i erosion sedimentcontrol · call the arc on 0800-80-60-40 or 09-377-3107. mulching needs to be...

125
erosion & sediment control Guidelines for Land Disturbing Activities in the Auckland Region Auckland Regional Council i March 1999 Auckland Regional Council Technical Publication No. 90 ISSN 1172 6415

Upload: others

Post on 23-Sep-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council i

March 1999

Auckland Regional CouncilTechnical Publication No. 90ISSN 1172 6415

Page 2: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

CHANGES TO TP90 – DECEMBER 2007 Chapter B1 – Section 1.6.3 Mulching Changes to Pages 13- 14 Definition The application of a protective layer of straw or other suitable material to the soil surface. Purpose To protect the soil surface from the erosive forces of raindrop impact and overland flow. Mulching also helps to conserve moisture, reduce runoff and erosion, control weeds, prevent soil crusting and promote the establishment of desirable vegetation. Application This practice applies to any site where vegetation establishment is important for the protection of bare earth surfaces. Mulching can be used at any time where the instant protection of the soil surface is desired. Mulching can be used in conjunction with seeding to establish vegetation, or by itself to provide temporary protection of the soil surface. Mulching is used during the winter months (30 April to 1 October) to provide immediate stabilisation. Because grass germination will be too slow to establish effective grass cover using conventional sowing methods. Design Not Applicable. Construction Specifications Site Preparation Before Mulching install any needed erosion and sediment control practices such as Runoff Diversion Channels and sediment retention structures. Mulching When mulching, use unrotted small grain straw applied at a density of 6,000 kg per ha such that the coverage is consistent or no bare soil is visible though the mulch layer. The mulch layer should remain until alternative stabilisation is achieved. Note that hay does not last long on the ground and remulching may be required. Ensure the material is free of any noxious plants as identified under the Auckland Regional Council policy. Call the ARC on 0800-80-60-40 or 09-377-3107.

Page 3: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate. For larger sites, apply mulch mechanically to ensure an even spread and appropriate application. Apply fertiliser with Mulching as outlined in Table 1.6 of these Guidelines. Alternatives such as wood chips and chemical soil binders can be utilised where appropriate. Wood chips are suitable for areas that will not be closely mowed around such as ornamental plantings. They do not require the application of a tackifier and if readily available can be a relatively inexpensive mulch. They are slow to break down and normally require nitrogen application to prevent nutrient deficiency in plants. Do not use woodchips around watercourses or in areas where water can pond. To avoid water contamination, any alternative to straw mulch must be approved by the Auckland Regional Council. Another alternative are rovings which are fibres that are teased out from spools of yarn by compressed air and woven onto the surface of the land. They are then stabilised with a tackifier, with seed sown beforehand. These alternatives should be discussed with ARC before their implementation. A wide range of synthetic mulching compounds are available to stabilise and protect the soil surface. These include emulsions, acrylimides and dispersions of vinyl compounds. They do not insulate the soil or retain moisture when used alone and therefore do little to aid seed establishment. They are also easily damaged by traffic, decompose relatively quickly and can be quite expensive in comparison to organic mulches. Anchoring Mulch Anchor Mulch in place immediately after application to avoid or minimise loss by wind or water. Numerous methods are available. Generally, although the Mulch is ‘settled’ in place by the first rainfall, the Auckland Regional Council also requires it be retained by crimping into the soil with discs or spraying a tackifier with the Mulch. When using some chemical tackifiers, take care to avoid adverse offsite effects of runoff particularly around watercourses.

Page 4: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

Chapter B1 – Section 1.8 Stabilised Construction Entrance Changes to Pages 20 - 21 Definition A stabilised pad of aggregate on a woven geotextile base located at any point where traffic will be entering or leaving a construction site. Purpose To prevent site access points from becoming sediment sources and to help minimise dust generation and disturbance of areas adjacent to the road frontage by giving a defined entry/exit point. Application Use a Stabilised Construction Entrance at all points of construction site ingress and egress with a construction plan limiting traffic to these entrances only. They are particularly useful on small construction sites but can be utilised for all projects. Design

o Clear the entrance and exit area of all vegetation, roots and other unsuitable material and properly grade it.

o Lay woven geotextile; pin down edges and overlap joins; o Provide drainage to carry runoff from the Stabilised Construction Entrance to a sediment

control measure; o Place aggregate to the specifications below and smooth it.

Table 1.8 Stabilised Construction Entrance Aggregate Specifications

Maintenance Maintain the Stabilised Construction Entrance in a condition to prevent sediment from leaving the construction site. After each rainfall inspect any structure used to trap sediment from the Stabilised Construction Entrance and clean out as necessary. When wheel washing is also required, ensure this is done on an area stabilised with aggregate which drains to an approved sediment retention facility.

Aggregate Range 50 – 150mm washed aggregate

Thickness 150mm minimum or 1.5 x aggregate size

Length 10m minimum length recommended

Width 4m minimum

Page 5: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

Changes to Page 21

Figure 1.8 Stabilised Construction Entrance

Page 6: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

Chapter B2 – Section 2.2 Silt Fence Changes to Pages 12 - 14 Definition A temporary barrier of woven geotextile fabric used to intercept runoff, reduce its velocity, filter and impound sediment laden runoff from small areas of disturbed soil. Purpose To detain flows from runoff so that deposition of transported sediment can occur through settlement and filtering through the fabric. Silt fences can only be used to intercept sheet flow. Do not use them as velocity checks in channels or place them where they will intercept concentrated flow. Application

o On low gradient sites or for confined areas where the contributing catchment is small, such as short steep batter fills and around watercourses.

o To delineate the limit of disturbance on an earthworks site such as riparian areas or bush reserves.

o To store runoff behind the Silt Fence without damaging the fence or the submerged area behind the fence.

o Do not install Silt Fences across watercourses or in areas of concentrated flows. Design

o Ensure Silt Fence height is a minimum of 600mm above ground level. o Place supporting posts/waratahs for Silt Fences no more than 2m apart unless additional

support is provided by tensioned wire (2.5mm HT) along the top of the Silt Fence. Where a strong woven fabric is used in conjunction with a wire support, the distance between posts can be extended up to 4m. Double the Silt Fence fabric over and fasten to the wire and posts with wire ties, cloth fastening clips or hog rings at 150mm spacings. Ensure supporting posts/ waratahs are embedded a minimum of 400mm into the ground.

o Always install Silt Fences along the contour. Where this is not possible or where there are long sections of Silt Fence, install short Silt Fence returns projecting up slope from the Silt Fence to minimise concentration of flows. Silt Fence returns are a minimum 2m in length, can incorporate a tie back and are generally constructed by continuing the Silt Fence around the return and doubling back, eliminating joins.

o Join lengths of Silt Fence by doubling over fabric ends around a wooden post or batten or by stapling the fabric ends to a batten and butting the two battens together or by overlapping at least 2m as shown in Figure 2.2.

Page 7: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

o Maximum slope lengths, spacing of returns and angles for Silt Fences are shown in Table 2.2.

o Install Silt Fence wings at either end of the Silt Fence projecting upslope to a sufficient height to prevent outflanking.

o Where impounded flow may overtop the Silt Fence, crossing natural depressions or low points, make provision for a riprap splash pad or other outlet protection device.

Table 2.2 Silt Fence Design Criteria

Construction Specifications

o Where water may pond behind the Silt Fence, provide extra support for the Silt Fence with tie backs from the Silt Fence to a central stable point on the upward side. Extra support can also be provided by stringing wire between support stakes and connecting the filter fabric to this wire.

o Excavate a trench a minimum of 200mm wide and 200mm deep along the proposed line of the Silt Fence. Install the support posts on the downslope edge of the trench and Silt Fence fabric on the upslope side of the support posts to the full depth of the trench, then backfill the trench with compacted soil.

o Use of Silt Fences in catchments of more than 0.5ha requires careful consideration of specific site measures, and other control measures may be better, such as a Super Silt Fence.

o Where water may pond behind the Silt Fence, provide extra support for the Silt Fence with tie backs from the Silt Fence to a central stable point on the upward side. Extra support can also be provided by stringing wire between support stakes and connecting the filter fabric to this wire.

o The fabric cloth must meet the following requirements for Geotextile fabric. Grab Tensile Strength: >440N (ASTM D4632) Tensile Modulus: 0.140 pa (minimum) Apparent Opening Size 0.1 – 0.5mm (ASTM D4751)

Slope Steepness % Slope Length (m) (Maximum) Spacing of Returns (m)

< 2% N/A Unlimited

2 – 10% 40 60

10 – 20% 30 50

20 – 33% 20 40

33 – 50% 15 30

> 50% 6 20

Page 8: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

o Use supporting posts of tanalised timber a minimum of 50mm square, or steel waratahs at least 1.5m in length.

o Reinforce the top & bottom of the Silt Fence fabric with a wire support made of galvanised wire of a minimum diameter of 2.5mm. Tension the wire using permanent wire strainers attached to angled waratahs at the end of the Silt Fence.

o Where ends of Silt Fence fabric come together, ensure they are overlapped, folded and stapled/screwed to prevent sediment bypass.

Maintenance

o Inspect Silt Fences at least once a week and after each rainfall. Make any necessary repairs when bulges occur or when sediment accumulation reaches 50% of the fabric height.

o Any areas of collapse, decomposition or ineffectiveness need to be immediately replaced. o Remove sediment deposits as necessary to continue to allow for adequate sediment

storage and reduce pressure on the Silt Fence. Ensure that the sediment is removed to a secure area.

o Do not remove Silt Fence materials and sediment deposition until the catchment area has been appropriately stabilised. Stabilise the area of the removed Silt Fence.

Page 9: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate
Page 10: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

Chapter B2 – Section 2.3 Super Silt Fence Changes to Pages 15 - 17 Definition A temporary barrier of woven geotextile fabric over chain link fence that is used to intercept runoff, reduce their velocity, filter and impound sediment-laden runoff from small areas of disturbed soil. Purpose To reduce runoff velocity so that deposition of transported sediment can occur through settlement and filtering through the fabric. A Super Silt Fence provides much more robust sediment control than a standard Silt Fence and allows up to four times the catchment area to be treated by an equivalent length of standard Silt Fence. Application

o Provides a barrier that can collect and hold debris and soil, preventing the material from entering critical areas, watercourses and streets.

o Can be used where the installation of an Earth or Topsoil Bund would destroy sensitive areas such as bush and wetlands.

o Should be placed as close to the contour as possible. No section of the fence should exceed a grade of 5% for a distance of more than 15m.

Design When considering Super Silt Fence installation for larger catchments (greater than 0.5ha) as in Table 2.3, carefully consider the specific site conditions and other alternative control measures available. Base the length of the Super Silt Fence on the limits shown in Table 2.3. Limits imposed by ultraviolet light affect the stability of the fabric and will dictate the maximum period that the Super Silt Fence may be used. Where ends of the geotextile fabric come together, overlap, fold and staple the fabric ends to prevent sediment bypass.

Table 2.3 Super Silt Fence Design Criteria

Slope Steepness % Slope Length (m) (Maximum) Spacing of Returns (m)

0 -10% Unlimited 60

10 – 20% 60 50

20 – 33% 30 40

33 – 50% 30 30

> 50% 15 20

Page 11: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

Construction Specifications

o Use a Silt Fence fabric that is appropriate to the site conditions and fits the manufacturer’s specifications.

o Excavate a trench 200mm wide by 300mm deep along the line of the Super Silt Fence. o Position the posts (No. 3 rounds, No. 2 half rounds or waratahs) at no greater than 3m

centres on the downslope side of the trench. While there is no need to set the posts in concrete, ensure the 1.8m long posts are driven to an appropriate depth (1metre minimum).

o Install tensioned galvanised wire (2.5 mmHT) at 400mm and again at 800mm above ground level using permanent wire strainers.

o Secure chain link fence to the fence posts with wire ties or staples, ensuring the chain link fence goes to the base of the trench.

o Fasten two layers of geotextile fabric securely to the Super Silt Fence with ties spaced every 600mm at the top and mid section of the Super Silt Fence.

o Place the two layers of geotextile fabric to the base of the trench (a minimum of 300mm into the ground) and place compacted backfill back to the original ground level.

o Embed geotextile support into the ground by 300mm upslope for 200mm. o When two sections of geotextile fabric adjoin each other, ensure they are doubled over a

minimum of 300mm, wrapped around a batten and stapled at 75mm spacings to prevent sediment bypass.

o The geotextile fabric must meet the following requirements: Grab Tensile Strength: >440N (ASTM D4632) Tensile Modulus: 0.140 pa (minimum) Apparent Opening Size 0.1 – 0.5mm (ASTM D4751)

Maintenance Inspect regularly and before and after storm events.

Undertake maintenance as needed and remove silt buildups when bulges develop in the Super Silt Fence or when sediment deposition reaches 50% of the Super Silt Fence height.

Page 12: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate
Page 13: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council i i

Auckland Regional Council acknowledges the assistance

of many earthwork consultants and contractors,

specifically Babington and Associates during the

development and compilation of these guidelines.

Special thanks also goes to Shelley Trueman and Clare

Feeney for providing valuable advice and guidance.

Copyright 1999 © Auckland Regional Council

No part of this publication may be reproduced, stored in a retrieval system or

transmitted in any form or by any means electronic, mechanical, photocopying,

recording or otherwise, without the prior permission of the publisher.

Printed on recycled paper.

A c k n o w l e d g e m e n t s

Page 14: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council i i i

These Guidelines replace Auckland Regional CouncilTechnical Publication Number 2 and are to be known asTechnical Publication Number 90 Erosion and SedimentControl Guidelines for Land Disturbing Activities in theAuckland Region.

The intent of these Guidelines is as follows:

o To provide a comprehensive guideline for erosionand sediment control.

o To detail the rules of the Proposed Regional Plan:Sediment Control.

o To minimise adverse environmental effects ofsediment discharge through appropriate use anddesign of specific measures.

These Guidelines outline the principles of erosion andsediment control including detailing the TenCommandments of Erosion and Sediment Control in theAuckland Region.

The practices detailed in these Guidelines are divided intoerosion control, sediment control, works within awatercourse, quarries and vegetation removal. For eachpractice these Guidelines outline the following:

o Definition

o Purpose

o Application

o Design/construction specifications

o Comments

o Maintenance

Executive Summary

Page 15: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council i v

We will be regularly reviewing these Guidelines. Please help us keep them accurate and practical - let us knowabout any changes we need to make by using this form.

Please photocopy this form before you fill it out, to keep this original for future use.

1. Errors

Are there any errors in the text or diagrams? If so, please tell us:

o which page and/or figure number it is on

o what the error is and how you would correct it

____________________________________________________________________________________

____________________________________________________________________________________

____________________________________________________________________________________

____________________________________________________________________________________

2. Omissions

Have we left out any measures/practices commonly used or which you find useful? If so, please list them belowand if possible, any design guidelines for us to include:

________________________________________________________________________________________

________________________________________________________________________________________

________________________________________________________________________________________

________________________________________________________________________________________

3. Effectiveness

Are these Guidelines helpful for complying with erosion and sediment control requirements. If not, please tell ushow we can improve these Guidelines:

________________________________________________________________________________________

________________________________________________________________________________________

________________________________________________________________________________________

________________________________________________________________________________________

Response Form

Page 16: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council v

4. Other Comments

Do you have any other comments or questions? If so, please note them below:

________________________________________________________________________________________

________________________________________________________________________________________

________________________________________________________________________________________

________________________________________________________________________________________

5. Your contact details

(Optional) Please note your name and phone number below in case we need to discuss your suggestions in moredetail:

Name: ______________________________________________ Phone: ______________________________

Thank you for taking the time to improve our Guidelines.

Feel free to phone us about your views on (09) 379 4420 (ask for the Sediment Management Team),or Freepost a copy of this response form to:

The Sediment Management Team, Auckland Regional Council, Private Bag 92012, Auckland. Freepost No. 4103.

Response Form

Page 17: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council v i

Par t B – Practices

Table of Contents

p a g e

A c k n o w l e d g e m e n t s i i

Executive Summary i i i

Response Form i v

Table of Contents v i

List of Plates v i i i

List of Figures i x

List of Tables x

1.0 I n t r o d u c t i o n

1.1 Intent of these Guidelines 1

1.2 How these Guidelines Work 1

1.3 Erosion and Sediment Control in the Auckland Region 1

1.4 Current Legislation: When is a Resource Consent Required? 2

1.5 When is Erosion and Sediment Control Required? 2

1.6 Auckland’s Clays: The Prime Impor tance of Erosion Control 3

2 . 0 Principles of Erosion and Sediment Control

2.1 Types of Erosion 1

2 . 2 Factor s Inf luencing the Erosion Process 3

3 . 0 The “Ten Commandments” of Erosion and Sediment Control

4 . 0 Types of Land Disturbing Activities Under taken in the Auckland Region

1.0 Erosion Control

1.1 Runof f Diversion Channel/Bund 1

1.2 Contour Drain 3

1.3 Benched Slope 5

1.4 Rock Check Dam 7

1.5 Top Soil ing 9

Par t A – Principles

Page 18: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council v i i

A p p e n d i c e s

1.6 Revegetation Techniques 10

1.6.1 Temporary and Permanent Seeding 10

1.6.2 H y d r o s e e d i n g 12

1.6.3 M u l c h i n g 13

1.6.4 Tu r f i n g 15

1.7 Geosynthetic Erosion Control Systems (GECS) 17

1.8 Stabilised Construction Entrance 2 0

1.9 Pipe Drop Str ucture/Flume 2 2

1.10 Level Spreader 2 5

1.11 Surface Roughening 2 7

2 . 0 Sediment Control

2.1 Sediment Retention Pond 1

2 . 2 Silt Fence 12

2 . 3 Super Silt Fence 15

2 . 4 Hay Bale Barrier 18

2 . 5 Stormwater Inlet Protection 2 0

2 . 6 Ear th Bund 2 2

2 . 7 Sump / Sediment Pit 2 4

3 . 0 Works Within a Watercourse

3.1 Temporary Watercourse Crossings 1

3 . 2 Temporary Watercourse Diversion 3

3 . 3 Rock Outlet Protection 6

4 . 0 Q u a r r i e s

5 . 0 Vegetation Removal

Appendix A Rules from Proposed Regional Plan: Sediment Control 1

Appendix B Land Use Consent: Sediment Control 4

Land Use Consent: Works Within a Watercourse 11

Appendix C Standard Symbols for Erosion and Sediment Controls 18

G l o s s a r y 1

B i b l i o g r a p hy 8

Par t B – Practices( C o n t i n u e d )

G l o s s a r y /B i b l i o g r a p hy

Table of Contents

p a g e

Page 19: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council v i i i

Par t B – Practices 1.0 Erosion Control

Plate 1.1 Runoff Diversion Channel/Bund 1

Plate 1.2 Contour Drain 3

Plate 1.3 Benched Slope 5

Plate 1.4 Rock Check Dam 7

Plate 1.6.3.1 M u l c h i n g 13

Plate 1.6.3.2 Mulch Crimping 14

Plate 1.6.4 Tu r f i n g 15

Plate 1.8 Stabilised Construction Entrance 2 0

Plate 1.9 Pipe Drop Str ucture 2 2

Plate 1.11 Surface Roughening 2 7

2 . 0 Sediment Control

Plate 2.1.1 Sediment Retention Pond Showing Decant Systems 1

Plate 2.1.2 Sediment Retention Pond Showing Baf f le to LengthenFlowpath and Create Cor rect Length: Width Ratio 5

Plate 2.2 Silt Fence 12

Plate 2.3 Super Silt Fence 15

Plate 2.4 Hay Bale Barrier 18

Plate 2.5 Stormwater Inlet Protection 2 0

Plate 2.6 Ear th Bund 2 2

Plate 2.7 Sump / Sediment Pit 2 4

3 . 0 Works Within a Watercourse

Plate 3.1 Temporary Watercourse Crossing 1

Plate 3.2 Temporary Watercourse Diversion 3

Plate 3.3 Rock Outlet Protection 6

List of Plates

p a g e

Page 20: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council i xList of Figures

Figure 2.1 Types of Erosion Common in the Auckland Region 2

1.0 Erosion Control

Figure 1.1.1 Cleanwater Runof f Diversion Bund 2

Figure 1.1.2 Runoff Diversion Channel 2

Figure 1.2 Contour Drain 4

Figure 1.3 Benched Slope 6

Figure 1.4 Rock Check Dam 8

Figure 1.7.1 Geotextile Laid on Slope 18

Figure 1.7.2 Geotextile at Culver t Outlet 19

Figure 1.8 Stabilised Construction Entrance 21

Figure 1.9 Pipe Drop Structure 2 4

Figure 1.10 Level Spreader 2 6

Figure 1.11 Tr ac k i n g 2 8

2 . 0 Sediment Control

Figure 2.1.1 Sediment Retention Pond 2

Figure 2.1.2 Sediment Retention Pond for Catchments up to 1.5 ha 8

Figure 2.1.3 Sediment Retention Pond for Catchments Between 1.5 and 3 ha 9

Figure 2.1.4 Sediment Retention Pond for Catchments Between 3 and 5 ha 10

Figure 2.1.5 Sediment Retention Pond - Decant Detail 11

Figure 2.2 Silt Fence 14

Figure 2.3 Super Silt Fence 17

Figure 2.4 Hay Bale Barrier 19

Figure 2.5 Stormwater Inlet Protection - Filter Media Design 21

Figure 2.6 Ear th Bund 2 3

Figure 2.7 Sump / Sediment Pit 2 5

3 . 0 Works Within a Watercourse

Figure 3.2.1 Temporary Watercourse Diversion Works Sequence 4

Figure 3.2.2 Temporary Watercourse Diver sion Dam Detail 5

Par t B – Practices

Par t A – Principles

p a g e

Page 21: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council xList of Tables

1.0 Erosion Control

Table 1.2 Positioning of Contour Drains 3

Table 1.3 Benched Slope Design 5

Table 1.4 Rock Check Dam Design 8

Table 1.6 Grass Seed and Fer til iser Application Rates 11

Table 1.8 Stabilised Construction Entrance Aggregate Specif ications 2 0

Table 1.9 Design Criteria for Pipe Drop Structure 2 2

Table 1.10 Level Spreader Design Criteria 2 5

2 . 0 Sediment Control

Table 2.2 Silt Fence Design Criteria 13

Table 2.3 Super Silt Fence Design Criteria 16

Par t B – Practices

p a g e

Page 22: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Introduction: 1 1

1.1 Intent of These Guidelines

These Guidelines have three main objectives:

1. To provide users, ranging from those directlyassociated with various Land Disturbing Activities(Land Disturbing Activities) to interest groups, witha series of comprehensive guidelines for erosion andsediment control for land disturbing activities by:

o outlining the principles of erosion andsediment control and the sediment transferprocess; and

o providing a range of erosion and sedimentcontrol practices that can be implemented onvarious Land Disturbing Activities.

2. To detail the rules in the Auckland RegionalCouncil’s Proposed Regional Plan: Sediment Control(September 1995) which define when a Land UseConsent is required.

3. To minimise adverse environmental effects of LandDisturbing Activities through appropriate use anddesign of erosion and sediment control techniques.

1.2 How These Guidelines Work

These Guidelines replace Technical Publication No. 2Erosion and Sediment Control Guidelines for Earthworks,updated March 1995. They overview the erosion andsediment controls that can be used when undertakingvarious Land Disturbing Activities and are known asTechnical Publication No. 90 Erosion and SedimentControl Guidelines for Land Disturbing Activities in theAuckland Region.

These Guidelines focus on the principles and practicesof erosion and sediment control recommended forvarious Land Disturbing Activities. While not providingthe full details of the Land Use Consent applicationprocess, they refer to the process and it is anticipatedthat they will form an integral part of the consent process.The Guidelines should be used during the developmentof an Erosion and Sediment Control Plan for a project,and must also be used as part of operating under theconditions of an approved consent.

These Guidelines are split into two main sections,Principles and Practices. The Principles section outlinesten critical elements that need to be considered whendeveloping an Erosion and Sediment Control Plan for

any Land Disturbing Activity. These ten elements arereferred to as the Ten Commandments of Erosion andSediment Control.

The Practices section covers on-site practices to be usedwhen implementing the Ten Commandments. In mostcircumstances, a range of practices will need to be used onany Land Disturbing Activity within the Auckland Region.

Standard symbols for erosion and sediment controls areused in Part B.

Auckland Regional Council staff are available forfurther advice and can be contacted at AucklandRegional Council, Private Bag 92 012, Auckland orby telephoning (09) 379 4420.

1.3 Erosion and Sediment Control inthe Auckland Region

Hundreds of hectares of land are stripped of vegetationor laid bare each year around Auckland for theconstruction of subdivisions, roads, landfills and otherdevelopments. Without protection measures, thetransformation of this land can result in accelerated on-site erosion and greatly increased sedimentation ofwaterways, estuaries and harbours.

Significant quantities of sediment are discharged frombare earth surfaces where appropriate erosion andsediment control measures are not implemented.

Various studies in Auckland indicate there is a 10 to 100times increase in sediment yield from construction sitescompared with pastoral land, while data from the UnitedStates suggests that there may be up to 1000 times thesediment yield from disturbed sites during constructioncompared with permanent forest cover.

In the 1996 – 97 earthworks season, 1000 ha of bare landwas worked around the Auckland region. If leftunprotected this could have resulted in a discharge ofup to 66,000 tonnes of sediment/year to aquatic receivingenvironments.

The adverse ecological effects caused by sediment inwaterways include:

o Modified or destroyed instream values.

o Modified estuarine and coastal habitats.

o Smothering and abrading of fauna and flora.

Page 23: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Introduction: 1 2

o Changes in food sources and interruption oflife cycles.

There is often a total change to instream communities.Recovery times from the impacts of sediment depositionare more likely to be measured in years rather thanmonths.

In addition to ecological changes, there may be damageto water pumps and other structures; the quality of watersupplies usually diminishes; localised flooding can occurand there is a loss of aesthetic appeal.

The Resource Management Act 1991 (RMA) establishesthe Auckland Regional Council’s statutoryresponsibilities for resource management. The purposeof the RMA is to promote the sustainable managementof natural and physical resources. ‘Sustainablemanagement’ is defined in Section 5 of the Act as:

‘managing the use, development and protection ofnatural and physical resources in a way or at a rate,which enables people and communities to provide fortheir social, economic, and cultural wellbeing and fortheir health and safety while:

‘(a) sustaining the potential of natural and physicalresources (excluding minerals) to meet thereasonably foreseeable needs of futuregenerations; and

‘(b) safeguarding the life supporting capacity of air,water, soil and ecosystems; and

‘(c) avoiding, remedying or mitigating any adverseeffects of activities on the environment.’

Historically, earthworks controls were based on voluntarycontrols initiated in the 1970s by the former AucklandRegional Water Board, which implemented guidelinesand a complaints response role. The 1980s saw theintroduction of Section 34 notices under the SoilConservation and River Control Amendment Act 1959,requiring consents be obtained from the Regional WaterBoard prior to undertaking earthworks. This remainedin effect until 30 September 1993 as part of AucklandRegional Council’s Transitional Regional Plan. A SoilConservation Consent for earthworks was then requiredunder the Auckland Regional Council’s Erosion and

Sediment Control Proposed Regional Plan. As a resultof further submissions and subsequent hearings this hasbeen replaced by the current Proposed Regional Plan:Sediment Control (September 1995), developed under theRMA, requiring a Land Use Consent: Sediment Controlto be obtained prior to undertaking a range of LandDisturbing Activities.

1.4 Current Legislation: When is aResource Consent Required?

The legal basis for requiring a Land Use Consent for LandDisturbing Activities is the Proposed Regional Plan:Sediment Control (September 1995). The Plan’s rulesapply to Land Disturbing Activities including earthworks,vegetation removal, roading, tracking, trenching andquarries. A copy of these rules can be found in AppendixA of these Guidelines. Consent application forms areprovided in Appendix B.

It is important to note that the rules are valid at thetime of publishing these Guidelines but are subject tochange. Contact the Auckland Regional Council toconfirm the status of the rules contained within theseGuidelines before making a decision based upon them.

1.5 When is Erosion and SedimentControl Required?

All projects involving Land Disturbing Activities in theAuckland Region must incorporate erosion and sedimentcontrols as an integral part of development. Projectswhich do not require a Land use Consent under theProposed Regional Plan: Sediment Control, and areclassified as permitted activities, MUST still implementappropriate erosion and sediment controls as detailedin these Guidelines.

On all projects, erosion and sediment controls shouldbe in place before earthworks commence and should beremoved only after the site has been fully stabilised toprotect it from erosion. The principles and practiceswithin these Guidelines should be referred to, and theErosion and Sediment Control staff at the AucklandRegional Council contacted for further advice if required.

Page 24: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Introduction: 1 3

Works Within a Watercourse

Any works within a watercourse must be carefullyplanned because controlling sediment generation fromthese activities is difficult.. These Guidelines include anumber of erosion and sediment control measures thatcan used for realignment, piping, culverting andstabilisation works.

The two most critical factors in minimising the impact ofworks of this nature are timing and duration of works.

Techniques for minimising sediment generation anddischarge when undertaking works within a watercourseare outlined in Part B, Section 3 of these Guidelines.

It should be noted that further consents may be requiredwhen undertaking such works, and contact should bemade with Auckland Regional Council staff to discussthe specific details of the proposed activity.

Cleanfills

Cleanfills are another Land Disturbing Activity that,while not directly referenced within the Proposed RegionalPlan: Sediment Control, do generate sediment. TheseGuidelines do not include a specific section on cleanfilloperations, but standard earthworks erosion andsediment control practices are appropriate for cleanfilloperations. The ARC’s definition of cleanfill (below)should be noted whenever cleanfill operations are to beundertaken:

o That cleanfill material is defined as a fillingoperation disposing of soil (other thancontaminated soil) rock, asphalt, fibrolite, plaster/clay products, and glass, and concrete with amaximum of 5% by volume per 10 truckloads ofattached structural building materials (wood andstructural steel excluding corrugated iron).

o Cleanfilling operations are permitted to accept onlythose materials outlined above. These operationsare not for the disposal of organic material,vegetation, contaminated soils or other wastematerials. Additionally cleanfilling operations arenot for the disposal of unattached structuralbuilding materials.

o Should non-cleanfill material be disposed to acleanfill site the site may be required to obtainauthorisation for any discharge of contaminants(other than sediment) under section 15 of theResource Management Act 1991, or remove non-cleanfill material from the site, whether or not thismaterial is part of the existing fill matrix.

1.6 Auckland’s Clays: The PrimeImportance of Erosion Control

The small size of soil particles typical of Auckland’s geologyreduces the effectiveness of erosion and sediment controls.The fine clays, once mobilised, take a much longer time tosettle than the coarser sand and silt material.

Bigger, better or more numerous sediment controlmeasures may therefore not be very effective in limitingoff-site transfer of sediments.

Most effort should be put into preventing sedimentgeneration in the first instance. That is, into erosioncontrol rather than sediment control. Erosion controltechniques include the following:

o Revegetation

o Minimisation of earthworks

o Timing

o Staging of earthworks operations

Other measures such as the use of chemical treatmentof runoff may also be necessary in some circumstances.

Page 25: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Principles of Erosion and Sediment Control: 2 1

2.1 Types of Erosion

Erosion is the process whereby the land surface is wornaway by the action of water, wind, ice or other geologicalprocesses. The resultant displaced material is known assediment. Sedimentation is the deposition of this erodedmaterial. Accelerated erosion, caused primarily by humandevelopment activities, is generally much more rapidthan natural erosion.

The basic erosion process is detachment, transport anddeposition (sedimentation). In Auckland, water is theusual eroding agent and transport medium, throughraindrop impact and overland flow energy. Waterdislodges exposed soil particles and transports themdownslope. Runoff and streamflow transport the erodedsoil particles to the final receiving environment wheresedimentation occurs.

There are seven main types of erosion associated withland disturbing activities.

o Splash erosion

o Sheet erosion

o Rill erosion

o Gully erosion

o Tunnel erosion

o Channel erosion

o Mass movement

These are outlined below.

Splash Erosion

o Soil erosion is a mechanical process that requiresenergy. Much of this energy is supplied by fallingrain drops.

o The impact of a single raindrop on a soil surface oron a thin film of water may break up the soilaggregates and cause individual particles to bethrown into the air. If this occurs on a slope thensome particles will move up-slope, but the net effectdue to gravity will cause splashed particles to movedownslope. Splash erosion is directly related to thesize, distribution, shape, velocity and direction ofthe raindrop.

o In Auckland, the erosive ability of splash erosion isenhanced by the typically intense cyclonic stormsthat can occur during the earthworks season.

Sheet Erosion

o When rainfall intensity exceeds the infiltration rateof a soil and the capacity of the available surfacedetention, excess water moves downslope,transporting soil particles detached by splasherosion.

o Sheet erosion or wash erosion is the uniformremoval of soil in thin layers by the forces ofraindrops and overland flow. It can be a verysignificant erosive process because it can cover largeareas of sloping land and may go unnoticed for sometime. Sheet erosion can be recognised by soildeposition at the bottom of a slope, or by theappearance of light coloured subsoil material on thesurface. If left unattended, sheet erosion of topsoilswill gradually remove the nutrients and organicmatter important to revegetation, and willeventually result in loss of soil productivity oncontributing slopes and elevated sedimentconcentrations in receiving waters.

Rill Erosion

o Rill erosion is the removal of soil by runoff movingin concentrated flows. As the flow changes fromsheet flow to deeper flow in these channels, or rills,the velocity and turbulence of the flow increases,and the energy of this flow is able to both detachand transport soil particles.

o Rill erosion has been estimated to be the dominantcontributor to erosion on hill slopes.

Gully Erosion

Gully erosion is the removal of soil by running waterresulting in the formation of channels greater than 300mm deep. Gullies can be distinguished from rills whennormal agricultural tillage operations cannot obliteratethem.

The following are the processes which act in theformation of gullies in Auckland.

o Waterfall erosion at the head of the gully

o Channel erosion

o Raindrop splash

o Diffuse flow from the side of the gully or fromseepage

o Slides or mass movement of soil within the gully.

Page 26: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Principles of Erosion and Sediment Control: 2 2

A gully may develop and grow rapidly and theirformation may generate a considerable amount oferosion. Therefore, their prevention and remediation isvital for erosion control.

Tunnel Erosion

Tunnel erosion, or piping, is the removal of subsurfacesoil by subsurface water while the surface soil remainsrelatively intact. This produces long cavities beneath theground surface, which may enlarge until the soil surfaceis no longer supported, at which point the surface maycollapse forming a circular hole, sometimes referred toas a ‘tomo’. Such erosion tunnels may range in size froma few centimetres to several metres in diameter andtypically form a series along the surface above a tunnel.

Channel Erosion

The erosion of ephemeral or perennial channels resultsfrom direct action of concentrated flow when the velocityor volume of flow in a stream increases. Natural channelsadjust over time to the volume and velocity of runoffthat normally occurs in the catchment. Channel erosionoccurs by scouring or undercutting of the stream bankbelow the water surface and generally happens duringmedium to high flows.

Channel erosion is a major contributor to sedimentationin the Auckland metropolitan area. High flows in streamchannels occur more frequently once a catchment hasbeen urbanised, eroding stream banks and enlarging thechannel. For example, an Auckland study showed a three-fold channel widening after 85% of the catchment hadbeen urbanised (Herald, 1989).

Mass Movement

Mass movement is the erosion of soil or rock by gravity-induced collapse. It is usually triggered by groundwaterpressure after heavy rain, but can also have other causes,notably streams undercutting the base of a slope orearthworks. Movement can be either rapid and nearinstantaneous (landslides, avalanches, debris flows), orslow and intermittent (earthflows and slumps). Earth andsoil slip movement are also often noted after the removalof vegetation from critical slopes associated with LandDisturbing Activities. These slopes need to be identifiedbefore development starts and should be avoidedwherever practicable.

Mass movement can cause major problems onearthworks sites and geotechnical investigations shouldbe undertaken where possible to avoid critical slopes orallow for the prevention of such erosion.

Figure 2.1 Types of Erosion Common in the Auckland Region

Splash Erosion

Sheet Erosion

Rill and Gully Erosion

Channel Erosion

Stream Flow

Ro tat i ona lS l u m p

Ea r t h s l i pE r o s i o n

Debris Flow

Page 27: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Principles of Erosion and Sediment Control: 2 3

2.2 Factors Influencing the ErosionProcess

The main factors influencing soil erosion are climate,soil characteristics, topography, ground cover andevapotranspiration.

Climate

Climate affects erosion potential both directly andindirectly. The direct relationship arises from the actionof rain - a driving force of erosion - where raindropsdislodge soil particles and runoff carries them away. Theannual pattern of rainfall and temperature change, byand large, determines the extent and growth rate ofvegetation. This is critical, because vegetation is currentlythe most important form of erosion control used onLand Disturbing Activities in Auckland.

The Auckland Region receives about 1200 mm of rainfallannually, with average monthly rainfalls being greatestthroughout the winter period. Summer has the greatestrainfall variability, some summers being very dry, others wet.

Intense cyclonic storms during summer also createmany erosion problems, with a large amount of rainfalling within a short time period. Erosion andsediment control for all Land Disturbing Activitiesmust be planned accordingly.

Soil Characteristics

Four soil characteristics are important in determiningsoil erodibility:

o Soil texture refers to the particle sizes making up aparticular soil and their relative proportions. Sand,silt and clay are the three major soil particle classes.Auckland soils tend to have a high content of finesands and silts, which are the more erodiblefractions of the soil. The clay content also createsdifficulty as once mobilised, it is very difficult tosettle out. This is due to the small nature ofindividual particles and the tendency for clayparticles to repel each other, thus keeping them insuspension.

o Organic matter improves soil structure andincreases permeability, water holding capacity andsoil fertility.

o Soil permeability refers to the ability of the soil toallow air and water to move through the soil. Soilswith a higher permeability produce less runoff at a

lower rate than soils with low permeability.Engineered fills have a very low permeability,resulting in increased levels of potentially erosiverunoff.

o Soil structure is the degree that soil particles arearranged into aggregates. A granular structure is themost desirable in both agricultural and erosioncontrol terms. When the soil surface is compactedor crusted, water tends to run off rather thaninfiltrate. Erosion potential increases with increasedrunoff.

Topography

Slope length and slope angle are critical factors in erosionpotential because they play a large part in determiningthe velocity of runoff. Long continuous slopes allowrunoff to build up velocity and to concentrate flow. Thisproduces rill and gully erosion.

The shape of a slope also has a major bearing on erosionpotential. The base of a slope is more susceptible toerosion than the top because runoff arriving there ismoving faster and is more concentrated. However,deposition may occur at the base of concave slopes whereslope angle diminishes.

Ground Cover

Ground cover includes vegetation and surface treatmentsuch as mulches and geotextiles. Vegetation is withoutquestion the most effective long term form of erosioncontrol for protecting surfaces that have been disturbed.Vegetation shields the soil surface from the impact offalling rain, slows the velocity of runoff, holds soilparticles in place and maintains the soil’s capacity toabsorb water.

Evapotranspiration

The Auckland Region has a fairly frequent rainfall duringthe winter, but due to high evapotranspiration and aminimum of rainfall in the summer period, soil moisturelevels are often so low that irrigation or watering is neededto achieve the moisture levels needed for plant growth.Evapotranspiration rates and the number of days of soilmoisture deficit vary across the region. Carefulconsideration needs to be given to evapotranspirationwhen attempting to establish a vegetative cover andprevent erosion.

Page 28: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council The “Ten Commandments” of Erosion and Sediment Control: 3 1

These “Ten Commandments,” summarise the ten principles to follow when preparing an Erosion and Sediment Control Plan.

4. Protect Watercourses

Existing streams, watercourses and proposed drainagepatterns need to be mapped. Clearing is not permittedadjacent to a watercourse unless the works have beenapproved by the Auckland Regional Council. Whereundertaken, work that crosses or disturbs the watercourse

Map all watercourses and show Limits of Disturbanceand protection measures; show all practices to be usedto protect new drainage channels; and indicatecrossings or disturbances and associated constructionmethods in the E&SCP.

5. Stabilise Exposed Areas Rapidly

The ultimate objective is to fully stabilise disturbed soilswith vegetation after each stage and at specific milestoneswithin stages. Methods are site specific and can rangefrom conventional sowing through to straw mulching.Mulching is the most effective instant protection.

Clearly define time limits for grass or mulch covers,outline grass rates and species and define conditionsfor temporary cover in the case of severe erosion orpoor germination in the E&SCP.

6. Install Perimeter Controls

Perimeter controls above the site keep clean runoff outof the worked area – a critical factor for effective erosioncontrol. Perimeter controls can also retain or directsediment laden runoff within the site. Commonperimeter controls are diversion drains, silt fences andearth bunds.

Detail the type and extent of perimeter controls in theE&SCP along with design parameters.

1. Minimise Disturbance

Fit land development to land sensitivity.

Some parts of a site should never be worked and othersneed very careful working. Watch out for and avoid areasthat are wet (streams, wetlands, springs), have steep orfragile soils or are conservation sites or features.

Bear in mind the minimum earthworks strategy (lowimpact design) – ideally, only clear areas required forstructures or access.

Show all Limits of Disturbance on the Erosion andSediment Control Plan (E&SCP). On site, clearly showLimits of Disturbance using fences, signs and flags.

2. Stage Construction

Carrying out bulk earthworks over the whole sitemaximises the time and area that soil is exposed andprone to erosion. “Construction staging”, where the sitehas earthworks undertaken in small units over time withprogressive revegetation, limits erosion.

Careful planning is needed. Temporary stockpiles, accessand utility service installation all need to be planned.Construction staging differs from sequencing. Sequencingsets out the order of construction to contractors.

Detail both construction staging and sequencing in theE&SCP.

3. Protect Steep Slopes

Existing steep slopes should be avoided. If clearing isabsolutely necessary, runoff from above the site can bediverted away from the exposed slope to minimiseerosion. If steep slopes are worked and need stabilisation,traditional vegetative covers like topsoiling and seedingmay not be enough – special protection is often needed.

Highlight steep areas on the E&SCP showing Limits ofDisturbance and any works and areas for specialprotection.

Page 29: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council The “Ten Commandments” of Erosion and Sediment Control: 3 2

7. Employ Detention Devices

Even with the best erosion and sediment practices,earthworks will discharge sediment laden runoff duringstorms. Along with erosion control measures, sedimentretention structures are needed to capture runoff sosediment generated can settle out. The fine grainednature of Auckland soils means sediment retentionponds are often not highly effective. Ensure the othercontrol measures used are appropriate for the projectand adequately protect the receiving environment.

Include sediment retention structure designspecifications; detailed inspection and maintenanceschedules of structures and conversion plans forpermanent structures, in the E&SCP.

8. Get Registered

A trained and experienced contractor is an importantelement of an E&SCP. These people are responsible forinstalling and maintaining erosion and sediment controlpractices. On-site staff certified through the AucklandRegional Council Industry Education Programme cansave project time and money, by identifying threatenedareas early on and putting into place correct practices.

Contact Auckland Regional Council aboutregistration. Include arrangements for a pre-construction meeting, regular inspection visits(including a pre-wintering meeting), and finalinspection.

9. Make Sure the Plan Evolves

An effective E&SCP is modified as the project progressesfrom bulk earthworks to developed individual lots.Factors such as weather, changes to grade and altereddrainage can all mean changes to planned erosion andsediment control practices.

Update the E&SCP to suit site adjustments in time forthe pre-construction meeting and initial inspection ofinstalled erosion and sediment controls, and make sureit is regularly referred to and available on site.

10. Assess and Adjust

Inspect, Monitor and Maintain Control Measures

Assessment of controls is especially important followinga storm. A large or intense storm will leave erosion andsediment controls in need of repair, reinforcement orcleaning out. Repairing without delay reduces further soilloss and environmental damage.

Assessment and adjustment is an important erosion andsediment control practice – make sure it figuresprominently in the E&SCP.

Assign responsibility for implementing the E&SCP andmonitoring control measures as the project progresses.

Page 30: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Types of Land Disturbing Activities Under taken: 4 1

The following are the main types of Land DisturbingActivities undertaken in the Auckland Region and theseare discussed in these Guidelines.

o Trenching

o Watercourse works

o Cleanfills

o Small sites and permitted activities

o Earthworks

o Roading

o Quarries and vegetation removal

The following is a brief summary of key considerationsfor minimising adverse environmental effects of theseactivities that are not found in the detailed descriptionof erosion and sediment control measures in Part B.

Trenching

Trenching, usually for installing utility services, oftenhappens towards the end of the bulk earthworks phaseof a project. The following points need to be consideredwhen trenching.

o The project needs to be undertaken in appropriatelysized stages such that the area exposed can be fullystabilised within an acceptable time frame.

o If trenching impacts on existing erosion andsediment control measures that are part of theoverall development, those measures should bereinstated as soon as possible. Contingencymeasures should be put in place until the originalmeasures are reinstated or replaced.

o All trenching operators working within a largersite must be familiar with the overall Erosion andSediment Control Plan for the site and must complywith this approved plan.

o Independent erosion and sediment controlmeasures detailed in these Guidelines should beemployed for the trenching operation.

o Topsoil and subsoils should be stockpiledseparately adjacent to the trench so that at thecompletion of the operation, these soils can bereplaced in the appropriate order and vegetationestablished.

o When trenching through overland flow paths, givespecial consideration to the diversion of any flows,which may occur during trenching, as well as

reinstating and stabilising the overland flow path.

Works Within a Watercourse

Works within a watercourse should be avoided whereverpossible, with all alternatives considered beforehand.Where watercourse works are unavoidable, they willcreate sedimentation downstream, so the followingpoints should be carefully considered when undertakingthese works.

o Have all alternatives been considered?

o Install a stabilised diversion so that works can beundertaken in the dry and reinstate the streamflowonly after these areas have been appropriatelystabilised. If a diversion is not a viable option, thenensure the alternative options are fully considered.

o Carry out works during a dry time of the year whenstream flows are low and the likelihood of a stormis low.

o Keep the duration of works short.

o Identify instream values so as to avoid criticalperiods such as fish spawning periods.

o Consider the direct short and long term impacts ofculverts or instream structures and installappropriately designed fish-pass provisions.

o Be sure to inform all downstream users, for examplewater-users, of potential downstream sedimentdischarges.

Cleanfills

Cleanfills dispose of unwanted fill material which maycontain some other material as in the definition ofcleanfill provided in Part A of these Guidelines.

Land Disturbing Activities associated with cleanfills rangefrom haul roads and access areas to tip faces and dumpingareas. Several controls are needed for adequate erosionand sediment control on such sites and the followingpoints should be carefully considered when undertakingsuch operations:

o The cleanfill operator needs to ensure that materialbeing accepted for the cleanfill fits within the ARC’sdefinition. In cases where it doesn’t, the operatormust reject such loads, which will then need to betransported to an approved landfill.

o Erosion and sediment controls should be installed

Page 31: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Types of Land Disturbing Activities Under taken: 4 2

in accordance with these Guidelines andappropriate maintenance undertaken.

o As a cleanfill operation is considered to be a landdisturbing activity, each operation should beassessed for any necessary consents within theProposed Regional Plan: Sediment Control.

o Staging of cleanfill operations is critical and aprogramme of progressive stabilisation of allcleanfill sites should be part of each operation.

Small Sites and Permitted Activities

After the bulk earthwork phase of an earthworksoperation, individual developers start houseconstruction. This is the phase of small site developmentswhich is considered permitted activities under theProposed Regional Plan: Sediment Control.The cumulative impact from small sites is considered tobe considerable and in some areas may cumulativelydischarge as much sediment as the initial developmentitself. Often at this stage of the proposal, stormwatersystems are in place and there are no, or minimal, erosionand sediment controls on the site. This results insediment discharging through an efficient conveyancesystem (the stormwater system) directly to the receivingenvironment.

The following points need to be considered whenundertaking small site development:

o The developer should be fully aware of thepermitted activity thresholds within the ProposedRegional Plan: Sediment Control and the conditionsit specifies.

o Erosion and sediment controls should be installedeither on an individual site-by-site basis or acombination of the sites, in accordance with theseGuidelines or the Small Site Guidelines forEarthworks in the Auckland Region.

o Stormwater runoff from small sites needs carefulplanning in terms of the location of roof downpipesso that runoff across bare sites does not scour soils.

o Areas of exposed soils should be stabilised uponcompletion of earthworks, including topsoil andsubsoil stockpiles, lawn areas and accessways.

o The site should be isolated from the subdivision’sroad system using silt fences to intercept flow from

the site, with a Stabilised Construction Entrance(see Part B, Section 1.8) of to provide site entry andexit.

Earthworks

Earthworks include a wide range of activities fromcleanfilling operations (defined above) through toearthworks associated with industrial, commercial andresidential developments. The Proposed Regional Plan:Sediment Control defines the thresholds for resourceconsent requirements for earthworking activities.Earthworks have a major potential to generate largeamounts of sediment, and if not controlled appropriately,can lead to large sediment discharges. Planning of thesedevelopments is critical to ensure that the activity isundertaken appropriately, and in a controlled manner toavoid unnecessary impacts on receiving environments.The “Ten Commandments” outline the critical featuresof an earthworks operation. The following are furtherkey points contractors need to be aware of whenundertaking earthworks operations.

o It is important to comply with the specificrequirements of the resource consent whenundertaking earthworks operations.

o Emphasis should be placed on erosion control,rather than sediment control, because preventingsediment generation is the best means of preventingsediment discharge from earthworks sites.

o Always produce an Erosion and Sediment ControlPlan (E&SCP) for an earthworks operation. Be surethat all parties involved with the operation, includingsubcontractors, are familiar with and have access toa current copy of this Plan.

o Always update the E&SCP with major variations onthe site and be sure these variations have theappropriate approvals. Keep this up-to-date versionin the site office at all times.

o Plan ahead and undertake consultation withnecessary parties as required. Get approvals and startthe operation early to avoid last minute delays andthe need to keep working into the undesirable wettermonths.

o Install appropriate controls in accordance with theapproved E&SCP and be sure that the designspecifications are appropriate for the operation.

Page 32: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Types of Land Disturbing Activities Under taken: 4 3

o Install subsurface drainage as required (to anagreed methodology) to divert subsurfacecleanwater past control structures and areas ofdisturbance as appropriate.

Roading

Like trenching, the linear nature of roading poseschallenges for erosion and sediment control. Measuresneed to be carefully planned to ensure controls aresuccessful. Often the operation can be undertakensequentially, stabilising worked areas as they arecompleted. This minimises the total sediment generatingarea of the proposal and helps prevent unnecessary roadmaintenance.

The following are some key points to consider whenworking through a roading proposal.

o Provide enough room for effective erosion andsediment control measures. Often the road corridoritself can involve the whole designation area andno room remains for such controls. Where space isa constraint, make sure that the erosion andsediment controls are approved and will give thenecessary protection to downstream receivingenvironments.

o Incorporate stormwater design into the E&SCP. Thisremoves the need to revisit the area to installstormwater systems and the unnecessary extraearthworks that their construction would require.

o Keep the areas of road corridor exposed at any onetime to a limit that can be practically stabilised withhardfill or by vegetative means, to minimise theexposed area at risk.

o When crossing watercourses, look for alternativeroutes and alternative designs and implement theoption which provides the best environmentalalternative.

o Control all upslope catchment runoff, divertingclean water around or safely through the area ofdisturbance.

Quarries and Vegetation Removal

Measures in these Guidelines are suitable for quarry andvegetation removal operations. However, the long termnature of many quarries and the clearfelling of wholecatchments during vegetation removal operations meanthat some special erosion and sediment control measuresneed to be implemented. Careful planning of suchoperations is thus critical. The key areas where attentionis required are discussed in detail in Part B of theseGuidelines and should be read in conjunction with theother erosion and sediment controls also detailed.

Page 33: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Par t B: Practices

Erosion and Sediment Control Practices

Part B outlines minimum criteria for the design,construction and implementation of a range of erosionand sediment control measures commonly used onearthworks sites and on other Land Disturbing Activities.These measures form one aspect of erosion and sedimentcontrol on any site, and should always be used inconjunction with the measures outlined in the TenCommandments of Erosion and Sediment Control in PartA of these Guidelines.

The most effective form of erosion control is to minimisethe area of disturbance, retaining as much existingvegetation as possible. This is especially important onsteep slopes or in the vicinity of watercourses, where nosingle measure will adequately control the erosion andtransport of sediment, and where receiving environmentsmay be highly sensitive.

The criteria outlined are the minimum standard for eachmeasure. Each Land Disturbing Activity must be assessedon an individual basis, and in many cases higherstandards may be required.

For every practice, these Guidelines outline the following.

o Definition

o Purpose

o Application

o Design/Construction Specifications

o Comments

o Maintenance

Symbols shown alongside controls are listed inAppendix C.

Page 34: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Erosion Control: 1 1

1.1 Runoff Diversion Channel/Bund

Plate 1.1 Runoff Diversion Channel/Bund

Definition

A non erodible channel or bund for the conveyance ofrunoff constructed to a site-specific cross section andgrade design.

Purpose

To either protect work areas from upslope runoff (cleanwater diversion), or to divert sediment laden water to anappropriate sediment retention structure.

Application

Runoff Diversion Channels/Bunds are used in thefollowing situations.

o To divert clean upslope water away from areas tobe worked (clean water diversion).

o To divert sediment-laden runoff from disturbedareas into sediment treatment facilities.

o At or near the perimeter of the construction areato keep sediment from leaving the site.

o In either temporary or permanent situations.

o Keep permanent diversions in place until thedisturbed area is permanently stabilised againsterosion.

o Stabilise Runoff Diversion Channels/Bunds (wherenecessary) before use.

Design

There are many designs for Runoff Diversion Channels/Bunds. The following outlines design criteriarequirements.

o Design the Runoff Diversion Channel to carry theflow from the 5% AEP rainfall event (plusfreeboard).

o Restrict use to grades to no more than 2% unlessarmoured.

o Construct with a trapezoidal cross sectional shapewith internal side slopes no steeper than 3:1, andexternal slopes no steeper than 2:1.

o Construct Runoff Diversion Bunds with side slopesno steeper than 3:1.

Page 35: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Erosion Control: 1 2

o Survey all gradients on the site.

o Ensure earth embankments used to constructRunoff Diversion Channels/Bunds are adequatelycompacted.

o Flow velocities greater than 1 o/s will cause theRunoff Diversion Channel/Bund to erode.Incorporate stabilisation measures (such asgeotextile, vegetative stabilisation or rock checkdams) to prevent erosion.

o Incorporate a stable erosion-proof outfall (such asa level spreader) in order to reduce water velocitiesand prevent scour at the outlet.

o Ensure the Runoff Diversion Channel/Bund outlet -

- functions with a minimum of erosion,

- directs clean runoff onto an undisturbed/stabilised area,

- directs flows containing sediment into asediment retention structure,

- is located in such a position that ideally suitsthe field conditions.

Considerations:

o Consider designing an emergency overflow sectionor bypass area to limit damage from storms thatexceed the design storm.

o Avoid abrupt changes in grade which can lead tosediment deposition and overtopping, or erosion.

Maintenance

Runoff Diversion Channels/Bunds need regularmaintenance to keep functioning throughout their life.Regular maintenance consists of the following.

o Inspect after every rainfall and during periods ofprolonged rainfall for scour and areas where theymay breach.

o Repair immediately if required to ensure that thedesign capacity is maintained.

o Remove any accumulated sediment deposited inthe Runoff Diversion Channel/Bund due to lowgradients and velocities.

o Carefully check outlets to ensure that these remainfree from scour and erosion.

Figure 1.1.2 Runoff Diversion Channel

Figure 1.1.1 Cleanwater Runoff Diversion Bund

Page 36: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Erosion Control: 1 3

1.2 Contour Drain

Plate 1.2 Contour Drain

Definition

A temporary ridge or excavated channel, or combinationof ridge and channel, constructed to convey water acrosssloping land on a minimal gradient.

Purpose

To break overland flow down disturbed slopes by limitingslope length and thus the erosive power of runoff, and todivert sediment laden water to appropriate controls orstable outlets.

Application

Use Contour Drains in the following situations.

o At intervals across disturbed areas to shortenoverland flow distances.

o As temporary or daily controls.

o To split and direct flow from disturbed areas toRunoff Diversion Channels/Bunds.

Design

Ensure gradients are no greater than 2% and the ContourDrains are kept as short as practicable in order tominimise erosion. The positioning of Contour Drains isoften determined by the necessity for stable outfalls, butin general the following spacing applies:

Table 1.2 Positioning of Contour Drains

Slope of Site (%) Spacing of Contour Drains (o)

5 50

10 40

15 30

Maintenance

o Install Contour Drains at the end of each day.

o Inspect Contour Drains after every rainfall andduring periods of prolonged rainfall.

o Immediately carry out any maintenance that isrequired.

Page 37: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Erosion Control: 1 4

Figure 1.2 Contour Drain

Page 38: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Erosion Control: 1 5

Definition

Modification of a slope by reverse sloping to divert runoffto an appropriate conveyance system.

Purpose

To limit the velocity and volume, and hence the erosivepower, of water moving down a slope and thereforeminimising erosion of the slope face.

Application

Benched Slopes are primarily used on long slopes and/or steep slopes where rilling may be expected as runofftravels down the slope. Consider Benched Slopes on allslopes however ensure that consideration of soil structureand stability occurs. The spacing of the Benched Slopesand the specific conditions for which they apply dependon slope height and angle. The primary purpose is toprevent the concentration of runoff which, in turn,increases erosion.

Table 1.3 Benched Slope Design

Slope Angle (%) Vertical Height (o) Between Benches

50 10

33 15

25 20

Design

o Provide Benched Slopes for slopes exceeding 25%– see Table 1.3.

o Locate Benched Slopes to divide the slope face asequally as possible and convey the water from eachbench to a stable outlet. Soil types, seeps andlocation of rock outcrops need to be taken intoconsideration when designing Benched Slopes.

o Ensure Benched Slopes are a minimum of 2 o wide,for ease of maintenance.

1.3 Benched Slope

Plate 1.3 Benched Slope

Page 39: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Erosion Control: 1 6

Figure 1.3 Benched Slope

o Design Benched Slopes with a reverse slope of 15%or flatter to the toe of the upper slope and with aminimum depth of 0.3 o. Keep the gradient of eachBenched Slopes to its outlet below 2 %, unlessdesign, stabilisation and calculations demonstratethat erosion is minimised.

o Keep the flow length along a Benched Slope to lessthan 250m unless design and calculations candemonstrate that erosion is minimised.

o Divert surface water from the face of all cut and/orfill slopes of Benched Slopes by the use of RunoffDiversion Channels/Bunds except where:

- the face of the slope is not subject to anyconcentrated flows of surface water such asfrom natural drainage, channels or otherconcentrated discharge points, and

- the face of the slope is protected by specialerosion control materials including, but notlimited to, approved vegetative stabilisationpractices, rip-rap, or other approvedstabilisation methods.

o Provide subsurface drainage where necessary tointercept seepage that would otherwise adverselyaffect slope stability or create excessively wet siteconditions. Check the requirements of the city ordistrict council.

o Do not construct Benched Slopes close to propertylines where they could endanger adjoiningproperties without adequately protecting suchproperties against sedimentation, erosion, slippage,settlement, subsidence or other related damages.Check the requirements of the city or districtcouncil.

o Stabilise all disturbed areas.

Construction Specifications

o Compact all fills to reduce erosion, slippage,settlement, subsidence, or other related problems.

o Keep all Benched Slopes free of unconsolidatedsediment during all phases of development.

o Permanently stabilise all graded areas immediatelyon completion of grading.

Page 40: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Erosion Control: 1 7

Definition

Small temporary dam constructed across a channel(excluding perennial watercourses), usually in series, toreduce flow velocity. May also help retain sediment.

Purpose

To reduce the velocity of concentrated flows, therebyreducing erosion of the channel. While trapping somesediment, they are not designed to be utilised as asediment retention measure.

Application

This practice applies primarily to earthworks sites whereit is necessary to slow velocity of flows in order to preventerosion. Do not use Rock Check Dams in a perennialwatercourse. Specific applications include the following.

o Temporary channels which, because of their shortlength of service, are not suitable for non-erodiblelining but still need some protection to reduceerosion.

o Permanent channels which for some reason cannotreceive a permanent non-erodible lining for anextended period of time.

o Temporary or permanent channels which needprotection during the establishment of a vegetativecover.

Design

o Ensure the catchment in question has acontributory drainage area of less than 1.0 ha.

o Direct all flows over the centre of the Rock CheckDam.

o Construct each Rock Check Dam with a maximumcentre height of 600 mm. Build the sides 200 mmhigher than the centre to direct flows to the centre.

o Do not use Rock Check Dams as a primary sedimenttrapping facility. Ensure that any sediment ladenrunoff passes through a sediment trapping deviceor devices before being discharged from the site.

Plate 1.4 Rock Check Dam

1.4 Rock Check Dam

Page 41: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Erosion Control: 1 8

o Place a mix of 100 mm to 300 mm diameter washedrock to completely cover the width of the channel.In steeper catchments use larger sized rock (0.5 –1.0 o) on the downstream side of the Rock CheckDam.

o Ensure rock batter slopes are 2:1.

o Locate Rock Check Dams at a spacing so that thetoe of the upstream dam is equal in height elevationto the crest of the downstream one. Ensure the toeof the upstream dam is never higher than the crestof the downstream dam.

Table 1.4 Rock Check Dam Design

Slope Spacing (o) Between Dams

450 mm 600 mm

Centre Height Centre Height

2% or less 24 30

2% to 4% 12 15

4% to 7% 8 11

7% to 10% 5 6

Over 10% Utilise Stabilised Channel

o Supply specific design and calculations if RockCheck Dams are to be used on catchments greaterthan 1.0 ha.

Maintenance

While this measure is not intended to be used primarilyfor sediment trapping, some sediment can accumulatebehind the Rock Check Dams. Remove this sedimentwhen it has accumulated to 50% of the original heightof the dam.

When temporary channels are no longer needed, removeRock Check Dams and fill in the channel. In permanentchannels, remove Rock Check Dams when a permanentlining can be installed. In the case of grass lined ditches,Rock Check Dams may be removed when grass hasmatured sufficiently to protect the channel. The areabeneath the Rock Check Dams needs to be seeded andmulched or stabilised with appropriate geotextileimmediately after removing the dams.

Figure 1.4 Rock Check Dam

Page 42: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Erosion Control: 1 9

Definition

The placement of topsoil over a prepared subsoil priorto the establishment of vegetation.

Purpose

To provide a suitable soil medium for vegetative growthfor erosion control while providing some limited shortterm erosion control capability by protecting subsoils andabsorbing water.

Application

Top Soiling is recommended in the following situations.

o Where the texture and/or the organic componentof the exposed subsoil or parent material can notproduce adequate vegetative growth.

o Where the soil material is so shallow that therooting zone is not deep enough to support plantsor furnish continuing supplies of moisture and plantnutrients.

o Where high quality turf and landscape plantingsare to be established.

Generally Top Soiling is combined with vegetationestablishment and is not seen as an erosion controlmeasure in itself. Top Soiling as a short term standaloneerosion control measure is limited to sites with an averageslope of less than 5 % with Contour Drains installed asper these Guidelines and for periods of less than twoweeks only.

Top Soiling alone will not provide sufficient erosionprotection to allow sediment control measures to be

removed.

When staging within an earthworks operation, TopSoiling as a treatment in itself is not acceptable andother means of stabilisation such as revegetation willalso be required.

Design

Not Applicable.

Construction Specifications

Once site shaping work has been completed, evenlyspread a minimum of 100 mm of topsoil beforerevegetating. On steeper sites (over 25%), scarify thesubsoils to a depth of a least 100 mm to ensure bondingbetween topsoil and subsoil before applying topsoil.

Incorporate Surface Roughening into all Top Soilingoperations in accordance with these Guidelines.

In general topsoil has a beneficial effect in light rainbecause it can hold more moisture than the underlyingclay material. However, during heavy rain, topsoil willbecome saturated and rill erosion and slumping canresult. For this reason it is important to establish a fullvegetative cover as soon as possible and retain allsediment retention facilities on the site until a vegetativecover is fully established.

Maintenance

Check the condition of the topsoil on a regular basis andregrade and/or replace where necessary so as to alwaysmaintain the 100 mm minimum depth of topsoil and

1.5 Top Soiling

Page 43: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Erosion Control: 1 1 0

Definition

The planting and establishment of quick growing and/or perennial vegetation to provide temporary and/orpermanent stabilisation on exposed areas.

Purpose

Temporary Seeding is designed to stabilise the soil andto protect disturbed areas until permanent vegetationor other erosion control measures can be established. Itmay be used where the area to be stabilised is not yet upto final grade and requires further earthworks, but needstemporary stabilisation.

Permanent Seeding is designed to permanently stabilisesoil on disturbed areas to reduce sediment and runoff todownstream or off-site areas.

Application

TTTTTeeeeemmmmmporaporaporaporaporarrrrry Sy Sy Sy Sy Seeeeeeeeeedingdingdingdingding

Use on any cleared or unvegetated areas which are subjectto erosion and will not be earthworked for a period of 14days or more. Temporary stabilisation is normallypractised where the vegetative cover is required for lessthan one year. In some circumstances straw mulchingmay be used as an alternative (see Part B, Section 1.6.3of these Guidelines).

PPPPPeeeeerrrrrmanemanemanemanemanennnnnt St St St St Seeeeeeeeeedingdingdingdingding

This practice applies to any site where establishingpermanent vegetation is important to protect bare earth.It may also be used on rough graded areas that will notbe brought to final grade for a year or more.

Design

Not Applicable.

Construction Specifications

o Site PreparationSite PreparationSite PreparationSite PreparationSite Preparation

Before seeding, install all required erosion andsediment control practices such as diversionchannels and sediment retention structures. Gradethe site as necessary to permit the use ofconventional equipment for soil preparation,seeding and maintenance.

o Seed Bed PreparationSeed Bed PreparationSeed Bed PreparationSeed Bed PreparationSeed Bed Preparation

Prepare a good seed bed to ensure successfulestablishment of vegetation. Take care to ensure thatthe seed bed is free of large clods, rocks and otherunsuitable material. Apply topsoil at a minimumdepth of 100 mm to allow for a loose and friablesoil surface.

o Soil AmendmentsSoil AmendmentsSoil AmendmentsSoil AmendmentsSoil Amendments

Apply fertiliser as outlined in Table 1.6 of theseGuidelines. This fertiliser application rate can bevaried with the approval of the Auckland RegionalCouncil.

For large sites or unusual site conditions it isadvisable to have soil fertility tests done. Some soilsmay require the addition of lime to improve pH.

o SeedingSeedingSeedingSeedingSeeding

Apply seed at a mixture and rate as in Table 1.6 ofthese Guidelines. This seeding rate can be variedwith approval from the Auckland Regional Council.Apply the seed uniformly and sow at therecommended rate. Seed that is broadcast must becovered by raking and then lightly tamped intoplace. If Hydroseeding is required, then it can beutilised in accordance with Part B Section 1.6.2 ofthese Guidelines.

surface roughening.

1.6 Revegetation Techniques1.6.1 Temporary and Permanent Seeding

Page 44: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Erosion Control: 1 1 1

o MulchingMulchingMulchingMulchingMulching

When working on steep sites (greater than 25%) orduring the winter period (between 30 April 30 and1 October) mulching will need to be applied inaccordance with Part B Section 1.6.3 of theseGuidelines immediately following seeding.

o IrrigationIrrigationIrrigationIrrigationIrrigation

Adequate moisture is essential for seed germinationand plant growth. Irrigation can be very helpful inestablishing vegetation during dry or hot weatherconditions or on adverse site conditions.

Irrigation must be carefully controlled to preventrunoff and subsequent erosion. Inadequate orexcessive irrigation can do more harm than good.

Table 1.6 Grass Seed and Fertiliser Application Rates

Mix Rate (kg/ha) Comments

Seeding Temporary 3 0 0 Annual Rye Grass mix is more

Annual Rye Grass suitable for colder times of the

(ie. Tama) and year when ground temperatures

Clover Seed mix are low.

Permanent Perennial – 120

Perennial Ryegrass Brown Top – 45

and Brown Top with a Clover – 45

Red/White Clover mix

Fertiliser Application D . A . P 2 4 0 D.A.P is an ideal fer ti l iser for the

( D i - A m m o n i u m rapid development of grass cover

P h o s p h a t e ) whilst neither damaging seed or

N P K S inhibiting seed germination.

18:20:0 :2

Maintenance Straight Nitrogen 120 Urea provides an efficient means of

Fertiliser eg Urea (46% N) encouraging fur ther development of

Application grass cover.

Maintenance

Reseed where seed germination is unsatisfactory orwhere erosion occurs. In the event of unsatisfactorygermination after 30 April, the area will also require theapplication of Mulch in accordance with Part B Section1.6.3 of these Guidelines.

Depending on site conditions it may be necessary toirrigate, fertilise, oversow or re-establish plantings inorder to provide vegetation for adequate erosion control.See Table 1.6 of these Guidelines for details ofmaintenance fertiliser applications.

Protect all revegetated areas from traffic flows and otheractivities such as the installation of drainage lines andutility services.

Page 45: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Erosion Control: 1 1 2

Definition

The application of seed, fertiliser and paper or woodpulp with water in the form of a slurry, sprayed over thearea to be revegetated.

Purpose

To establish vegetation quickly while providing a degreeof instant protection from rain drop impact.

Application

This practice applies to any site where vegetationestablishment is important for the protection of bareearth surfaces. For example:

o Critical areas on the site prone to erosion such assteep slopes and Sediment Retention Pond batters.

o Critical areas on the site that cannot be stabilisedby conventional sowing methods.

o Around watercourses or Runoff Diversion Channelswhere rapid establishment of a protective vegetativecover is required before introducing flows.

Design

Not Applicable.

Construction Specifications

The seed generally adheres to the pulp which improvesthe microclimate for germination and establishment.This method allows vegetation to establish on difficultsites and can extend into cooler winter months providedit is utilised with Mulching.

o Site PreparationSite PreparationSite PreparationSite PreparationSite Preparation

Before Hydroseeding, install any needed erosionand sediment control practices such as RunoffDiversion Channels. Scarify any steep or smoothclay surfaces to improve retention of theHydroseeding slurry.

Hydroseeding specifications need to be verified bythe Auckland Regional Council prior toimplementation, with recommended seeding andfertiliser application rates outlined in Table 1.6 ofthese Guidelines.

o WWWWWaaaaattttteeeeerrrrringinginginging

Hydroseeding requires moisture for germinationand growth. Because Hydroseeding is often used fordifficult sites the timing of the application to getfavourable growing conditions is an importantfactor.

Maintenance

Heavy rainfall can wash Hydroseeding away, particularlyfrom smooth clay surfaces and overland flowpaths.Where vegetation establishment is unsatisfactory the areawill require Hydroseeding again. In the event ofunsatisfactory germination after 30 April, the area willalso require Mulching in accordance with Part B, Section1.6.3 of these Guidelines.

Protect all revegetated areas from traffic flows and otheractivities such as the installation of drainage lines andutility services.

1.6.2 Hydroseeding

Page 46: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Erosion Control: 1 1 3

Mulching is used during the winter months (30 April to1 October) to provide immediate stabilisation. Becausegrass germination will be too slow to establish effectivegrass cover using conventional sowing methods.

Design

Not Applicable.

Construction Specifications

Site Preparation

Before Mulching install any needed erosion and sedimentcontrol practices such as Runoff Diversion Channels andsediment retention structures.

Mulching

When Mulching, use unrotted small grain straw appliedat a minimum rate of 6000 kg per ha.

Ensure the material is free of any noxious plants asidentified under Auckland Regional Council policy. CallEnviroline on 0800 80 60 40 for an up-to-date list of plantpests.

1.6.3 Mulching

Plate 1.6.3.1 Mulching

Definition

The application of a protective layer of straw or othersuitable material to the soil surface.

Purpose

To protect the soil surface from the erosive forces ofraindrop impact and overland flow. Mulching also helpsto conserve moisture, reduce runoff and erosion, controlweeds, prevent soil crusting and promote theestablishment of desirable vegetation.

Application

This practice applies to any site where vegetationestablishment is important for the protection of bareearth surfaces.

Mulching can be used at any time where the instantprotection of the soil surface is desired. Mulching can beused in conjunction with seeding to establish vegetation,or by itself to provide temporary protection of the soilsurface.

Page 47: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Erosion Control: 1 1 4

include emulsions, acrylimides and dispersions of vinylcompounds. They do not insulate the soil or retainmoisture when used alone and therefore do little to aidseed establishment. They are also easily damaged bytraffic, decompose relatively quickly and can be quiteexpensive in comparison to organic mulches.

Rovings, another alternative, are fibres that are teasedout from spools of yarn by compressed air and wovenonto the surface of the land. They are then stabilised witha tackifier, with seed sown beforehand. These alternativesmay be acceptable in certain circumstances but shouldbe discussed in detail with the Auckland Regional Councilprior to their implementation.

Anchoring Mulch

Anchor Mulch in place immediately after application toavoid or minimise loss by wind or water. Numerousmethods are available. Generally, although the Mulch is‘settled’ in place by the first rainfall, the AucklandRegional Council also requires it be retained by crimpinginto the soil with discs or spraying a tackifier with theMulch. When using some chemical tackifiers, take careto avoid adverse offsite effects of runoff.

Mulching needs to be spread uniformly and secured tothe soil surface. For smaller areas hand spreading ofmulch material can be adequate. For larger sites, applymulch mechanically to ensure even spread andappropriate application.

Apply fertiliser with Mulching as outlined in Table 1.6of these Guidelines.

Alternatives such as wood chips and chemical soil binderscan be utilised where appropriate.

Wood chips are suitable for areas that will not be closelymowed around such as ornamental plantings. They donot require the application of a tackifier and if readilyavailable can be a relatively inexpensive mulch. They areslow to break down and normally require nitrogenapplication to prevent nutrient deficiency in plants. Donot use woodchips around watercourses or in areas wherewater can pond.

To avoid water contamination, any alternative to strawmulch must be approved by the Auckland RegionalCouncil.

A wide range of synthetic mulching compounds areavailable to stabilise and protect the soil surface. These

Plate 1.6.3.2 Mulch Crimping

Page 48: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Erosion Control: 1 1 5

Definition

The establishment and permanent stabilisation ofdisturbed areas by laying a continuous cover of grass turf.

Purpose

To provide immediate vegetative cover to stabilise soilon disturbed areas such as. For example:

o Critical erosion prone areas on the site.

o Critical areas on the site that cannot be stabilisedby conventional sowing methods.

o Runoff Diversion Channels and other areas ofconcentrated flow where velocities will not exceedthe specifications for a grass lining.

Application

Turfing is the preferred method for disturbed areas thatmust be immediately stabilised. It is particularly usefulfor:

o Watercourses and channels carrying intermittentflow.

1.6.4 Turfing

Plate 1.6.4 Turfing

o Areas around drop inlets.

o Residential or commercial lawns to allow promptuse and for aesthetic reasons.

o Steep areas.

Design

While there are no specific design criteria for Turfing,Turf reinforced with geosynthetic matting should beconsidered for areas of high erosion potential; forexample, steep slopes or concentrated overland flowpaths.

Construction Specifications

Site Preparation

Before Turfing, properly prepare the site in order toensure the successful establishment of vegetation. Thisincludes applying fertiliser as in Table 1.6 of theseGuidelines, uniformly grading the area, clearing all debris,removing stones and clods and scarifying hard packedsurfaces.

Page 49: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Erosion Control: 1 1 6

Turf Installation

During periods of high temperatures, lightly irrigate soilimmediately before laying turf.

Lay the first row of turf in a straight line with subsequentrows placed parallel to and tightly wedged against eachother. Stagger lateral joints in a brick-like pattern. Donot stretch or overlap turf and make sure all joints arebutted tight in order to prevent voids, which can causedrying of the grass roots.

On sloping areas or channels where erosion may be aproblem, lay turf downslope with the ends of the turfmaterial overlapped such that the upslope turf overlapsthe downslope turf by at least 100 mm. It may benecessary to secure the turf with pegs or staples. Ensurethe turf at the top of the slope is appropriately trenchedin to prevent runoff moving underneath it.

As Turfing is completed in one area, roll or tamp theentire area to ensure solid contact of the grass roots withthe soil surface. After rolling, immediately water the Turfuntil the underside of the new turf and soil surface belowthe turf are thoroughly wet.

Maintenance

o Water daily during the first week of laying unlessthere is adequate rainfall.

o Do not mow the area until the turf is firmly rooted.

o Apply fertiliser regularly as in Table 1.6 of theseGuidelines for ongoing successful establishment.

Page 50: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Erosion Control: 1 1 7

1.7 Geosynthetic Erosion Control Systems (GECS)

Permanent Non-Degradable GECS

These are used to extend the erosion control limits ofvegetation, soil, rock or other materials. Commonpermanent GECS are three-dimensional erosion controland revegetation mats, geocellular confinement systems,reno mattresses and gabions.

The selection of an appropriate GECS is a complexbalancing of the relative importance of the followingrequirements.

o Endurance: durability, degree of resistance todeformation over time and ultraviolet radiation andto chemicals (natural or as pollutants).

o Physical: thickness, weight, specific gravity anddegree of light penetration. Generally a thickerheavier material will provide better protection.

o Hydraulic: ability of the system to resist tractiveshear strength and protect against channel erosion,erosion of underlying soils or slope erosion fromrainfall impact.

o Mechanical: deformation and strength behaviour.Tensile strength and elongation, stiffness (how wellit will conform to the subgrade) and how well itwill resist tractive shear forces.

When a geotextile is to be used for temporary channelor spillway protection, consider combining a highstrength, low permeability cloth over a soft pliable needlepunch cloth pinned to ensure the cloth is in contact withthe entire soil surface. Trench and pin all flow entry pointssuch that the upslope geotextile edge overlaps thedownslope geotextile mat. Toe in the upslope end of thedownslope mat.

In high risk areas such as spillways and diversions, pingeotextiles down on a 0.5 o grid or in accordance withthe manufacturers’ specifications, whichever provides thegreatest number of contact points.

There is a large number of products available for allsituations and depending on the degree of protectionneeded, a product or combination of products will beavailable to suit the situation. It is vital that the productutilised is designed for the intended use and installed

Definition

The artificial protection of channels and erodible slopesutilising artificial erosion control material such asgeosynthetic matting, geotextiles or erosion matting.

Purpose

To immediately reduce the erosion potential of disturbedareas and/or to reduce or eliminate erosion on criticalsites during the period necessary to establish protectivevegetation. Some forms of artificial protection may alsohelp to establish protective vegetation.

Application

o On short steep slopes.

o On areas that have highly erodible soils.

o In situations where tensile and shear strengthcharacteristics of conventional mulches limit theireffectiveness in high runoff velocities.

o In channels (both perennial and ephemeral) wherethe design flow produces tractive shear forces greaterthan in-situ soil can withstand.

o In areas where there is not enough room to installadequate sediment controls.

o In critical erosion-prone areas such as sedimentretention pond outlet and inlet points.

o In areas that may be slow to establish an adequatepermanent vegetative cover.

o In areas where the downstream environment is ofhigh value and rapid stabilisation is needed.

Design

There are two categories of GECS; temporary degradableand permanent non-degradable.

Temporary Degradable GECS

These are used to prevent loss of seedbed and to promotevegetation establishment where vegetation alone will besufficient for site protection once established. Commontemporary GECS are erosion control blankets, openweave meshes/matting and organic erosion controlnetting (fibre mats factory-bonded to synthetic netting).

Page 51: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Erosion Control: 1 1 8

and maintained according to its specifications. Decisionanalysis techniques ranking the various GECS availableshould be used based on the following categories.

o Sediment yield (generally ranked highest)

o Stability under flow

o Vegetation enhancement

o Durability

o Cost

When installing GECS within a channel, it is importantthat the design velocity of the product is considered andagain that the product chosen is appropriate for the use.

Many products provide for the combination of arevegetation technique and an artificial erosion controlmeasure. Again, design specifications need to be closelyfollowed in all cases.

Maintenance

Inspect after every rainfall and undertake anymaintenance immediately.

Figure 1.7.1 Geotextile Laid on Slope

Page 52: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Erosion Control: 1 1 9

Figure 1.7.2 Geotextile at Culvert Outlet

Page 53: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Erosion Control: 1 2 0

Definition

A stabilised pad of aggregate on a filter cloth baselocated at any point where traffic will be entering orleaving a construction site.

Purpose

To prevent site access points from becoming sedimentsources and to help minimise dust generation anddisturbance of areas adjacent to the road frontage bygiving a defined entry/exit point.

Application

Use a Stabilised Construction Entrance at all points ofconstruction site ingress and egress with a constructionplan limiting traffic to these entrances only. They areparticularly useful on small construction sites but canbe utilised for all projects.

Design

o Clear the entrance and exit area of all vegetation,roots and other unsuitable material and properlygrade it.

o Provide drainage to carry runoff from the StabilisedConstruction Entrance to a sediment control measure.

o Place aggregate to the specifications below andsmooth it.

Table 1.8 Stabilised Construction EntranceAggregate Specifications

Aggregate Size 50 – 75 mm washed aggregate

T h i c k n e s s 150 mm minimum

L e n g t h 10 minimum

Width 4 o minimum

1.8 Stabilised Construction Entrance

Plate 1.8 Stabilised Construction Entrance

Page 54: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Erosion Control: 1 2 1

Maintenance

Maintain the Stabilised Construction Entrance in acondition to prevent sediment from leaving theconstruction site. After each rainfall inspect any structureused to trap sediment from the Stabilised ConstructionEntrance and clean out as necessary.

Figure 1.8 Stabilised Construction Entrance

When wheel washing is also required, ensure this isdone on an area stabilised with aggregate which drainsto an approved sediment retention facility.

Page 55: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Erosion Control: 1 2 2

1.9 Pipe Drop Structure/Flume

Plate 1.9 Pipe Drop Structure

Definition

A temporary pipe structure or constructed flume placedfrom the top of a slope to the bottom.

Purpose

A Pipe Drop Structure or a Flume is installed to conveysurface runoff down the face of unstabilised slopes inorder to minimise erosion on the slope face.

Application

Pipe Drop Structures or Flumes are used in conjunctionwith Runoff Diversion Channels. The Runoff DiversionChannels direct surface runoff to the Pipe Drop Structureor Flume which conveys concentrated flow down the faceof a slope. Limit the catchment area of each Pipe DropStructure or Flume to 1.0 ha. If other forms of Pipe DropStructures or Flumes are being considered, AucklandRegional Council approval of those structures will benecessary on a case by case basis.

Design

o Construct all Pipe Drop Structures or Flumes ofwatertight materials.

o Extend the Pipe Drop Structure or Flume beyondthe toe of the slope and adequately protect the outletfrom erosion using riprap over a geotextile apron.

o Use of the following Design Criteria for Pipe DropStructure, is shown in Figure 1.9.

Table 1.9 Design Criteria for Pipe DropStructure

Pipe Diameter (mm) Maximum Catchment Area (ha)

150 0 .05

3 0 0 0 . 2

4 5 0 0 . 6

5 0 0 1.0

6 0 0 1.0

Page 56: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Erosion Control: 1 2 3

o Ensure that at the Pipe Drop Structure or Flumeinlet, the height of the Runoff Diversion Channel isat least twice the pipe diameter or height of Flumeas measured from the invert.

o Install a flared entrance section of compacted earth.To prevent erosion, place impermeable geotextilefabric into the inlet extended a minimum of 1.0 oin front of and to the side of the inlet and up thesides of the flared entrance. Ensure this geotextileis keyed 150 mm into the ground along all edges.

o When the catchment area is disturbed, ensure thePipe Drop Structure or Flume discharges into aSediment Retention Pond or a stable conveyancesystem that leads to a pond. When the catchmentarea is stabilised, ensure the Pipe Drop Structure orFlume outlets onto a stabilised area at a non-erosivevelocity. The point of discharge may be protectedby rock rip rap.

o Ensure the Pipe Drop Structure or Flume has aminimum slope of 3%.

Construction Specifications for Pipe DropStructures

o A common cause of failure of Pipe Drop Structuresis water saturating the soil and seeping along thepipe where it connects to the Runoff DiversionChannel. Backfill properly around and under thepipe with stable material in order to achieve firmcontact between the pipe and the soil at all pointsto eliminate this type of failure. Pipe material usedfor the Pipe Drop Structure can consist of rigid pipematerial or flexible pipe as required. If flexible pipematerial is utilised, it is vital that the material bepinned to the slope in the required position.

o Place Pipe Drop Structures on undisturbed soil orwell-compacted fill at locations as detailed withinthe Erosion and Sediment Control Plan for the site.

o Immediately stabilise all disturbed areas followingconstruction.

o Secure the Pipe Drop Structure to the slope at leastevery 4 o. Use no less than two anchors equallyspaced along the length of the pipe.

o Ensure all pipe connections are watertight.

Construction Specifications for Flumes

o A common failure of Flumes is outflanking of theFlume entrance or scouring of the invert to the Flume.This can be prevented by waterproofing the entranceto the Flume by trenching in an appropriateimpervious geotextile or plastic liner so that all flowsare channelled directly into the flume. Alternativelya piped entrance can be installed.

o Flumes can be constructed from materials such ascorrugated steel, construction ply, sawn timber orhalved plastic piping.

o Construct the Flume to ensure there are no leaks.For wooden or plywood Flumes or Flumes whereleakage is likely, extend an impervious liner downthe full length of the Flume structure.

o For slopes greater than 30%, a Flume can beconstructed from a standard 1.2 o x 2.4 o x 22mmplywood sheet. This will be adequate for a catchmentof up to one ha. Specific design is required for largercatchments.

o Fasten the Flume to the slope using waratahs orwooden stakes placed in pairs down the slope at 1to 4 o spacings, depending on the Flume materialused. Fasten the Flume to the waratahs or stakesusing wire or steel strapping.

o Place Flumes on undisturbed soil or wellcompacted fill at locations as detailed in the site’sErosion and Sediment Control Plan.

Maintenance

o Inspect the Pipe Drop Structure/Flume periodicallyand after each rain event. Immediately carry out anymaintenance required.

o Keep the inlet open at all times.

Page 57: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Erosion Control: 1 2 4

Figure 1.9 Pipe Drop Structure

Page 58: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Erosion Control: 1 2 5

Definition

A non-erosive outlet for concentrated runoff constructedtodisperse flows uniformly across a slope.

Purpose

To convert concentrated flow to sheet flow and release ituniformly over a stabilised area to prevent erosion.

The Level Spreader provides a relatively low cost optionwhich can release concentrated flow where site conditionsare suitable. Particular care is needed to ensure the LevelSpreader outlet lip is completely level and is in stable,undisturbed soil or is well armoured. Any depressionsin the Level Spreader lip will reconcentrate flows,resulting in further erosion.

Application

o Where sediment-free storm runoff can be releasedin a sheet flow over a stabilised slope without causingerosion.

o Where sediment-laden overland flow can bereleased in sheet flow across the inlet to a SedimentRetention Pond.

o Where the area below the Level Spreader lip isuniform with the slope of 10% or less and/or isstable for the anticipated flow conditions.

o Where the runoff water will not re-concentrate afterrelease.

o Where there will be no traffic over the LevelSpreader.

Design

o Determine the capacity of the Level Spreader byestimating peak flow from the 20 year storm.

o Where possible, choose a site for the Level Spreaderthat has a natural contour that will allow for therapid spreading of flows, for example, at the end ofa knoll or ridge.

o Select the appropriate length, width and depth ofthe spreader from Table 1.10 below.

Table 1.10 Level Spreader Design Criteria

Design Flow I n l e t D e p t h End Width L e n g t h

(m3/sec) Width (o) (mm) (o) (o)

0 – 0.3 3 150 1 3

0.3 – 0.6 5 180 1 7

0.6 – 0.9 7 220 1 10

o Construct a 6 o long transition section in the RunoffDiversion Channel leading up to the Level Spreaderso the width of the Runoff Diversion Channel willsmoothly meet the width of the Level Spreader toensure uniform outflow. The Level Spreader trenchtapers down to 1 o at the end of the Level Spreader.

o Maintain a minimum inlet width of 3 o.

o Ensure that the grade of the Level Spreader is 0%.

o Construct the Level Spreader lip on undisturbedsoil, incorporating a 50 x 150 mm board (SpreaderBeam) levelled and positioned edge on as shownbelow. An alternative is to armour the Level Spreaderto a uniform height and zero grade over the lengthof the Level Spreader. Use geotextile and ensure thedisturbed area is seeded and fertilised for vegetationestablishment.

Maintenance

Inspect Level Spreaders after every rainfall untilvegetation is established and promptly undertake anynecessary repairs. Ensure vegetation is kept in a healthyand vigorous condition.

Figure 1.10 Level Spreader

1.10 Level Spreader

Page 59: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Erosion Control: 1 2 6

1.11 Surface Roughening

Page 60: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Erosion Control: 1 2 7

To aid in the establishment of vegetative cover from seed,to reduce runoff velocity, to increase infiltration, toreduce erosion and assist in sediment trapping.

Application

Apply Surface Roughening on all construction sitesrequiring slope stabilisation with vegetation, particularlyon slopes steeper than 25%.

Design

Not Applicable.

Construction Specifications

Surface Roughening is promoted by the AucklandRegional Council because it aids the establishment ofvegetation, improves infiltration and decreases runoffvelocity. Graded areas with smooth, hard surfaces maybe initially attractive but such surfaces increase thepotential for erosion. A rough, loose soil surface gives amulching effect that protects fertiliser and seed.

Various methods are available for Surface Rougheningsuch as stair step grading, discing and forming groovesby machinery tracking. Factors to be taken into accountwhen choosing a method are slope steepness, mowing/maintenance requirements and whether the slope isformed by cutting or filling.

Machinery tracking up and down the slope is therecommended method, with the cleats of the machinetracks providing a series of mini contour drains, slowingoverland flow down the slope and helping to keep thegrass seed on the slope.

Maintenance

Periodically check the slopes for rills and washes. Reseedand/or rework the area as necessary.

Purpose

DefinitionRoughening a bare earth surface with horizontal grooves

running across the slope, or tracking with construction

equipment.

Figure 1.11 Tracking

1.11 Surface Roughening

Page 61: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Erosion Control: 1 2 8

Dozer cleats create grovesperpendicular to the slope

Slope

Page 62: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Sediment Control: 2 1

2.1 Sediment Retention Pond

Plate 2.1.1 Sediment Retention Pond Showing Decant Systems

Definition

A temporary pond formed by excavation into naturalground or by the construction of an embankment, andincorporating a device to dewater the pond at a rate thatwill allow suspended sediment to settle out.

Purpose

To treat sediment laden runoff and reduce the volumeof sediment leaving a site, thus protecting downstreamenvironments from excessive sedimentation and waterquality degradation.

Application

Sediment Retention Ponds are appropriate wheretreatment of sediment laden runoff is necessary, and aregenerally considered the appropriate control measure forexposed catchments of more than 0.3 ha. It is vital thatthe Sediment Retention Pond is maintained until thedisturbed area is fully protected against erosion bypermanent stabilisation.

The location of the Sediment Retention Pond needs tobe carefully considered in terms of the overall project,available room for construction and maintenance andthe final location of any permanent stormwater retentionfacilities that may be constructed at a later stage. Anothermajor consideration is whether drainage works can berouted to the Sediment Retention Pond until such timeas the site is fully stabilised. This eliminates the problemof installing and maintaining Stormwater Inlet Protectionthroughout the latter stages of a development.

The general design approach is to create animpoundment of sufficient volume to capture asignificant proportion of the design runoff event, and toprovide quiescent (stilling) conditions which promotethe settling of suspended sediment. The SedimentRetention Pond design is such that very large runoffevents will receive at least partial treatment and smallerrunoff events will receive a high level of treatment. Toachieve this, the energy of the inlet water needs to be lowto minimise re-suspension of sediment and the decant

Page 63: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Sediment Control: 2 2

rate of the outlet also needs to be low to minimise watercurrents and to allow sufficient detention time for thesuspended sediment to settle out.

Specific design criteria are discussed below, but can besummarised as the following.

o Generally use Sediment Retention Ponds for bareareas of bulk earthworks of 0.3 ha or greater.

o Restrict catchment areas to less than 5.0 ha perSediment Retention Pond. This limits the length ofoverland flowpaths and reduces maintenanceproblems.

o Locate Sediment Retention Ponds so as to providea convenient collection point for sediment ladenflows from the catchment area. This will requirestrategic use of cut-offs, Runoff Diversion Channelsand Contour Drains.

o Locate Sediment Retention Ponds to allow accessfor removing sediment from the pond.

o Wherever possible, locate Sediment RetentionPonds to allow the spillway to discharge overundisturbed, well vegetated ground.

o Keep the Sediment Retention Pond life to less thantwo years. If a longer term is required then furthermeasures to ensure stability and effectiveness arelikely to be needed.

o Do not locate Sediment Retention Ponds withinwatercourses.

o Embankment and spillway stability are generallythe weak point in Sediment Retention Pondconstruction. Correct compaction particularlyaround emergency spillways, discharge pipes andantiseep collars, will keep the system robust.

Figure 2.1.1 Sediment Retention Pond

Page 64: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Sediment Control: 2 3

Design – Size of the Pond

Calculate the volume of the Sediment Retention Pondusing the depth measured from the base of the SedimentRetention Pond to the top of the outlet riser. Thefollowing design criteria apply.

o On earthwork sites with slopes less than 10% andless than 200m in length, construct a SedimentRetention Pond with a minimum volume of 2% ofthe contributing catchment (200m3 for each ha ofcontributing catchment).

o On sites with slopes greater than 10% and/or 200 oin length, construct Sediment Retention Ponds witha minimum volume of 3% of the contributingcatchment (300m3 capacity for each ha ofcontributing catchment).

o The slope angle is determined by that slopeimmediately above the Sediment Retention Pondor by the average slope angle over the contributingcatchment, whichever is the greater.

o For sand soils (less than 8% clay and less than 40%silt) the size of the Sediment Retention Pond maybe calculated using the following formula –

- Pond Surface Area (square metres) = 1.5 x PeakInflow Rate (litres per second),

- calculate the inflow rates using the 5% AEPrainfall event. Ensure the Sediment RetentionPond has a minimum depth of 1.0m,

- alternatively, construct Sediment RetentionPonds with a minimum volume of 1% of thecontributing catchment (100 m3 capacity foreach ha of contributing catchment).

o On sites that are particularly steep or have sensitivedownstream environments, a greater SedimentRetention Pond volume may be required.

o Clean out Sediment Retention Ponds when thevolume of sediment accumulated within themreaches 20% of the design volume.

o Clearly show the Sediment Retention Ponddimensions necessary to obtain the requiredvolume, as detailed above, on the site’s Erosion andSediment Control Plan(s).

Design – Dead Storage (Permanent Storage)

o Dead storage is the component of impoundmentvolume that does not decant and remains in theSediment Retention Pond. It is important fordissipating the energy of inflows.

o Ensure dead storage is 30% of the total SedimentRetention Pond storage by positioning the lowestdecant 0.4 – 0.8m above the invert of the SedimentRetention Pond.

o The approved decant design detailed in theseGuidelines allows the lower decant arm to be raisedas sediment deposition increases, therebymaintaining the percentage volume of dead storage.

Design – Live Storage (Decant Storage)

o Live storage is the volume between the lowestdecant outlet level and the crest of the SedimentRetention Pond primary spillway.

o Ensure that the live storage volume capacity is 70%of the total Sediment Retention Pond storage.

o The approved decant design detailed in theseGuidelines allows the decant system to be raised assediment deposition increases, thereby maintainingthe percentage volume of live storage.

Design – Decanting/Outlet Dewatering Device

o Dewater the Sediment Retention Pond so as toremove the relatively clean water without removingany of the settled sediment, and without removingany appreciable quantities of floating debris.

o Various dewatering devices are available, howeverthe Auckland Regional Council prefers the use of afloating T-bar dewatering device, which allows forthe decanting of the cleaner surface water from thetop of the water column. Substantiated performancedesign will need to be submitted to the AucklandRegional Council for decant systems other than thefloating T-bar dewatering device.

o The recommended decant rate from a SedimentRetention Pond is 3 litres/second/ha of contributingcatchment. This rate ensures that appropriatedetention times are achieved.

Page 65: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Sediment Control: 2 4

o A standard T-bar design is detailed in Figure 2.1.5for various sized catchments. For simplicity, givepreference to producing a standard T-bar decant thatprovides a decant rate of 4.5 litres/second per decantwhich can be added in discrete increments toaccommodate various sized catchments.

o To achieve a decant rate of 4.5 litres/second per decant,drill 6 rows of 10mm diameter holes at 60mm spacings(200 holes) along the 2m long decant arm.

o For catchments of less than 1.5ha, seal off theappropriate number of holes to achieve a 3 litres/second/hectare discharge rate.

o Single T-bar decants must be able to operatethrough the full live storage depth of the SedimentRetention Pond.

o If two decant systems are required, ensure the lowerT-bar decant operates through the full live storagedepth of the Sediment Retention Pond. The upperT-bar decant is to operate through the upper 50%of the live storage depth of the Sediment RetentionPond only.

o If three decant systems are to be used, then thelower T-bar decant operates through the full livestorage depth and the second T-bar decant throughthe upper two thirds of live storage depth of theSediment Retention Pond. The upper T-bar decantoperates through the upper one third of live storagedepth of the Sediment Retention Pond as detailedin Figure 2.1.4.

o Ensure that the T-bar decant float is securelyfastened with steel strapping directly on top of thedecant arm and weight it to keep the decant armsubmerged just below the surface through all stagesof the decant cycle. This will also minimise thepotential for blockage of the decant holes by floatingdebris. The most successful method found to dateis to weight the decant arm by strapping a 1.8m longwaratah between the float and the decant(approximately 4kg of weight).

o Position the T-bar decant at the correct height bytying 5mm nylon cord through decant holes ateither end of the decant arm and fastening it towaratahs driven in on either side of the decant.

o Lay the discharge pipe at a 1 – 2% gradient, compactthe fill material around it using a machinecompactor and incorporate anti-seep collars withthe following criteria:

o install collars around the pipe to increase theseepage length along the pipe with a spacing ofapproximately 10m;

o the vertical projection of each collar is 1.0m;ensure all anti seep collars and their connectionsare watertight.

o Use a flexible thick rubber coupling to provide aconnection between the decant arm and the primaryspillway or discharge pipe. To provide sufficientflexibility (such as is required for the lower decantarm) install two couplings. Fasten the flexiblecoupling using strap clamps and glue.

o Where a concrete riser decant system is utilised,ensure the lower decant connection is positionedon an angle upwards from the horizontal so as tosplit the operational angle that the decant worksthrough. This will reduce the deformation force onthe coupling used.

Design – Shape of the Pond

o Ensure the length to width ratio of the SedimentRetention Pond is no less than 3:1 and no greaterthan 5:1. The length of the Sediment Retention Pondis measured as the distance between the inlet andthe outlet (decant system). A 2:1 ratio may be usedif the pond depth is no greater than 1.0m.

o Maximise the distance between the inlet and theoutlet (including the emergency spillway) to reducethe risk of short circuiting and to promote quiescentconditions. If this can not be achieved by correctlypositioning the inlet and outlets, install baffles toachieve the appropriate length to width ratio design.

o Ensure that the Sediment Retention Pond has a levelinvert as described below to promote the even andgradual dissipation of the heavier inflow wateracross the full area of the Sediment Retention Pond.

Page 66: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Sediment Control: 2 5

Design – Level Spreader

o Incorporate a Level Spreader into the inlet designto spread inflow velocities, thereby allowing rapiddissipation of inflow energies. Combine the LevelSpreader with a well compacted and smoothed inletbatter (no steeper than a 3:1 gradient), stabilisedover its entire area. The essential design feature isto ensure the Level Spreader is level, non-erodibleand spans the full width of the Sediment RetentionPond.

o To ensure even inflows, install a trenched andpegged 150mm x 50mm timber weir or similaracross the full width of the inlet. Bund the edgeswith compacted earth to prevent outflanking. Thistimber weir also serves to toe in any geotextileprotection which may be required. Sedimentaccumulated behind the Level Spreader may requireperiodic removal.

o Position the top of the Level Spreader weir 100 –200 mm above the invert of the emergency spillway.

o The shape of the Level Spreader will vary with thedirection and volume of the inlet diversion, but theentrance to the Level Spreader must be widened andflared to promote even flow, as in Part B, Section1.10 of these Guidelines.

Design – Baffles

o Incorporate baffles in the Sediment Retention Ponddesign where the recommended pond shape cannotbe achieved. Extend baffles the full depth of theSediment Retention Pond and place them tomaximise dissipation of flow energy.

o Generally, baffles are in the form of a wing to directinflows away from the outlet and maximise thestilling zone. A series of compartments within thepond can be used to achieve this, although care mustbe taken to avoid creating in-pond currents andresuspension of light particulates.

Plate 2.1.2 Sediment Retention Pond Showing Baffle to Lengthen Flowpath and Create Correct Length:Width Ratio

Page 67: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Sediment Control: 2 6

o Baffles may be constructed from various materialsranging from solid shutter boards to bracedgeotextile curtains.

Design – Depth of Pond

o Sediment Retention Pond depths may be 1 – 2mdeep, but no deeper than 2m. Deeper ponds aremore likely to cause short circuiting problemsduring larger storm events and require specificallydesigned floating decant systems.

o The decant design in these Guidelines operatesthrough a maximum live storage range of 1.5m.

Design – Embankment

o Before building a Sediment Retention Pond, installsediment controls such as Silt Fences below theconstruction area and maintain them to a functionalstandard until the Sediment Retention Pond battersare fully stabilised.

o Thoroughly compact the Sediment Retention Pondembankment, with material laid in 150 mm layersand compacted to engineering standards.

o Where possible install the discharge pipes throughthe embankment as the embankment is beingconstructed.

o Fully stabilise the external batter face, by vegetativeor other means, immediately after construction.

o Ensure all bare areas associated with the SedimentRetention Pond (including internal batters) arestabilised with vegetation if the Sediment RetentionPond is to remain in place over winter.

Design – Primary Spillway

o For larger catchments (greater than 1.5ha) theSediment Retention Pond requires a piped primaryspillway (refer Figures 2.1.3 and 2.1.4).

o For catchments up to 1.5ha, decant flows can bepiped using the same diameter piping as the decantsystem (100mm PVC smooth bore) directly throughthe Sediment Retention Pond wall to dischargebeyond the toe of the Sediment Retention Pond wall.

o For contributing catchments between 1.5 and 3hain area, use a discharge and primary spillway pipediameter of 150mm.

o Where contributing catchments are 3ha or greaterand/or the long term stability of the SedimentRetention Pond emergency spillway is questionable(for example, built in fill) then consideration shouldbe given to incorporating a concrete manhole riserand larger diameter pipe outlet as a primary spillwaysufficient to accommodate the 5% AEP rainfallevent.

o If the Sediment Retention Pond is to operate overthe winter and the contributing catchment is fullystabilised, disconnect the T-bar decant to reduce thefrequency of emergency spillway activation andconsequent erosion.

o Where a primary spillway upstand riser is used,place the top of the riser a minimum 600mm lowerthan the top of the Sediment Retention Pondembankment and a minimum 300mm lower thanthe emergency spillway crest. Ensure the riser andthe discharge pipe connections are all completelywatertight.

o Where possible, install the piping through theembankment as the embankment is beingconstructed.

Design – Emergency Spillway

o An emergency spillway is essential for all SedimentRetention Ponds.

o Emergency spillways must be capable ofaccommodating the 1% AEP event without eroding.

o The outer emergency spillway crest and batterrequires a very high standard of stabilisation withthe fill material of the spillway batter wellcompacted.

o Construct the emergency spillway as a stabilisedtrapezoidal cross section with a minimum bottomwidth of 6m or the width of the pond floor,whichever is the greater.

o When utilising geotextile for emergency spillwaystabilisation purposes, the batter face must besmooth and all voids eliminated.

o If geotextile is used, a soft neddle punch geotextileis laid first and then covered with a strong wovenlow permeability geotextile. Ensure the geotextileis pinned at 0.5m centres over the full area of theemergency spillway.

Page 68: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Sediment Control: 2 7

o Where possible, construct emergency spillways inwell vegetated, undisturbed ground (not fill) anddischarge over long grass.

o If the emergency spillway is constructed on baresoil, provide complete erosion protection by meanssuch as grouted riprap, asphalt, erosion matting/geotextile or concrete.

o Construct the emergency spillway with a minimumof 300mm freeboard height above the primaryspillway.

Construction Specifications

o Construct a fabric silt fence across the downslopeend of the proposed works.

o Clear areas under proposed fills of topsoil or otherunsuitable material down to competent material.Large fill embankments may need to be keyed in.

o Use only approved fill.

o Place and compact fill in layers as per the engineer’sspecifications.

o Do not place pervious materials such as sand orgravel within the fill material.

o Construct fill embankments approximately 10%higher than the design height to allow for settlementof the material. Install appropriate pipe work andantiseep collars during the construction of theembankment and compact around theseappropriately.

o Install the emergency spillway.

o Install and stabilise the Level Spreader.

o Securely attach the decant system to the horizontalpipework. Make all connections watertight. Placeany manhole riser on a firm foundation ofimpervious soil.

o Do not place pervious material such as sand orscoria around the discharge pipe or the antiseepcollars.

o Install baffles if required.

o Check Sediment Retention Pond freeboard fordifferential settlement and rectify as necessary.

o Stabilise both internal and external batters withvegetation and the emergency spillway inaccordance with the site’s approved Erosion andSediment Control Plan.

Pond Maintenance and Disposal of Sediment

o Clean out Sediment Retention Ponds before thevolume of accumulated sediment reaches 20% ofthe total Sediment Retention Pond volume. To assistin gauging sediment loads, clearly mark the 20%volume height on the decant riser.

o Clean out Sediment Retention Ponds with highcapacity sludge pumps, or with excavators (longreach excavators if needed) loading onto sealed tiptrucks or to a secure area.

o The Erosion and Sediment Control Plan shouldidentify disposal locations for the sediment removedfrom the Sediment Retention Pond. Deposit thesediment in such a location so that it does not leadto a direct discharge to receiving environments.Stabilise all disposal sites as required and approvedin the site’s Erosion and Sediment Control Plan.

o Inspect Sediment Retention Ponds every day andbefore every forecasted rainfall event. Inspect forcorrect operation after every runoff event.Immediately repair any damage to SedimentRetention Ponds caused by erosion or constructionequipment.

Safety

Sediment Retention Ponds are attractive to children andcan become safety hazards if not appropriately fencedand if safety rules are not followed. Low gradient pondbatters provide an additional safety measure. Check thesafety requirements of the City or District CouncilAuthority and the Occupational Safety and Healthbranch of the Department of Labour.

Chemical Treatment

Some chemicals can be used successfully to promoteflocculation (clumping together) of suspended solids inthe Sediment Retention Pond to increase the particlemass and speed the rate of settling.

Page 69: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Sediment Control: 2 8

Recent trials have identified a simple and effectivechemical dosing system that does not require a powersupply. This system uses poly aluminium chloride (PAC)and has been found to be particularly effective in settlingfine particulate such as fine silts and clays. Otherchemicals may become available as more trial data isobtained.

Figure 2.1.2 Sediment Retention Pond for Catchments up to 1.5 ha

Chemical dosing systems are likely to be required wherethe design Sediment Retention Pond volume cannot beachieved because of site constraints and/or where a highlevel of treatment is required because of the sensitivityof the receiving environment. Chemical treatment is alsomore likely to be required where the clay component ishigh or where the cumulative effects of sedimentdischarge are significant.

Page 70: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Sediment Control: 2 9

Figure 2.1.3 Sediment Retention Pond for Catchments Between 1.5 and 3 ha

Page 71: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Sediment Control: 2 1 0

Figure 2.1.4 Sediment Retention Pond for Catchments Between 3 and 5 ha

Page 72: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Sediment Control: 2 1 1

Figure 2.1.5 Sediment Retention Pond – Decant Detail

Page 73: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Sediment Control: 2 1 2

2.2 Silt Fence

Definition

A temporary barrier of woven geotextile fabric used tointercept runoff, reduce its velocity and impoundsediment laden runoff from small areas of disturbed soil.

Purpose

To detain flows from runoff so that deposition oftransported sediment can occur through settlement. Siltfences can only be used to intercept sheet flow. Do notuse them as velocity checks in channels or place themwhere they will intercept concentrated flow.

Application

o On low gradient sites or for confined areas wherethe contributing catchment is small, such as shortsteep batter fills and around watercourses.

o To delineate the limit of disturbance on anearthworks site such as riparian areas or bushreserves.

o To store runoff behind the Silt Fence withoutdamaging the fence or the submerged area behindthe fence.

o Do not install Silt Fences across watercourses orin areas of concentrated flows.

Design

o Ensure Silt Fence height is a minimum of 400mmabove ground level.

o Place supporting posts/waratahs for Silt Fences nomore than 2m apart unless additional support isprovided by tensioned wire (2.5mm HT) along thetop of the Silt Fence. Where a strong woven fabricis used in conjunction with a wire support, thedistance between posts can be extended up to 4m.Double the Silt Fence fabric over and fasten to thewire and posts with wire ties or cloth fastening clipsat 150mm spacings. Ensure supporting posts/waratahs are embedded a minimum of 400mm intothe ground.

Plate 2.2 Silt Fence

Page 74: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Sediment Control: 2 1 3

o Always install Silt Fences along the contour. Wherethis is not possible or where there are long sectionsof Silt Fence, install short Silt Fence returnsprojecting upslope from the Silt Fence to minimiseconcentration of flows. Silt Fence returns are aminimum 2m in length, can incorporate a tie backand are generally constructed by continuing the SiltFence around the return and doubling back,eliminating joins.

o Join lengths of Silt Fence by doubling over fabricends around a wooden post or batten or by staplingthe fabric ends to a batten and butting the twobattens together as shown in Figure 2.2.

o Maximum slope lengths, spacing of returns andangles for Silt Fences are shown in Table 2.2.

o Install Silt Fence wings at either end of the SiltFence projecting upslope to a sufficient height toprevent outflanking.

o Where impounded flow may overtop the Silt Fence,crossing natural depressions or low points, makeprovision for a riprap splash pad or other outletprotection device.

o Use of Silt Fences in catchments of more than 0.5harequires careful consideration of specific sitemeasures, and other control measures maybe better,such as Super Silt Fence.

o Where water may pond behind the Silt Fence,provide extra support for the Silt Fence with tiebacks from the Silt Fence to a central stable pointon the upward side. Extra support can also beprovided by stringing wire between support stakesand connecting the filter fabric to this wire.

o The fabric cloth must meet the followingrequirements for Geotextile fabric.

Tension Strength: 0.345 pa (minimum)

Tensile Modulus: 0.140 pa (minimum)

Apparent Opening Size 100 mm

Table 2.2 Silt Fence Design Criteria

Slope Steepness % Slope Length (o) (Maximum) Spacing of Returns (o) Silt Fence Length (o) (Maximum)

Flatter than 2% Unlimited N/A Unlimited

2 – 10% 40 60 300

10 – 20% 30 50 230

20 – 33% 20 40 150

33 – 50% 15 30 75

> 50% 6 20 40

Construction Specifications

o Use Silt Fence material appropriate to the siteconditions and in accordance with themanufacturer’s specifications.

o Excavate a trench a minimum of 100mm wide and200mm deep along the proposed line of the SiltFence. Install the support posts on the downslopeedge of the trench and Silt Fence fabric on theupslope side of the support posts to the full depthof the trench, then backfill the trench withcompacted soil.

o Use supporting posts of tanalised timber aminimum of 50mm square, or steel waratahs at least1.5m in length.

o Reinforce the top of the Silt Fence fabric with awire support made of galvanised wire of a minimumdiameter of 2.5mm. Tension the wire usingpermanent wire strainers attached to angledwaratahs at the end of the Silt Fence.

o Where ends of Silt Fence fabric come together,ensure they are overlapped, folded and stapled toprevent sediment bypass.

Page 75: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Sediment Control: 2 1 4

Maintenance

o Inspect Silt Fences at least once a week and aftereach rainfall. Make any necessary repairs whenbulges occur or when sediment accumulationreaches 50% of the fabric height.

o Any areas of collapse, decomposition orineffectiveness need to be immediately replaced.

o Remove sediment deposits as necessary to continueto allow for adequate sediment storage and reducepressure on the Silt Fence. Ensure that the sedimentis removed to a secure area.

o Do not remove Silt Fence materials and sedimentdeposition until the catchment area has beenappropriately stabilised. Stabilise the area of theremoved Silt Fence.

Figure 2.2 Silt Fence

Page 76: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Sediment Control: 2 1 5

2.3 Super Silt Fence

Plate 2.3 Super Silt Fence

Definition

A temporary barrier of geotextile fabric over chain linkfence that is used to intercept flows, reduce their velocityand impound sediment-laden runoff from smallcatchment areas.

Purpose

To reduce runoff velocity and allow the deposition oftransported sediment to occur.

A Super Silt Fence provides much more robust sedimentcontrol than a standard Silt Fence and allows up to fourtimes the catchment area to be treated by an equivalentlength of standard Silt Fence.

Application

o Provides a barrier that can collect and hold debrisand soil, preventing the material from enteringcritical areas, watercourses and streets.

o Can be used where the installation of an Earth orTopsoil Bund would destroy sensitive areas such asbush and wetlands.

o Should be placed as close to the contour aspossible. No section of the fence should exceed agrade of 5% for a distance of more than 15m.

Design

When considering Super Silt Fence installation for largercatchments (greater than 0.5ha) as in Table 2.3, carefullyconsider the specific site conditions and other alternativecontrol measures available. Base the length of the SuperSilt Fence is based on the limits shown in Table 2.3.

Limits imposed by ultraviolet light affect the stability ofthe fabric and will dictate the maximum period that theSuper Silt Fence may be used.

Where ends of the geotextile fabric come together,overlap, fold and staple the fabric ends to preventsediment bypass.

Page 77: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Sediment Control: 2 1 6

Table 2.3 Super Silt Fence Design Criteria

Slope % Slope Length (o) Super Silt Fence

(maximum) Length (o) (maximum)

0 – 10 Unlimited Unlimited

10 –20 60 450

20 – 33 30 300

33 – 50 30 150

> 50 15 75

Construction Specifications

o Use a Silt Fence fabric that is appropriate to thesite conditions and fits the manufacturer’sspecifications.

o Excavate a trench 100mm wide by 200mm deepalong the line of the Super Silt Fence.

o Position the posts (No. 3 rounds, No. 2 half roundsor waratahs) at no greater than 3 o centres on thedownslope side of the trench. While there is no needto set the posts in concrete, ensure the 1.8m longposts are driven to an appropriate depth(1m minimum).

o Install tensioned galvanised wire (2.5 mmHT) at400mm and again at 800mm above ground levelusing permanent wire strainers.

o Secure chain link fence to the fence posts with wireties or staples, ensuring the chain link fence goes tothe base of the trench.

o Fasten two layers of geotextile fabric securely tothe Super Silt Fence with ties spaced every 60cm atthe top and mid section of the Super Silt Fence.

o Place the two layers of geotextile fabric to the baseof the trench (a minimum of 200mm into theground) and place compacted backfill back to theoriginal ground level.

o When two sections of geotextile fabric adjoin eachother, ensure they are doubled over a minimum of300mm, wrapped around a batten and stapled at75mm spacings to prevent sediment bypass.

o The geotextile fabric must meet the followingrequirements:

Tension Strength 0.345 pa (minimum)

Tensile Modulus 0.140 pa (minimum)

Apparent Opening Size 100 – 500 mm

Maintenance

Inspect regularly and before and after storm events.

Undertake maintenance as needed and remove siltbuildups when bulges develop in the Super Silt Fence orwhen sediment deposition reaches 50% of the Super SiltFence height.

Page 78: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Sediment Control: 2 1 7

Figure 2.3 Super Silt Fence

Page 79: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Sediment Control: 2 1 8

2.4 Hay Bale Barrier

Definition

Temporary barriers of hay bales used to intercept anddirect surface runoff from small areas.

Purpose

To intercept or direct sediment laden runoff from smallareas to a sediment retention facility so that depositionof transported sediment can occur. Hay Bale Barriers donot filter sediment.

Application

o Hay Bale Barriers are not primary sediment controlmeasures. They easily deteriorate and requirefrequent maintenance.

o Only use Hay Bale Barriers to meet short term needsof less than one month duration.

o Only use Hay Bale Barriers to intercept sheet flow.Do not use them as velocity checks in channels orplace them where they will intercept concentratedflow. They do not act as filters and are easilyovertopped or scoured out.

o Do not use with a catchment area of more than0.2ha per 100 o length of haybales.

o Do not use Hay Bale Barriers on slopes exceeding20%.

Design

Not Applicable.

Plate 2.4 Hay Bale Barrier

Page 80: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Sediment Control: 2 1 9

Figure 2.4 Hay Bale Barrier

Construction Specifications

o Place Hay Bale Barriers along the contour withbales in a row with the ends tightly abuttingadjacent bales.

o Dig each bale into the ground 100mm and place sothe bale bindings are horizontal.

o Do not place bales more than one bale high.

o Secure bales in place by two stakes driven throughthe bale 300 to 400mm into the ground. Drive thefirst stake toward the previously laid bale at an angleto force the bales together. Drive stakes flush withthe top of the bale.

Maintenance

Inspect Hay Bale Barriers frequently and after each rainevent. Undertake maintenance as necessary.

Remove all bales when the site has been fully stabilised.Stabilise the trench where the bales were located andgrade flush.

F l o w

String Binder

Undisturbed Ground

100mm Ver tical Face

Bedding Detail

Angle first stake towardthe previously placed bale

Entrench bales a minimum of100mm into the ground

Trench cut into ground

2 Re-bars or 50mm x 50mm stakesdriven 300mm minimum into theground. Stakes are to be drivenflush with the top of the bales

Bound balesplaced alongc o n t o u r

Page 81: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Sediment Control: 2 2 0

2.5 Stormwater Inlet Protection

Plate 2.5 Stormwater Inlet Protection

Application

o Do not use Stormwater Inlet Protection as aprimary method of treatment instead of othersediment retention facilities.

o Use only in small catchments of less than 0.5 ha.

o Use only where the catchment area to an inlet isdisturbed and it is not possible to temporarily divertthe storm drain outfall into a sediment retentionfacility.

Stormwater Inlet Protection only offers limited treatmentof sediment-laden water, because of the concentratedflows arriving at them. Stormwater systems are, bydesign, very efficient at conducting flows away frominlets, and therefore, once any sediment reaches thestormwater system, it will be discharged directly to thereceiving environment.

Therefore, the need to use Stormwater Inlet Protectioncan indicate poor erosion and sediment control and/orinadequate stabilisation on the site.

Design

There are various design options for reducing sedimentinputs to the stormwater cesspits.

Silt Fence Design

A Silt Fence can be erected around the inlet (see Part BSection 2.2). This method is appropriate where cesspitshave been connected to a stormwater system and arecollecting runoff from disturbed soil surfaces.

Filter Media Design

Two common methods use geotextile and scoria or gravelto treat sediment laden flows. All points where runoffcan enter the cesspit must be protected with suitablegeotextile fabric.

o Wrap geotextile fabric around the cesspit grate asa barrier to flow directly from the roadside gutter.Pay special attention to the inlet above the grateback of the cesspit where a geotextile fabric sockfilled with gravel must be placed to intercept runoff.

o Lay coarse geotextile fabric over the cesspit andup onto the kerb with a layer of aggregate materialto act as a primary filter and to hold the fabric in

Definition

A barrier across or around a cesspit (stormwater inlet).

Purpose

To intercept and filter sediment-laden runoff before itenters a reticulated stormwater system via a cesspit,thereby preventing sediment-laden flows from enteringreceiving environments. The protection may take variousforms depending upon the type of inlet to be protected.Stormwater Protection is a secondary sediment controldevice. It must only be used in conjunction with othererosion and sediment control measures.

If good erosion and sediment control measures are inplace on the site, then Stormwater Inlet Protection willnot be required.

Page 82: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Sediment Control: 2 2 1

place.

Check Dams

Place a series of low sandbag check dams up the gutterfrom cesspits to act as a series of sediment traps. Thecheckdams require a spillway lower than the kerb toensure that runoff does not encroach onto the berm areaand cause scouring. Construct checkdams out of up tosix sandbags laid end to end with no gaps in an arc awayfrom the kerb and up the road to create a series ofimpoundment areas.

Excavated Inlet Protection

Excavating around a stormwater inlet creates storagecapacity where suspended material can settle out. Ensurethat seepage holes allow for filtered dewatering, and thatthe capacity provided around the inlet for storage is aminimum of 1% of the catchment (1m3 of capacity per100 m2 of contributing catchment).

Maintenance

Maintenance requirements for cesspit protectionmeasures are high because they clog easily. When cloggingoccurs, remove accumulated sediment and clean orreplace the geotextile fabric and aggregate.

Inspect all Stormwater Inlet Protection measuresfollowing any rainfall event and maintain as necessaryto ensure they operate effectively.

Stormwater Inlet Protection provides at best limitedsediment retention. Do not use it as a primary methodof sediment control. Use additional measures up-slope,such as topsoil bunds and cut-off drains, to minimisethe volume of sediment reaching any stormwaterinlets. Cesspits must at all times remain able to conveyflow from the site to prevent large concentrated highlyerosive flows from building up and causing washoutsin secondary overland paths.

Construction Specifications

Construct Silt Fences for Stormwater Inlet Protection as outlined in Part B Section 2.2 of these Guidelines.

Page 83: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Sediment Control: 2 2 2

Figure 2.5 Stormwater Inlet Protection – Filter Media Design

2.6 Earth Bund

Plate 2.6 Earth Bund

Definition

A temporary berm or ridge of compacted soil(including topsoil) constructed to create impoundmentareas where ponding of runoff can occur and suspendedmaterial can settle before runoff is discharged.

Purpose

Used to intercept sediment-laden runoff and reduce theamount of sediment leaving the site by detainingsediment-laden runoff.

Application

Earth Bunds can be constructed across disturbed areasand around construction sites and subdivisions. Keepthem in place until the disturbed areas are permanentlystabilised or adequately replaced by other means. EarthBunds can assist the settling of sediment-laden runoff.

Earth Bunds are particularly useful for controlling runoffafter topsoiling and grassing before vegetation becomesestablished. Where works are occurring within the bermarea, compact the topsoil over the berm area as a bundadjacent and parallel to the berm. This will act as animpoundment area while also keeping overland flowaway from the construction area.

Design

o Earth Bunds need a constructed outlet structureand spillway as designed for Sediment RetentionPonds (Part B, Section 2.1 of these Guidelines).Alternatively, construct an outlet of perforated pipeconnected to a non-perforated pipe that passesthrough the Earth Bund and either discharges tothe gutter or directly to a stormwater inlet. Ensurethat the section of pipe within the impoundmentarea is supported by means of a rigid post, allowingfiltration to occur.

Page 84: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Sediment Control: 2 2 3

o Ensure the top opening of the perforated pipe is100 mm lower than the stabilised spillway.

o Ensure the section of pipe leading through the EarthBund and continuing downslope below the EarthBund is non-perforated.

which may cause overtopping. Check any discharge points for signs of scouring and install further armouring or other

o Construct the Earth Bund such that the maximumcontributing catchment does not exceed 0.3 ha.

Maintenance

Inspect and maintain Earth Bunds regularly and aftereach rainfall event to check for accumulated sediment

Page 85: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Sediment Control: 2 2 4

stabilisation if scouring is evident.

Figure 2.6 Earth Bund

2.7 Sump / Sediment Pit

Plate 2.7 Sump / Sediment Pit

Definition

A temporary pit which is constructed to trap and filterwater before it is pumped to a suitable discharge area.

Purpose

To treat sediment-laden water that has been removedfrom areas of excavation, or areas where pondedsediment laden-water can not drain by other means.

Application

o When water collects during the excavation phaseof construction.

o Particularly useful in urban areas during excavationfor building foundations.

o May also be used to de-water sediment retentionmeasures.

Design

The design is based on a perforated vertical standpipe

placed in the centre of a pit which is then backfilledwith aggregate.

o Determine the number of Sump/Sediment Pits andtheir locations on site in accordance with therequired dewatering facilities and proceduresoutlined below.

o Pump water from the centre of the pipe to a suitabledischarge area.

o Direct the discharge to an appropriate outlet.

o If the water is pumped directly to a receivingenvironment, then wrap a geotextile fabric aroundthe standpipe to help achieve a clean waterdischarge. When a geotextile fabric is used, thesurface area of the standpipe will need to beincreased and the pumping rate decreased toprevent the geotextile becoming rapidly blocked.

o Sump/Sediment Pit dimensions are variable, butrequire a minimum depth of 1m and a minimumvolume of 2m3.

o Construct the standpipe from 300 – 600mm

Page 86: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Sediment Control: 2 2 5

diameter pipe with a grid of 10 mm diameterperforations at 60mm spacings along the standpipe.

o Place a base of 50mm aggregate in the Sump/Sediment Pit to a depth of 300mm.

o After placing the standpipe in position, backfill thearea with 50mm aggregate.

o Extend the standpipe 300mm above the lip of theSump / Sediment Pit with the aggregate extended100 mm above the anticipated standing waterelevation.

Maintenance

Undertake ongoing checks throughout the use of theSump/Sediment Pit to ensure effective operation.

For isolated areas where dewatering must occur tofacilitate progress, other methods may be appropriate.These alternatives include the following.

o Pumping accumulated sediment-laden water to asediment retention pond.

o Constructing a Silt Fence and pumping water tobehind the Silt Fence to be retained for treatment.Do not let water to be treated enter the Silt Fenceas a concentrated flow or outflank the Silt Fence.

o Discharge accumulated sediment laden water to

land where soakage may occur. Ensure that this untreated sediment-laden runoff cannot enter to a stormwatersystem or any watercourse.

Page 87: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Wor ks Within a Watercourse: 3 1

Works within watercourses have very high potential forerosion and discharge of sediment. This is because suchwork is undertaken in or near flowing water – the majorcause of erosion. Flowing water causes ongoing scourand provides the transport mechanism to allow sedimentto be dispersed downstream of the works and ultimately,into the marine environment.

The following erosion and sediment control methods andtechniques are specific to temporary watercourse worksonly. Such works may also require a range of control

measures additional to those detailed below. These othermeasures are described in other sections of theseGuidelines and include both erosion control andsediment control techniques.

Design and planning consideration for a permanentwatercourse crossing need to take into account thepermanent nature of the crossing in question. Be surethat they are constructed in accordance with all relevantrequirements.

3.1 Temporary Watercourse Crossings

Plate 3.1 Temporary Watercourse Crossing

Definition

A bridge, ford or temporary structure installed across awatercourse for short term use by construction vehicles.

Purpose

To provide a means for construction vehicles to crosswatercourses without moving sediment into thewatercourse, damaging the bed or channel, or causing

flooding during the construction, maintenance orremoval of the structure.

Application

Where heavy equipment is required to be moved fromone side of a watercourse to the other, or where trafficmust cross the watercourse frequently for a short periodof time.

Page 88: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Wor ks Within a Watercourse: 3 2

Design

Careful planning can minimise the need for watercoursecrossings. Wherever possible, avoid crossingwatercourses by completing the development separatelyon each side of the channel, thus leaving the watercoursein its natural state.

If no other option exists and a watercourse crossing isrequired, select a location where the potential effects ofthe crossing (including construction) are minimised.

Plan watercourse crossings well before you need themand if possible, construct them during periods of dryweather. Complete construction as rapidly as possibleand stabilise all disturbed areas immediately during andfollowing construction.

Do not build a watercourse crossing during the fishmigration period for the watercourse. The AucklandRegional Council can help identify these periods forparticular watercourses.

There are three main types of crossing; bridges, culvertsand fords.

Bridges

Where available materials and designs are adequate tobear the expected loadings, bridges are the preferredtemporary watercourse crossing method. They providethe least obstruction to flow and fish migration, causelittle or no modification of the bed or banks and generallyrequire little maintenance.

It should be noted, however, that bridges can be a safetyhazard if not designed, installed and maintainedappropriately.

Culvert Crossings

Culverts are the most commonly used type of temporarywatercourse crossing, and can be easily adapted to mostsite conditions. The installation and removal of culverts,however, causes considerable damage to watercoursesand can also create the greatest obstruction to floodflows.

Fords

Made of stabilising material such as rock, fords are oftenused in steep catchments subject to flooding, but wherenormal flows are shallow. Only use fords where crossingrequirements are infrequent. They can offer little or noobstruction to flows, are relatively easy to install andmaintain, and in most cases can be left in place at the endof the construction activity.

As well as erosion and sediment control measures,structural stability, utility and safety must also be takeninto account when designing temporary watercoursecrossings. These details must be supplied to the AucklandRegional Council for approval prior to construction. Inaddition, a resource consent may be required for theconstruction of the proposed crossing. This can bedetermined by consultating with the Auckland RegionalCouncil.

Any temporary crossing shall comply with the technicalrequirements of the various agencies involved and anyspecific requirements imposed by the Auckland RegionalCouncil.

If the structure is no longer needed, remove the structureand all material from the site. Immediately stabilise allareas disturbed during the removal process byrevegetation or artificial protection as a short term controlmeasure. Keep machinery clear of the watercourse whileremoving the structure.

Maintenance

Inspect temporary watercourse crossings after rain tocheck for blockage in the channel, erosion of the banks,channel scour or signs of instability. Make all repairsimmediately to prevent further damage to the installation.Permanent crossings need to be inspected followingmajor storm events, again with all repairs being madeimmediately.

Page 89: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Wor ks Within a Watercourse: 3 3

3.2 Temporary Watercourse Diversion

Plate 3.2 Temporary Watercourse Diversion

Definition

A short term watercourse diversion to allow works tooccur within the main watercourse channel under dryconditions.

Purpose

To enable watercourse works to be undertaken withoutworking in wet conditions and without moving sedimentinto the watercourse.

Application

Temporary watercourse diversions are used as temporarymeasures to allow any works to be undertaken withinpermanent and ephemeral watercourses.

Design

Divert all flow via a stabilised system around the area ofworks and discharge it back into the channel below theworks to avoid scour of the channel bed and banks. Figure3.2.1 shows the suggested steps to minimise sedimentgeneration and discharge from works within awatercourse.

Page 90: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Wor ks Within a Watercourse: 3 4

Figure 3.2.1 Temporary Watercourse Diversion Works Sequence

Step 1

Excavate the diversion channel leaving a plug at each endso that the watercourse does not breach the diversion.Size the diversion channel to allow for a 5% AEP rainevent. Stabilise the diversion channel appropriately toensure it does not become a source of sediment. Anchorsuitable geotextile cloth in place to the manufacturer’sspecifications, which will include trenching into the topof both sides of the diversion channel to ensure that thefabric does not rip out. Open the downstream plug andallow water to flow up the channel, keeping some waterwithin the channel to reduce problems when theupstream plug is excavated. Open the upstream plug andallow water to flow into the channel.

Step 2

Immediately place a non-erodible dam in the upstreamend of the existing channel. Construct the dam asspecified in Figure 3.2.2 ,where a compacted earth bundhas shotcrete/ concrete placed, or appropriate geotextilepinned over it, with rock rip-rap extending over the upperface and adjacent to the lower face for scour protection.

Step 3

Immediately install a non-erodible downstream dam toprevent backflow into the construction area. Drain theexisting watercourse by pumping to a SedimentRetention Pond where treatment of the ponded watercan occur prior to re-entering the live section of thewatercourse. Construct the structure and complete allchannel work.

Step 4

Remove the downstream dam first, allowing water toflood back into the original channel. Remove theupstream dam and fill in both ends of the diversionchannel with non-erodible material. Pump any sediment-laden water to a Sediment Retention Pond. Fill in theremainder of the diversion and stabilise.

P r o p o s e dw a t e r c o u r s ed i ve r s i o n

Existing watercourse

Plug stil l tobe opened

F l o w

Existing watercourse

F l o w

New watercourse diver sion

D a m

D a m

Existing watercourse

F l o w

Watercour se diver sion

Proposed structure

S e d i m e n tr e t e n t i o np o n d

E x i s t i n gw a t e r c o u r s e

Location ofw a t e r c o u r s ed i ve r s i o n

F l o w

New structure

N e wr o a d

Page 91: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Wor ks Within a Watercourse: 3 5

Maintenance

Any works within a watercourse will require ongoingand vigilant maintenance to minimise sedimentgeneration. To achieve this, identify and correct any signsthat may indicate a potential problems. Take particularnotice of the following signs.

o The geotextile lining ripping.

o Scour occurring where the flow re-enters thechannel.

o Undercutting of the diversion lining.

Make repairs immediately.

Figure 3.2.2 Temporary Watercourse Diversion Dam Detail

Page 92: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Wor ks Within a Watercourse: 3 6

3.3 Rock Outlet Protection

Plate 3.3 Rock Outlet Protection

Definition

Rock placed at the outfall of channels or culverts.

Purpose

To break up concentrated flows, to reduce the velocityof flows to non erosive rates and to stabilise the outfallpoint.

Application

This practice applies where discharge velocities andenergies at the outlets of pipes, culverts or flumes aresufficient to cause erosion. This will apply to mostconcentrated flow outfalls and outlets of all types suchas sediment retention ponds, stormwater managementponds and road culverts.

Design

The following design does not apply to rock lining ofwatercourse channels. Detailed design of Rock OutletProtection depends on the location.

o Do not use ROP to protect pipe outlets at the top ofcuts or on slopes steeper than 10 % because theyreconcentrate flows and generate high velocitiesafter the flow leaves the apron.

o Ensure the channel containing the Rock OutletProtection is straight throughout its entire lengthand is constructed using rock rip rap or gabionbaskets/reno mattresses.

o Remove soft material down to a firm bed andsmooth and level the outfall area to eliminate voids.

Page 93: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Wor ks Within a Watercourse: 3 7

o Ensure rip rap is composed of a well graded mixtureof washed rock and has an appropriate geotextileplaced underneath it at all times to prevent soilmovement into and through the rip-rap.

o Construct gabion baskets of hexagonal twist meshwith heavy galvanised steel wire. Ensure foundationconditions for the gabion baskets/reno mattressesare the same as for rock rip rap and place filter clothbeneath all gabion baskets. In some circumstancesa key may be needed to prevent undermining of themain gabion structure.

o Design the structure in accordance with AucklandRegional Council approval and use materials withinthe relevant manufacturer’s and engineeringspecifications.

o Remember that works within a watercourse suchas the placement of rock rip rap or gabion basketsmay require a resource consent from the AucklandRegional Council. Contact the Council well aheadof time so that any consents needed may be obtainedbefore works are due to start.

Maintenance

Once installed, the maintenance requirements of the suchstructures is very low. Inspect after high flows to checkscour and dislodgement and make repairs immediately.

Page 94: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Quarries: 4 1

Quarries are potentially a major source of sediment.They are often exposed for long periods of time and thearea of bare earth can be considerable. Their continuousoperation means that site conditions continually change.Careful planning is required to ensure that the operationsare carried out with minimal environmental impact. Itis the responsibility of the quarry operator to minimisethe adverse environmental effects of the operation.

This section of these Guidelines is designed to help quarryoperators address soil and water problems which mayarise as a result of quarry operations. It should be readin conjunction with Part B, Sections 1 and 2 of theseGuidelines, which detail specific erosion and sedimentcontrol practices. Quarries are required to producemanagement plans covering the various aspects of theiroperation. These Guidelines will help in the productionof such plans.

The following specific issues associated with quarryoperations are discussed below.

o Road access

o Stormwater

o Overburden disposal

o Stockpile areas

o Rehabilitation of worked out areas

o Riparian protection areas

o Maintenance schedule for erosion and sedimentcontrol treatment structures

Road Access

Many quarries in the Auckland Region are serviced bymetal roads, used in all weather conditions. Vehiclemovements during rain can generate a lot of sediment.These roads, however, are not always within thedesignated quarry area and therefore, are not covered bythe Quarry Management Plan. Careful considerationneeds to be given to managing roads and traffic. In casessuch as these, erosion and sediment control measuresneed to be installed along roads as outlined in Part B,Sections 1 and 2 of these Guidelines.

Where possible, incorporate road access into the QuarryManagement Plan, ensuring all measures necessary areput in place to protect receiving environments.

Stormwater

Clean Runoff

As far as it is possible, divert clean water flow away fromworking and bare areas to prevent them from becomingcontaminated by sediment. This aids in reducing thevolume of contaminated runoff needing to be controlledand treated. Runoff Diversion Channels around theworking site, as outlined in Part B, Section 1.1, are thesimplest way to deal with the clean runoff.

Contaminated Runoff

Any runoff from bare areas will collect sediment andbecome contaminated. This contaminated runoff, whichincludes runoff from aggregate wash processes, must becontained and treated in an appropriate manner beforebeing discharged to natural watercourses. The QuarryManagement Plan must detail the methods forcontainment and treatment of all contaminated runoff.Particular attention should be paid to sensitive areas suchas permanent watercourses, watercourse crossings andsteeply sloping bare areas. Design all structures for the5% AEP rainfall event.

Overburden Disposal

Methods of overburden disposal vary for each quarryoperation. Overburden removal and disposal sites canbe a major source of erosion and sediment dischargesfrom quarries, particularly if the disposal site is notproperly located and managed. The Quarry ManagementPlan for the site should give a reasonable indication ofthe following.

o The timing and extent of overburden stripping,which will be related to an expected volume andarea of extraction.

o The methods to be employed for disposing theoverburden.

o Ongoing management of disposal sites, includingprovision for regular disposal of material trappedin sediment retention ponds.

If overburden disposal is dealt with in isolation from theQuarry Management Plan, consideration must be givento the following points.

Page 95: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Quarries: 4 2

o Selection of disposal site (why the site was chosen).

o Stability of the site and subsequent overburden fill(batter slopes, safety factors, benching, underlyingmaterial, drainage).

o Erosion and sediment control measures.

o Rehabilitation of disposal site (revegetation,contouring).

Stockpile Areas

Stockpile areas include those used for stockpiling bothraw or finished quarry products prior to furtherprocessing or final despatch. These areas can be a majorsource of contaminated runoff if not properly controlled.Position stockpiles well away from any watercourses andrunoff flow paths.

Rehabilitation of Worked Out Areas

Planning for rehabilitation must be an integral part ofall quarry operations. A properly planned andimplemented rehabilitation programme will reduce theneed for expensive ongoing erosion control, and controland treatment of contaminated runoff. The aim of siterehabilitation, whether temporary or permanent, is tomaintain the site in a condition such that erosion andcontaminated runoff are limited to an acceptable level.The prime areas for consideration are:

o establishing suitable final ground contours;

o establishing a suitable environment for vegetationgrowth;

o revegetating the site with suitable vegetation cover.

Riparian Protection Areas

Riparian protection areas rely on vegetation to providea buffer between the quarry operations and a water bodysuch as a watercourse or wetland. These margins act as aphysical barrier to keep machines away from sensitiveareas as well as serving as a last resort sediment trap fordiffuse runoff and/or unforeseen discharges. Do not,however, rely on riparian protection areas as a primarysediment control mechanism.

Maintenance Schedule for Erosion and SedimentControl or Treatment Structures

Because quarry operations continue over a very long timeframe, it is important to develop a maintenance schedulefor any control/treatment structures that are put in place.Money spent on designing and constructing control/treatment structures will be wasted if these structures arenot adequately maintained.

Properly maintained structures will provide optimumperformance at all times, thereby minimising the adverseenvironmental effects of the quarry operation.Conversely, poorly maintained structures are likely toresult in unsatisfactory environmental protection despitebeing initially well designed and constructed.

Develop a maintenance schedule for the site that clearlyindicates what is to be done in terms of visual inspectionsand maintenance works. Undertake routine maintenanceworks when they will cause the least possible detrimentalenvironmental effects (either directly or indirectly). Forexample, do not clean sediment retention ponds duringor immediately after rainfall events. To ensure that theoperation of the pond is not affected at these criticaltimes, maintenance should be done prior to events.

It is also particularly important that all control/treatmentstructures are inspected after significant rainfall events,or during prolonged rainfall, in addition to any regularscheduled inspections.

In the maintenance schedule include a procedure forimmediately repairing and remedying any damage causedto control/treatment structures from daily quarryactivities.

Within the overall quarry operation, give the inspectionand maintenance of control/treatment structures a highpriority. Ensure every person involved in the quarryoperation is familiar with all aspects of erosion andsediment control on the site, including any specialconditions of consents that are relevant. For example,specific water quality sampling requirements.

For all aspects of quarry operations where erosion andsediment controls are required, install the erosion andsediment control practices as specified in theseGuidelines.

Page 96: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Vegetation Removal: 5 1

Vegetation removal operations can be a major source ofsediment. They often involve earthworks associated withroading and landing (skid site) formation, as well as thedirect disturbance and exposure of the soil surface.Careful planning is required to ensure that theseoperations are carried out with minimal environmentalimpact.

This section of these Guidelines is designed to help peopleinvolved with vegetation removal operations to addresssoil and water problems which may arise as a result oftheir operation. This section should be read inconjunction with Part B, Sections 1 and 2 of theseGuidelines, which detail specific erosion and sedimentcontrol practices. Vegetation removal operations are alsorequired to produce Harvesting Management Plans thatcover the various aspects of their operation. TheseGuidelines can be used to assist in the production of theseplans.

Various specific issues associated with vegetation removaloperations are discussed below.

o Roading

o Firebreaks

o Landings and tracks

o Land preparation

o Harvesting and management after harvesting

Roading

Roading activities undertaken as part of vegetationremoval operations have a large potential impact on soiland water values.

Planning, Location and Design

o Locate roads on ridge tops, natural benches andflatter slopes, avoiding steep side slopes wherepossible.

o Do not locate roads in gully bottoms.

o Minimise gully crossings where possible.

o Locate roads a safe distance from watercourses andgullies.

o Do not discharge runoff directly to a watercourse,and where possible, ensure runoff is filtered throughvegetation.

o Where steep side cuts cannot be avoided, ensureadequate cross-formation drainage is installed andthat these channels flow onto stable or erosion proofareas such as spurs. Ensure they do not dischargeonto areas of soft fill.

Construction

o Where construction operations are to beundertaken in erosion-prone areas or adjacent to awatercourse, use an excavator to enable soil andother loose material to be placed in a stableposition.

o Do not bulldoze loose material into watercoursesor areas where it may wash into watercourses.

o Keep machines out of watercourses and minimisethe number of crossings.

o If operations are suspended, put adequate drainageprovisions in place to avoid concentration of runoffand scour problems until work resumes.

o Stabilise cut and fill slopes where required, usingmeasures such as hydroseeding and straw mulching.

o Install contour drains and flumes to preventscouring.

o Flume or pipe runoff to solid ground and thendischarge onto logging slash, gravel, rock rip-rap,or geotextiles.

o Plan the operational sequence of installing culvertsand bridges across watercourses. Ensure allmaterials, machinery and labour are on hand beforecommencing construction.

o Ensure that the supervision of culvert and bridgeinstallations is carried out by a suitably experiencedperson.

o Complete the construction of watercoursecrossings, approach roads and associated erosionand sediment control measures as a continuousoperation.

Page 97: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Vegetation Removal: 5 2

Firebreaks

o Locate firebreaks to minimise the possibility ofdebris entering watercourses.

o Keep earthworks associated with firebreaks clearof steep drop-offs and watercourses. Considerationmust be given to the erosion potential of tracksformed along gully bottoms. These areas should beavoided.

o Maintain firebreaks to a reasonable standard tocontrol runoff, rilling and gully erosion.

o Construct contour drains as required.

o Avoid ponding of water above steep drop-offs and,if ponding occurs, implement an appropriatedrainage design to prevent gully erosion.

o At the completion of operations, check firebreaksfor any potential erosion problems.

Landings and Tracks

Landings and tracks are generally permanent featuresand therefore require careful location preparation,direction of fall and control of runoff. Skid tracks, whilegenerally more of a temporary feature, also requirecareful consideration of the above.

Any tracking results in concentration of runoff andconsequently, an increase in erosion. Minimise erosionby tracking across contours and where possible, locatingtracks on ridges rather than in gullies.

Ensure that extraction tracks do not lead directly downtowards watercourses where runoff may go directly intothe channel.

Where possible try to keep skid tracks and landings atleast 20 o away from watercourses.

At the completion of logging operations, constructcontour drains across skid tracks wherever runoff maybe concentrated. Ensure that contour drains dischargeto solid ground and not to areas of fill.

Keep landings well clear of permanent watercourses.Where no alternative exists, ensure that the watercourseis not obstructed. Form all landings so that surface runoffdoes not flow down towards or directly into awatercourse. Construct earth bunds along watercourseedge boundaries to prevent debris and sediment fromentering watercourses. Extra caution must also beexercised in the planning and construction measures

which control water flowing off skid tracks onto landings,so as to minimise water runoff onto the landing.

Take extra caution when forming landings within drygullies. Where this is done, ensure the following.

o A slash is placed across the gully floor to act as asediment barrier.

o Fill batters are sown with a suitable vegetation cover.

Land Preparation

Planning

Plan and implement all land preparation and forestestablishment to match an appropriate proposed methodof harvesting.

Protection Areas (Riparian Margins)

Retain or establish protection areas along all watercourses.Where protection areas do not exist, they can beestablished in conjunction with the following operations.

o Land clearing or site preparation on areas beingconverted to production forestry.

o Planting on farm land or similar sites.

o Replanting on exotic clearfelled areas.

o Vegetation removal on terrain which may bedifficult, very steep or erosion prone.

Re-evaluate all existing protection areas when harvestingor replanting adjacent to production stands.

Generally, protection areas can be left to regeneratenaturally. However, in some cases it may be appropriateto accelerate revegetation by actively planting protectionspecies.

Planting Boundaries

When re-planting, establish planting boundaries adjacentto watercourses in order to minimise potentialwatercourse damage from future harvesting operations.Establish planting boundaries on a ‘case by case’ basis withconsideration to both topography and soil stability.

V-Blading/Line Raking

Where possible operate across the contour, to minimiserunoff concentration down the blade lines.

Where downhill runs are unavoidable, limit them to 50o maximum length. Do not attempt these runs on slopestoo steep for the tractor to reverse up. Blade or rake at

Page 98: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Vegetation Removal: 5 3

least one line on the contour along the lower boundaryof downhill operations to prevent runoff concentrationat low points or gully systems. Finish downhill runs wellbefore any fill batter slopes such as landings and accessroads.

Near watercourses, ensure the operation runs parallel tothem at a minimum distance of 20 o. At the completionof the operation, inspect the site for areas of erosionpotential and undertake appropriate remedial action.

Establishing and Tending

During establishing and tending stages, minimise soil lossand prevent contamination of watercourses withchemicals, fertilisers, debris or detritus and.

During thinning to waste operations, fell trees away fromwatercourses where possible.

Harvesting and Management After Harvesting

Planning of Logging Operations

Plan all logging operations, particularly the location ofskid tracks and roads, to protect water and soil values.

Off-site adverse effects must be avoided or minimisedwhen determining the ability and management of acatchment to be harvested. When harvesting nearsensitive areas, extract towards landings located awayfrom them.

Felling Operations

When trees are being felled within reach of a watercourse,ensure an experienced feller is in control of the operation.Where possible, fell trees away from watercourses. Extractany trees that have fallen into watercourses beforedelimbing and cross cutting them. Back pull, or employother acceptable directional felling techniques to fellproblem trees, particularly on steep or unstablewatercourse faces and edges. Remove all large loggingdebris from watercourses at the completion of theoperation, keeping machinery out of the watercourse.

Extraction Operations

o Ground Based Systems

- Keep tracking and stumping activities to apractical minimum. Use a few carefully chosentracks and stay on these rather than takingshortcuts which cause unnecessary grounddisturbance.

- Carry logs off the ground or on the machinewhere possible.

- Keep the machines blade up and do notbulldoze soil and stumps needlessly.

- Do not cross watercourses (other than atapproved crossing points) and do not haulalong them.

- On soft and/or wet soils or steeper slopes, uselow-ground-pressure machines such asflexible-track or wide-tyre skidders.

o Cable Systems

- Where cable systems are used inenvironmentally sensitive areas, keep thesettings small, the haul distances short and thehauling direction uphill wherever practicable.Avoid cross slope haul lines that damageprotection areas or sweep slash and soil intowatercourses.

- Whenever possible when hauling acrosswatercourses, use a system such as a skylinewhich allows full suspension of logs. Lift logsclear of watercourse banks and protectionareas.

Cleanup Operations

On completion of logging operations, carry out thefollowing procedures.

o Remove all temporary crossings.

o Construct contour drains on skid tracks to preventrunoff concentration and sediment flow.

o Ensure landings are properly drained and thatsediment and debris are unable to directly enter anywatercourse.

o Stabilise fill batters on landings and tracks bysowing with suitable grass seed.

o Ensure runoff is channelled safely over batter slopesand onto stable areas.

On all aspects of vegetation removal operations whereerosion and sediment controls are required, install theerosion and sediment control measures as specified inthese Guidelines.

Page 99: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Appendix: A 1

Rules from Proposed Regional Plan: Sediment Control

Table A Permitted Activities

Type of Activity Within the Sediment Outside the Sediment

Control Protection Area Control Protection Area

Vegetation Removal

o On Sand Soils Area less than 0.25 ha All vegetation removal

o On all Soils other than Sand Soils Area less than 0.25 ha Area less than 10.0 ha

Earthworks

o On all Soils Area less tha 0.25 ha Area less than 1.0 ha where the land

has a slope less than 15o

Area less than 0.25 ha where

the land has a slope equal

to or greater than 15o

Roading/Tracking/Trenching

o On Sand Soils Length less than 100 o All roading, tracking and trenching.

o On Soils other than Sand Soils Length less than 100 o Area less than 1.0 ha where the

land has a slope less than 15o

Area less than 0.25 ha where the land

has a slope equal to or greater than 15o

Quarries

o Where no runoff leaves the All quarries All quarries

site and no wash process on site

o Remainder where runoff leaves Quarry area less than Quarry area less than

the site and/or there are wash 1000 m2 and/or less than 1000 m2 and/or less than

processes on site 1.0 ha catchment 1.0 ha catchment

Note(1) Sediment Control Protection Area is defined as:

a) 100 metres either side of a foredune or 100 metres landward of the coastal marine area

(whatever is the more landward of mean high water springs); or

b) 50 metres landward of the edge of a watercourse, or wetland of 1000 m2 or more.

Page 100: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Appendix: A 2

Table B Controlled Activities

Type of Activity Outside the Sediment Control Protection Area

Vegetation Removal

o On soils other than Sand Soils Area greater than or equal to 10.0 hectares

where the land has a slope less than 15o

Earthworks

o On all soils including Sand Soils Area between 1.0 and 5.0 hectares

where the land has a slope less than 15o

Roading/Tracking/Trenching

o On Soils other than Sand Soils Area between 1.0 and 5.0 hectares where the

land has a slope less than 15o

Note(1) Sediment Control Protection Area is defined as:

a) 100 metres either side of a foredune or 100 metres landward of the coastal marine area

(whatever is the more landward of mean high water springs); or

b) 50 metres landward of the edge of a watercourse, or wetland of 1000m2 or more.

Page 101: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Appendix: A 3

Table CRestricted Discretionary Activities

Type of Activity Within the Sediment Control Outside the Sediment Control

Protection Area Protection Area

Vegetation Removal

o On sand soils Area greater than or equal to 0.25 ha (Refer to Table A – Permitted Activities)

o On all Soils other than Sand Soils Area greater than or equal to 0.25 ha Area greater than or equal to 10.0 ha

on land with a slope greater than

or equal to 15o

E a r t h wo r k s

o On all Soils including Sand Soils Area greater than or Area greater than or equal to 5.0 ha

equal to 0.25 ha on land with a slope less than 15o

Area greater than or equal to 0.25 ha

on land with a slope greater than

or equal to 15o

Ro a d i n g / Tr a c k i n g / Tr e n c h i n g

o On Sand Soils Length of 100 o or more (Refer to Table A – Permitted Activities)

o On soils other than sand soils Length of 100 o or more Area greater than or equal to 5.0 ha

where the land has a slope less than 15o

Area greater than or equal to 0.25 ha

where the land has a slope greater to

or equal to 15o

Q u a r r i e s

o Where runoff leaves the Quarry area of 1000 m2 or Quarry area of 1000 m2 or more and/or

site and/or there are wash more and/or with a catchment with a catchment of 1.0 ha or more

processes on site of 1.0 ha or more

Note(1) Sediment Control Protection Area is defined as:

a) 100 metres either side of a foredune or 100 metres landward of the coastal marine area

(whatever is the more landward of mean high water springs); or

b) 50 metres landward of the edge of a watercourse, or wetland of 1000 m2 or more.

Page 102: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Appendix – Application Forms: B 4

Land Use ConsentSediment Control and Land Use Consent

Works Within a Watercourse

Land Use Consent: Sediment Control

To: Consent ServicesAuckland Regional CouncilPrivate Bag 92012AucklandPh: (09) 379 4420Fax: (09) 366 2155

Pursuant to Section 88 of the Resource Management Act 1991, the undersigned hereby applies for a consent, inaccordance with the details below:

(All units should be in metric)

Name of Site: ___________________________________ Amount forwarded with this application: $ _________

PART A – APPLICANT DETAILS

1. Applicant Details

a) Full name(s) or company name of applicant(s): _______________________________________________

b) Postal address: _________________________________________________________________________

c) Telephone number: Business: ____________________ Fax number: ______________________________

d) Name of contact person: _________________________________________________________________

e) Nature of applicant (tick as appropriate): ο Owner ο Other (specify) ___________________

2. Consultant/Agent Details (if applicable)

a) Name: _______________________________________________________________________________

b) Postal Address: ________________________________________________________________________

c) Telephone number: _______________________ Fax number: _________________________________

d) Name of contact person: _________________________________________________________________

3. Site Engineer (if applicable)

a) Name: _______________________________________________________________________________

b) Postal address: ________________________________________________________________________

c) Telephone number: _______________________ Fax number: _________________________________

For Office Use Only: 12/93

Consent No.:

Fee: $

Page 103: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Appendix – Application Forms: B 5

Land Use ConsentSediment Control and Land Use Consent

Works Within a Watercourse

4. All correspondence relating to this application should be sent to:

Applicant: ο Consultant/Agent ο Other (give details): ___________________________

5. In which Territorial Authority (TA) is the proposal situated?

ο Rodney ο North Shore ο Auckland ο Waitakere

ο Manukau ο Franklin ο Papakura

6. Are there any previous or existing consents already granted related to this proposal?

ο Yes ο No

If yes, give reference number(s) and description (e.g. Stormwater Discharge Consent Br XXXXX):

TA: _____________________________ Regional Council: ________________________________________

7. Are there any further consents required from TA/Regional Council?

ο Yes ο No

Name of consent authority: __________________________________________________________________

Name of Consent Authority: __________________________________________________________________

Have these consents been applied for? ο Yes ο No

If yes, what is the status of these consents? _______________________________________________________

PART B – SITE DETAILS

1. Type of Development

________________________________________________________________________________________(e.g. quarry, residential subdivision, roadworks, cleanfill, forestry operation, etc)

2. Programme

a) Work commencement date: _____________________________________________________ 19 _____

b) Work completion date: _________________________________________________________ 19 _____

c) Requested expiry date of consent: _________________________________________________ 19 _____

Page 104: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Appendix – Application Forms: B 6

Land Use ConsentSediment Control and Land Use Consent

Works Within a Watercourse

3. Site Details

a) Total property area (ha): _________________________________________________________________

b) Location – address and legal description: ____________________________________________________

____________________________________________________________________________________(give full legal description, e.g. certificate of title, survey district, lot number – attach certificate of title search)

c) Zoning of area under District Plan: ________________________________________________________

d) Map reference: ________________________________________________________________________[Use NZMS 260 (1:50,000), or for urban localities NZMS 271 (1:20,000), eg. R11 672814]

e) Water body into which runoff will be discharged: _____________________________________________

4. Site Size

a) Total area of bare ground on site (accumulative total through development period): __________________

b) Total length of site (roading, trenching, tracking only): _________________________________________

c) Volume of proposed earthworks: __________________________________________________________

PART C – OPERATION

1. Management Plan

Please supply an erosion and sediment control plan for the operation. This should be done in conjunction withthe required Assessment of Effects (Part D). Details to be included in the erosion and sediment control planshould be appropriate to the scale of operation, but should generally include the following:

ο Detailed location map including boundaries, location of stream, roads, etc.(Ensure the map includes a scale bar).

ο Site description, ie topography, vegetation, soils, etc.

ο Details of proposed activity, eg. proposed quarrying, vegetation removal or cleanfill operation.

ο Details of plans (with a scale bar) to avoid sediment removal off site (including drawings, specificationsand supporting calculations). (Please provide 2 copies):

- erosion control

- sediment control

- work programme details (eg. timing, scheduling of works, etc).

ο Details of any stream crossing – type of crossing, size, etc, and measures taken to avoid sediment impact.

ο Rehabilitation details.

Page 105: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Appendix – Application Forms: B 7

Land Use ConsentSediment Control and Land Use Consent

Works Within a Watercourse

ο Details of proposed monitoring measures to assess/demonstrate effectiveness of control measures.

ο Details of any other measures designed to reduce impact on the environment.

2. Vegetation Removal

a) Purpose of land clearing operation: ________________________________________________________

b) Area of land in native vegetation: (specify type) _______________________________________________

Area of land in native scrub: ______________________________________________________________

Area of land in other: ___________________________________________________________________

c) Proposed method (eg. tractor, hauler, crushing, spraying): ______________________________________

d) Proposed use or management of the area following operation: ___________________________________

3. Earthworks (includes roadworks, etc)

a) Runoff control:- diversions around site (attach design details)- on-site (attach details)

b) Sediment control:

i) Sediment retention ponds. Please complete the table below. Attach details on pond design includingspillway and dewatering measures. Show catchment boundaries and pond location on managementplan.

Catchment Construction Catchment Area Sediment PondPond No. Period (Stage) (hectares) Volume (m3)

ii) Silt fences (specify with design details)

iii) Stormwater inlet protection (specify with design details)

iv) Other (specify with design details)

Will sediment control measures vary during the project? (eg. roading and stormwater drainage develops).

ο Yes ο No

If yes, then please provide measures of progressive runoff and sediment control methods proposed.

Page 106: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Appendix – Application Forms: B 8

Land Use ConsentSediment Control and Land Use Consent

Works Within a Watercourse

4. Quarries and Cleanfills

a) Runoff control

- diversion around site (attach details)

- on-site (attach details)

b) Sediment control

- sediment retention ponds (as for 3(b)(i))

- chemical treatment of runoff as appropriate (attach design details)

c) Fill/dump sites

- details on stability and compaction of fill and overburden dumps and associated land

- runoff control and drainage

- sediment control and revegetation details

d) Process water

- attach details of operation and discharge

5. Revegetation

Specify with seed/fertiliser mix and timing. Hydrology and mulching also needs to be specified.

PART D – ASSESEMENT OF EFFECTS ON THE ENVIRONMENT

(Reference must be made to Assessment of Environmental Effects Guideline for Land Disturbing Activities)

NB. It is recommended that the applicant consults with the Tangata Whenua prior to submitting an application for aLand Use Consent: Sediment Control.

1. Matters that should be included in an Assessment of Effects on the environment

Subject to the provisions of any policy statement or plan, an assessment of effects on the environment for thepurposes of section 88(6)(b) should include:

a) A description of the proposal.

b) Where it is likely that an activity will result in any significant adverse effect on the environment, adescription of any possible alternative locations or methods for undertaking the activity.

c) An assessment of the actual or potential effect on the environment of the proposed activity.

d) Where the activity includes the use of hazardous substances and installations, an assessment of any risks tothe environment which are likely to arise from such use.

Page 107: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Appendix – Application Forms: B 9

Land Use ConsentSediment Control and Land Use Consent

Works Within a Watercourse

e) Where the activity includes the discharge of any contaminant, a description of:

i) The nature of the discharge and the sensitivity of the proposed receiving environment to adverseeffects; and

ii) Any possible alternative methods of discharge, including discharge into any other receivingenvironment.

f) A description of the mitigation measures (safeguards and contingency plans where relevant) to beundertaken to help prevent or reduce the actual or potential effect.

g) An identification of those persons interested in or affected by the proposal, the consultation undertaken,and any response to the views of those outlined.

h) Where the scale or significance of the activity’s effect are such that monitoring is required, a description ofhow, once the proposal is approved, effects will be monitored and by whom.

2. Matters that should be considered when preparing an assessment of effects on the environment

Subject to the provisions of any policy statement or plan, any persons preparing an assessment of the effects onthe environment should consider the following matters:

a) Any effect on those in the neighbourhood and, where relevant, the wider community including any socio-economic and cultural effects.

b) Any physical effect on the locality, including any landscape and visual effects.

c) Any effect on ecosystems, including effects on plants or animals and any physical disturbance of habitats inthe vicinity.

d) Any effect on natural and physical resources having aesthetic, recreational, scientific, historical, spiritual, orcultural, or other special value for present or future generations.

e) Any discharge of contaminants into the environment, including any unreasonable emission of noise andoptions for the treatment and disposal of contaminants.

f) Any risk to the neighbourhood, the wider community, or the environment through natural hazards or theuse of hazardous substances or hazardous installations.

Page 108: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Appendix – Application Forms: B 1 0

Land Use ConsentSediment Control and Land Use Consent

Works Within a Watercourse

PART E - CHECK LIST

Have you remembered to: Yes

a) Fully complete this application form ____________________________________________________ ο

b) Include a location plan (with scale bar) __________________________________________________ ο

c) Include design calculations for erosion and sediment control _________________________________ ο

d) Include an erosion and sediment control plan _____________________________________________ ο

e) An Assessment of Environmental Effects (see Guideline) _____________________________________ ο

f) Include written approval from all affected persons __________________________________________ ο

g) Pay the application fee ________________________________________________________________ ο

List any other supporting information supplied with this application, eg. archaeological assessments, technicalspecifications, consultation documents, etc.

____________________________________________________________________________________________

____________________________________________________________________________________________

____________________________________________________________________________________________

____________________________________________________________________________________________

____________________________________________________________________________________________

____________________________________________________________________________________________

Signature of Applicant or Agent:_____________________________________________ Date: ________________

Name (block capitals): _________________________________________________________________________

Designation: (eg. Owner, Manager, Consultant) ______________________________________________________

Please attach your Deposit Fee payment to this application. Make cheques payable to ‘Auckland Regional Council’.

Refer to the deposit fee schedule for details.

Page 109: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Appendix – Application Forms: B 1 1

Land Use ConsentSediment Control and Land Use Consent

Works Within a Watercourse

Application for Consent to Undertake Works in a Watercourse or Lake(Section 13 of the Resourse Management Act)

To: Consent ServicesAuckland Regional CouncilPrivate Bag 92012AucklandPh: (09) 379 4420Fax: (09) 366 2155

Pursuant to Section 88 of the Resource Management Act 1991, the undersigned hereby applies for a consent, inaccordance with the details below:

(All units should be in metric)

Name of Site: ___________________________________ Amount forwarded with this application: $ _________

PART A – APPLICANT DETAILS

1. Applicant Details

a) Full name(s) or company name of applicant(s): _______________________________________________

b) Postal address: _________________________________________________________________________

c) Telephone number: Business: ____________________ Fax number: ______________________________

d) Name of contact person: _________________________________________________________________

e) Nature of applicant (tick as appropriate): ο Owner ο Other (specify) ___________________

2. Consultant/Agent Details (if applicable)

a) Name: _______________________________________________________________________________

b) Postal Address: ________________________________________________________________________

c) Telephone number: _______________________ Fax number: __________________________________

d) Name of contact person: _________________________________________________________________

3. Site Engineer (if applicable)

a) Name: _______________________________________________________________________________

b) Postal address: _________________________________________________________________________

c) Telephone number: _______________________ Fax number: __________________________________

For Office Use Only: 12/93

Consent No.:

Fee: $

Page 110: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Appendix – Application Forms: B 1 2

Land Use ConsentSediment Control and Land Use Consent

Works Within a Watercourse

4. All correspondence relating to this application should be sent to:

Applicant: ο Consultant/Agent ο Other (give details): ___________________________

5. In which Territorial Authority (TA) is the proposal situated?

ο Rodney ο North Shore ο Auckland ο Waitakere

ο Manukau ο Franklin ο Papakura

6. Are there any previous or existing consents already granted related to this proposal?

ο Yes ο No

If yes, give reference number(s) and description (e.g. Land Use Consent: Sediment Control Sc11111):

TA: _____________________________ Regional Council: _________________________________________

7. Are there any further consents required from TA/Regional Council?

ο Yes ο No

Name of consent authority: __________________________________________________________________

Name of Consent Authority: __________________________________________________________________

Have these consents been applied for? ο Yes ο No

If yes, what is the status of these consents? _______________________________________________________

PART B – SITE DETAILS

1. Type of Development

________________________________________________________________________________________(e.g. bridge construction, channel lining/works, diversion)

2. Programme

a) Work commencement date: _____________________________________________________ 19 _____

b) Work completion date: _________________________________________________________ 19 _____

c) Requested expiry date of consent: _________________________________________________ 19 _____

Page 111: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Appendix – Application Forms: B 1 3

Land Use ConsentSediment Control and Land Use Consent

Works Within a Watercourse

3. Site Details

a) Total property area (ha): _________________________________________________________________

b) Location – address and legal description: ____________________________________________________

____________________________________________________________________________________(give full legal description, e.g. certificate of title, survey district, lot number – attach certificate of title search)

c) Zoning of area under District Plan: ________________________________________________________

d) Map reference: ________________________________________________________________________[Use NZMS 260 (1:50,000), or for urban localities NZMS 271 (1:20,000), eg. R11 672814]

e) Water body into which runoff will be discharged: _____________________________________________

f) Total length of works: ___________________________________________________________________

g) Will chemicals or toxic substances be used on the site? ο Yes ο No

If yes, please provide details: ______________________________________________________________

4. Name of watercourse or natural water on which the works will take place:

Name: _________________________________ or Tributary of:_____________________________________

River Number (office use only)

5. Summary of flow information for works in a watercourse (not required for lakes):

a) Area of catchment contributing to the flow at the site: __________________________ ha _____________

b) i) _______________________ Calculation of 1% Annual Exceedance Probability (AEP) at the site. If yourmethod of calculation is the Rational formula, complete the following table.

Area (ha) Design Runoff Coefficient

Undeveloped: Left in natural state

Developed: Grassed, cultivated

Developed, impervious surfaces; roads, carparks, roofed

Other: Please specify

ii) Time of concentration at site: _______________________________ mins ____________________

iii) Design rainfall intensity corresponding to storm of 1% AEP: ______ mm/hr __________________

iv) Location of the rainfall station and how the intensity data was derived from its records: ___________

________________________________________________________________________________

v) 1% AEP design flow at site: _________________________________ m3/s _____________________

Page 112: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Appendix – Application Forms: B 1 4

Land Use ConsentSediment Control and Land Use Consent

Works Within a Watercourse

c) If your method of flow calculation is other than the Rational formula:

i) State the method: __________________________________________________________________

ii) 1% AEP design discharge: ______________________________________ m3/s _________________

iii) Provide details of calculations on a separate sheetd) _______________________________ Estimate of 1% AEP flood level at site:___________________________________ RL (ο) ____________

________________________________ Provide details of method used for estimated on a separatesheet.

6. Is the work going to be completed in stages?

ο Yes ο No

7. Supporting information

a) Names and addresses of all property owners/occupiers immediately upstream and downstream of the site,and any other party who may be affected by the proposed works.

b) An accurate plan (drawn to scale and with a scale bar) showing the location of the site, the immediatedownstream and upstream properties listed in (a) above, and any other relevant features. Please provide areduced copy of the plan in A3 size (42cm x 30cm) which we can use to notify affected parties.

c) A full set of plans showing the works. Please provide a reduced copy of the plans in A3 size (42cm x 30cm)which we can use to notify affected parties.

PART C – OPERATION

1. Management Plan

Please supply an erosion and sediment control plan for the operation. This should be done in conjunction withthe required Assessment of Effects (Part D). Details to be included in the erosion and sediment control planshould be appropriate to the scale of operation, but should generally include the following:

ο Detailed location map including boundaries, location of stream, roads, etc.(Ensure the map includes a scale bar).

ο Site description.

ο Details of plans (with a scale bar) to avoid sediment removal off site (including drawings, specificationsand supporting calculations). (Please provide 2 copies):

- erosion control

- sediment control

- work programme details (eg. timing, scheduling of works, etc).

Page 113: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Appendix – Application Forms: B 1 5

Land Use ConsentSediment Control and Land Use Consent

Works Within a Watercourse

ο Rehabilitation details.

ο Details of proposed monitoring measures to assess/demonstrate effectiveness of control measures.

ο Details of any other measures designed to reduce impact on the environment.

PART D – ASSESEMENT OF EFFECTS ON THE ENVIRONMENT

(Reference must be made to Assessment of Environmental Effects Guideline for Land Disturbing Activities)

NB. It is recommended that the applicant consults with the Tangata Whenua prior to submitting an application for aLand Use Consent: s13.

1. Matters that should be included in an Assessment of Effects on the environment

Subject to the provisions of any policy statement or plan, an assessment of effects on the environment for thepurposes of section 88(6)(b) should include:

a) A description of the proposal.

b) Where it is likely that an activity will result in any significant adverse effect on the environment, adescription of any possible alternative locations or methods for undertaking the activity.

c) An assessment of the actual or potential effect on the environment of the proposed activity.

d) Where the activity includes the use of hazardous substances and installations, an assessment of any risks tothe environment which are likely to arise from such use.

e) Where the activity includes the discharge of any contaminant, a description of:

i) The nature of the discharge and the sensitivity of the proposed receiving environment to adverseeffects; and

ii) Any possible alternative methods of discharge, including discharge into any other receivingenvironment.

f) A description of the mitigation measures (safeguards and contingency plans where relevant) to beundertaken to help prevent or reduce the actual or potential effect.

g) An identification of those persons interested in or affected by the proposal, the consultation undertaken,and any response to the views of those outlined.

h) Where the scale or significance of the activity’s effect are such that monitoring is required, a description ofhow, once the proposal is approved, effects will be monitored and by whom.

Page 114: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Appendix – Application Forms: B 1 6

Land Use ConsentSediment Control and Land Use Consent

Works Within a Watercourse

2. Matters that should be considered when preparing an assessment of effects on the environment

Subject to the provisions of any policy statement or plan, any persons preparing an assessment of the effects onthe environment should consider the following matters:

a) Any effect on those in the neighbourhood and, where relevant, the wider community including any socio-economic and cultural effects.

b) Any physical effect on the locality, including any landscape and visual effects.

c) Any effect on ecosystems, including effects on plants or animals and any physical disturbance of habitats inthe vicinity.

d) Any effect on natural and physical resources having aesthetic, recreational, scientific, historical, spiritual, orcultural, or other special value for present or future generations.

e) Any discharge of contaminants into the environment, including any unreasonable emission of noise andoptions for the treatment and disposal of contaminants.

f) Any risk to the neighbourhood, the wider community, or the environment through natural hazards or theuse of hazardous substances or hazardous installations.

PART E - CHECK LIST

Have you remembered to: Yes

a) Fully complete this application form ____________________________________________________ ο

b) Include a location plan (with scale bar) __________________________________________________ ο

c) Include design calculations for erosion and sediment control _________________________________ ο

d) Include an erosion and sediment control plan _____________________________________________ ο

e) An Assessment of Environmental Effects (see Guideline) _____________________________________ ο

f) Include written approval from all affected persons __________________________________________ ο

g) Pay the application fee ________________________________________________________________ ο

Page 115: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Appendix – Application Forms: B 1 7

Land Use ConsentSediment Control and Land Use Consent

Works Within a Watercourse

List any other supporting information supplied with this application, eg. archaeological assessments, technicalspecifications, consultation documents, etc.

____________________________________________________________________________________________

____________________________________________________________________________________________

____________________________________________________________________________________________

____________________________________________________________________________________________

____________________________________________________________________________________________

____________________________________________________________________________________________

Signature of Applicant or Agent:_____________________________________________ Date: ________________

Name (block capitals): _________________________________________________________________________

Designation: (eg. Owner, Manager, Consultant) ______________________________________________________

Please attach your Deposit Fee payment to this application. Make cheques payable to ‘Auckland Regional Council’.

Refer to the deposit fee schedule for details.

Page 116: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Appendix: C 1 8

Runoff Diversion Channel/Bund

Contour Drain

Benched Slope

Rock Check Dam

Top Soiling

Temporary Seeding

Permanent Seeding

Hydroseeding

Mulching

Turfing

Geosynthetic Erosion Control Systems

Stabilised Construction Entrance

Standard Symbols for Erosion and Sediment Controls

Page 117: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council Appendix: C 1 9

Pipe Drop Structure/Flume

Level Spreader

Surface Roughening

Sediment Retention Pond

Silt Fence

Super Silt Fence

Hay Bale Barrier

Stormwater Inlet Protection

Earth Bund

Sump/Sediment Pit

Temporary Watercourse Crossing

Temporary Watercourse Diversion

Rock Outlet Protection

Page 118: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council G l o s s a r y 1

(AEP) Annual Exceedance Probability

A statistical term defining the probability of an eventoccurring annually. Expressed as a percentage andgenerally used in hydrology to define rainstorm intensityand frequency. For example, a 5% AEP event has a 5%chance of being exceeded in any one year. This hasreplaced the return period concept. A 5% AEP eventexpresses the 20 year return period in more probabilityterms.

Antiseep Collar

An impermeable barrier, usually of concrete, constructedat intervals within the zone of saturation along theconduit of a primary outlet pipe to increase the seepagelength along the conduit and thereby prevent piping orseepage in the compacted fill material along the outsideof the pipe.

Area of Disturbance

The area of exposed soil.

Baffles

Semi-permeable or solid barriers placed in a sedimentretention pond to deflect or regulate flow and effect amore uniform distribution of velocities, hence creatingbetter settling conditions.

Batter

A constructed slope of uniform gradient.

Berm

Narrow strip beside road.

B P O

Best Practicable Option.

Bulk Ear thworks

This term is generally used to describe the cut to fillearthworks required to regrade an area. It also applies tolarger scale earthworks such as for building excavations.

Catchment

A geographical unit within which surface runoff is carriedunder gravity by a single drainage system to a commonoutlet or outlets. Also commonly referred to as aWatershed or Drainage Basin.

Channel

That part of a watercourse system where normal flow iscontained. The channel is generally incised into the floodplain and for many of the stable stream systems in NewZealand can be defined in capacity as being just able toaccommodate the annual return period flow (100% AEP)without overtopping.

Also refers to an artificial conduit such as a ditchexcavated to convey water.

Channel Stabilisation

Stabilisation of the channel profile by erosion controland/or velocity distribution through reshaping, the useof structural linings, mass blocks, vegetation and othermeasures.

Channel Storage

The amount of water temporarily stored in channelswhile en route to an outlet.

Clay (Soils)

A mineral soil consisting of particles less than 0.002 mmin equivalent diameter.

A soil texture class.

Clean Water

Any water that has no visual signs of suspended solids,e.g. overland flow (sheet or channelled) originating fromstable well-vegetated or armoured surfaces.

Cohesion

The capacity of a soil to resist shearing stress, exclusiveof functional resistance.

Cohesive Soil

A soil that, when unconfined, has considerable strengthwhen air-dried and significant cohesion whensubmerged.

Compaction

For construction work in soils, engineering compactionis any process by which the soil grains are rearranged todecrease void space and bring them into closer contactwith one another, thereby increasing the weight of solidmaterial per unit of volume, increasing their shear andbearing strength and reducing permeability.

Page 119: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council G l o s s a r y 2

Concentrated Flow

The accumulation of sheet flow into discrete rills, gulliesor channels, significantly increasing erosive forces.

Conduit

Any channel intended for the conveyance of water,whether open or closed.

Construction Staging - The phasing of bulk earthworksto minimise the area of bare earth exposed at any onetime.

Contour

A line across a slope connecting points of the sameelevation.

Contributing Drainage Area

All of that drainage area that contributes to the flow intoa treatment device. A contributing drainage area caninclude both clean and sediment-laden water flows.Commonly referred to as the catchment area.

Crimping

The embedding of straw mulch into the soil surface byusing implements such as a disc cultivator set at zerocut.

Critical 20 Year Return Period Storm

A rainfall event that has a 5% Annual ExceedanceProbability and a duration equal to the Time ofConcentration.

Cumulative Effect

The combination of discrete isolated effects, the sum ofwhich can have a major long term detrimental impact.

D a m

A barrier to confine or raise water for storage ordiversion, to create a hydraulic head, to prevent gullyerosion, or to retain soil, rock or other debris.

Decant Rate

The rate at which surface water is decanted from asediment retention pond.

Deposition

The accumulation of material that has settled because ofreduced velocity of the transporting agent (water orwind).

Detention Dam

A dam, constructed for the temporary storage of stormflow, which releases the stored water at controlled ratesin order to reduce flooding hazard downstream of thedam.

Dewatering

The removal of impounded water, generally by pumping.Refer Sump Pit.

Di-ammonium phosphate (DAP)

A high percentage nitrogen and phosphate fertilisersuitable for the rapid establishment of grass.

Disturbed Area

An area of exposed soil.

Diversion

A channel or bund constructed to convey concentratedflow.

Drainage

The removal of excess surface water or groundwater fromland by means of surface or subsurface drains.

Drainage Basin

Refer Catchment.

Emergency Spillway

A Sediment Retention Pond or Dam spillway designedand constructed to discharge flow in excess of thestructure’s primary spillway design discharge.

Energy Dissipator

A designed device such as an apron of rip-rap or aconcrete structure placed at the end of a water conduitsuch as a pipe, paved ditch or flume for the purpose ofreducing the velocity and energy of the discharged water.

Page 120: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council G l o s s a r y 3

Ephemeral Watercourse

A watercourse that flows only part of the year; includesoverland flowpaths such as grassland swales and drygullies which only flow during more intensive rainstorms.

Erodible

An erodible soil is a soil that is readily entrained (moved)by actions such as rain drop impact, overland flow orwind.

Erosion and Sediment Control Plan (E&SCP)

A detailed Plan normally prepared by the Developer’sengineer that details the way erosion is to be minimisedand treatment of sediment-laden overland flow is to beundertaken.

Erosion Matting

A manufactured matting of either synthetic or naturalfibre used to minimise surface erosion and in some cases,promote revegetation.

Erosive

Refers to the ability of erosional agents such as wind orwater to cause erosion. Not to be confused with erodible,as a quality of soil.

Erosive Velocities

Velocities that are high enough to wear away the landsurface. Exposed soils erode faster than stabilised soils.Erosive velocities vary according to the soil type, slope,and structural or vegetative stabilisation used to protectthe soil.

Estuary

Area where fresh water meets salt water, where the tidemeets the river current (eg., bays, mouths of rivers, saltmarshes and lagoons). Estuaries serve as nurseries andspawning and feeding grounds for large groups of marinelife and provide shelter and food for birds and wildlife.The majority of the estuaries in the Auckland region arelow energy systems where sediment readily settles.

Evapotranspiration

The sum of surface evaporation and plant transpiration.

Fill

Earth placed (normally under a strict compactionregime) to raise the land surface.

Filter Blanket

A layer of sand and/or gravel designed to prevent themovement of fine-grained soils.

Filter Fabric

A woven or non-woven, water-permeable geotextilemade of synthetic products such as polypropylene usedfor such purposes as preventing clogging of aggregateby fine soil particles. Refer Geotextile Fabric.

Filter Strip

A long, narrow vegetative planting used to retard orcollect sediment for the protection of adjacent propertiesor receiving environments.

Fines (Soil)

Generally refers to the silt and clay size particles in soil.

Fire Breaks

Specific deforested strips within a forest to act as a barrierin the event of fire.

Flocculation

The process whereby fine particles suspended in the watercolumn clump together and settle. In some instances thiscan occur naturally, such as when fresh clay-laden flowsmix with saline water, as occurs in estuaries. Flocculationcan be used to promote rapid settling in sedimentretention ponds by the addition of flocculating chemicals(flocculants).

Flume

A high-velocity, open channel for conveying water to alower level without causing erosion. Also referred to as achute.

Gabion Basket

A flexible woven-wire basket composed of two to sixrectangular cells filled with small stones. Gabions maybe assembled into many types of structures such asretaining walls, channel liners, drop structures andgroynes.

Page 121: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council G l o s s a r y 4

Geosynthetic Erosion Control Systems (GECS)

The artificial protection of erodible channels and slopesusing artificial erosion control material such asgeosynthetic matting, geotextiles or erosion matting.

Geotextile Fabric

A woven or non-woven, impermeable or semi-permeablematerial generally made of synthetic products such aspolypropylene and used in a variety of engineering,stormwater management, and erosion and sedimentcontrol applications.

Grade

The slope of a road, channel or natural ground.

The finished surface of a channel bed, road bed, top ofembankment or bottom of excavation. Any surfaceprepared for the support of construction like paving orfor laying conduit.

To finish the surface of a channel bed, road bed, top ofembankment or bottom of excavation.

Gravel

Aggregate consisting of mixed sizes of 5 mm to 75 mmparticles which normally occur in or near old streambedsand have been worn smooth by the action of water.

Harvesting Management Plans

A plan detailing how the forest harvest operation is to beconducted to minimise earth disturbance and tomaximise the protection of adjoining land and naturalfeatures such as watercourses and native vegetation.

Headwater

The source of a watercourse. The water upstream of astructure or point on a watercourse.

Hydrology

The science of the behaviour of water in the atmosphere,on the surface of the earth and underground.

Hydroseeding

The spraying of a slurry of seed, fertiliser and paper orwood pulp over a surface to be revegetated.

Impervious

Not allowing infiltration of water.

Industry Education Programme

An Erosion and Sediment Control training programmerun by the ARC for Plan Implementors or Plan Preparersto increase knowledge and ownership of both principlesand practices of erosion and sediment control. Theprogramme allows participants to become ARCRegistered in erosion and sediment control.

Landings

Forestry. A log production and assembly area.

Level Spreader

A device used to convert concentrated flow into sheetflow.

Mitigation

Measures taken to off-set adverse environmental effectscaused by Land Disturbing Activities.

Mu l ch

Covering on surface of soil to protect it and enhancecertain characteristics, such as protection from rain dropimpact and improving germination.

Overburden (Quarries)

Unusable soil/rock stripped from above suitableproduction material.

Overland Flow Path

The route of concentrated flow.

Perennial Stream

A stream that maintains water in its channel throughoutthe year or maintains a series of discrete pools thatprovides habitats for the continuation of the aquaticecosystem.

Permeability (Soil)

The rate at which water will move through a saturatedsoil.

Page 122: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council G l o s s a r y 5

Permitted Activity

An activity that does not exceed the thresholds specifiedby a Regional or District Plan whereby a resource consentis required (in the Auckland region, Land DisturbingActivities are controlled by rules specified by theProposed Regional Plan: Sediment Control (PRPSC)).Permitted Activities must, however, meet certainperformance standards in terms of minimising adverseeffects.

Pervious

Allowing movement of water.

Poly aluminum Chloride (PAC)

A long chain chemical that is used as a flocculant incertain situations.

Primary Spillway

The Riser inlet within a Sediment Retention Pond.

Quarry Management Plans

A plan detailing how a quarry operation is to beconducted to minimise earth disturbance, to maximisethe protection of adjoining land and natural features suchas watercourses and native vegetation, and to minimisethe effect on adjoining residents and/or landowners.

Rainfall Intensity

The volume of rainfall falling in a given time. Normallyexpressed as mm/hour.

Rehabilitation

Restoration to as near to pre-disturbance conditions aspossible. This may entail such measures as revegetationfor erosion control, enhancement planting, modificationand armouring of watercourses.

Reno Mattress

A shallow (300-500 mm deep), wide, flexible woven-wirebasket composed of two to six rectangular cells filled withsmall stones. Often used at culvert inlets and outlets todissipate energy and prevent channel erosion.

Return Period

The statistical interpretation of the frequency of a givenintensity and duration rainstorm event. Refer AEP.

Revegetation

The establishment of vegetation to stabilise a site.

Riparian Protection Area

An area adjacent to a watercourse designated as a non-disturbance zone to provide a buffer between receivingenvironments (eg. watercourses) and the area ofoperation.

Riser

In a Sediment Retention Pond, a vertically placed pipeto which decant pipes are attached, which forms the inletto the primary spillway.

Saturation Point

In soils, the point at which a soil or an aquifer will nolonger absorb any amount of water without losing anequal amount.

Scarified

Shallow subsurface disturbance with a tine implementto provide surface roughening. Utilised before topsoilingand revegetation.

Scour

The erosive or digging action of flowing water; thedownward or lateral erosion caused by water. Channel-forming stream scour is caused by the sweeping away ofmud and silt from the outside bank of a curved channel(meander), particularly during a flood.

Sediment

Solid material, both mineral and organic, that is insuspension, is being transported, or has been moved fromsite of origin by air, water, gravity, or ice and has come torest on the earth’s surface either above or below water.

Sediment Control Protection Area

The area 50 o landward of the edge of a watercourse orwetland of 1000 m2 or more, or 100 o either side of aforedune, or 100 o landward of the coastal marine area(whichever is the more landward of mean high watersprings). Inside this area and on hills with slopes greaterthan 15°, earth disturbance over areas of 0.25 has orgreater or 100 o of tracking or trenching requires aresource consent.

Page 123: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council G l o s s a r y 6

Sediment Delivery Ratio

The proportion of the soil eroded from within acatchment area that actually reaches sediment treatmentcontrols or waterbodies.

Sediment Texture

The relative proportions of different sized of sedimentand soil particles that can be separated by screening. Thesize of sediment particulate. Refer Soil Texture.

Sediment Yield

The quantity of sediment discharged from a particularsite or catchment in a given time, measured in dry weightor by volume. When erosion and sediment controlmeasures are in place, sediment yield is the sedimentdischarged from the site after passing through thosemeasures.

Settling

The downward movement of suspended solids throughthe water column.

Shear Strength

The ability to resist shear (slip) forces.

Sheet flow

Shallow dispersed overland flow.

Shutter Boards

Plywood or similar sheeting supported by light timberframing normally used for boxing concrete forms.

Silt

A soil consisting of particles between 0.05 and 0.002 mmin equivalent diameter. A soil textural class.

Silt Loam

A soil textural class containing a large amount of silt andsmall quantities of sand and clay.

Silty Clay

A soil textural class containing a relatively large amountof silt and clay and a small amount of sand.

S lash

Branches trimmed from production logs.

Small Site

Small areas of earth disturbance that normally do notrequire a Land Use Consent: Sediment Control, such asindividual residential building sites. Refer PermittedActivities.

Soil

The unconsolidated mineral and organic material on thesurface of the earth that serves as a natural medium forthe growth of land plants.

Earth and rock particles resulting from the physical andchemical disintegration of rocks, which may or may notcontain organic matter. Includes fine material (silts andclays), sand and gravel.

Soil Structure

Soil structure reflects the pore space within a soil availablefor aeration and storage of water. It is a measure of bulkdensity and as a rule the higher the soil bulk density thepoorer the structure. The combination or arrangementof primary soil particles into secondary particles, unitsor peds. Good soil structure is important for plantgrowth.

Soil Texture

The relative proportions of various particle sizes in a soilmaterial. Refer Sediment Texture.

Spreader (Hydraulics)

A device for distributing water uniformly in or from achannel.

Stabilisation

Providing adequate measures, vegetative and/orstructural that will protect exposed soil to preventerosion.

Stabilised Area

An area sufficiently covered by erosion-resistant materialsuch as a good cover of grass, or paving by asphalt,concrete or aggregate, in order to prevent erosion of theunderlying soil.

Subsoil

The B horizons of soils with distinct profiles. In soils withweak profile development, the subsoil can be defined as

Page 124: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council G l o s s a r y 7

the soil below the ploughed soil (or its equivalent ofsurface soil), in which roots normally grow.

Surface Runoff

Rain that runs off rather than being infiltrated or retainedby the surface on which it falls.

Surface Water

All water with its surface exposed to the atmosphere.

Suspended Solids

Solids either floating or suspended in water.

Swale

A constructed elongated depression in the land surfacethat can be seasonally wet, is usually heavily vegetated,and is normally without flowing water. Swales conductstormwater into primary drainage channels and canprovide some groundwater recharge.

Tackifier

A compound that is added to straw mulch to bind ittogether and prevent it being blown around by the wind.

Temporary Watercourse Crossing

A stable watercourse crossing that is installed for theduration of an operation and is removed in its entiretyat the completion of the operation.

Tensile Strength

Resistance to elongation and tearing.

Time of Concentration

The time for runoff to flow from the most remote partof the drainage area to the outlet.

Toe (of Slope)

Where the slope stops or levels out. Bottom of the slope.

Topsoil

Fertile or desirable soil material (suitable organic andstructural properties) used to top-dress roadbanks,subsoils, parent material, etc to provide a suitablemedium for plant growth.

Unified Soil Classification System (Engineering)

A classification system based on the identification of soilsaccording to their particle size, gradation, plasticity indexand liquid limit.

Uniform Flow

A state of steady flow occurring when the mean velocityand cross-sectional area are equal at all sections of a reach.

Universal Soil Loss Equation

An equation used for the design of a water erosion controlsystem:

A = RKLSCP where:

A = the soil loss in tons per ha per annum

R = the rainfall factor

K = the soil erodibility factor

LS = the slope length and gradient factor

C = the vegetation factor

P = the surface roughness factor

Water Body

Any type of surface water such as watercourses, lakes andwetlands.

Watercourse

Any pathway for concentrated overland flow, includingrivers, streams and ephemeral channels.

Watershed

Refer Catchment.

Water Table

The upper surface of the free groundwater in a zone ofsaturation; locus of points in soil water at which hydraulicpressure is equal to atmospheric pressure.

Water Table Drain

A drain that parallels a carriageway to drain surface andsubsurface water from the road formation.

Page 125: i erosion sedimentcontrol · Call the ARC on 0800-80-60-40 or 09-377-3107. Mulching needs to be spread uniformly. For smaller areas hand spreading of mulch material can be adequate

Auckland Regional Council, 1995: Proposed RegionalPlan: Sediment Control

Auckland Regional Council Technical Publication No. 511994: Storm Sediment Yields from Basins with VariousLanduses in Auckland Area

Auckland Regional Council Technical Publication No. 531995: The Environmental Impacts of Urban StormwaterRunoff

Auckland Regional Council Technical Publication No. 691996: The Environmental Impacts of Accelerated Erosionand Sedimentation

Department of Natural Resources and EnvironmentalControl, Delaware, USA 1989: Delaware Erosion andSediment Control Handbook

Environment B.O.P. Guideline, 1993: Forest OperationsGuidelines

Environment B.O.P. Guideline No. 1, Version 2, 1996:Erosion and Sediment Control Guidelines for Earthworks

Environment B.O.P. Guideline No. 2: Erosion andSediment Control Guidelines for Quarries

Environment Protection Section, ACT Government,Australia, 1989: Guidelines for Erosion and SedimentControl on Building Sites

Environment Waikato Technical Publication No. 1995/8, 1995: Design Guidelines for Earthworks, Tracking andCrossings

Goldman, S.J. Jackson, K, Bursztynsky, T.A. 1986: Erosionand Sediment Control Handbook. McGraw-Hill. USA

Herald, J.R. 1989: Hydrological impacts of urbandevelopment in the Albany Basin, Auckland. PhD Thesis,University of Auckland

Maryland Department for the Environment, Maryland,USA, 1994: Maryland Standards and Specifications for SoilErosion and Sediment Control

New Zealand Logging Industry Research Organisation,1993: New Zealand Forest Code of Practice

NSW Department of Housing, Australia, 1993: Soil andWater Management for Urban Development

State of North Carolina, USA, 1988: Erosion and SedimentControl Planning and Design Manual

USDA-Soil Conservation Service, Syracuse, New York,1991: New York Guidelines for Urban Erosion & SedimentControl

Winter, R, 1998: Predicting Sediment Yield During theEarthworks Development Stage of a Subdivision, Auckland,and Assessment of the Efficiency of a Sediment RetentionPond. MSc Thesis, University of Waikato

erosion&sedimentcontrolGuidelines for Land Disturbing Activities in the Auckland Region

Auckland Regional Council 8B i b l i o g r a p hy