iec 62368-1: the latest on impact, transition - amazon...
TRANSCRIPT
UL AND THE UL LOGO ARE TRADEMARKS OF UL LLC © 2017. ALL RIGHTS RESERVED
IEC 62368-1:
The Latest on Impact, Transition &
Status…
Jeff Pasternak
Product Regulatory
Business Strategist
Data Center Group
Intel Corporation
Tom Burke
Principal Product Safety Engineer,
Consumer & Enterprise
Technology Equipment
UL LLC
Grant Schmidbauer, Nemko USA, Inc.
In preparation with:
IEEE/PSES Sand Diego Chapter meeting Dec. 2017
2
Abstract
• Tom Burke UL LLC, and Jeff Pasternak, Intel Corp.
presented a status update on IEC 62368-1 at ISPCE 2017 in
San Jose, CA (May 2017).
• This presentation is a recap of that presentation with latest
updates since May 2017.
• IEC 62368-1 Ed. 2 (Safety of AV/ICT Equipment) has been
adopted in two major regions of the world, North America
(Canada & U.S.) and Europe (EU), and is in the process of
being adopted in other countries & regions, some possibly
as early as the second half of this year.
• Formal transition dates are approaching fast, driving a
recent uptick in worldwide interest in the standard,
especially by manufacturers who will be directly impacted.
2
3
Abstract
• IEC TC108’s Hazard-Based Standard Development Team (HBSDT) met previously this year in April and have met again in October, thus providing a good opportunity for PSES members attending SPCE 2017 (Boston, MA) to get an update on the latest work on Ed. 3 of IEC 62368-1, plus other late-breaking updates and developments associated with the Edition No. 2 transition, including planned adjustment of the EU formal transition date (DOW) by 18 months.
• This presentation will concentrate on key challenges and observations from a manufacturer’s perspective, and from a certifier’s experience, but also allow ample time for audience members to share personal knowledge, experiences, perspectives and concerns.
3
4
Topics
IEC 62368-1: Introduction
A Manufacturer’s Perspective: Key Considerations
IEC 62368-1, Edition No. 3 (pending)
Transition Update
USB issues & (new) IEC 62368-3 (time permitting)
4
IEC 62368-1: Introduction
5
6
The IEC & IEC 62368-1
• The International Electrotechnical Commission (IEC) drives global
standardization in the field of safety
• IEC standard development committees consist of deemed experts
• Globally countries adopt the use of IEC standards with National
differences
• IEC 62368 is the safety standard of Audio, Visual, Information &
Communication Technology Equipment
developed to be technology independent
a hazard-based safety standard
7
TC74
Transition History to IEC 62368-1
IEC 380
Office Equipment
IEC 435
Data Office
Equipment
IEC 60950-1
Information
Technology
Equipment
IEC 60065
Audio, Video ,
Similar Apparatus
IEC Guide 112
Guide for Safety
of Multimedia
Equipment
ACOS(Advisory Committee
on Safety)
TC92
IEC 62368-1
Audio / Video
Information and
Communication Technology
Equipment
TC108
HBSDT
Hazard Based Safety Standard
Technology Independent
8
IEC 62368-1 - Market Relevance
Total 43% of the CB Scheme
Covers almost all electronic equipment in your living rooms
9
IEC 62368-1 Uses a Three Block Model
Hazardous
Energy
Source
Transfer
MechanismBody Part
Model for Injury
Hazardous
Energy
Source
Body PartSafe Guard
Model for Safety
10
Hazards Covered by in IEC 62368-1
10
For each hazard, energy sources are classified into three levels:
Level 1: Non-detectable to a detectable energy source
Level 2: Detectable to painful energy
Level 3: Painful to harmful energy
Electric Shock
Fire (internal / external)
Hazardous Substances (battery, chemical, ozone)
Mechanical (stability, sharp edges, moving parts)
Thermal Burn (hot surfaces)
Radiation (laser, x-ray, optical, sound)
11
IEC 62368-1 Required Safeguards (ISO/IEC Guide 51 principles)
Level 3 EnergyPainful to harmful
Level 2 EnergyDetectable to
painful
Level 1 EnergyNon-detectable to
detectable
Energy Source
Hazardous?
NO
YESNo safeguard
required
Single
Safeguard
Double
Safeguard
Ordinary Person
Instructed Person
Skilled Person
IEC 62368-1
A Manufacturer’s Perspective w’ Key
Considerations
12
13
Scl. 4.1.1 Acceptance of IEC 60950/60065
Components
Sub-clause 4.1.1 was purposely included in IEC62368-1
to help manufacturers during transition period
Sub-clause 4.1.1 has caused debates:
• What is a component or subassembly?
• Why only valid in second edition?
There is a note in IEC 62368-1, 2nd Edition that reference components and subassemblies that already
comply with IEC 60950-1 or IEC 60065 are to be acceptable as part of the equipment covered by
IEC62368-1 without further evaluation other than to give consideration to appropriate use of the
component or subassembly in the end-product.
There is also an additional note in IEC 62368-1 to eliminate Scl.4.1.1 in ed. 3 of the standard, however
this is now removed..
14
Why is Scl. 4.1.1 so Important to Manufacturers?
To ease the transition for manufacturers
Manufacturers currently cannot procure certified wiring to IEC wiring
standards (IEC 60332-series) referenced in IEC 62368-1
Its inevitable some countries will be late in adopting 3rd Edition - some
products not able to certified to 2nd Edition without 4.1.1
Helps with many near end of life component products – alleviates
unnecessary need to not update a new certification – especially when
new standard technically is NOT developed to deal with safety issues
15
Why is Scl. 4.1.1 so Important to Manufacturers?
IEC 62368-1 references the requirement for wiring to be compliant
with IEC 60695- and 60332-based Standards for flammability of wire
insulation and tubing. Very few suppliers of wiring complying with
these standards available.
We need to find a way to allow manufacturers to use the existing
evaluation for wire and tubing insulation, while the industry prepares
for the IEC wiring standards
Wiring
• 3rd Edition to include alternative acceptance criteria based on similar testing for UL
approved wire
• Wire insulation shall comply with the recommended performance requirements of the
applicable IEC 60332 standards. Alternatively, the wire insulation and tubing shall comply
with IEC/TS606095-11-21, with the sample conditioning of 6h minimum and without
consideration for pigmentation
Additional TC108 work to help…
16
Avoid:
• Redesign of ventilation openings new IEC 62368-1
flame cone area requirements
• Sourcing / certifying wire to IEC wiring standards
Component Power Supplies
Why is Scl. 4.1.1 so Important to Manufacturers?
17
240VA (Energy Hazard)
YES currently sited as hazard in IEC 60950-1
NOT sited as hazard in IEC 62368-1
What can this mean?
18
What Does It Mean – No 240VA Required Protection?
Accessibility by Ordinary Person deemed acceptable
Power Supply – No need for 240VA
output limits (e.g. splitting 12V rails)
Motherboard – 240VA
access permitted by
Elimination of cover
screws – serviceability
now OK without need of
a tool
19
Global Adoption of IEC 62368-1
Drive Bay Backplane Accessibility – No need
for current limiting or insulation barriers
Potential design costs saving opportunities right!
Not so fast…what may prevent this?
What Does It Mean – No 240VA Required Protection?
20
Fire Enclosure Plastics Flammability
IEC 62368-1 based on power NOT weight!
Standard CriteriaFlame
Rating
IEC 60950-1 > 18 Kg 5V
< 18 Kg V-1
IEC 62368-1 > 4000W 5V
< 4000W V-1
small medium large
< 4000W = V1> 4000W = 5V
21
Fire Enclosure Ventilation Opening Designs
IEC 62368-1, 2nd Edition identified as being “more
onerous” for side ventilation openings!
IEC 62368-1, 2nd Edition bases requirements on flame
cone area for side ventilation openings making
requirements more onerous!
22
Flame Cone Area Requirements
Top Openings
Bottom OpeningsWith respect to the Potential
Ignition Source (PIS), bottom
openings are any openings with
15mm areas
Potential Ignition
Source (PIS)
15mm 15mm
With respect to the Potential
Ignition Source (PIS), top
openings are any openings within
2mm area around the cone
Side Openings
Any opening that falls within either
the top or bottom areas! – MORE
ONEROUS THAN IEC 60950-1!
- 5mm any dimension; or
- 1mm in width, regardless length
- 3mm any dimension; or
- 1mm in width, regardless length
23
Ed. 2 Air Flow Consideration - Flame Cone Area
Requirements
Top Openings
Air Flow
Top Openings – with Air Flow
Considerations
45 Degree Rotation
With respect to the Potential
Ignition Source (PIS), top
openings are any openings with
within the extended area as a
result of the 45 degree rotation
15mm 15mm
Potential Ignition
Source (PIS)
24
Ed. 2 Assessing Fire Enclosure Side Ventilation
Openings
With a PIS at the edge of the
component zone the bottom portion of
the flame cone extends out through
the side vents.
With a PIS at the edge of the component
zone, the top portion of the flame cone
(cone straight with no airflow
considerations) extends through the side
vents
With a PIS at the edge of the component
zone, the top portion of the flame cone
with airflow considerations) extends further
through the side vents
25
Current constructions today
comply with IEC 60950-1
5 degree projection requirements
Ed. 3 Assessing Fire Enclosure Side Ventilation
Openings
3rd Edition adds 6.8.4.3.5 for Side Openings
Clause 6.8.4.3.5 references new Figure
Current constructions “ DO
NOT” comply with IEC
62368-1 flame cone
requirements
5o
PIS
IEC 62368-1 Edition No. 3 (pending FDIS)
26
27
Ed. 3 of IEC 62368-1:
Publication Schedule
Current Stage (June 2017) –> Committee Draft for Vote
(CDV), with 3 month voting period.
Vote closed Sept. 2017, with positive result, and comments
Next Stage (Q1 2018) –> Final Draft International
Standard (FDIS), with 3 month voting period.
Expected IS to be published in mid-2018.
Target Publication Date -> July 2018
28
29
Ed. 3 of IEC 62368-1:
Anticipated Changes
Clause 1 (Scope)
• Modernization of examples of products under scope,
incl. 3D Printers, Kiosks & Wearable Technology
(Annex A).
• Incorporation of IEC 60950-22 (Outdoor Equipment) into
scope/body.
• Incorporation of IEC 60950-23 (ICT w/Robotics) into
scope/body.
30
Ed. 3 of IEC 62368-1:
Anticipated Changes
Clause 1 (Scope)
• IEC 60950-21 (RFT) requirements being incorporated
into new IEC 62368-3, DC power transfer through
communication cables or ports, with expansion to
cover both RFT & USB/PoE/etc. interfaces…
PSE – Power Sourcing Equipment
PD – Powered Devices
31
Ed. 3 of IEC 62368-1:
Anticipated Changes
Clause 2 (Norm. References) & Clause 3 (Terms/Defs.)
• Various updates & refinements.
• New terms/definitions, include,
• Backfeed
• Calculated Sound Dose (CSD)
• Fixed Equipment
• Insulating Liquid
• Professional Equipment
• Wireless Power Transmitter
• Work Cell
31
32
Ed. 3 of IEC 62368-1:
Anticipated Changes
Clause 4 (General)
• IEC TC108 has decided to keep the legacy component
(60065 & 60950-1) provision in 4.1.1 (for Ed. 3 FDIS).
Note: IEC TC108 Interpretation Panel has now
completed a formal interpretation of 4.1.1, and its
application to systems of AV/ICT, including external
components like external power supplies, and will publish
(soon) as an INF.
32
33
Ed. 3 of IEC 62368-1:
Anticipated Changes
Clause 4 (General)
• New requirements for insulating liquids (also Cl 5 & 6).
• New requirements for coin/button cell batteries.
• For equipment installed by Ordinary Persons, all likely
positions of orientation of the equipment to be taken
into account, incl. possibility of mounting to a non-vertical
surface, and regardless of instructions provided by the
manufacturer…
34
Ed. 3 of IEC 62368-1:
Anticipated Changes
Clause 5 (Electric Shock)
• Refinement of requirements for Clearances, incl. new
prescriptive option (Annex X) based on 60950-1 Tables.
• New requirements (w/Annex G) for enameled Fully
Insulated Wire (FIW), sometimes known a Zero Defect
Wire.
• New requirements for safeguards associated with
Backfeed.
35
Ed. 3 of IEC 62368-1:
Anticipated Changes
Clause 5 (Electric Shock)
• New material on interconnected ES3/ES2/ES1 circuits
in secondary circuits of SMPSs (similar to 60950-1
approach).
• Note: Recently announced -> CENELEC OSM (EU) now
accepts UL 1446 for EIS (electrical insulation system)
instead of IEC 60085.
36
Ed. 3 of IEC 62368-1:
Anticipated Changes
Clause 6 (Fire)
• Refined Top, Side & Bottom Opening requirements, incl.
re-introduction of 5 degree principle from 60950-1.
• Critical for products requiring high air flow, eg. enterprise
servers.
36
37
Ed. 3 of IEC 62368-1:
Anticipated Changes
Clause 6 (Fire)
• Refined Top, Side & Bottom Opening requirements, incl.
change in consideration for flame cone for top openings.
37
38
Ed. 3 of IEC 62368-1:
Anticipated Changes
Clause 6 (Fire)
• Removal of forced air flow considerations…
• Glow Wire Test reintroduced as option for parts outside
Fire Enclosure.
• New allowance for VW-1 rated wiring instead of IEC
wiring flammability standards.
39
Ed. 3 of IEC 62368-1:
Anticipated Changes
Clause 6 (Fire)
• Note: Agreement also reached by HBSDT to pursue a
Formal Interpretation.
• For Peripherals (PDs) not investigated in a system (PSE &
PD), and connected to common industry busses featuring
power delivery (e.g., USB, PoE, etc.), we no longer can
automatically assume supplied by PS2 or LPS (i.e., they
may not be < 100 W).
• Rationale: Such busses are potentially > 100 W, especially
non-industry-spec-compliant PSE .
• Impact: Enclosure flammability rating of peripherals (PDs).
39
40
Ed. 3 of IEC 62368-1:
Anticipated Changes
Clause 8 (Mechanical)
• Refinement of Slide Rail Mounted Equipment (SRME)
requirements.
• For new definition Work Cells, new 60950-23 based
requirements included.
41
Ed. 3 of IEC 62368-1:
Anticipated Changes
Clause 9 (Touch Temperatures)
• Refinement of Touch Temperature Limits (Table 38).
• New requirements for Wireless Power Transmitters.
• New allowance for devices/parts w/ Small Heat
Capacity (considerations per IEC Guide 117) instead of
Table 38.
41
42
Ed. 3 of IEC 62368-1:
Anticipated Changes
Clause 10 (Radiation)
• Refinement of Radiation Energy Source Classifications.
• Refinement of Acoustic Energy requirements for PMPs,
including addition of Dose Methodology.
• Additional of IEC 62471-5 for laser illuminated
projectors.
43
Ed. 3 of IEC 62368-1:
Anticipated Changes
Annex F (Markings & Instructional Safeguards)
• Removal of maximum altitude symbol (from earlier
draft).
• Rev to rated current, will accept 100-240V, max 6A
Annex G (Components)
• Refinement of Resistor (as safeguard) requirements.
• Refinement of IC Current Limiter requirements (incl.
replacement of current three (3) test program options
with refined single (1) test program).
43
44
Ed. 3 of IEC 62368-1:
Anticipated Changes
Annex M (Batteries)
• Update to latest IEC 62133-1 & IEC 62133-2
• Addition of IEC 62619 for non-portable applications.
• IEC 62619: Secondary cells and batteries containing alkaline or other
non-acid electrolytes - Safety requirements for secondary lithium cells
and batteries, for use in industrial applications
• Refined Battery Ventilation requirements.
44
IEC 62368-1 – Transition Update
45
46
47
Countries in Process of Implementing
IEC 62368-1 as National Standard (examples)Country Standard IEC Equivalent Implementation
Date
Notes
Australia AS/NZS 62368.1 IEC 62368-
1:2014
TBD November 2017 – Expected completion date
China GBxxx IEC 62368-
1:2014
N/A May 2017 – standard to be reviewed
June 2017 – submit to SAC for approval
Q4 2018 – Implement as GB national standard
European Union EN 62368-
1:2014
IEC 62368-
1:2014
20 June 2019
20 December 2020
Compliance per EN 62368-1 or EN 60065 / EN 60950-1 currently
allowed.
If modified DOW published in EU OJ, extension will impact LVD
and RED
Japan J 62368-1 IEC 62368-
1:2014
TBD - 2019? 2018 – Expected publication
Korea KN 62368-1 IEC 62368-
1:2014
2018 – Expected publication
Mexico NMX-I-62368-1-
NYCE-2015
IEC 62368-
1:2014
Voluntary - TBD Study continues towards utilizing NOM standard for mandatory
approval
South Africa SANS 62368-
1:2011 (Ed. 1.00)
IEC 62368-
1:2010
Voluntary - TBD In process of issuing Ed. 2 (TBD)
Taiwan CNS 15598-1
(2012)
IEC 62368-1:
2010
N/A BSMI initial plan
Announcement: in 2018
Enforced: in 2020
48
EU Announced Formal Transition Dates
EU Date of Withdrawal (DOW) - Legacy Standards
(60065/60950-1): June 20, 2019 (original)
Official Journal (OJ) of the EU (latest): Sept. 8, 2017
DOW = Date superseded standards (60065 & 60950-1) cease to give
‘presumption of conformity’ with the essential requirements of the
relevant Union legislation (LVD & RED).
48
49
Recent EU Activity on EN 62368-1 Ed. 2
• CENELEC BT voted to extend DOW from June 20, 2019
to December 20, 2020 (18 mo extension).
• Active discussion between CENELEC & European
Regulators to establish the revised DOW as new published
date that superseded standards (EN 60065 & 60950-1)
cease to give ‘presumption of conformity’ with the essential
requirements of the relevant Union legislation (LVD &
RED).
• Need change published formally in EU Official Journal
(OJ)!
• Outcome expected Q4 2017 (we thought it would have
already happened by now)!
50
Recent EU Activity on EN 62368-1 Ed. 2
• CENELEC also agreed to remove the legacy component
provision in 4.1.1 from Ed. 2 (effective Dec. 20, 2020).
o Legacy component provision also will be removed from Ed. 3
of EN 62368-1, even if IEC TC108 keeps it in.
• In EU, after Dec. 20, 2020, EN 60065 & EN 60950-1
certified components no longer will be permitted in
equipment investigated to EN 62368-1 without additional
investigation.
• However, as a formal amendment process, CLC TC108 has
started an UAP (Unique Acceptance Procedure) for an
Amendment for a Common Modification of EN 62368-
1:2014 to delete the allowance to use the legacy standards
for components in clause 4.1.1.
51
Recent EU Activity on EN 62368-1 Ed. 2
If DOW/Date of Cessation extended, and announced in the
EU Official Journal (OJ):
Manufacturers have option to transition from EN 60065 or EN
60950-1 to Ed. 3 of EN 62368-1 directly, bypassing Ed. 2 of
EN 62368-1.
By December 20, 2020, manufacturers would need to
transition to either, Ed. 2 or Ed. 3 of EN 62368-1
And by December 20, 2020, manufacturers would need to
ensure that their complete supply chain of legacy
components (system parts) are also transitioned to Ed. 2 or
Ed. 3 of EN 62368-1.
51
52
UL Announced Formal Transition Dates
US (UL) Effective Date – New Products: June 20, 2019
Soft Transition: No formal Industry File Review (IFR) of
existing certifications.
Will modify
transition in
alignment with EU
(ie, Dec. 20, 2020
when published)
52
53 53
54
IEC 62368-1 Transition Time
Lines
2010 Jan
2017 2019
IEC 62368-1 1st Edition
2020
IEC 62368-1 2nd Edition
2018
Publishing of
IEC 62368-1 3rd Edition
2016
Dec ’16 IEC 62368-1 3rd Ed. - CD
May’16
Critical Standard Issues
Discovered
Jun 20’19
CENELEC EN 62368-1 2nd Edition DOW
5 Year Time Frame to Transition – Cl 4.1.1 to Aid Smooth Transition
~1 Year Time Frame to Transition
2014 Feb
May’17 Oct’17
CDV Vote Period
Dec 20, 2020
TC108X Proposal Extend DOW
CENELEC EN 62368-1, 3rd Edition
~1.5 Year Addition to Transition
Jul’18 Int’l Adoption Gate Opens
CENELEC
China
India
Taiwan
US/Canada
Australia/NZS
No DOW UL/CSA 62368-2nd Edition
TBD
TBD
TBD
TBD
Current Status
Current DOW Status
Status Assumptions
EDCOM Process FDIS
Jan’18
5-6 month 2-3 month 2-3 month
FDIS Vote Period
Apr’18
EDCOM & Translation
2-3 month
Jul’18
BEST CASE
55
Manufacturer’s Decision
Bottom Line -> Important Decision needed by manufacturers on transition
from legacy standards, 60065 & 60950-1, to 62368-1….
IEC 60065, Ed8,
or
IEC 60950-1,
Ed2, Am2
IEC 62368-1, Ed2
IEC 62368-1, Ed3
… use Ed. 2 now,
or wait until mid
2018,
for Ed. 3…
USB issues & (new) IEC 62368-3
(time permitting)
56
57
Ed. 1 of IEC 62368-3:
Publication Schedule
Current Stage (Oct 2017) –> Final Draft International
Standard (FDIS), with 1.5 month voting period.
Vote closes Nov. 17, 2017, expected positive result,
w’comments
Next Stage (Q1 2018) –> International Standard (IS).
Expected IS to be published in early 2018.
Target Publication Date -> April 2018
58
59
Limited Power Sources & Evolution of USB 3.0 /3.1
- Allows charging at 5V, 12 & 20V
- Up to 5A currents / 100 W charging
- Likely new standard for cell phone
- Becoming more popular on tablets &
laptops
Quick Charging Standardization
-12V @ 2A on micro-USB
-12V @ 3A on USB-C
-20V @ 3A on USB-C (Profile 4)
• It is a propriety system
• Certification is required
• Quick charge is one of the most common protocols
60
Limited Power Sources – USB Challenges
PS3
> 100 watts
PS2
< 100 watts
After 5 sec.
PS1
< 15 watts
After 3 sec.
Electrically caused fire
power source classes
IEC 62368 – USB typically assessed to PS2 / maybe PS3
MUST think about:
A device connected to a USB >100W (PS3) – REQUIRES fire
enclosure
Inoperability's between the host and USB device• IEC TC100 has issued Committee Draft for IEC 63002 covering inoperability guidelines for USB-C
power supplies
• Many concerns can be addressed by communication between the power supply and host device
• The draft standard covers potential issues for the cable connecting the EPS to the host device
• Inoperability affects both functionality and safety
61
USB-C Safety Certification Design Challenges
Ensure cable can support maximum current
Safe guard against:
• Fault condition – contamination causing a short
• Inoperability – supply to device (communication)
• Voltage differences – Will device need voltage protection?
• Power limiting – will supply provide current limiting?
• Common Connector – fits into USB slot – however no
certification is required on common connectors
62
New IEC 62368-3 (108/695/FDIS): DC power transfer
through communication cables or ports
• Equipment interface requirements for both,
a) IEC 60950-21 (RFT) circuits @ ES3, and
b) other low voltage busses @ ES1 & ES2 with DC power
transfer, such as USB, and PoE, and in-building telecom
(formerly TNV-2).
• Covers both Power Sourcing Equipment (PSE) &
Powered Devices (PD)
63
New IEC 62368-3 (108/695/FDIS): DC power transfer
through communication cables or ports
Power limitation for PSE @ ES1/ES2 (e.g., USB, PoE, etc.):
a) If powering building wire (e.g., PoE) = LPS (Q.1);
b) If powering other equipment = PS2 or LPS; and
• under abnormal & single fault conditions, the PSE
output current shall not exceed, 50 % (for circuits ≤ 2 A) rated max. for more than 5 seconds; and
30 % (for circuits > 2 A) rated max. for more than 5 seconds; and
8.0 A under any circumstances.
• Note: Exception if power delivery spec. has specific limits
for fault current, use spec. limit.
64
New IEC 62368-3 (108/695/FDIS): DC power transfer
through communication cables or ports
Voltage limitation for ES1/ES2 (e.g., USB, PoE, etc.),
a) PSE: Output voltage, under single fault, shall be limited
to, 130% of rated for circuits, w/o negotiation; or
130% of rated for circuits > 5V (max 7.5 V), w/negotiation;
150% of rated for circuits ≤ 5V, w/negotiation.
b) PD: Shall not create any hazard when supplied with
130 % of nominal rated for circuits > 5V (min. 7.5 V);
150 % of nominal rated for circuits ≤ 5V.
65
New IEC 62368-3 (108/695/FDIS): DC power transfer
through communication cables or ports
• In Amendment No. 1, RFT requirements also will need
to be aligned with (new): ITU-T K.50, Safe limits for
operating voltages and currents of telecommunication
systems powered over the network.
• Other refinements for ES1 & ES2 also anticipated !
• IEC TC 64 will have a similar function for IEC 60364-7-
716, which includes the electrical installation/
infrastructure, like PoE outlets in the wall and PoE
wire/cabling behind the wall.
Thank you
for attending
2017 SPCE Boston!
Q&A
Discussion
66