iberdrola usa ami data supplier access to hourly ami data

4
Iberdrola USA AMI DATA Supplier Access to Hourly AMI Data

Upload: elwin-walters

Post on 17-Dec-2015

217 views

Category:

Documents


5 download

TRANSCRIPT

Page 1: Iberdrola USA AMI DATA Supplier Access to Hourly AMI Data

Iberdrola USA AMI DATA

Supplier Access to Hourly AMI Data

Page 2: Iberdrola USA AMI DATA Supplier Access to Hourly AMI Data

222

RELIABILITY

Assets In Service

Capital PlanTotal Projects In Service: 47

CMP: 15 NYSEG: 14 RGE: 18

RELIABILITY

Assets In Service

Capital PlanTotal Projects In Service: 47

CMP: 15 NYSEG: 14 RGE: 18

Business Process for Suppliers to Obtain Access to CMP’s Secure FTP SiteBusiness Process for Suppliers to Obtain Access to CMP’s Secure FTP Site

CMP Secure FTP Site

Supplier Provides Public Encryption Key

•Link to create Public Encryption Key

•The file should be an asc. File. You will also need GnuPG software. It is freeware. Once this is downloaded and installed, the instructions will make more sense.

•www.gnupg.org/download

Supplier Provide a Public IP Address that will be used when accessing the CMP FTP site

•Link to instruction on providing IP address to CMP •http://www.whatismyip.com/

Valid IP address and Public Encryption Key must be provided by 1st of month

Data to be populated starting with the 15th of the month after IP and Encryption Key are validated

Suppliers will receive a unique user name and password that they will use to access CMP’s secure FTP site

The FTP site will contain files identified by your ISO-NE Load Asset ID number(s).

The FTP site and hourly AMI data is available to Competitive Electricity Providers – not available to Standard Offer Service Providers

CMP Secure FTP Site

Supplier Provides Public Encryption Key

•Link to create Public Encryption Key

•The file should be an asc. File. You will also need GnuPG software. It is freeware. Once this is downloaded and installed, the instructions will make more sense.

•www.gnupg.org/download

Supplier Provide a Public IP Address that will be used when accessing the CMP FTP site

•Link to instruction on providing IP address to CMP •http://www.whatismyip.com/

Valid IP address and Public Encryption Key must be provided by 1st of month

Data to be populated starting with the 15th of the month after IP and Encryption Key are validated

Suppliers will receive a unique user name and password that they will use to access CMP’s secure FTP site

The FTP site will contain files identified by your ISO-NE Load Asset ID number(s).

The FTP site and hourly AMI data is available to Competitive Electricity Providers – not available to Standard Offer Service Providers

Page 3: Iberdrola USA AMI DATA Supplier Access to Hourly AMI Data

Purpose and Format of AMI Hourly Data Files

CMP will provide a CSV file to provide hourly AMI data for each account enrolled by the supplier for the settlement day.

A sample format for the CSV file is as follows:• 04460502334,003,10/12/2013,2.3,4.4,5.1,6.22,5,5.1,4,3,4.41,5.4,6,66,7.2,8.1,7.88,6.5,6.5,6.7,5.4,6,66,7,2,7.7,

CMP will populate the FTP site each ISO-NE settlement day (weekends and holidays will not be populated with new data).

Files will be available to suppliers by 8:00 a.m. each settlement day. Prior daily files will be deleted each settlement day at 6:00 a.m. CMP will not repopulate or resend files that are not retrieved by the supplier

for any given settlement day. The first business day after a weekend or holiday will contain multiple days

in the same CSV file for each customer enrolled by the supplier. The date for the AMI date is shown in the example above.

During the monthly ISO-NE Resettlement process, larger CSV files will be placed on the FTP site and these files will contain a calendar month’s worth of AMI data for accounts enrolled by the supplier. Only days enrolled with the supplier will be provided. (i.e., enrollment on the 15th of the month would result in the month-end file containing data from the 15th to the 31st)

Page 4: Iberdrola USA AMI DATA Supplier Access to Hourly AMI Data

Q&A Regarding Customer AMI data

All questions regarding the AMI data/issues must be sent to [email protected]

Will supplier still have access to MV-Web? CMP will maintain the MV-Web site until notice is provided to all suppliers that the site is no longer available.

Can suppliers still request interval data from CMP? Yes – CMP will still provide data and the $25 per account fee will remain effective for that service.

Do suppliers have to subscribe to the FTP site for AMI data? No, this is an optional service and there is no requirement that all suppliers use this data.

Who do I contact with questions regarding the IP address and Encryption Key? Please send all questions to [email protected]

Can I ask for data for prior days that my team forgot to download? No, the data is made available each day and once removed, will not be resent. CMP is not storing this large volume of data on our side so suppliers must implement a process to sweep our FTP site each day.