![Page 1: IDBI Bank Limited Bank's response to the Pre bid queries ...considered for Finacle CBS downtime. More clarity is required. Penalty clauses will require waiver The uptime will be calucated](https://reader034.vdocument.in/reader034/viewer/2022042101/5e7db4595f85dc14d16b9967/html5/thumbnails/1.jpg)
IDBI Bank Limited
S.No Page no RFP Clause no Existing clause Details Clarification Sought Bank Response
1 6 Document Control Sheet Last Date and Time for Receipt/ Submission of Bids We request Bank to provide atleast 4 week
time post pre bid response to submitt the
quality bid
No change in this RFP Clause
2 10 Section 1 Introduction
3. Eligibility Criteria / Preliminary
Examination
3.10
The bidder can make consortium but cannot sub-
contract the job to any other company or firm and the
implementation for the Bank must be done by the
employees of the consortium members only. Consortium
agreement to be shared with the Bank clearly specifying
the roles and responsibilities and services rendered.
Prime bidder will be sole responsible for the entire
project
we request deletion of this clause Please refer Corrigendum.
3 17 Section 3: Instruction to Bidders
(ITB)
5. Bid Security (EMD)
5.6.3
The Bid Security shall be forfeited:
5.6.3 If the successful Bidder fails to sign the contract or
furnish performance security and other guarantee(s) /
security in the form and manner to the satisfaction of
the Bank, as mentioned in the Bid Documents; or
We submit that the Bid Security should be
forfeited only if the successful Bidder fails to
sign a mutually agreed contract. Hence, we
submit that the reference of "contract" or
"document" required to be signed by the
successful Bidder should be changed to
mutually agreed contract or document.
No change in this RFP Clause
4 17 Section 3: Instruction to Bidders
(ITB)
5. Bid Security (EMD)
5.6.4
The Bid Security shall be forfeited:
5.6.4 In the event of any evasion, avoidance, refusal or
delay on the part of the Bidder to sign and execute any
document, as may be required by the Bank.
We submit that the Bid Security should be
forfeited only if the successful Bidder fails to
sign a mutually agreed contract. Hence, we
submit that the reference of "contract" or
"document" required to be signed by the
successful Bidder should be changed to
mutually agreed contract or document.
No change in this RFP Clause
5 17 Section 3: Instruction to Bidders
(ITB)
5. Bid Security (EMD)
5.6.5
The Bid Security shall be forfeited:
5.6.5 Any decision in this regard by the Bank shall be
final, conclusive and binding on the Bidder.
We submit that the Bid Security should be
forfeited only if the successful Bidder fails to
sign a mutually agreed contract. Hence, we
submit that the reference of "contract" or
"document" required to be signed by the
successful Bidder should be changed to
mutually agreed contract or document.
No change in this RFP Clause
RFP for Core Banking System Upgrade / Migration (Migration to Finacle 10.x)
Ref No: IDBI/PCell/RFP/2015-16/026 Dated: 25-January-2016
Bank's response to the Pre bid queries
Page 1 of 41
![Page 2: IDBI Bank Limited Bank's response to the Pre bid queries ...considered for Finacle CBS downtime. More clarity is required. Penalty clauses will require waiver The uptime will be calucated](https://reader034.vdocument.in/reader034/viewer/2022042101/5e7db4595f85dc14d16b9967/html5/thumbnails/2.jpg)
IDBI Bank Limited
S.No Page no RFP Clause no Existing clause Details Clarification Sought Bank Response
RFP for Core Banking System Upgrade / Migration (Migration to Finacle 10.x)
Ref No: IDBI/PCell/RFP/2015-16/026 Dated: 25-January-2016
Bank's response to the Pre bid queries
6 21 Section 3: Instruction to Bidders
(ITB)
19. Evaluation and comparison of
Bids
19.1.6
The Bank may, in its absolute discretion, apply whatever
criteria it deems appropriate in the selection of vendor,
not limited to those selection criteria set out in this RFP
document.
Request IDBI to freeze the selection criteria.
Ambiguity in selection raises undue concerns.
No change in this RFP Clause
7 23 Section 3: Instruction to Bidders
(ITB)
19.2 Bid evaluation methodology
that the Bank would adopt is as
given below:
4. Phase 4 - Weighted Evaluation
The evaluation of the response to this RFP will be
calculated on a 70-30 Techno-Commercial evaluation
method
We request Bank to change the evaluation as
per L1 bid method.
No change in this RFP Clause
8 24 Section 3: Instruction to Bidders
(ITB)
22 Notifcation of Acceptance of
Bid
a
Notification of acceptance of Bid
a) Notification to Bidder Before the expiry of the period
of validity of the proposal, The Bank shall notify the
successful Bidder (TC1) in writing by registered letter or
by fax or by hand-delivery, that its Bid has been
accepted. The Bidder shall acknowledge in writing
receipt of the notification of acceptance and has to
convey his absolute, unconditional and unqualified
acceptance and thereafter enter into Agreement /
Contract within seven (7) days from the date of
acceptance.
we submit that there are certain terms and
conditions which would need discussion
between Bank and the Vendor prior to
entering into the contract. We submit that the
contract should be signed on the basis of
mutual discussion and agreement between the
parties.
No change in this RFP Clause
9 24 Section 3: Instruction to Bidders
(ITB)
22 Notifcation of Acceptance of
Bid
b
Notification of acceptance of Bid
b) Signing of the Contract shall follow the notification of
the acceptance. However, the Bank may negotiate
certain terms with successful Bidder before signing of
the Contract. The Bidder should sign the Contract Form,
Refer Annexure-1 (Form-8) the signing of Contract will
amount to award of contract and Bidder will initiate the
execution of the work as specified in the Contract. The
signing of contract shall be completed within 7 days of
receipt of notification of the acceptance of bid.
we submit that there are certain terms and
conditions which would need discussion
between Bank and the Vendor prior to
entering into the contract. We submit that the
contract should be signed on the basis of
mutual discussion and agreement between the
parties.
No change in this RFP Clause
Page 2 of 41
![Page 3: IDBI Bank Limited Bank's response to the Pre bid queries ...considered for Finacle CBS downtime. More clarity is required. Penalty clauses will require waiver The uptime will be calucated](https://reader034.vdocument.in/reader034/viewer/2022042101/5e7db4595f85dc14d16b9967/html5/thumbnails/3.jpg)
IDBI Bank Limited
S.No Page no RFP Clause no Existing clause Details Clarification Sought Bank Response
RFP for Core Banking System Upgrade / Migration (Migration to Finacle 10.x)
Ref No: IDBI/PCell/RFP/2015-16/026 Dated: 25-January-2016
Bank's response to the Pre bid queries
10 25 Section 3: Instruction to Bidders
(ITB)
22 Notifcation of Acceptance of
Bid
d
Performance Security Bidder requests for inclusion of a provision in
the referenced clause to state that
Performance Bank Guarantee (PBG) will be
invoked only for material breach after Bidder
being given 30 days cure period.
No change in this RFP Clause
11 25 Section 3: Instruction to Bidders
(ITB)
22 Notifcation of Acceptance of
Bid
d (i)
Within 15 days of signing the contract by the Bank, the
successful Bidder shall furnish the Performance Bank
Guarantee as per the format provided in Annexure-1
(Form-7). The Performance Bank Guarantee furnished by
the Bidder shall be unconditional and irrevocable.
Bidder proposes that the PBG will be
submitted within 15 days from the date of
signing the contract as the process of PBG is
initiated only after contract conclusion and
signing.
No change in this RFP Clause
12 25 Section 3: Instruction to Bidders
(ITB)
22 Notifcation of Acceptance of
Bid
d (v)
The Performance Bank Guarantee should be valid till 3
years from the project commencement, with 90 (ninety)
days claim period from the date of the expiry of the
validity period
We also submit that the PBG should be valid
only for the term of this contract.
The total Project Period will be 3
years which includes 18 months
of migration, 3 months warranty,
12 months of AMS and 3 months
of cooling period.
13 25 Section 3: Instruction to Bidders
(ITB)
22 Notifcation of Acceptance of
Bid
f
Failure to abide by the Agreement / Contract The
conditions stipulated in the Agreement / Contract shall
be strictly adhered to and any Breach / violation thereof
will entail termination of the Contract without prejudice
to the other rights of the Bank including recovery of
penalties as specified in this RFP or Agreement /
Contract.
We request that any termination of the
Agreement/Contract should be as per the
provisions on termination agreed between the
parties, after expiry of a reasonable cure
period of not less than 30 days.
No change in this RFP Clause
Page 3 of 41
![Page 4: IDBI Bank Limited Bank's response to the Pre bid queries ...considered for Finacle CBS downtime. More clarity is required. Penalty clauses will require waiver The uptime will be calucated](https://reader034.vdocument.in/reader034/viewer/2022042101/5e7db4595f85dc14d16b9967/html5/thumbnails/4.jpg)
IDBI Bank Limited
S.No Page no RFP Clause no Existing clause Details Clarification Sought Bank Response
RFP for Core Banking System Upgrade / Migration (Migration to Finacle 10.x)
Ref No: IDBI/PCell/RFP/2015-16/026 Dated: 25-January-2016
Bank's response to the Pre bid queries
14 29 SECTION 4: TERMS AND
CONDITIONS OF THE RFP /
CONTRACT
4. Standard of Performance and
Service Level Definition and
Measurement
a) Timeline and Penalty for delay
in project implementation
Penalty will be applicable for late delivery of the
customized software where 0.5% of ‘cost of the
deliverable ’ will be deducted as penalty per week or
part thereof for failure as indicated in the RFP with the
maximum penalty of10% of ‘cost of the contract’.
However, Bank reserve the right to terminate the
contract at any time, if the project is not delivered as per
scheduled timelines and Bank will claim entire amount
paid to the vendor with simple interest @18% p.a. along
with additional 10%of ‘cost of the contract’, as
compensation.
Request penalty for delay in project
implementation to be capped at 5% of the
value of affected deliverable.
We also propose that this para stipulating for
termination and right of Bank to claim the
entire amount paid, should be deleted. It is
submitted that any termination of the contract
should be as per the provisions on termination
agreed between the parties, after expiry of a
reasonable cure period of not less than 30
days.
No change in this RFP Clause
15 29 SECTION 4: TERMS AND
CONDITIONS OF THE RFP /
CONTRACT
4. Standard of Performance and
Service Level Definition and
Measurement
b) Penalty for downtime for Post
implementation:
The uptime will be calculated based on 24/7 excluding
the planned downtime on monthly basis and penalty will
be charged
The down time can be due to network or
hardware, OS related issues, which cant be
considered for Finacle CBS downtime. More
clarity is required. Penalty clauses will require
waiver
The uptime will be calucated on
24/7 for Finacle appliction and
it's related application
components.
16 29 SECTION 4: TERMS AND
CONDITIONS OF THE RFP /
CONTRACT
4. Standard of Performance and
Service Level Definition and
Measurement
b) Penalty for downtime for Post
implementation:
The uptime will be calculated based on 24/7 excluding
the planned downtime on monthly basis and penalty will
be charged
Pentaly charges is stated as a percentage of
Cost of Contract, however no period is
mentioned. Our assumption is that the penlaty
percentage will be applied on the Cost of
Contract for the month in which the SLA is
missed. Please do advise if this is the correct
understanding
As per RFP terms, uptime will be
calculated on monthly basis. And
penalty will be calculated on the
contract value of AMS and
charged /
deducted during the subsequent
payment as per RFP payment
terms
Page 4 of 41
![Page 5: IDBI Bank Limited Bank's response to the Pre bid queries ...considered for Finacle CBS downtime. More clarity is required. Penalty clauses will require waiver The uptime will be calucated](https://reader034.vdocument.in/reader034/viewer/2022042101/5e7db4595f85dc14d16b9967/html5/thumbnails/5.jpg)
IDBI Bank Limited
S.No Page no RFP Clause no Existing clause Details Clarification Sought Bank Response
RFP for Core Banking System Upgrade / Migration (Migration to Finacle 10.x)
Ref No: IDBI/PCell/RFP/2015-16/026 Dated: 25-January-2016
Bank's response to the Pre bid queries
17 29 SECTION 4: TERMS AND
CONDITIONS OF THE RFP /
CONTRACT
4. Standard of Performance and
Service Level Definition and
Measurement
b) Penalty for downtime for Post
implementation:
Below 95.00% -10% of Cost of contract Request penalty for downtime for post
implementation to be capped at 5% of the
value of affected deliverable.
No change in this RFP Clause
18 29 SECTION 4: TERMS AND
CONDITIONS OF THE RFP /
CONTRACT
4. Standard of Performance and
Service Level Definition and
Measurement
b) Penalty for downtime for Post
implementation:
The uptime will be calculated on monthly basis and
penalty will be charged
Please advise, whether the penalties
mentioned in the table will be calculated on
the monthly amount payable to vendor and
deducted on the monthly payable amount of
AMS and not entire contract value.
As per RFP terms, uptime will be
calculated on monthly basis. And
penalty will be calculated on the
contract value of AMS and
charged /
deducted during the subsequent
payment as per RFP payment
terms
19 29 SECTION 4: TERMS AND
CONDITIONS OF THE RFP /
CONTRACT
4. Standard of Performance and
Service Level Definition and
Measurement
b) Penalty for downtime for Post
implementation:
The Finacle CBS system has to be up for at least 99.50%.
The Finacle CBS is deemed to be up if the users are able
to log into the system
Please advise, uptime will be calculated based
on working hours of the CBS and advise the
relevant working business hours.
Uptime will be calculated based
on 24/7
excluding the planned down
time.
20 29 SECTION 4: TERMS AND
CONDITIONS OF THE RFP /
CONTRACT
4. Standard of Performance and
Service Level Definition and
Measurement
b) Penalty for downtime for Post
implementation:
General We request to have 1 month of penalty
moratorium period after go-live of CBS.
No change in this RFP Clause
Page 5 of 41
![Page 6: IDBI Bank Limited Bank's response to the Pre bid queries ...considered for Finacle CBS downtime. More clarity is required. Penalty clauses will require waiver The uptime will be calucated](https://reader034.vdocument.in/reader034/viewer/2022042101/5e7db4595f85dc14d16b9967/html5/thumbnails/6.jpg)
IDBI Bank Limited
S.No Page no RFP Clause no Existing clause Details Clarification Sought Bank Response
RFP for Core Banking System Upgrade / Migration (Migration to Finacle 10.x)
Ref No: IDBI/PCell/RFP/2015-16/026 Dated: 25-January-2016
Bank's response to the Pre bid queries
21 29 SECTION 4: TERMS AND
CONDITIONS OF THE RFP /
CONTRACT
4. Standard of Performance and
Service Level Definition and
Measurement
b) Penalty for downtime for Post
implementation:
The Finacle CBS system has to be up for at least 99.50%.
The Finacle CBS is deemed to be up if the users are able
to log into the system.
We presue that CBS system uptime is only the
application avaialbility excluding the
hardware/OS/DB as bank team manages it and
SI is not repsonsible for it. Please confirm.
Bidder is expected to provide the
99.5% Availablity of CBS
Application.
22 29 SECTION 4: TERMS AND
CONDITIONS OF THE RFP /
CONTRACT
4. Standard of Performance and
Service Level Definition and
Measurement
c) SLA for Software Support
Any software bug identified by Bank / vendor’s service
engineer would have to be fixed within the stipulated
time depending upon the criticality of the issue. Refer to
Annexure-3 (Service Level Requirements)
We are not agreeable for the SLA clauses and
penalty clauses as mentioned in RFP. We will
go with our Finacle standard SLA clauses
limited to Finacle application as mentioned in
SOW (SLA Section) Other OS, H/W, 3rd party
related aspects will be out of our scope.
No change in this RFP Clause
23 30 SECTION 4: TERMS AND
CONDITIONS OF THE RFP /
CONTRACT
8.Delay in the Vendor’s / Bidder’s
Performance
a
a) Performance of the Contract shall be made by the
Vendor / Bidder in accordance with the time schedule
specified by the Bank.
We submit that since there is provision for
liquidated damages for delay, the provisions
pertaining to forfeiture of performance
guarantee and/or termination of contract
should be invoked only if the amount of
liquidated damages reaches its maximum
extent.
No change in this RFP Clause
24 30 SECTION 4: TERMS AND
CONDITIONS OF THE RFP /
CONTRACT
8.Delay in the Vendor’s / Bidder’s
Performance
b
b) Any delay by the Vendor / Bidder in the performance
of its Contractual obligations, which the Bank shall in its
sole discretion may adjudge, shall render the Vendor /
Bidder liable to any or all the following sanctions:
i.Forfeiture of its performance guarantee
ii.Imposition of liquidated damages, and / or
iii.Termination of the Contract for default
Bidder requests for deletion of Cl 8 (b) (ii) & 8
(b) (iii) as the PBG can be invoked only for
material breach remaining uncured even after
30 days cure period. Similarly, the termination
of the contract shall be only for material
breach after providing 30 days cure period.
No change in this RFP Clause
25 31 SECTION 4: TERMS AND
CONDITIONS OF THE RFP /
CONTRACT
9.Payment Terms
Payment Terms Our undertanding is that payment will be
made immediately upon achivement and
acceptance of the relevant milestones subject
to Vendor providing a valid invoice
No change in this RFP Clause
Page 6 of 41
![Page 7: IDBI Bank Limited Bank's response to the Pre bid queries ...considered for Finacle CBS downtime. More clarity is required. Penalty clauses will require waiver The uptime will be calucated](https://reader034.vdocument.in/reader034/viewer/2022042101/5e7db4595f85dc14d16b9967/html5/thumbnails/7.jpg)
IDBI Bank Limited
S.No Page no RFP Clause no Existing clause Details Clarification Sought Bank Response
RFP for Core Banking System Upgrade / Migration (Migration to Finacle 10.x)
Ref No: IDBI/PCell/RFP/2015-16/026 Dated: 25-January-2016
Bank's response to the Pre bid queries
26 31 SECTION 4: TERMS AND
CONDITIONS OF THE RFP /
CONTRACT
9.Payment Terms
We propose payment terms as below:
For Item code A1 to A5, B1 to B3 and B11- 20%
Advance at the time of the project ; 20%
against completion Training, DRG, BPD, 20%
against installation of s/w, 30% completion of
UAT and 10% against GO Live.
For Item code B5 CBT- 50% against PO and
50% against Installation.
For Item code B4: Advance at the start of the
L2 services paid quarterly in advance.
For Item code B6: Against completition of
training against each batch.
For Item code B9 & B10, Archival and APM
tool: 100% against Licenses; 50% advance for
services implementation, 50% against UAT.
Please refer Corrigendum.
27 31 SECTION 4: TERMS AND
CONDITIONS OF THE RFP /
CONTRACT
9.Payment Terms
A Payment Schedule (A1 to A5 and
B1,B2,B3& B11)
Software, Installation, Configuration, Customization,
Implementation and Migration:
i. 10% on completion of installation of new version and
CSS
ii. 20% on completion of DRG
iii. 20% on completion of UAT-1 (Migration)
iv. 20% on complete UAT-2
v. 20% on Post ‘Go Live’
vi. 10 % on completion of Warranty
Bidder Request payment terms to be changed
to:
1). 15% on project initiation, detailed project
plan submission and sign off
2). 15% on completion of installation of new
version and CSS
3). 20% on completion of DRG
4). 20% on completion of UAT-1 (Migration)
5). 20% on complete UAT-2
6). 10% on Post ‘Go Live’.
No change in this RFP Clause
Page 7 of 41
![Page 8: IDBI Bank Limited Bank's response to the Pre bid queries ...considered for Finacle CBS downtime. More clarity is required. Penalty clauses will require waiver The uptime will be calucated](https://reader034.vdocument.in/reader034/viewer/2022042101/5e7db4595f85dc14d16b9967/html5/thumbnails/8.jpg)
IDBI Bank Limited
S.No Page no RFP Clause no Existing clause Details Clarification Sought Bank Response
RFP for Core Banking System Upgrade / Migration (Migration to Finacle 10.x)
Ref No: IDBI/PCell/RFP/2015-16/026 Dated: 25-January-2016
Bank's response to the Pre bid queries
28 31 SECTION 4: TERMS AND
CONDITIONS OF THE RFP /
CONTRACT
9.Payment Terms
B Payment Schedule (B5,B9 and
B10) :
Computer based training Module / Tool, Data Archival
and purging solution and Application Performance
Monitoring Tool
i. 30% on delivery
ii. 20% on completion of UAT
iii. 40 % on complete Go live
iv. 10 % on completion of Warranty
Bidder Request payment terms to be changed
to:
1). 20% on project initiation, detailed project
plan submission and sign off
2). 30% on delivery
3). 20% on completion of UAT
4). 20% on completion of UAT-1 (Migration)
5). 10 % on complete rollout
We also submit that Bank shall make payment
within 30 days from the date of invoice.
Please refer Corrigendum.
29 32 SECTION 4: TERMS AND
CONDITIONS OF THE RFP /
CONTRACT
10. Liquidated Damages
Liquidated damages We submit that this provision is a repitition.
We understand that this clause is same as
Section 4.a i.e Penalty for delay in Project
Implementation. Please clarify.
Penalty and liquidity damages
are two different clauses
Page 8 of 41
![Page 9: IDBI Bank Limited Bank's response to the Pre bid queries ...considered for Finacle CBS downtime. More clarity is required. Penalty clauses will require waiver The uptime will be calucated](https://reader034.vdocument.in/reader034/viewer/2022042101/5e7db4595f85dc14d16b9967/html5/thumbnails/9.jpg)
IDBI Bank Limited
S.No Page no RFP Clause no Existing clause Details Clarification Sought Bank Response
RFP for Core Banking System Upgrade / Migration (Migration to Finacle 10.x)
Ref No: IDBI/PCell/RFP/2015-16/026 Dated: 25-January-2016
Bank's response to the Pre bid queries
30 32 SECTION 4: TERMS AND
CONDITIONS OF THE RFP /
CONTRACT
10 Liquidated damages
If the Vendor fails to deliver any or all of the Service(s) /
Systems or perform the Services within the time
period(s) specified in the Contract / Agreement / fails to
meet the Service Level Requirements, IDBI / Purchaser
shall, without prejudice to its other rights and remedies
under and in accordance with the Contract / Agreement,
deduct from the Contract price, as liquidated damages, a
sum equivalent to 0.50% per week or part thereof of
cost of the contract subject to maximum deduction of
10% of ‘cost of the contract’ of the delayed Service(s) or
unperformed Service(s). However, Bank reserve the right
to terminate the contract at any time, if the project is
not delivered as per scheduled timelines and Bank will
claim entire amount paid to the vendor with simple
interest @18% p.a. along with additional 10% of ‘cost of
the contract’, as compensation.
We seek to deviate on amount and terms of
liquidated damages to be levied
No change in this RFP Clause
Page 9 of 41
![Page 10: IDBI Bank Limited Bank's response to the Pre bid queries ...considered for Finacle CBS downtime. More clarity is required. Penalty clauses will require waiver The uptime will be calucated](https://reader034.vdocument.in/reader034/viewer/2022042101/5e7db4595f85dc14d16b9967/html5/thumbnails/10.jpg)
IDBI Bank Limited
S.No Page no RFP Clause no Existing clause Details Clarification Sought Bank Response
RFP for Core Banking System Upgrade / Migration (Migration to Finacle 10.x)
Ref No: IDBI/PCell/RFP/2015-16/026 Dated: 25-January-2016
Bank's response to the Pre bid queries
31 32 SECTION 4: TERMS AND
CONDITIONS OF THE RFP /
CONTRACT
10 Liquidated damages
(a)
If the Vendor fails to deliver any or all of the Service(s) /
Systems or perform the Services within the time
period(s) specified in the Contract / Agreement / fails to
meet the Service Level Requirements, IDBI / Purchaser
shall, without prejudice to its other rights and remedies
under and in accordance with the Contract / Agreement,
deduct from the Contract price, as liquidated damages, a
sum equivalent to 0.50% per week or part thereof of
cost of the contract subject to maximum deduction of
10% of ‘cost of the contract’ of the delayed Service(s) or
unperformed Service(s). However, Bank reserve the right
to terminate the contract at any time, if the project is
not delivered as per scheduled timelines and Bank will
claim entire amount paid to the vendor with simple
interest @18% p.a. along with additional 10% of ‘cost of
the contract’, as compensation.
If there is a delay in performance then the
Vendor should be allowed to cure the
breach/delay. IDBI should be allowed to
terminate only if the delay/breach has not
been cured/ addressed. Cure period should be
thirty days from the date when the breach was
notified to the Vendor/Bidder.
No change in this RFP Clause
32 32 SECTION 4: TERMS AND
CONDITIONS OF THE RFP /
CONTRACT
10 Liquidated damages
(d)
IDBI / the Purchaser may without prejudice to its right to
effect recovery by any other method, deduct the amount
of liquidated damages from any money belonging to the
Vendor in its hands (which includes IDBI's/ the
Purchaser’s right to claim such amount against Vendor's
Bank Guarantee) or which may become due to the
Vendor. Any such recovery or liquidated damages shall
not in any way relieve the Vendor from any of its
obligations to complete the works / service(s) or from
any other obligations and liabilities under the Contract /
Agreement.
LD should be imposed separately and not by
withholding payments.
No change in this RFP Clause
Page 10 of 41
![Page 11: IDBI Bank Limited Bank's response to the Pre bid queries ...considered for Finacle CBS downtime. More clarity is required. Penalty clauses will require waiver The uptime will be calucated](https://reader034.vdocument.in/reader034/viewer/2022042101/5e7db4595f85dc14d16b9967/html5/thumbnails/11.jpg)
IDBI Bank Limited
S.No Page no RFP Clause no Existing clause Details Clarification Sought Bank Response
RFP for Core Banking System Upgrade / Migration (Migration to Finacle 10.x)
Ref No: IDBI/PCell/RFP/2015-16/026 Dated: 25-January-2016
Bank's response to the Pre bid queries
33 33 SECTION 4: TERMS AND
CONDITIONS OF THE RFP /
CONTRACT
12. ‘NO CLAIM’ Certificate
No Claim' Certificate: Vendor is not entitled to make any
claim against IDBI by virtue of this Agreement.
Vendor shall not be entitled to make any claim,
whatsoever, against IDBI, under or by virtue of or arising
out of, the Contract / Agreement, nor shall IDBI entertain
or consider any such claim, if made by the Vendor after
he has signed a ‘No Claim’ Certificate in favour of IDBI in
such forms as shall be required by IDBI after the works /
Service(s) are finally accepted.
Vendor reserves its rights to make claims
against IDBI for non-payment of fees, material
breach of the terms of contract and to this
extent shall not be able to sign the 'No claim'
certificate.
No change in this RFP Clause
34 33 SECTION 4: TERMS AND
CONDITIONS OF THE RFP /
CONTRACT
13. Survival
Survival The survival of the indemnity provisions will be
limited to only third party IPR infringement,
specifically patent, trademark and industrial
designs, claims.
No change in this RFP Clause
35 33 SECTION 4: TERMS AND
CONDITIONS OF THE RFP /
CONTRACT
15 No Set-off, counter-claim and
cross claims
No Set-off, counter-claim and cross claims:
In case the Vendor / Bidder has any other business
relationship with IDBI / the Purchaser, no right of set-off,
counter-claim and cross-claim and or otherwise will be
available under this Contract / Agreement to the Vendor
/ Bidder for any payments receivable under and in
accordance with that business.
We submit that this provision should be made
mutual and applicable to both the parties.
No change in this RFP Clause
36 34 SECTION 4: TERMS AND
CONDITIONS OF THE RFP /
CONTRACT
18 Statutory Requirements
Statutory Requirements
During the tenure of the Contract / Agreement nothing
shall be done by the Vendor / Bidder in contravention of
any law, act and / or rules / regulations, there under or
any amendment thereof governing inter-alia customs,
foreign exchange, etc., and shall keep IDBI / the
Purchaser, its directors, officers, employees,
representatives, agents and consultants indemnified in
this regard.
We submit that we will comply with the laws
applicable to us as service provider and will
defend any claims by regulatory authorities in
relation thereto. However, the indemnity
requirement mentioned herein should be
deleted.
No change in this RFP Clause
Page 11 of 41
![Page 12: IDBI Bank Limited Bank's response to the Pre bid queries ...considered for Finacle CBS downtime. More clarity is required. Penalty clauses will require waiver The uptime will be calucated](https://reader034.vdocument.in/reader034/viewer/2022042101/5e7db4595f85dc14d16b9967/html5/thumbnails/12.jpg)
IDBI Bank Limited
S.No Page no RFP Clause no Existing clause Details Clarification Sought Bank Response
RFP for Core Banking System Upgrade / Migration (Migration to Finacle 10.x)
Ref No: IDBI/PCell/RFP/2015-16/026 Dated: 25-January-2016
Bank's response to the Pre bid queries
37 34 SECTION 4: TERMS AND
CONDITIONS OF THE RFP /
CONTRACT
19 IDBI Bank's / Purchaser’s Right
of Inspection and Periodic Audit
(a)
IDBI / the Purchaser reserve the right to inspect and
monitor / assess the progress of the Services at any time
during the course of the Contract / Agreement. The
Purchaser may demand and upon such demand being
made, IDBI / the Purchaser shall be provided with any
document, data, material or any other information,
which it may require, to enable it to assess the progress
of the Service(s).
There is no prior notification process in order
to invoke audit rights. IDBI should ideally
provide Vendor prior notice of its audit. IDBI
to clarify if prior notice will be provided and
the time frame as well. Such audit shall be
conducted in a manner that causes minimum
business interupptions.
No change in this RFP Clause
38 35 SECTION 4: TERMS AND
CONDITIONS OF THE RFP /
CONTRACT
20 Insurance to be taken out by
the bidder
Insurance coverage to be maintained by the Vendor Bidder proposes that it shall take all such
necessary insurances as required under
applicable laws. No project specific insurances
can be taken. However, the transit insurance
shall cover only till the delivery of products to
the customer’s premises.
No change in this RFP Clause
39 35 SECTION 4: TERMS AND
CONDITIONS OF THE RFP /
CONTRACT
21 Contract Prices
c)
The prices stated, shall remain valid for the contract
period. Bank may give orders for additions at the same
price. Any reduction in prices due to the principal
reducing the prices, reduction in duties, taxes etc., by
the Government, shall be passed on to the Bank during
the validity period.
With specifc reference to reduction in duties,
taxes, etc. by the Government. In the event
there is an increase in duties, taxes by the
Government and it leads to increase in input
cost to vendor will the same be paid for by the
Bank as an addition to the total cost of
contract. In such a case will Clause 21 d)
No change in this RFP Clause
Page 12 of 41
![Page 13: IDBI Bank Limited Bank's response to the Pre bid queries ...considered for Finacle CBS downtime. More clarity is required. Penalty clauses will require waiver The uptime will be calucated](https://reader034.vdocument.in/reader034/viewer/2022042101/5e7db4595f85dc14d16b9967/html5/thumbnails/13.jpg)
IDBI Bank Limited
S.No Page no RFP Clause no Existing clause Details Clarification Sought Bank Response
RFP for Core Banking System Upgrade / Migration (Migration to Finacle 10.x)
Ref No: IDBI/PCell/RFP/2015-16/026 Dated: 25-January-2016
Bank's response to the Pre bid queries
40 35 SECTION 4: TERMS AND
CONDITIONS OF THE RFP /
CONTRACT
21 Contract Prices
a)The quoted prices shall be all exclusive of all applicable
taxes, duties. There will be no price escalation during the
contract period and any extension thereof.
b) Prices should be furnished item-wise with break-up of
unit costs as per Commercial bid. The bidder will pass on
to the Bank, the benefit of discounts if any announced
during the period of rate contract in respect of the cost
of the items for which orders have been placed during
the period of contract.
c) The prices stated, shall remain valid for the contract
period. Bank may give orders for additions at the same
price. Any reduction in prices due to the principal
reducing the prices, reduction in duties, taxes etc., by
the Government, shall be passed on to the Bank during
the validity period
We agree that the since this would be a fixed
priced contract, the agreed prices will remain
applicable during the tenure of the contract.
However, we submit that prices for any
extension period should be mutually agreed
between the parties at the time of such
extension. Hence, we propose deletion of "and
any extension thereof".
No change in this RFP Clause
Page 13 of 41
![Page 14: IDBI Bank Limited Bank's response to the Pre bid queries ...considered for Finacle CBS downtime. More clarity is required. Penalty clauses will require waiver The uptime will be calucated](https://reader034.vdocument.in/reader034/viewer/2022042101/5e7db4595f85dc14d16b9967/html5/thumbnails/14.jpg)
IDBI Bank Limited
S.No Page no RFP Clause no Existing clause Details Clarification Sought Bank Response
RFP for Core Banking System Upgrade / Migration (Migration to Finacle 10.x)
Ref No: IDBI/PCell/RFP/2015-16/026 Dated: 25-January-2016
Bank's response to the Pre bid queries
41 38 SECTION 4: TERMS AND
CONDITIONS OF THE RFP /
CONTRACT
25. Representations and
Warranties
xvi)
xvi. That the Vendor / Bidder owns, has license to use or
otherwise has the right to use, free of any pending or
threatened liens or other security or other interests all
Intellectual Property Rights, which are required or
desirable for the Service(s) and the Vendor / Bidder does
not, in carrying on its business and operations, infringe
any Intellectual Property Rights of any person. None of
the Intellectual Property or Intellectual Property Rights
owned or enjoyed by the Vendor / Bidder or which the
Vendor / Bidder is licensed to use, which are material in
the context of the Vendor's / Bidder’s business and
operations are being infringed nor, is there any
infringement or threatened infringement of those
Intellectual Property or Intellectual Property Rights
licensed or provided to the Vendor / Bidder by any
person. All Intellectual Property Rights (owned by the
Vendor / Bidder or which the Bidder is licensed to use)
are valid and subsisting. All actions (including
registration, payment of all registration and renewal
fees) required to maintain the same in full force and
effect have been taken thereon and shall keep IDBI/the
Purchaser, its directors, officers, employees, agents,
representatives and consultants indemnified in relation
We submit that since the finacle licenses will
be in the name of the Bank and Bank will enter
into license agreement directly with the
Licensor, these provisions are not relevant,
and should be removed.
It is hereby clarified that the
indemnties/recourses provided by the Licensor
will be applicable to the Bank.
Finacle licenses will be in the
name of the bank and the bidder
is epxected to comply with this
clause in terms of all other
aspects.
Page 14 of 41
![Page 15: IDBI Bank Limited Bank's response to the Pre bid queries ...considered for Finacle CBS downtime. More clarity is required. Penalty clauses will require waiver The uptime will be calucated](https://reader034.vdocument.in/reader034/viewer/2022042101/5e7db4595f85dc14d16b9967/html5/thumbnails/15.jpg)
IDBI Bank Limited
S.No Page no RFP Clause no Existing clause Details Clarification Sought Bank Response
RFP for Core Banking System Upgrade / Migration (Migration to Finacle 10.x)
Ref No: IDBI/PCell/RFP/2015-16/026 Dated: 25-January-2016
Bank's response to the Pre bid queries
42 41 SECTION 4: TERMS AND
CONDITIONS OF THE RFP /
CONTRACT
27. Termination
c)Termination for Default
IDBI / the Purchaser, without prejudice to any other
right or remedy for breach of Contract, by a written
notice of default sent to the Vendor / Bidder, may
terminate the Contract / Agreement in whole or in part.
We submit that termination for default should
be invoked for serious and material breaches
and not for minor breaches/delays. We also
submit that reasonable cure period should be
provided prior to invocation of termination for
default and this clause should be made
mutual. Hence we propose replacement of this
clause with the following:
“Either party may terminate the contract if the
other party commits a material breach of the
contract (including non-payment of fees) and
fails to cure the same within 45 days of receipt
of a written notice for cure.”
No change in this RFP Clause
43 41 SECTION 4: TERMS AND
CONDITIONS OF THE RFP /
CONTRACT
28 Termination
Consequenses of Termination In the event of a Termination there is no clear
provision for payments to be made by Bank to
Vendor for Services performed till the date of
Terminaiton in the event of Termiantion under
Section 27(a), 27(b ) and 27(d)and for Serivce
performed and accepted in the event of
Termiantion under Section 27(c). Request the
same be clarified in the Terms and Conditions
No change in this RFP Clause
44 41 SECTION 4: TERMS AND
CONDITIONS OF THE RFP /
CONTRACT
27. Termination
d)Termination for other than
Default:
IDBI Bank / the Purchaser, without prejudice to any
other right or remedy and without assigning any reason,
may at its sole discretion, serve upon the Vendor /
Bidder a written notice of 30 (thirty) days, indicating its
intention to terminate the Contract / Agreement and
may terminate the Contract / Agreement in whole or in
part
Bidder requests to delete the clause as this is
termination for convenience
No change in this RFP Clause
Page 15 of 41
![Page 16: IDBI Bank Limited Bank's response to the Pre bid queries ...considered for Finacle CBS downtime. More clarity is required. Penalty clauses will require waiver The uptime will be calucated](https://reader034.vdocument.in/reader034/viewer/2022042101/5e7db4595f85dc14d16b9967/html5/thumbnails/16.jpg)
IDBI Bank Limited
S.No Page no RFP Clause no Existing clause Details Clarification Sought Bank Response
RFP for Core Banking System Upgrade / Migration (Migration to Finacle 10.x)
Ref No: IDBI/PCell/RFP/2015-16/026 Dated: 25-January-2016
Bank's response to the Pre bid queries
45 41 SECTION 4: TERMS AND
CONDITIONS OF THE RFP /
CONTRACT
28 Consequences of Termination
(c )
Where the termination of the Contract / Agreement is
prior to its stipulated term on account of a default on the
part of the Vendor / Bidder or due to the fact that the
survival of the Vendor / Bidder as an independent
corporate entity is threatened/has ceased, IDBI/ the
Purchaser shall pay the Vendor / Bidder for that part of
the Service(s) which have been authorized by IDBI/ the
Purchaser and satisfactorily performed by the Vendor /
Bidder up to the date of termination, without prejudice
to any other rights, IDBI / the Purchaser may retain such
amounts from the payment due and payable by IDBI /
the Purchaser to the Vendor / Bidder as may be required
to offset any losses caused to IDBI / the Purchaser as a
result of any act / omissions of the Vendor / Bidder. In
case of any loss or damage due to default on the part of
the Vendor / Bidder in performing any of its obligations
with regard to executing the Service(s) under the
Contract / Agreement [as laid down in the Service Level
Requirements Annexure-3,] the Vendor / Bidder shall
compensate IDBI /the Purchaser for any such loss,
damages or other costs, incurred by IDBI / the Purchaser.
Additionally, the sub Vendor / Bidder / other members
of its team shall continue to perform all its obligations
and responsibilities under the Contract / Agreement in
Biddder requests to amend this clause to state
that Bidder will be paid based on acceptance
of services/deliverables per the acceptance
criteria. Also, please delete set off and
withholding requirements.
No change in this RFP Clause
46 42 SECTION 4: TERMS AND
CONDITIONS OF THE RFP /
CONTRACT
28 Consequences of Termination
(d)
Nothing herein shall restrict the right of IDBI / the
Purchaser to invoke the Performance Bank Guarantee
and other guarantees, securities furnished, enforce the
Deed of Indemnity and pursue such other rights and / or
remedies that may be available to IDBI / the Purchaser
under law or otherwise
Please delete this clause to reflect that IDBI
should as a first option invoke the 30 days cure
period. Invoking all the guarantees puts the
Vendor in an inherently disadvantageous
position since the actual loss may not be
commensurate with the total value of all the
guarantees and infact the actual loss may be
lesser than the total value of all the
guarantees.
No change in this RFP Clause
Page 16 of 41
![Page 17: IDBI Bank Limited Bank's response to the Pre bid queries ...considered for Finacle CBS downtime. More clarity is required. Penalty clauses will require waiver The uptime will be calucated](https://reader034.vdocument.in/reader034/viewer/2022042101/5e7db4595f85dc14d16b9967/html5/thumbnails/17.jpg)
IDBI Bank Limited
S.No Page no RFP Clause no Existing clause Details Clarification Sought Bank Response
RFP for Core Banking System Upgrade / Migration (Migration to Finacle 10.x)
Ref No: IDBI/PCell/RFP/2015-16/026 Dated: 25-January-2016
Bank's response to the Pre bid queries
47 42 SECTION 4: TERMS AND
CONDITIONS OF THE RFP /
CONTRACT
28 Consequences of Termination
(f)
In the event of termination, IDBI has the right to
publicise such termination to caution customers from
transacting with the Vendor/Bidder
Section 28 (f) - Bidder requests for deletion of
this clause.
No change in this RFP Clause
48 43 SECTION 4: TERMS AND
CONDITIONS OF THE RFP /
CONTRACT
35.Time limit for commencement
of work
Time limit for commencement of work shall be one (1)
week from the date of issuance of purchase order.
Bidder requests to modify the clause to state
that the commencement of work will be post
contract signing as agreed in the SoW by the
parties.
No change in this RFP Clause
49 43 SECTION 4: TERMS AND
CONDITIONS OF THE RFP /
CONTRACT
34.Suspension of Payment to the
Vendor / Bidder
Suspension of Payment to the Vendor / Bidder Bidder request deletion of this clause No change in this RFP Clause
Page 17 of 41
![Page 18: IDBI Bank Limited Bank's response to the Pre bid queries ...considered for Finacle CBS downtime. More clarity is required. Penalty clauses will require waiver The uptime will be calucated](https://reader034.vdocument.in/reader034/viewer/2022042101/5e7db4595f85dc14d16b9967/html5/thumbnails/18.jpg)
IDBI Bank Limited
S.No Page no RFP Clause no Existing clause Details Clarification Sought Bank Response
RFP for Core Banking System Upgrade / Migration (Migration to Finacle 10.x)
Ref No: IDBI/PCell/RFP/2015-16/026 Dated: 25-January-2016
Bank's response to the Pre bid queries
50 44 SECTION 4: TERMS AND
CONDITIONS OF THE RFP /
CONTRACT
38. Intellectual Property Rights
and Patent Rights
c
The Bidder shall ensure that while it uses any software,
hardware, processes or material in the course of
performing the Service(s), it does not infringe the
Intellectual Property Rights of any person and the Bidder
/ Vendor shall keep the Purchase / IDBI, its directors,
employees, agents and representatives indemnified
against all costs, charges, expenses, liabilities, claims,
damages, litigations, suits, judgments and / or otherwise
howsoever, arising out of any illegal or unauthorized use
(piracy) or in connection with any claim or proceedings
relating to any breach or violation of any
permission/license terms or infringement of any
Intellectual Property Rights by the Bidder/Vendor or any
sub-Bidder during the course of performance of the
Service(s).The liability of the bidder in such scenario shall
be unlimited.
We submit that the following exclusions
should be included in the contract:
“Exclusions: Vendor has no obligation for any
claim of infringement to the extent arising
from: (i) any third party materials; (ii) Vendor’s
compliance with or use of Bank’s information,
technology, designs, specifications or
instructions, including those incorporated into
any Statement of Work or deliverable; (iii)
modification of the deliverables by Bank or a
third party; (iv) use of the deliverables in a way
not indicated in the Statement of Work or in
any specifications or documentation provided
with such deliverable; or (v) use of the
deliverables with products not supplied by
Vendor.
Remedies: In the event that an infringement
claim regarding any deliverables appears likely,
Vendor may at its sole discretion, and as
Bank’s sole and exclusive remedy, either:
1. obtain for Bank the right to use the
infringing deliverables; or
2. modify the infringing deliverables so that it
is no longer infringing; or
3. obtain and substitute a functionally similar
deliverables that are not infringing.
No change in this RFP Clause
Page 18 of 41
![Page 19: IDBI Bank Limited Bank's response to the Pre bid queries ...considered for Finacle CBS downtime. More clarity is required. Penalty clauses will require waiver The uptime will be calucated](https://reader034.vdocument.in/reader034/viewer/2022042101/5e7db4595f85dc14d16b9967/html5/thumbnails/19.jpg)
IDBI Bank Limited
S.No Page no RFP Clause no Existing clause Details Clarification Sought Bank Response
RFP for Core Banking System Upgrade / Migration (Migration to Finacle 10.x)
Ref No: IDBI/PCell/RFP/2015-16/026 Dated: 25-January-2016
Bank's response to the Pre bid queries
51 44 SECTION 4: TERMS AND
CONDITIONS OF THE RFP /
CONTRACT
38.Intellectual Property Rights and
Patent Rights
a)
(Purchaser / IDBI shall own and have a right in perpetuity
to use all Intellectual Property Rights which have arisen
out of or in connection with the implementation of the
Contract, including all processes and products which
have been developed by the Bidder/Vendor during the
performance of Service(s) and for the purposes of inter-
alia, use or sub-license of Service(s) under the Contract.
The Bidder undertakes to disclose all Intellectual
Property Rights arising out of or in connection with the
performance of the Service(s) to the Purchaser / IDBI and
execute all such agreements / documents and file all
relevant applications, effect transfers and obtain all
permits, approvals, consents and no objections that may
be necessary in this regard to effectively transfer and
conserve the Intellectual Property Rights of the
Purchaser / IDBI.)
We hereby clairfy that IPR and patent rights of
each party shall continue to vest with the
respective party. SInce, 3rd party software will
be provided / implemented, the provisions
stiuplating Bank's ownership of IPR is not
relevant and should be removed.
We submit for inclusion of the following
provisions in this clause:
“Notwithstanding anything to the contrary
contained elsewhere:
• Each party shall retain ownership of its pre-
existing Intellectual Property Rights (“Pre-
existing IPR”) and any improvements, up-
gradations, enhancements, modifications and
enhancements to and derivative works
thereto;
• Bidder shall retain ownership of all IPR in the
deliverables, materials and reports developed
by the Bidder during the course of the
Agreement and remain therefore able to re-
use any copyrightable or patentable elements
of the deliverables, materials and reports in
any of its future engagements.
• IPR ownership in any third party products
provided by Bidder, and all improvements, up-
No change in this RFP Clause
52 45 SECTION 4: TERMS AND
CONDITIONS OF THE RFP /
CONTRACT
40 User Acceptance Test and
Quality Check
The UAT to be completed to the satisfaction of IDBI and
as per the time frame prescribed by the Bank.
There is no acceptance criteria defined in the
clause and the Business/Operations is
requested to define parametres of acceptance.
The time frame for completion of acceptance
testing is not specified.
Details of acceptance criteria and
the time frame will be mutually
agreed with the successful
bidder.
Page 19 of 41
![Page 20: IDBI Bank Limited Bank's response to the Pre bid queries ...considered for Finacle CBS downtime. More clarity is required. Penalty clauses will require waiver The uptime will be calucated](https://reader034.vdocument.in/reader034/viewer/2022042101/5e7db4595f85dc14d16b9967/html5/thumbnails/20.jpg)
IDBI Bank Limited
S.No Page no RFP Clause no Existing clause Details Clarification Sought Bank Response
RFP for Core Banking System Upgrade / Migration (Migration to Finacle 10.x)
Ref No: IDBI/PCell/RFP/2015-16/026 Dated: 25-January-2016
Bank's response to the Pre bid queries
53 45 SECTION 4: TERMS AND
CONDITIONS OF THE RFP /
CONTRACT
39 Warranty
(b)
Bidder / Vendor should provide software patches /
upgrades towards complying with all the statutory and
any other requirements from the Bank as specified from
time to time during the Contract period, free of cost
Any software patches/upgrades will be at
additional cost to Bank.
No change in this RFP Clause
54 45 SECTION 4: TERMS AND
CONDITIONS OF THE RFP /
CONTRACT
39 Warranty
(f)
The Bank shall notify the Vendor of any claims arising
under this warranty. If the Vendor / Bidder, having been
notified, fails to remedy the defect(s) within a timeframe
specified in the Service Level Requirements in Annexure-
3, the Bank shall proceed to take such remedial action as
may be necessary, at the Vendor’s / Bidder's risk and
expense and without prejudice to any other rights which
the Bank may have against the Vendor under the
Contract or applicable laws or in equity.
Bidder requests that the risk purchase right
under this clause will be invoked only after
providing 30 days cure period to Bidder and
will be capped at 10% of the affected
deliverable.
No change in this RFP Clause
Page 20 of 41
![Page 21: IDBI Bank Limited Bank's response to the Pre bid queries ...considered for Finacle CBS downtime. More clarity is required. Penalty clauses will require waiver The uptime will be calucated](https://reader034.vdocument.in/reader034/viewer/2022042101/5e7db4595f85dc14d16b9967/html5/thumbnails/21.jpg)
IDBI Bank Limited
S.No Page no RFP Clause no Existing clause Details Clarification Sought Bank Response
RFP for Core Banking System Upgrade / Migration (Migration to Finacle 10.x)
Ref No: IDBI/PCell/RFP/2015-16/026 Dated: 25-January-2016
Bank's response to the Pre bid queries
55 46 SECTION 4: TERMS AND
CONDITIONS OF THE RFP /
CONTRACT
45 Limitation of Liability
The Parties acknowledge that circumstances may arise
where on account of a breach by Bidder of the terms of
this RFP and subsequent Agreement, or other
contractual or tortuous claim, the Bank may be entitled
to damages from Bidder.
a) Bidder’s aggregate liability shall be subject to an
overall limit of 100% of the Total Project Cost for the
Contract period.
b) The limits specified in Sub-Clause (a) above shall not
apply to:
i. claims made by the Bank for claims relating to the loss
of or damage to real property and tangible personal
property and for bodily injury or death which is caused
by sole gross negligence or sole willful misconduct of the
Bidder or its employees;
ii. claims against the Bank resulting from misconduct or
gross negligence of the Bidder, its employees and
subcontractors or from infringement of patents,
trademarks, copyrights or such other Intellectual
Property Rights or breach of confidentiality obligations;.
c) The Bank shall not be held liable for and is absolved of
We submit that the aggregate cummulative
liability of the Bidder should be limited to
100% of the total contract value payable by
Bank to the Bidder.
We can agree for liability exclusions
mentioned in sub-point i., however, we submit
that sub-point ii. of sub-clause b) should be
modified as follows:
"ii. claims against the Bank resulting from sole
Gross Negligence or sole Willful Misconduct or
from infringement of patents, trademarks,
copyrights or such other Intellectual Property
Rights ;
We submit that the terms "Gross Negligence"
and "Willful Misconduct" should be defined as
follows
."Willful Misconduct” means any act or
omission of a party which is willfully intended
to harm the interests of the other party,
provided however, that Willful Misconduct
does not include ordinary negligence, an error
of judgment or mistake of a person."
“Gross Negligence” means an indifference to,
and a blatant violation of a legal duty with
respect to the rights of others, being a
conscious and voluntary disregard of the need
to use reasonable care, which is likely to cause
No change in this RFP Clause
56 46 SECTION 4: TERMS AND
CONDITIONS OF THE RFP /
CONTRACT
41 Migration
Time is the essence of this Contract / Agreement and
entire project should be completed within 18 months
from the date of issuance of Contract. A tentative
schedule for project implementation has been provided
under Section 5, Clause 9: Schedule, which can be used
as reference / guidelines
Any delay might constitute material breach
and may result in termination of the contract.
Further, there are remedies which are already
mentioned in the agreement for any delay.
Hence it is proposed that this clause be struck
out/deleted.
No change in this RFP Clause
Page 21 of 41
![Page 22: IDBI Bank Limited Bank's response to the Pre bid queries ...considered for Finacle CBS downtime. More clarity is required. Penalty clauses will require waiver The uptime will be calucated](https://reader034.vdocument.in/reader034/viewer/2022042101/5e7db4595f85dc14d16b9967/html5/thumbnails/22.jpg)
IDBI Bank Limited
S.No Page no RFP Clause no Existing clause Details Clarification Sought Bank Response
RFP for Core Banking System Upgrade / Migration (Migration to Finacle 10.x)
Ref No: IDBI/PCell/RFP/2015-16/026 Dated: 25-January-2016
Bank's response to the Pre bid queries
57 48 Section 5: Scope of Work
b) Scope of the
Service(s), X
Bank will carry out Load/Performance/Stress testing of
the upgraded/migrated version of Finacle /add-on
applications to test the scalability of the applications as
per the projected volumes. Bidder has to provide all
required end to end support (including Application, OS,
Database, middleware, etc.) to carry out the successful
testing with the vendor identified by the Bank.
Bank to share the projected volumes and
period of projections for all the three
instances.
Required details will be shared to
the successful bidder
58 48 Section 5: Scope of Work
1. Broad Scope
b) Scope of the Service(s) X
Performance testing Database for Load/Performance testing is to
be made ready by the Bidder. We believe that
all Hardware and DB/OS/Storage related
services will be provided by bank. Please
confirm.
Refer Section 5, 1 b x. For
Hardware the bidder is expected
to provide only the
recommendation.
59 48 Section 5: Scope of Work 2. Scope
– Details:
Scope We believe that all the licenses for Finacle
upgrade from 7 to 10.x will be procured by
Bank for all the modules that are provided by
Infosys for the three instances in scope.
Necessary license will be
procured by the bank and bidder
will be responsible for
implementation.
60 48 Section 5: Scope of Work 2. Scope
– Details:
Scope We believe that Hardware and all platform
related softwares (Operating system, RDBMS,
Real application cluster, Middleware (WAS,
Weblogic etc)) are being procured by Bank
directly and vendor need not factor for it in
their solution.
The successful Bidder is expected
to provide necessary
recommendation only
61 48 Section 5: Scope of Work 2. Scope
– Details:2.1. Finacle Version
upgrade (Migration to new version
10.x) and data migration.
CBS (India and Dubai) and CBS (Corporate Finance) is
running on AIX with Oracle
RFP mentions use of existing infrastructure
...Request to please confirm the inventory of
the current hardware detailing hardware and
DB configuration. This will help us to
appropriately size the solution
The Details will be provided to
the Successful
bidder.
62 48 Section 5: Scope of Work 2. Scope
– Details:2.1. Finacle Version
upgrade (Migration to new version
10.x) and data migration.
DC is located at Belapur Navi Mumbai Request to please clarify where the DR site is
located and if there is any current redunduncy
setup
DR is at chennai and NDR at
mumbai
Page 22 of 41
![Page 23: IDBI Bank Limited Bank's response to the Pre bid queries ...considered for Finacle CBS downtime. More clarity is required. Penalty clauses will require waiver The uptime will be calucated](https://reader034.vdocument.in/reader034/viewer/2022042101/5e7db4595f85dc14d16b9967/html5/thumbnails/23.jpg)
IDBI Bank Limited
S.No Page no RFP Clause no Existing clause Details Clarification Sought Bank Response
RFP for Core Banking System Upgrade / Migration (Migration to Finacle 10.x)
Ref No: IDBI/PCell/RFP/2015-16/026 Dated: 25-January-2016
Bank's response to the Pre bid queries
63 49 Section 5: Scope of Work
2. Scope – Details:
2.1. Finacle Version upgrade
(Migration to
new version 10.x) and data
migration.
2.1.5. Functional and Technical
Training
Training Training given in Table 2.1.5 and the
subsections in 2.1.5, are these repetitive
trainings or additional trainings? EAP does not
appear in subsections, but pre-DRG training is
mentioned. Trainings in Table to be provided
by OEM, is training in subsection also to be
provided by OEM?
Explanation is provided in the
sub sections for the table given
in 2.1.5
64 50 Section 5: Scope of Work
2. Scope – Details:
2.1.6 DR site and NDR setup
support
a) Bidder / Vendor should carry out the deployment of
the application / DB in DR and NDR as applicable.
Please provide the location details of DR &
NDR
DR - Chennai;NDR - Mumbai
65 50 Section 5: Scope of Work
2. Scope – Details:
2.1.6 DR site and NDR setup
support
a) Bidder / Vendor should carry out the deployment of
the application / DB in DR and NDR as applicable.
What is the RPO/RTO expected? Existing RPO/ RTO are to be
Maintained, The
details will be shared with the
successful Bidder
66 50 Section 5: Scope of Work
2. Scope – Details:
2.1.6 DR site and NDR setup
support
a) Bidder / Vendor should carry out the deployment of
the application / DB in DR and NDR as applicable.
NDR is required to have only the storage
replication and No CBS solution (CBS servers)
required from NDR. Please confirm
NDR - Mumbai will have only the
Storage Replication.
67 50 Section 5: Scope of Work
2. Scope – Details:
2.1.6 DR site and NDR setup
support
a) Bidder / Vendor should carry out the deployment of
the application / DB in DR and NDR as applicable.
DR solution can be standalone and NO High
Avaialbility (HA) required. Please confirm
Oracle RAC needs to be
implemented in Both DC and DR.
68 51 Section 5: Scope of Work
2. Scope – Details:
2.2. Customization Retrofits and
Interface Porting.
2.2.4. Existing Interfaces of Finacle
Core (India / Dubai /IBU
Operations / CFS)
Interfaces Please confirm that Bank will take ownership
for all Interfacing systems (other than CBS) and
interface changes required at their end,
including testing and porting to Production on
other system's end.
Bidder is expected to take care of
interfacing /integrating the
Interfaces at CBS side . Bank will
provide necessary liasoining with
the third party vendor , if any
Page 23 of 41
![Page 24: IDBI Bank Limited Bank's response to the Pre bid queries ...considered for Finacle CBS downtime. More clarity is required. Penalty clauses will require waiver The uptime will be calucated](https://reader034.vdocument.in/reader034/viewer/2022042101/5e7db4595f85dc14d16b9967/html5/thumbnails/24.jpg)
IDBI Bank Limited
S.No Page no RFP Clause no Existing clause Details Clarification Sought Bank Response
RFP for Core Banking System Upgrade / Migration (Migration to Finacle 10.x)
Ref No: IDBI/PCell/RFP/2015-16/026 Dated: 25-January-2016
Bank's response to the Pre bid queries
69 52 Section 5: Scope of Work
2. Scope – Details
2.3.Installation, Integration and
Implementation of new modules /
Add-on Applications
2.3.2.1
Single Sign On a. We presume that Bank already have Single
Sign On solution and bidder expected to only
integrate it with application. Please confirm
b. Please provide the details of Bank's existing
Single Sign On solution
Finacle SSO is to be implemented
by the bidderas per RFP section
5, sub section 2.3
70 53 Section 5: Scope of Work
2. Scope – Details
2.5.Application Maintenance,
Support Services (AMS)
2.5.7
The support coverage would be limited to the Finacle
10.x suite of products (Finacle Core, CRM, SSO, SVS etc)
including the interfaces and new licensed modules that
would be implemented as part of the proposed Finacle
10.x migration / version upgrade and the customizations
that have been done as part of this project
Is Bidder expected to provide the
Infrastructure support for the propsoed HW,
OS, DB. Middleware Or Bank will take care of
the same? Or Only AMS is in scope .Please
confirm
Bidder is expected to provide
only for AMS
71 54 Section 5: Scope of Work
2. Scope – Details
2.5.Application Maintenance,
Support Services (AMS)
2.5.8
Upon intimation of the issue from the IDBI help Desk
Team, the AMS / L2 Support Team would analyze the
issue.
We presume that Helpdesk services (Call
logging/First call resolution) is out of scope for
bidder and bank will take care of the same.
Please confirm
services for Finacle 10.x suit of
products as well
72 54 Section 5: Scope of Work
2. Scope – Details
2.6.Computer Based Training (CBT)
CBT should have interactive video solution with human
voice.
Is the bank expecting the voice of one
standard person through out? This will have
cost implications and other implications as
below
The human recorded voice, will have
dependency on the talent that recorded this
voice. If any changes are required in future and
if that particular talent is not available, the
whole course will have to be rerecorded and
integrate it all over again.
Human recorded audio from
professional talents is expected
Page 24 of 41
![Page 25: IDBI Bank Limited Bank's response to the Pre bid queries ...considered for Finacle CBS downtime. More clarity is required. Penalty clauses will require waiver The uptime will be calucated](https://reader034.vdocument.in/reader034/viewer/2022042101/5e7db4595f85dc14d16b9967/html5/thumbnails/25.jpg)
IDBI Bank Limited
S.No Page no RFP Clause no Existing clause Details Clarification Sought Bank Response
RFP for Core Banking System Upgrade / Migration (Migration to Finacle 10.x)
Ref No: IDBI/PCell/RFP/2015-16/026 Dated: 25-January-2016
Bank's response to the Pre bid queries
73 55 Section 5: Scope of Work
2. Scope – Details
2.8.Go Live Support to the
Branches
Go Live Support to the Branches Where are these 60 regional centers located?
Please share the list of centers which will help
us to plan the Support with 180 people. This is
an logistical challenge. The bank need to have
a finacle champion who is trained on this
version who will handle the issue at his
repective branch.
The Details will be provided to
the Successful
bidder.
74 55 Section 5: Scope of Work
2. Scope – Details
2.8.Go Live Support to the
Branches
Go Live Support to the Branches Such type of Branch Handholding Support
across India Operations is managed by Infosys
along with its business partners to be more
cost effective. Hope IDBI is ok with this sort of
engagement
Please refer Corrigendum.
75 56 Section 5: Scope of Work 2. Scope
– Details: 2.10. Application
Performance Monitoring Tool
Bidder is required to identify and deploy an automated
application monitoring tool for CBS Application. In
future, if the Bank desires to extend this facility to other
application, then tool should be compatible to extend for
other applications available in the banks environment.
Bank will procure the additional licenses for
the future application monitoring requirments
Please confirm
as new licensed modules as per
the RFP terms
76 56 Section 5: Scope of Work
2. Scope – Details:
2.10. Application Performance
Monitoring Tool
Bidder is required to identify and deploy an automated
application monitoring tool for CBS Application. In
future, if the Bank desires to extend this facility to other
application, then tool should be compatible to extend for
other applications available in the banks environment.
Please provide the details of bank's existing
helpdesk & server, DB monitoring tools which
bidder can leverage or bidder expected to
provide the same? Please confirm
Necessary details will be shared
to the successful bidder
77 56 Section 5: Scope of Work
2. Scope – Details:
2.10. Application Performance
Monitoring Tool
Bidder is required to identify and deploy an automated
application monitoring tool for CBS Application. In
future, if the Bank desires to extend this facility to other
application, then tool should be compatible to extend for
other applications available in the banks environment.
Is bidder expected to manage the application
monitoring tool as part of AMS or Bank
existing bank team will take care of the same?
Bidder is expected to handle the
monitoring during the contract
period till the end of AMS period.
Post AMS period , bidder will
handover the same to Bank's
team
Page 25 of 41
![Page 26: IDBI Bank Limited Bank's response to the Pre bid queries ...considered for Finacle CBS downtime. More clarity is required. Penalty clauses will require waiver The uptime will be calucated](https://reader034.vdocument.in/reader034/viewer/2022042101/5e7db4595f85dc14d16b9967/html5/thumbnails/26.jpg)
IDBI Bank Limited
S.No Page no RFP Clause no Existing clause Details Clarification Sought Bank Response
RFP for Core Banking System Upgrade / Migration (Migration to Finacle 10.x)
Ref No: IDBI/PCell/RFP/2015-16/026 Dated: 25-January-2016
Bank's response to the Pre bid queries
78 56 Section 5: Scope of Work
2. Scope – Details:
2.10. Application Performance
Monitoring Tool
1. Should APM have out-of-box capabilities to
monitor Finacle services monitoring at various
levels, such as Finacle Application server (C++
Services), Uniser, CDCI, etc..?
Bidder is expected to provide the
APM solution to monitor the
performance of the end to end
transactions, which includes all
under lined components like
Application ,servers, Os , DB etc
79 56 Section 5: Scope of Work
2. Scope – Details:
2.10. Application Performance
Monitoring Tool
2. Should APM trigger forensic actions based
on alert generated?
Functionality is not required
80 56 Section 5: Scope of Work
2. Scope – Details:
2.10. Application Performance
Monitoring Tool
3. Should APM trigger remedial actions based
on alert generated?
Functionality is not required
81 56 Section 5: Scope of Work
3. System &Security Audit
System security Please confirm that all the security
equipments, their configuration and changes
are out of scope of this RFP, whether they are
for Internet or Intranet. Only CBS application
level security and database inherent security is
in scope.
Bidder is expected to comply
with the security /Audit
requirements for CBS Application
and it ismigration process as per
the RFP terms.
Page 26 of 41
![Page 27: IDBI Bank Limited Bank's response to the Pre bid queries ...considered for Finacle CBS downtime. More clarity is required. Penalty clauses will require waiver The uptime will be calucated](https://reader034.vdocument.in/reader034/viewer/2022042101/5e7db4595f85dc14d16b9967/html5/thumbnails/27.jpg)
IDBI Bank Limited
S.No Page no RFP Clause no Existing clause Details Clarification Sought Bank Response
RFP for Core Banking System Upgrade / Migration (Migration to Finacle 10.x)
Ref No: IDBI/PCell/RFP/2015-16/026 Dated: 25-January-2016
Bank's response to the Pre bid queries
82 56 Section 5: Scope of
Work
2. Scope – Details:
2.10. Application
Performance
Monitoring Tool:
Bidder is required to identify and deploy an automated
application monitoring tool for CBS Application. In
future, if the Bank desires to extend this facility to other
application, then tool should be compatible to extend for
other applications available in the banks environment.
Tool should have the facility to configure various
parameters and set their threshold limit with tolerance
Tool should generate pro-active alerts whenever the
performance of the application is lower / higher than the
defined levels, peak load conditions.
Dash board for monitoring various performance
parameters
Does Infosys (OEM) have to certify proposed
APM solution?
Bidder is expected to provide
APM solution
certified by OEM vendor of CBS
83 56 Section 5: Scope of
Work
2. Scope – Details:
2.10. Application
Performance
Monitoring Tool:
Bidder is required to identify and deploy an automated
application monitoring tool for CBS Application. In
future, if the Bank desires to extend this facility to other
application, then tool should be compatible to extend for
other applications available in the banks environment.
Tool should have the facility to configure various
parameters and set their threshold limit with tolerance
Tool should generate pro-active alerts whenever the
performance of the application is lower / higher than the
defined levels, peak load conditions.
Dash board for monitoring various performance
parameters
How many minimum installations should
proposed APM solution have for Finacle 10
environment?
It should be implemented in DC
and DR
Page 27 of 41
![Page 28: IDBI Bank Limited Bank's response to the Pre bid queries ...considered for Finacle CBS downtime. More clarity is required. Penalty clauses will require waiver The uptime will be calucated](https://reader034.vdocument.in/reader034/viewer/2022042101/5e7db4595f85dc14d16b9967/html5/thumbnails/28.jpg)
IDBI Bank Limited
S.No Page no RFP Clause no Existing clause Details Clarification Sought Bank Response
RFP for Core Banking System Upgrade / Migration (Migration to Finacle 10.x)
Ref No: IDBI/PCell/RFP/2015-16/026 Dated: 25-January-2016
Bank's response to the Pre bid queries
84 56 Section 5: Scope of
Work
2. Scope – Details:
2.10. Application
Performance
Monitoring Tool:
Bidder is required to identify and deploy an automated
application monitoring tool for CBS Application. In
future, if the Bank desires to extend this facility to other
application, then tool should be compatible to extend for
other applications available in the banks environment.
Tool should have the facility to configure various
parameters and set their threshold limit with tolerance
Tool should generate pro-active alerts whenever the
performance of the application is lower / higher than the
defined levels, peak load conditions.
Dash board for monitoring various performance
parameters
How many numbers of branches APM should
support?
The APM solution should not
depend upon number of
branches as monitoring is
needed at centralized location at
DC/DR
85 56 Section 5: Scope of
Work
2. Scope – Details:
2.10. Application
Performance
Monitoring Tool:
Bidder is required to identify and deploy an automated
application monitoring tool for CBS Application. In
future, if the Bank desires to extend this facility to other
application, then tool should be compatible to extend for
other applications available in the banks environment.
Tool should have the facility to configure various
parameters and set their threshold limit with tolerance
Tool should generate pro-active alerts whenever the
performance of the application is lower / higher than the
defined levels, peak load conditions.
Dash board for monitoring various performance
parameters
Should APM solution be able to monitor
Finacle CBS transaction/menu SLA’s which
include their response times in application
environments within the data center & at
branch level?
Bidder is expected to provide the
APM solution to monitor the
performance of the end to end
transactions, which includes all
under lined components like
Application ,servers, Os , DB etc.,
Page 28 of 41
![Page 29: IDBI Bank Limited Bank's response to the Pre bid queries ...considered for Finacle CBS downtime. More clarity is required. Penalty clauses will require waiver The uptime will be calucated](https://reader034.vdocument.in/reader034/viewer/2022042101/5e7db4595f85dc14d16b9967/html5/thumbnails/29.jpg)
IDBI Bank Limited
S.No Page no RFP Clause no Existing clause Details Clarification Sought Bank Response
RFP for Core Banking System Upgrade / Migration (Migration to Finacle 10.x)
Ref No: IDBI/PCell/RFP/2015-16/026 Dated: 25-January-2016
Bank's response to the Pre bid queries
86 56 Section 5: Scope of
Work
2. Scope – Details:
2.10. Application
Performance
Monitoring Tool:
Bidder is required to identify and deploy an automated
application monitoring tool for CBS Application. In
future, if the Bank desires to extend this facility to other
application, then tool should be compatible to extend for
other applications available in the banks environment.
Tool should have the facility to configure various
parameters and set their threshold limit with tolerance
Tool should generate pro-active alerts whenever the
performance of the application is lower / higher than the
defined levels, peak load conditions.
Dash board for monitoring various performance
parameters
Should APM solution be able to track Finacle
transaction/menu with user ID?
Bidder is expected to provide the
APM solution to monitor the
performance of the end to end
transactions, which includes all
under lined components like
Application ,servers, Os , DB etc.,
87 56 Section 5: Scope of
Work
2. Scope – Details:
2.10. Application
Performance
Monitoring Tool:
Bidder is required to identify and deploy an automated
application monitoring tool for CBS Application. In
future, if the Bank desires to extend this facility to other
application, then tool should be compatible to extend for
other applications available in the banks environment.
Tool should have the facility to configure various
parameters and set their threshold limit with tolerance
Tool should generate pro-active alerts whenever the
performance of the application is lower / higher than the
defined levels, peak load conditions.
Dash board for monitoring various performance
parameters
Should APM have out-of-box capabilities to
monitor Finacle services monitoring at various
levels, such as Finacle Application server (C++
Services), Uniser, CDCI, etc..?
Bidder is expected to provide the
APM solution to monitor the
performance of the end to end
transactions, which includes all
under lined components like
Application ,servers, Os , DB etc.,
Page 29 of 41
![Page 30: IDBI Bank Limited Bank's response to the Pre bid queries ...considered for Finacle CBS downtime. More clarity is required. Penalty clauses will require waiver The uptime will be calucated](https://reader034.vdocument.in/reader034/viewer/2022042101/5e7db4595f85dc14d16b9967/html5/thumbnails/30.jpg)
IDBI Bank Limited
S.No Page no RFP Clause no Existing clause Details Clarification Sought Bank Response
RFP for Core Banking System Upgrade / Migration (Migration to Finacle 10.x)
Ref No: IDBI/PCell/RFP/2015-16/026 Dated: 25-January-2016
Bank's response to the Pre bid queries
88 56 Section 5: Scope of
Work
2. Scope – Details:
2.10. Application
Performance
Monitoring Tool:
Bidder is required to identify and deploy an automated
application monitoring tool for CBS Application. In
future, if the Bank desires to extend this facility to other
application, then tool should be compatible to extend for
other applications available in the banks environment.
Tool should have the facility to configure various
parameters and set their threshold limit with tolerance
Tool should generate pro-active alerts whenever the
performance of the application is lower / higher than the
defined levels, peak load conditions.
Dash board for monitoring various performance
parameters
Should APM have support to monitor Finacle
services performance or only availability is
needed?
Monitoring of Finacle services
includes
performance as well as
availability
89 57 Section 5: Scope of Work
5. Other important points to be
noted by the bidder:
Successful bidder will be solely responsible for any delay
in integration with Bank's business applications.
Since integration with Bank's business
applications also involve other vendors, a
delay in providing the required data, etc. by
these vendors can delay the integration. Thus
the bidder should not be held solely
responsible for other vendors delay. Kindly
confirm.
Bidder is responsible for the
delay in their part of work
90 57 Section 5: Scope of Work
5. Other important points to be
noted by the bidder:
The Bidder has to provide all customization source codes
and Documentation to the bank. The relevant IPR related
to customization will be with Bank.
This requirement needs the concurrence of
OEM. Hence request the bank to directly get
the confirmation of OEM (Infosys) instead of
the bidder for the same.
This RPF is for customization and
Migration to Finacle 10.x. The SI
is responsible for the Handover
of the IPR related to bank
specific customization
91 59 Section 5: Scope of Work
6. Deliverables:
a) Finacle 10.x Upgrade /
Migration
Should take care of providing the training to the Core
Team as per the scope.
Kindly clarify who should take care of training
to the Core Team. Is the Bidder supposed to
give the training or the OEM.
Refer to RFP
Page 30 of 41
![Page 31: IDBI Bank Limited Bank's response to the Pre bid queries ...considered for Finacle CBS downtime. More clarity is required. Penalty clauses will require waiver The uptime will be calucated](https://reader034.vdocument.in/reader034/viewer/2022042101/5e7db4595f85dc14d16b9967/html5/thumbnails/31.jpg)
IDBI Bank Limited
S.No Page no RFP Clause no Existing clause Details Clarification Sought Bank Response
RFP for Core Banking System Upgrade / Migration (Migration to Finacle 10.x)
Ref No: IDBI/PCell/RFP/2015-16/026 Dated: 25-January-2016
Bank's response to the Pre bid queries
92 59 Section 5: Scope of Work
6. Deliverables:
a) Finacle 10.x Upgrade /
Migration
1.Server and Database Capacity
Planning
Bank will arrange for the hardware / software / network
based upon Infosys Server and Database capacity
planning recommendations. All the necessary hardware,
Software and network installations and Maintenance
Bank will procure the required proposed HW
and AMC/ATS is out of scope for bidder. Please
confirm
Bidder is expected to provide
only the sizing.
93 59 Section 5: Scope of Work
6. Deliverables:
a) Finacle 10.x Upgrade /
Migration
1.Server and Database Capacity
Planning
Bank will arrange for the hardware / software / network
based upon Infosys Server and Database capacity
planning recommendations. All the necessary hardware,
Software and network installations and Maintenance
Bank will provide all required Network &
security devices like switch, router, firewall,
IPS, Antivirus, VA/PT for the propsoed
environement and management of the same is
out of scope for bidder.Please confirm.
Bank will provide as well as
manage all required Network &
security devices
94 59 Section 5: Scope of Work
6. Deliverables:
a) Finacle 10.x Upgrade /
Migration
1.Server and Database Capacity
Planning
Bank will arrange for the hardware / software / network
based upon Infosys Server and Database capacity
planning recommendations. All the necessary hardware,
Software and network installations and Maintenance
DC/NDR and DR LAN cabling is out of scope for
bidder and Bank will take care of the same .
Please confirm
DC,DR and NDR are in place with
LAN cabling.
95 59 Section 5: Scope of Work
6. Deliverables:
a) Finacle 10.x Upgrade /
Migration
1.Server and Database Capacity
Planning
Bank will arrange for the hardware / software / network
based upon Infosys Server and Database capacity
planning recommendations. All the necessary hardware,
Software and network installations and Maintenance
Netowrk (WAN & Link) management is out of
scope for bidder. Please confirm.
Network (WAN & Link)
management is in place and will
continue.
96 59 Section 5: Scope of Work
5.Other important points to be
noted by the bidder
5.12.9.
periodic run like regular EOD / BOD , month end ,
quarter end , half year end
More clarity is required on expectation, as
EOD/BOD operations are normally run by bank
personnel.
Executing the regular Finacle
related activiies like EOD, BOD
Month end etc .. in UAT during
all the migration iterations are to
be done by the bidder.
97 60 Section 5: Scope of Work
6. Deliverables:
a) Finacle 10.x Upgrade /
Migration
3.Training
User Manuals including the customizations specifically
done for IDBI Bank Ltd.
Is it ok to create Job Aids which will serve as a
ready reckoner for users for their specific
processes. This will also have screenshots of
the actual system.
Base product manuals can be provided
seperately
Bidder is expected to deliver
base product user manuals along
with documents on
customization.
Page 31 of 41
![Page 32: IDBI Bank Limited Bank's response to the Pre bid queries ...considered for Finacle CBS downtime. More clarity is required. Penalty clauses will require waiver The uptime will be calucated](https://reader034.vdocument.in/reader034/viewer/2022042101/5e7db4595f85dc14d16b9967/html5/thumbnails/32.jpg)
IDBI Bank Limited
S.No Page no RFP Clause no Existing clause Details Clarification Sought Bank Response
RFP for Core Banking System Upgrade / Migration (Migration to Finacle 10.x)
Ref No: IDBI/PCell/RFP/2015-16/026 Dated: 25-January-2016
Bank's response to the Pre bid queries
98 60 Section 5: Scope of Work
6. Deliverables:
a) Finacle 10.x Upgrade /
Migration
3. Training
Training scope Please confirm that training infrastructure for
onsite trainings will be provided by Bank.
Refer Page 49 section 5 , 2.1.5.
(iii) and (iv).
99 60 Section 5: Scope of Work
6. Deliverables:
a) Finacle 10.x Upgrade /
Migration
2.Set up and Maintenance of
various Environments
Production, Daily MIS, Monthly MIS and DR, Test server
(End User familiarity), Environments will be maintained
by Bank Team.
Is Infrastructure setup of different
environments (T&D, UAT, Prod etc..) and
maintenance out of scope for bidder & only
Application setup & maintenance is in scope
for bidder? Please confirm
Bidder is expected to provide
Application setup,maintenance
and support of listed servers
/environments as per the RFP
100 64 Section 5: Scope of Work
6. Deliverables:
b) Customization Retro Fitting /
Porting and Interface porting
i. The Vendor / Bidder shall provide the technical design
document including
Deliverables shall comprise:
Design Specification document.
System Requirement specification document
Release Notes
Source Codes
User Manuals
Release notes will be provided for logical set of
customisations along with source codes. User
manuals and job cards need to be prepared by
bank.
UET manuals will be provided for base product
funactionalities and not for customisations.
No change in this RFP Clause
101 67 Section 5: Scope of Work
10.Responsibilities of OEM Vendor
(Infosys)
The OEM’s involvement in the project should be at least
20% of the efforts as specified in Annexure-2 (Table – A:
Cost of Migration / Up gradation) and detailed
accountability of OEM as specified in Section – 5, Clause
– 6: Deliverables during various stages of migration
As OEM/Its sister concern may compete with
other Bidders. Hence bidder requests either
OEM should not compete or Bank should take
separate quote common to all bidders for fixed
mandays from the OEM, which may not be the
part of the TCO
No change in this RFP Clause
102 68 Section 6: Functionality and
Architectural Details
2. Hardware Recommendations
Hardware We are assuming that all Hardware, including
DAR, APM etc will be procured by Bank.
Please confirm
The successful Bidder is expected
to provide necessary
recommendation only
103 68 Section 6:
Functionality and
Architectural Details
2. Hardware
Recommendations
Hardware Sizing Please share the business volumes,users,
customers, transactions, no. of policies etc and
the projected growth over a period of next 5
years?
Required details will be shared to
the successful bidder
Page 32 of 41
![Page 33: IDBI Bank Limited Bank's response to the Pre bid queries ...considered for Finacle CBS downtime. More clarity is required. Penalty clauses will require waiver The uptime will be calucated](https://reader034.vdocument.in/reader034/viewer/2022042101/5e7db4595f85dc14d16b9967/html5/thumbnails/33.jpg)
IDBI Bank Limited
S.No Page no RFP Clause no Existing clause Details Clarification Sought Bank Response
RFP for Core Banking System Upgrade / Migration (Migration to Finacle 10.x)
Ref No: IDBI/PCell/RFP/2015-16/026 Dated: 25-January-2016
Bank's response to the Pre bid queries
104 68 Section 6:Functionality and
Architectural Details
2. Hardware Recommendations
e
e. The proposed system should be able to communicate
with the fallback / backup / disaster systems in case the
main central server fails.
Since the current setup is on AIX, could the
bank please clarify if there a current cluster
setup in place (PowerHA)? Whether its an
Active-Active or Active-Passive setup
Cluster set up is in place (Power
HA) with Active-Passive setup.
105 68 Section 6:Functionality and
Architectural Details
2. Hardware Recommendations
f
f .The Vendor should advise details of the minimum
configuration of various Hardware components like
Servers, Storage, Scanners, etc and any other Software
like Databases, Application servers and third party
software required to make the FINACLE 10.x application
functional and operational for the above specified
volumes. The bidders should also specify the backup
mechanisms supported by the solution along with the
hardware and software required for the same
Request to please clarify if any backup
infrastrucutre exists and can be utilized or a
new solution is to be proposed
Backup infrastructure is already
there and the same can be used
for New solutions
106 68 Section 6:Functionality and
Architectural Details
2. Hardware Recommendations
f
f. The bidders should also specify the backup
mechanisms supported by the solution along with the
hardware and software required for the same.
a. Bidder is expected to propose only the
additional tape libraries and Bank will provide
the required backup software and agents for
the propsoed servers. Please confirm
b. Please provide the current backup software
details.
Backup infrastructure is already
there and the same can be used
for New solutions.. Successful
bidder will be provided with the
necessary details
107 69 Section 6:Functionality and
Architectural Details
2. Hardware Recommendations
g
g) If the Application is portable on multiple platforms like
AIX / HP-UX / Sun Solaris Based servers then specify the
minimum configuration for each of the platform.
is bidder also allowed to propose the X86
platform along with RISC/EPIC platforms
mentioned?
This will be discussed with the
successful bidder during the
sizing recommendation
Page 33 of 41
![Page 34: IDBI Bank Limited Bank's response to the Pre bid queries ...considered for Finacle CBS downtime. More clarity is required. Penalty clauses will require waiver The uptime will be calucated](https://reader034.vdocument.in/reader034/viewer/2022042101/5e7db4595f85dc14d16b9967/html5/thumbnails/34.jpg)
IDBI Bank Limited
S.No Page no RFP Clause no Existing clause Details Clarification Sought Bank Response
RFP for Core Banking System Upgrade / Migration (Migration to Finacle 10.x)
Ref No: IDBI/PCell/RFP/2015-16/026 Dated: 25-January-2016
Bank's response to the Pre bid queries
108 70 Section 7: Technical Details
Required From Bidder
The bidder is required to provide
the following information in the
Technical Bid
1
Vendor / Bidder should provide extensive
documentation related to the CBS Application’s new
version Finacle 10.x (along with the new modules which
will get implemented ) such as
User Manuals
System Reference Manuals
Error Messages and their Meanings
Training Manuals
Additions / changes to the database / application after
migration / upgrades
Operations Manuals
Data Dictionary
Many of these items (under section 7) can be
provided only after the contract is signed
and/or along with the defined milestones
related to the project like UET, Migration etc.
These cannot be provided upfront.
Bidder is expected to submit an
undertaking letter for providing
the referred documents as per
this clause while submitting the
bid. Successful bidder has to
deliver the referred documents
during project initiation.
109 84 Form-1('c)Fulfillment of Eligibility
Criteria
10
The bidder can make consortium but cannot sub-
contract the job to any other company or firm and the
implementation for the Bank must be done by the
employees of the consortium members only. Consortium
agreement to be shared with the Bank clearly specifying
the roles and responsibilities and services rendered.
Prime bidder will be sole responsible for the entire
project.
This clause needs to be removed. The
ownership for the project is with Finacle and
any sub contracting or outsourcing will be
done in the interest of the project. Fiancle is
committed and take full ownership of the
project. It is diffucult to anticipate the
requriements at this stage and request bank to
reconsider the removal of the consortium
clauses.
No change in this RFP Clause
110 100 Form-9
Technical Bid Evaluation Criteria
Should have successfully implemented or under process
of new implementation Finacle CBS within last 10 years
for Banks in India having at least 500 branches Proof of
such work should be submitted along with the response
As IDBI Bank is a PSU Bank and has more than
1500 branches. We request Bank to amend
this evalution cluase as "Should have
successfully implemented or under process of
new implementation Finacle CBS within last 10
years for PSU Banks in India having at least
1500 branches Proof of such work should be
submitted along with the response"
No change in this RFP Clause
Page 34 of 41
![Page 35: IDBI Bank Limited Bank's response to the Pre bid queries ...considered for Finacle CBS downtime. More clarity is required. Penalty clauses will require waiver The uptime will be calucated](https://reader034.vdocument.in/reader034/viewer/2022042101/5e7db4595f85dc14d16b9967/html5/thumbnails/35.jpg)
IDBI Bank Limited
S.No Page no RFP Clause no Existing clause Details Clarification Sought Bank Response
RFP for Core Banking System Upgrade / Migration (Migration to Finacle 10.x)
Ref No: IDBI/PCell/RFP/2015-16/026 Dated: 25-January-2016
Bank's response to the Pre bid queries
111 100 Form-9
Technical Bid Evaluation Criteria
Should have done upgrade /migrate of Finacle CBS from
version 6.x to 7.x within last 10 years for banks in India
having at least 500 branches. Proof of such work should
be submitted along with the response.
We request to delete this point as no Major
Bank compare to type and size of IDBI Bank
has gone for 6.x to 7.x upgrade in last 10 years.
In our view having this experience will not add
any value to a big PSU Bank.
No change in this RFP Clause
112 100 Form-9
Technical Bid Evaluation Criteria
Should have done upgrade /migrate or under process of
migration of Finacle CBS from version 7.x to 10.x within
last 10 years for banks in India having at least 500
branches. Proof of such work should be submitted along
with the response
As IDBI Bank is a PSU Bank and has more than
1500 branches. We request Bank to amend
this evalution cluase as "Should have done
upgrade /migrate or under process of
migration of Finacle CBS from version 7.x to
10.x within last 10 years for PSU banks in India
having at least 1500 branches. Proof of such
work should be submitted along with the
response"
No change in this RFP Clause
113 112 Annexure - 2:
Commercial bid- Contents and
Formats
Cost of Additional Customization efforts for30 days (as
per Man-days applicable post implementation - for
arriving at Rate Contract)
1 month is rquivalent to 22 person days.
Please rectify.
No change in this RFP Clause
114 112 Annexure - 2:
Commercial bid- Contents and
Formats
Cost of Additional Customization efforts for30 days (as
per Man-days applicable post implementation - for
arriving at Rate Contract)
There are multiple people involved in any
project and hence the T&M rate will vary for
SSE, TL/TA, PM, Trainer. Further onsite rates
will have perdiem and travel airfare costs.
Airfare will be billed as actuals.
No change in this RFP Clause
115 112 Annexure - 2: Commercial bid-
Contents and Formats
Cost of customization and porting / development/
debugging/ implementation / minor enhancements and
interface integration for Finacle (IBU Operations) as of
DRG commencement date. (Approx. 40 Menu Options
including Core Menu Customizations, which consists of
around 100 (SCR/MRT/COM/MRI/SQL)).
Since IBU is not implemented, please explain
the logic behind 40 menu options.
The requirement is on the similar
lines of Finacle Core (Dubai
Operations)
116 116 Annexure 3
Service Level Expectations
SLA Matrix Request to please specify the uptime
requirements of the systems
Refer Page No 29 - Section 4
clause 4
Page 35 of 41
![Page 36: IDBI Bank Limited Bank's response to the Pre bid queries ...considered for Finacle CBS downtime. More clarity is required. Penalty clauses will require waiver The uptime will be calucated](https://reader034.vdocument.in/reader034/viewer/2022042101/5e7db4595f85dc14d16b9967/html5/thumbnails/36.jpg)
IDBI Bank Limited
S.No Page no RFP Clause no Existing clause Details Clarification Sought Bank Response
RFP for Core Banking System Upgrade / Migration (Migration to Finacle 10.x)
Ref No: IDBI/PCell/RFP/2015-16/026 Dated: 25-January-2016
Bank's response to the Pre bid queries
117 116 Annexure 3
Service Level Expectations
Showstopper- Response-Immediate; Resolution-
Immediate
Please eloborate Immediate resolution ?
Request bank to change the response as 15
mins and resolution as 2 hours as it depends
on root cause analysis and resolution
Please refer Corrigendum.
118 117 Annexure - 4:
Unconditional
Acceptances of the
Terms & Conditions
We need to have deviations and assumptions
which will be part of SOW and proposal
No change in this RFP Clause
119 120 Annexure 6
Application Maintenance Support
services - Resource Requirement
9. One Senior Technical Expert for Infrastructure (OS/DB configuration, all Finacle services set-up / administration, WAS setup / administration etc.) Understand that the RFP states requirement
for one Senior Technical Expert for
OS/DB/Finacle Services/WAS
setup/configuration? We would like to
highlight that it will not be possible for one
resource to handle both Infrastructure and
Application/WAS related configuration.
The numbers given in the RFP, is
the minimum expectation and
the bidder is required to provide
optimum team over and above
the minimum level specified.
120 122 Annexure - 4:
Unconditional
Acceptances of the
Terms & Conditions of
the RFP
Unconditional Acceptance of T&Cs of the RFP: Requires
Bidder to unconditionally accept the terms and
conditions of the RFP.
We request to modify this clause to include
that the deviations proposed by the Bidder
shall form integral part of Bidder's proposal.
We also understand that upon downselection
the terms and conditions of the governing
contract will be mutually discussed and agreed
between the parties.
No change in this RFP Clause
121 999 EMD & DD EMD & DD We have submitted the bid the bid earlier
along woth DD and BG towards the RFP. Trust
bank will consider the earlier issued DD and BG
for this RFP as well as infosys will not be
issuing fresh DD and BG.
Bidders who have submitted the
DD earlier need not submit
again. For BG , the validity
period should be exteneded as
per the present RFP terms.
Page 36 of 41
![Page 37: IDBI Bank Limited Bank's response to the Pre bid queries ...considered for Finacle CBS downtime. More clarity is required. Penalty clauses will require waiver The uptime will be calucated](https://reader034.vdocument.in/reader034/viewer/2022042101/5e7db4595f85dc14d16b9967/html5/thumbnails/37.jpg)
IDBI Bank Limited
S.No Page no RFP Clause no Existing clause Details Clarification Sought Bank Response
RFP for Core Banking System Upgrade / Migration (Migration to Finacle 10.x)
Ref No: IDBI/PCell/RFP/2015-16/026 Dated: 25-January-2016
Bank's response to the Pre bid queries
122 999 General Monitoring Please confirm if we need to propose
infrastructure monitoring tools? Are there
already monitoring tools available with the
bank on the existing infrastructure that can be
leveraged
Bidder is expected to provide the
APM solution to monitor the
performance of the end to end
transactions, which includes all
under lined components like
Application ,servers, Os , DB etc.
123 999 General Network While we can give recommendation on
bandwidth required, bank will procure and
provide the bandwidth for replication and
connectivity of their branches?
The successful Bidder is expected
to provide necessary
recommendation only.
124 999 General Network Please confirm if we need to propose the
networking equipments like
Firewall,Router,Ethernet Switches as part of
the solution?
The successful Bidder is expected
to provide necessary
recommendation only.
125 999 General Incident logs and SR log Bank to please share list of incidents and
service requests for last one year for all the
three instances.
Required details will be shared to
the successful bidder.
126 999 General Customization and reports Bank to please share list of customizations,
reports and interfaces that are done on Finacle
v7.
Approx no of customization are
given in
Annexure -2 , B1 and B2. Further
details will be shared to the
successful bidder.High level
classification are given under
section 1, point 2
127 999 General Travel we are assuming that entire project will be
carried out from Mumbai and no travel to
Dubai or elsewhere will be required. The
project team from Bidder and Bank, both will
be workint out of Mumbai office.
The bidder is expected to carry
out the entire migration project
from DC at Navi Mumbai except
the 'Core Team Training ' (partly),
'Enduser training' and 'Go Live
Support to Branches' as per RFP
terms
Page 37 of 41
![Page 38: IDBI Bank Limited Bank's response to the Pre bid queries ...considered for Finacle CBS downtime. More clarity is required. Penalty clauses will require waiver The uptime will be calucated](https://reader034.vdocument.in/reader034/viewer/2022042101/5e7db4595f85dc14d16b9967/html5/thumbnails/38.jpg)
IDBI Bank Limited
S.No Page no RFP Clause no Existing clause Details Clarification Sought Bank Response
RFP for Core Banking System Upgrade / Migration (Migration to Finacle 10.x)
Ref No: IDBI/PCell/RFP/2015-16/026 Dated: 25-January-2016
Bank's response to the Pre bid queries
128 999 General (Approx. 1700 Menu Options including Core Menu
Customizations, which consists of around 10,000
(scripts/mrt/com/mri/sql)).
Can we assume this as the total customisation
efforts for India operations? Can the Bank
share the man-months customisation efforts
done on the existing version.
It has been built gradually over
the period of 15 years the over
all customisation is provided for
reference.
129 999 General (Approx. 40 Menu Options including Core Menu
Customizations, which consists of around 300
(scripts/mrt/com/mri/sql)).
Can we assume this as the total customisation
efforts for Dubai operations? Can the Bank
share the man-months customisation efforts
done on the existing version.
It has been built gradually over
the period of 5 years the over all
customisation is provided for
reference.
130 999 General Acceptance We submit that the following provision on
accptance should be included in the contract:
"All products (hardware and software) will be
accepted on delivery. Bidder will provide
notice to Customer when the Deliverables are
ready for acceptance. Acceptance of
Deliverables will occur upon the date Bidder
demonstrates to Customer, by the successful
completion of acceptance tests that the
Deliverables substantially conform to the
acceptance criteria as agreed between
Customer and Bidder and mentioned in the
SOWs attached. Acceptance will not be
delayed for any reason (s) other than non-
conformance with the requirements specified
in the terms of Contract and SOW. The
acceptance test results will be declared by
Bank within a maximum of 7 (seven) days from
the completion of acceptance tests. In case the
7 (seven) days period after completion of
acceptance tests has elapsed without the
acceptance test results being declared, then
the system or the portion thereof, subject to
acceptance testing would be deemed
accepted. If Bank fails to give Bidder written
notice of non-conformance within the 7
(seven) day period or, prior to expiry of the 7
(seven) day period, uses the system or any
No change in this RFP Clause
Page 38 of 41
![Page 39: IDBI Bank Limited Bank's response to the Pre bid queries ...considered for Finacle CBS downtime. More clarity is required. Penalty clauses will require waiver The uptime will be calucated](https://reader034.vdocument.in/reader034/viewer/2022042101/5e7db4595f85dc14d16b9967/html5/thumbnails/39.jpg)
IDBI Bank Limited
S.No Page no RFP Clause no Existing clause Details Clarification Sought Bank Response
RFP for Core Banking System Upgrade / Migration (Migration to Finacle 10.x)
Ref No: IDBI/PCell/RFP/2015-16/026 Dated: 25-January-2016
Bank's response to the Pre bid queries
131 999 General Product Separation The acceptance criteria or procedures for
Deliverables set forth in this Agreement and as
particularly described in any SOW will only
apply to the services provided herein. It will
not apply to any product the Bidder may
supply or has supplied to customer, regardless
of whether such products can be used in
connection with the services or Deliverables.
Any refund/return or penalty rights as set
forth hereon apply only to the services
provided.
No change in this RFP Clause
132 999 General Onsite support Please specify the scope of activities for the
onsite support team for Infrastructure?
Details will be shared to the
successful bidder
133 115,
16,35
Note, 3.8, 21(a) The price quoted must be exclusive of all taxes. The
service tax, if applicable, will be paid on actual. Other
applicable tax would be deducted at source, if any, as
per prevailing rates.
The quoted prices shall be all exclusive of all applicable
taxes, duties
Bidder requests the Bank to make the tax
clauses consistent as per pricing template note
with GST note i.e. The Total Cost quoted will
be exclusive of applicable taxes viz. sales tax,
VAT, Service tax, Octroi / Entry Tax / Local
Body Tax (LBT) and change changes thereof,
will be payable at actuals. All other taxes &
levies have to be included total cost as
mentioned above. Please note receipt can be
provided for Octroi and not for service tax,
VAT etc. in the name of 'IDBI Limited' as those
are paid against specific name.
No change in this RFP Clause
Page 39 of 41
![Page 40: IDBI Bank Limited Bank's response to the Pre bid queries ...considered for Finacle CBS downtime. More clarity is required. Penalty clauses will require waiver The uptime will be calucated](https://reader034.vdocument.in/reader034/viewer/2022042101/5e7db4595f85dc14d16b9967/html5/thumbnails/40.jpg)
IDBI Bank Limited
S.No Page no RFP Clause no Existing clause Details Clarification Sought Bank Response
RFP for Core Banking System Upgrade / Migration (Migration to Finacle 10.x)
Ref No: IDBI/PCell/RFP/2015-16/026 Dated: 25-January-2016
Bank's response to the Pre bid queries
134 30 SECTION 4: TERMS AND
CONDITIONS OF THE RFP /
CONTRACT
6. Indemnity
Indemnity
The Bidder / Vendor shall execute and furnish to the
Purchaser / the Bank, a deed of indemnity in favour of
the Purchaser / the Bank in a form and manner, as given
in Annexure 1 (Form -5) and shall indemnify the Bank
against all third party claims of infringement of patent,
trademark or industrial design rights arising from use of
the Goods, or any part thereof in India. The Bidder /
Vendor shall, at their own expense, defend and
indemnify the Bank against all third party claims or
infringement including that on account of intellectual
Property Right, including Patent, trademark, copyright,
trade secret or industrial design rights arising from use
of the products or any part thereof in India or abroad.
We will defend or settle any third party claims
alleging that the HPE branded
products/services being provided by us
infringe any third party IPR.
The standard IPR infringement indemnity that
is offered by third party branded OEM
manufacturers and licensors will be directly
available to the Customer.
No change in this RFP Clause
Page 40 of 41
![Page 41: IDBI Bank Limited Bank's response to the Pre bid queries ...considered for Finacle CBS downtime. More clarity is required. Penalty clauses will require waiver The uptime will be calucated](https://reader034.vdocument.in/reader034/viewer/2022042101/5e7db4595f85dc14d16b9967/html5/thumbnails/41.jpg)
IDBI Bank Limited
S.No Page no RFP Clause no Existing clause Details Clarification Sought Bank Response
RFP for Core Banking System Upgrade / Migration (Migration to Finacle 10.x)
Ref No: IDBI/PCell/RFP/2015-16/026 Dated: 25-January-2016
Bank's response to the Pre bid queries
135 30, 34,
38
88 - 90
a Indemnity: The indemnity terms address all third party
claims and all third party IPR claims including
infringement on account of infringement including that
on account of intellectual Property Right, including
Patent, trademark, copyright, trade secret or industrial
design rights arising from use of the products or any part
thereof in India or abroad.
Annexure 1 (Form 5) - Deed of indemnity
There are several indemnity clauses in the RFP that creates
inconsistency, therefore Bidder requests to modify the existing
clauses to reflect the below:
"The Indemnifying Party ("Bidder") shall defend (settle and/or
pay damages awarded by the court) the Indemnified Party
("Bank") against any third party claims arising from the
following:
a. Claims for loss or damage to third party tangible property;
b. claim by any person in respect of bodily injury or death;
c. claims by any third party in respect of any IP infringement;
brought against or recovered from Indemnified Party by reasons
of any act or omission of the Indemnifying Party , his agents or
employees in the performance of the contractual obligation.
The indemnification by Indemnifying Party shall be subject to
Indemnified Party i) notifying the Indemnifying Party promptly
in writing of the claim in respect of which the indemnity applies
in order to allow the Indemnifying Party the opportunity to
investigate and defend the matter; ii) agrees to cooperate in
good faith with the Indemnifying Party at the request and
expense of the Indemnifying Party; and iii) giving the
Indemnifying Party the right to defend and settle the claim,
including any agreement relating to settlement; provided that
settlement of claim shall not imposes any financial obligation on
the Indemnified Party. iv) Duty to mitigate the loss
In case of any Indemnity claim by third party related to bodily
injury, death, tangible property, IPR Infringement the
Indemnifying Party shall pay defense cost, settlement amount or
court awarded damage. Both Indemnifying Party and
Indemnified Party specifically agree that Indemnifying Party is
not liable to the Indemnified Party for indemnification
obligations under the agreements to the extent that the act or
omission of the Indemnified Party or any of its agent or
employee or subcontractor contributed to that breach which
gave rise to a claim for indemnity. Indemnified Party also
undertakes to take reasonable effort to mitigate the loss to
Indemnifying Party as any reasonable person would do in similar
circumstances.
No change in this RFP Clause
Place : Mumbai
Date : 11 February 2016
Page 41 of 41