icfi.com © 2006 ICF International. All rights reserved.
Wyoming Collector and Transmission System Project
– Status Report
Presented to:
Wyoming Infrastructure Authority Board of Directors
November 10, 2009
![Page 2: Icfi.com © 2006 ICF International. All rights reserved. Wyoming Collector and Transmission System Project – Status Report Presented to: Wyoming Infrastructure](https://reader036.vdocument.in/reader036/viewer/2022081603/56649f135503460f94c26acf/html5/thumbnails/2.jpg)
icfi.com2
Contents
• Background• Current Status• Going Forward
![Page 3: Icfi.com © 2006 ICF International. All rights reserved. Wyoming Collector and Transmission System Project – Status Report Presented to: Wyoming Infrastructure](https://reader036.vdocument.in/reader036/viewer/2022081603/56649f135503460f94c26acf/html5/thumbnails/3.jpg)
icfi.com3
Background
![Page 4: Icfi.com © 2006 ICF International. All rights reserved. Wyoming Collector and Transmission System Project – Status Report Presented to: Wyoming Infrastructure](https://reader036.vdocument.in/reader036/viewer/2022081603/56649f135503460f94c26acf/html5/thumbnails/4.jpg)
icfi.com4
Renewable Energy Development
• State Renewables Portfolio Standard (RPS)
– California 33% by 2020– Potential National RPS
• Production and Investment Tax Credits
• GHG Emission Reduction Legislation
![Page 5: Icfi.com © 2006 ICF International. All rights reserved. Wyoming Collector and Transmission System Project – Status Report Presented to: Wyoming Infrastructure](https://reader036.vdocument.in/reader036/viewer/2022081603/56649f135503460f94c26acf/html5/thumbnails/5.jpg)
icfi.com5
Wyoming Proposed Transmission Lines
• 7 extra-high voltage• Issues: impact,
reliability, cost, and spacing of lines
• Spacing affects BLM ROW application processing
![Page 6: Icfi.com © 2006 ICF International. All rights reserved. Wyoming Collector and Transmission System Project – Status Report Presented to: Wyoming Infrastructure](https://reader036.vdocument.in/reader036/viewer/2022081603/56649f135503460f94c26acf/html5/thumbnails/6.jpg)
icfi.com6
Transmission Line Separation
• WIA Board of Directors funds independent study to address issues
• Published August 2009
![Page 7: Icfi.com © 2006 ICF International. All rights reserved. Wyoming Collector and Transmission System Project – Status Report Presented to: Wyoming Infrastructure](https://reader036.vdocument.in/reader036/viewer/2022081603/56649f135503460f94c26acf/html5/thumbnails/7.jpg)
icfi.com7
WGA and DOE - Western Renewable Energy Zones (WREZ)
• WREZ Phase I Report Published June 2009
• Includes Hub Map of Renewable Resource Potential
![Page 8: Icfi.com © 2006 ICF International. All rights reserved. Wyoming Collector and Transmission System Project – Status Report Presented to: Wyoming Infrastructure](https://reader036.vdocument.in/reader036/viewer/2022081603/56649f135503460f94c26acf/html5/thumbnails/8.jpg)
icfi.com8
Western Area Power Administration and the ARRA
• TIP Purpose: “…constructing, financing, facilitating or studying construction of new or upgraded transmission facilities to deliver or facilitate delivery of renewable resources…
• Applications submitted April 2009
![Page 9: Icfi.com © 2006 ICF International. All rights reserved. Wyoming Collector and Transmission System Project – Status Report Presented to: Wyoming Infrastructure](https://reader036.vdocument.in/reader036/viewer/2022081603/56649f135503460f94c26acf/html5/thumbnails/9.jpg)
icfi.com9
Wyoming Wind Collector and Transmission Task Force
• Develop a coordinated, staged, conceptual plan for a collector system
• Accommodate the interstate transmission lines and corridors required to collect and export these new resources
![Page 10: Icfi.com © 2006 ICF International. All rights reserved. Wyoming Collector and Transmission System Project – Status Report Presented to: Wyoming Infrastructure](https://reader036.vdocument.in/reader036/viewer/2022081603/56649f135503460f94c26acf/html5/thumbnails/10.jpg)
icfi.com10
Current Status
![Page 11: Icfi.com © 2006 ICF International. All rights reserved. Wyoming Collector and Transmission System Project – Status Report Presented to: Wyoming Infrastructure](https://reader036.vdocument.in/reader036/viewer/2022081603/56649f135503460f94c26acf/html5/thumbnails/11.jpg)
icfi.com11
Current Status
• WIA contracted with ICF to develop a conceptual design of a collector system
• One meeting and several conference calls held to date
• Scope of Work is complete and ICF began work in October
![Page 12: Icfi.com © 2006 ICF International. All rights reserved. Wyoming Collector and Transmission System Project – Status Report Presented to: Wyoming Infrastructure](https://reader036.vdocument.in/reader036/viewer/2022081603/56649f135503460f94c26acf/html5/thumbnails/12.jpg)
icfi.com12
Scope of Work
Tasks1. Technical Analysis*1.1: Develop Analysis Scenarios*
1.2: Perform Reliability Analyses*
1.3: Update Energy Corridor Map
1.4: Estimate Costs*
1.5: Summarize the Collector System Design Alternatives*
2. Commercial Structure
3. Administrative/Outreach* Funded subtasks
StartOctober
2009
Task 1 Technical Analysis
Task 2 Commercial
Analysis
Task 3 Administrative
Support
Collector System Design
Alternatives
![Page 13: Icfi.com © 2006 ICF International. All rights reserved. Wyoming Collector and Transmission System Project – Status Report Presented to: Wyoming Infrastructure](https://reader036.vdocument.in/reader036/viewer/2022081603/56649f135503460f94c26acf/html5/thumbnails/13.jpg)
icfi.com13
Current Effort – Subtasks 1.1 and 1.2
1.1 Develop Analysis Scenarios (in progress)
• Examining two wind resource development options • Analyzing two collector system design options: radial vs. networked
1.2 Perform Reliability Analysis (start 11/09)
• Performing engineering feasibility analysis to ensure basic security and reliability of conceptual design for a 15GW system
• Developing a starting point for evaluating collector system design options from a cost basis
![Page 14: Icfi.com © 2006 ICF International. All rights reserved. Wyoming Collector and Transmission System Project – Status Report Presented to: Wyoming Infrastructure](https://reader036.vdocument.in/reader036/viewer/2022081603/56649f135503460f94c26acf/html5/thumbnails/14.jpg)
icfi.com14
Going Forward
![Page 15: Icfi.com © 2006 ICF International. All rights reserved. Wyoming Collector and Transmission System Project – Status Report Presented to: Wyoming Infrastructure](https://reader036.vdocument.in/reader036/viewer/2022081603/56649f135503460f94c26acf/html5/thumbnails/15.jpg)
icfi.com15
Going Forward
1.4 Estimate Cost of Collector Design Options
• Estimate cost of design options• Rank options based on cost
1.5 Summary of Technical Analysis
• Identify collector system elements common to all scenarios• Discuss possible integration with existing grid• Discuss possible staged development of the collector system• Describe radial and networked design options and discuss trade-
offs
![Page 16: Icfi.com © 2006 ICF International. All rights reserved. Wyoming Collector and Transmission System Project – Status Report Presented to: Wyoming Infrastructure](https://reader036.vdocument.in/reader036/viewer/2022081603/56649f135503460f94c26acf/html5/thumbnails/16.jpg)
icfi.com16
Going Forward (Cont’d.)
Considerations Outside Scope of Work• Integration of wind generation with other energy sources