIAN BRIDGE
Advanced Bridges Phase 1
Advanced Bridges Phase 1 (Unbundled Packages)
PKG WORK CONST. YEAR
4 Landscaping/Gratiot 2018
5 Landscaping/2nd and Cass 2019
6 Turf Establishment/Chene and Gratiot 2018
7 Turf Establishment/Mt. Elliott, Concord and French 2018‐2019
8 Turf Establishment/2nd, Cass and Brush 2019
9 Fence‐Guardrail/Concord, French and Mt. Elliott 2018‐2019
10 Lighting/Chene and Gratiot 2018
11 Lighting/Concord, French and Mt. Elliott 2018‐2019
12 Sidewalks‐Driveways/Chene and Gratiot 2018
13 Sidewalks‐Driveways/Concord, French, Mt. Elliott 2018‐2019
14 Sidewalks‐Driveways/2nd, Cass and Brush 2019
Advanced Bridges Phase 1 (Bridge Packages)
PKG WORK CONST. YEAR
1
Chene St. over I‐94 2018
Gratiot Ave. over I‐94 2018
Helen St.* over I‐94 2018
Rohns St.* over I‐94 2018
Springfield* 2018
3
Mt. Elliott St. over I‐94 2019
Concord Ave. over I‐94 2018
French Rd. over I‐94 2018
2Second Ave. over I‐94 2019
Cass Ave. over I‐94 2019
Brush St. over I‐94 2019
*Helen St., Rohns St., Springfield Ave. pedestrian bridge removals only.
SMALL BUSINESS ENGAGEMENT UPDATE
I-94 MODERNIZATION
QUESTIONS
Contact information:Terry Stepanski, PEMDOT Senior Project ManagerEmail: [email protected]