[ieee 2010 international conference on power system technology - (powercon 2010) - zhejiang,...
TRANSCRIPT
2010 International Conference on Power System Technology
Study on the dynamic performance of a microtubine based microgrid X.Q. Xiao, W.M.Kan, C.Xun, G.R.Zheng, B.Wang, X.G.Zheng
Abstract: As a kind of clean and high efficiency technology, micro turbine has a broad application prospect in China. Combining the micro turbine with local load to form micro grid could realize high efficient of energy and high reliability of power
supply. With the rapid development of the smart grid concept and micro grid technology, distributed generation based on micro turbine play a more and more important role. Base on the national 863 goal-oriented project "The key technology and demonstration project of grid-connecting issue for a MW level CCP distributed energy MicroGrid", this paper investigate the dynamic performance of a micro grid based on capstone C100 micro turbine. The structure of the micro grid and general control principle of the turbine is studied first. After that, several tests including start, stop, load swing, mode transition and so on are conducted. to study the dynamic response of the voltage and frequency of the micro grid in both grid connect and stand alone mode. The tests result could be used to further evaluate the dynamic behavior of micro grid and validate models for simulation studies.
Index-term: micro turbine; micro grid; duel mode; control principle; dynamic performance; grid connect; stand alone
I. INTRODUCTION
Nowadays, the concept of smart grid is more and more
popular. Microgrid is one of the key technologies of smart
grid. Micro turbine is a kind of newly developed small thermal
generator, ranged from 25kW to 300kW. Micro turbine has a
series of advanced technology features of wide applicability,
low consumption, low noise, low emission, low vibration, low
maintenance, remote control and diagnosis ability. With the
low carbon economy policy, micro turbine based micro grid
has a broad application prospect in China.
The grid-connecting technology for distributed generations
is a kind of special issue. Generally, micro turbine could run
at either grid-connect(GC) mode or Stand alone(SA) mode.
Micro turbine and important load can be combined together to
form micro grid. With some dual mode function, a micro grid
based on micro grid could run at both GC and SA mode, and
could switch between these two modes automatically. When
fault of external grid occurs, micro grid is disconnected from
the grid, and runs at SA Mode. After the fault is cleared,
micro grid with automatically reconnect to the external grid if
condition allows. This special operation mode can effectively
enhance power supply reliability of important load, and exert
the potential of distributed generation[l].
In 2007, China Southern Power Grid Company undertook
This work was supported by Nationa1863 project (No.2007AA05Z250). Xiao Xiaoqing is with Power Test and Research Institute, Guangdong,
China. (e-mail: [email protected])
978-1-4244-5940-7/1 0/$26.00©20 1 0 IEEE
national 863 goal-oriented project "The key technology and
demonstration project of grid-connecting issue for a MW level
combined cool distributed generation micro grid". In this
project a typical demonstration project of a CCP micro grid
was built. The project not only initiates a new operation mode
for the promotion and application of Chinese CCP distributed
energy technologies, but also provides experimental basis for
the mutual influence research between micro grid and the
main power grid.
II. INTRODUCTION TO THE MICRO GRID
A. System structure Substation I Substation 2
f 603
M2
� � T3
! t LM2
10kY
O.4kY
Part load of
Load of Building 3
�--��:� ���-----------
Fig. I. Diagram of micro grid structure
building 2
The demonstration project is built in FoShan, which
consists of three buildings, named as building 1 to building 3.
Fig. 1 shows the structure of the power supply system. The
demonstration project consists of three buildings, named as
building 1 to building 3. The power supply for the three
buildings is from two different substations and different load
of buses, named as Ml and M2 respectively. The power loads
of building 1 are supplied by bus Ml through transformer T1
independently. Switch 600 being installed between bus Ml
and M2 is a backup automatic switch. The connecting switch
4000 between LMI and LM2 needs manual operation. In
normal operation, connection switch 600 of I OkV bus and
connectiong switch 4000 of OAk V bus are both open.
The loads of building 3 are supplied by OAkV bus MCC,
which is connected to a low voltage switchboard from
distribution house of building 2 through switch AI . Three
Capstone C200 micro turbines, which have a rated load of
200kW, are also connected at bus MCC. Dual power supply
design is used for building 3.
At grid connect mode, the switch Al closed and the power
output of the micro turbine could supply not only the loads of
building 3, but also the loads of building 1 , 2 and even goes to
the grid.
At stand alone mode, the switch Al is opened. The loads of
building 3 and the three micro turbine could form an island.
Micro turbines would fulfill the power demand of building 3.
The electrical load and cooling load of each building are
shown in Tab. 1 . Especially, the electrical load merely
includes common lighting, elevator, computers and water
heaters, and does not include fire safety load, high level
facilities and air conditioner which needs higher power supply
requirement. TABLE I MAXIMUM LOAD OF EACH BUILDING
Building 1 Building 2 Building 3 Total Maximum cooling
1484.57 1238.48 544.61 3256.43 load (kW) Maximum air conditioner 645.5 538.47 113.5 1297.47 electric load (kW) Maximum electrical load 302.82 330.90 84.89 718.21 (kW)
B. Micro turbine
LilhiULn bromjdc refrigcrnlor Coolin
Fig. 2 Typical CCHP system based on Capstone C200 microturbine
The demonstration project consists of three capstone C200
microturbine. The rated power of each turbine is 200kW. In
order to meet the power demand of the project, the three units
are run paralleled as a group, with the total rated power of
600kW, to supply the whole project. Through lithium bromide
refrigerator, the waste heat of the exhaust gas of microturbine
is absorbed to generate cooling, which can meet the cooling
demand of building 1 and 2. Fig. 2 shows the typical CCHP
system based on capstone C200 microturbine.
Capstone C200 microturbine runs at high-speed and drive
permanent magnet generator. The high frequency AC
electricity is transformed to DC and then inverted to SO/60Hz
frequency AC electricity through power electronic device.
2
Capstone C200 microturbine includes two large battery
packs that store energy for microturbine startup when
disconnected from the electric utility grid. They also provide
an electrical buffer for sudden increases or decreases in load
during SA operation. Management of the batteries and their
state of charge is automatic within the microturbine.
III. MICROTURBINE TESTS
In order to study the performance of the micro grid, it's
necessary to study the performance of the micro turbine itself
first.
A. Start operation Fig.3 shows the power output and turbine speed of the
micro turbine group during startup at grid connect mode. The
speed of the turbine is first accelerated to I 7000r/min and fire,
after warn-up for around 20 s, the turbine is then accelerated
to 34000r/min and ready for generate power. During this
initial period, auxiliary power is provided by the grid, which is
shown as negative power output in Fig. 3. After the warm-up
period, the microturbine controls increase the speed to obtain
the desired output power setting. The characteristic is
basically the same regardless of the power output setting for
startup. As shown in Fig. 3, the total startup period requires
around 1 50 seconds. Speed(dmin)
70000 -Speed(dmin)
60000 --Output Power (kW)
50000
40000
J I I
-;r-
30000
20000
10000 130s from
I
.......-� : ( /f! :
� f I I
/ : � I
I
start to f 111 load : 50 100 150
Load (kW) 600
500
400
300
200
100
-100
-200 200 Time (s) 250
Fig. 3 Startup power output and turbine speed
At stand alone mode, the startup sequence is almost the
same as at grid connect mode except that the auxiliary power
needed for acceleration is provide by the battery and full
recharge of the battery is required before the turbine could
output power.
B. Stop operation When stop, the power output of the turbine decreases
quickly to zero within 20 seconds. Although the power output
dropped off fairly linearly, the turbine speed stayed at 34,000
r/min for nearly all the shutdown time. This period is for the
turbine to cool down its hot path. As shown in FigA, the cool
down time is about 1 30 seconds, which depends on the
exhaust temperature of the turbine.
At stand alone mode, a battery recharge time is required
during stop to ensure that the battery is enough for next start.
During stop sequence, the turbine could restart any time when
needed.
Speed IX/min)
10000 �
50000
50000 1\
I - Engine Speed
-Output Power
LoadM) 180
IXpm)
M)
\: 130. for c 01 down I
150
140
120
100
80
50
40
20
40000 \!
\: \J
30000
20000
10000
o o 50 100 150
I
I
tL-, -
-20 200 Time (. ) 250
Fig. 4 Startup power output and turbine speed
C. Load step change To evaluate the dynamic performance of micro turbine at
GC mode, several tests of step up or down in power output
are developed. As shown in Fig. 5, several characteristics
could be seen. When the new power command was entered,
the power output of the turbine would suffer a sudden
change reversely. That is, when power command increase,
the output power would suffer a sudden decrease before
increase and vice versa. The speed of the rotor would also
change during the step change of power command. As the
micro turbine reached the new power level, turbine speed
stabilized at a new level. Based on the tests of both loading
sequences, we highlight that the transition times during
power increase and decrease are similar. Furthermore, the
tests demonstrate the fast dynamic behavior of the micro
turbine, and show that this device can respond to load
changes rapidly. It takes about 50 seconds for the turbine to
reach another stable status. 650 600 550 I---
r---j500 �450 03400
350 300 250
o
65000
60000 � �55000 � "" �50000 Po '"
45000
40000 o
L-
}'--
\ 200
\ / \......
200
1\
1\ 400 600
(a) Power output
\.... h
T 'I
r -Power demandM)
-Output power M)
�
800 Time (s) 1000
'--1
400 600 (b) rotor speed
r- Speed(r/min)
T 800 Time (s) 1000
Fig. 5 dynamic response at step change of power command
The power assignment method in the test above is balance
equal division, that is, each turbine output one third of the
3
power demand. Actually, to get high efficiency, it's better to
optimize the power assignment method. Better way is to stop
one or two turbine at part load. When the power demand is
less than the rated power of one turbine, only one turbine is
running and when the power demand is less than the rated
power of two turbines, two turbines run and each has a equal
power output. At this assignment method, the load step
change response would change with start or stop of turbines
included. At that time, the start and stop time of turbine should
be consider in system design.
D. Power factor In grid connect mode, the reactive power of the micro
turbine is kept at a very low status. As shown in Fig. 6, when
the active power changes from 20 to the full load of I 60kW,
the reactive power is always below 5 kVar. So at most power
level, the power factor of the turbine could be assumed to be 1 .
6 5.5
j 5 to: 4.5 � 0... 4 � ·t 3.5 '" � 3
2.5
2
.----/
I - �
H ----.-Reactive PowerM) 1 --- Power factor r
o 50 100 Acti ve Power M)
�
150
Fig. 6 Reactive power at different power level
200
0.99 .... o
+' 0.98 g """' ....
O. 97 � o
""'
0.95
0.95
At stand alone mode, the power output of the turbine is
determined by the load in the micro grid. The turbine is
running at constant voltage mode and tries to keep the
voltage of three phases to be stable.
E. Load rejection 250 700
-- Gen Power M)
--Output Power M) 500 200
-- Brake Temp ( C) 500
j 150 400 8 to: Po
E � 300 t! � 100
200 50
100
o b::::l __ ======� o 20 40 50 80 100 120 140 Time (s)
Fig.7 dynamic response at load rejection
The load rejection test is conduct by opening the switch Al
suddenly when the turbine is running at full load. Fig.7
shows the response of the turbine at load rejection. The
output power of the turbine goes to 0 as soon as the switch
Al opens. However, the generator power of the turbine
decreases smoothly goes to zero in about 40 seconds. At the
same time, the speed of the turbine decreases smoothly from
60,000 r/min to 34,000r/min. Actually, the power difference
between generator power and the output power is absorbed
by the battery and the brake connect to the high voltage DC
bus inside the turbine. As is shown in Fig.7, when load
rejection occurs, the temperature of the brake increases
significantly to around 600 Celsius degree. With the help of
the brake and battery, the turbine could keep stable voltage
of the DC bus inside and regulate the output power freely.
F. Power quality Power quality is tests under GC and SA mode respectively.
Tab. 2 shows the harmonic test result in SA mode. The
THVD of micro turbine is a bit higher, which exceed the
requirement of 5% in GBIT1 4549-1993. Three phase
imbalance is also higher than the requirement of 2% in
GB/T15543-2008.
In GC mode, three phase imbalance is less than 0.8% and
THVD is less than 1 %. Both of them fit GB requirements. TABLE 2 HARMONIC TEST RESULT IN SA MODE Harmonic voltage ratio
Harmonic current (A) Harmonic (%)
A B C A B C 2 0.47 0.76 0.57 4.24 4.06 4.03 3 3.60 0.88 5.48 4.73 3.51 4.66 4 0.22 0.32 0.26 2.40 2.35 2.17 5 2.28 2.37 2.13 5.91 6.09 5.45 6 0.13 0.15 0.18 0.33 0.25 0.28 7 1.49 1.29 1.29 3.95 3.78 3.21 8 0.17 0.23 0.24 0.91 0.86 1.04 9 1.40 0.84 1.69 0.86 0.81 1.12
10 0.18 0.22 0.19 0.36 0.39 0.45 11 0.73 0.75 0.66 0.82 1.16 0.81 12 0.21 0.12 0.20 0.18 0.16 0.16 13 0.97 1.10 1.00 1.03 1.03 0.81 14 0.13 0.15 0.20 0.39 0.41 0.35 15 1.05 1.06 0.65 0.40 0.36 0 72 16 0.30 0.27 0.21 0.27 0.27 0.28 17 1.24 1.48 1.23 0.63 0.69 0.52 18 0.20 0.15 0.20 0.18 0.13 0.16 19 1.20 1.65 0.85 0.45 0.53 0.46 20 0.30 0.27 0.25 0.35 0.31 0.35 21 1.09 1.07 0.82 0.28 0.26 0.34 22 0.17 0.25 0.20 0.34 0.34 0.35 23 1.24 1.46 0.83 0.46 0.56 0.54 24 0.18 0.13 0.20 0.20 0.18 0.18 25 1.14 1.22 0.62 0.39 0.46 0.35
THO 5.20 4.19 6.33
IV. DUEL MODE OPERA nON
In order to switch smoothly between GC mode and SA
mode, a mode control device named DMSC (Duel Mode
System Controller) is installed in this project. Logic in the
DMSC activates a motor-operated disconnect device that
isolates the micro turbine and protected loads from the grid
during Stand Alone operation. When the grid power is
restored, the DMSC automatically reconnects to the grid.
Fig.8 shows the control scheme of the DMSC. Two
switches are present: Ml and M2. Switch Ml could isolate the
microgrid from the utility grid, which in this project is switch
AI . Switch M2 is the inner contactor of the micro turbine.
DMSC consists of a voltage detecting relay UVR (Under
Voltage Relay). UVR is used to detect the voltage and send
logic control signal to controls the open and closing of Ml;
4
meanwhile, it sends mode transition signal to micro turbine,
which controls the mode transit of micro turbine between the
GC mode and SA mode. In normal operation, Ml is closed;
micro turbine is in the GC Mode, which supplies power to the
grid. When the fault of external grid occurs, the protection of
micro turbine detects the voltage below normal level, M2 is
open immediately, and micro turbine transfers to hot standby
mode. Meanwhile, while UVR detects the voltage below
normal level, it sends an open command signal to Ml, which
is open in a short time. Also, UVR sends out mode transition
signal, and micro turbine begins to transit from GC Mode to
SA Mode. After a fixed time delay, micro turbine
accomplishes mode transition. With its inner contactors M2 is
closed, micro turbine supplies power to important load alone.
J.v r··-TD�����."!!�.",! i > i Distribution bus : J Distribution bus : 1 1 : J J 1 : 1 I 1 ! tj}}'>-! _ . . _ .. _. - . . . . _ . . _ . . -
. llmoc ti= 'u Non,polOr laros
Vac (50I-lz)
1-"-"- ._ .. , Tripingl � ). MI �<k:ol1lCClin . . closlllg 1 1 S\,;lch i ModeconlrOllcq- ----- ;- 1-_____ ..... :_ ._ . . _ . . _ .. ..: Lowvohll!J"-" . . _ . . ....
tro1<clion }Ml
"-"-"- " - " - ' :r�::l-t"-"-"-"-"-"-"l 1-"-"-"-'" pro M2 1 iProtedion eel \
-Tri�i�l!I-
i :_ .. _ . . . . - .. ...: dosing :
Micro lucbine 1-"-"-"-",
--"i Callrol ce l l t-._ . . _ . . _ . . _ . . -
._ .. _ .. _ .. _ .. _ .. _ .. _ .. _ .. _ .. _ .. _ .. _ .. _ .. _ .. _ .. _ .. _ .. _ .. �
Fig. 8 Grid·connected structure diagram
A. GC mode to SA mode operation
Prin" loads
Grid fault is simulated by opening the switch A2. When A2
open, micro turbine detects voltage change immediately and
the protection inside turbine would trip the inner contactor. As
shown in Fig. 9, as soon as grid voltage disappears, the
turbine goes to stand by mode. The interval from grid fault to
turbine trip is inside 0.2 seconds, which fit the requirement of
IEEE standard 1 547. DMSC detects the under voltage of the
grid and UVR relay activate. It opens the A 1 switch and
isolates the local load from the grid. Then, DMSC tells the
turbine to transit to SA mode. After about 12 seconds, the
mode transition is finished and micro turbine close inner
contactor automatically to run at SA mode.
"--I
J ., 0,
Grid Vol r"c
Turbine Vol tDp.e
IIVR
!;wi 1(:11 AI Pill;; tim1
10, ", ", !C,
Fig. 9 Time sequence ofGC to SA test
B. Stand alone to Grid connect operation
It, ",
To test the SA to GC mode, manually close switch A2 to
simulate grid power is restored. Fig.I O shows the time
sequence of SA to GC test. DMSC detects the voltage has
recovered to normal level. It sends out mode transition signal
after 4 seconds of delay to confirm that the grid power is
stable. The turbine gets the mode transition signal and open
the inner contactor is open firstly and micro turbine transfers
to stand-by mode, which results in power off of the MCC bus.
It takes about 7 seconds for the micro turbine to get ready for
mode transition. Then DMSC sends close signal to AI , the
load of building 3 is supplied by the grid. After A 1 is closed,
micro turbine reconnects to the grid and run at GC mode.
(iritl V
•• 6. Is 10, 12, 14, 16. Fig. 10 Time sequence of SA to GC test
V. CONCLUSION
In this paper, the structure of a Capstone C200 micro
turbine based micro grid is introduced first. Several tests are
conducted to find out its dynamic behavior. The Capstone
micro turbine uses constant power control at grid-connect
mode and constant voltage control at stand alone mode.
Tests of loading sequence show similar transition times
during power increase and decrease. The micro turbine has
fast dynamic behavior when power command step change. At
certain extreme condition such as load rejection or fast load
demand changes, the battery and the brake play an important
role in stabilizing the voltage and frequency of the micro grid.
With duel mode controller, the micro grid could switch
flexibly between GC and SA mode. The local load in the
micro grid would suffer a short time of blackout when the
5
micro turbine conducts mode transition. The black out interval
for mode transition is around 1 0 seconds.
[I]
[2]
[3]
[4]
VI. REFERENCES
R. H. Lasseter and P. Piagi, "MicroGrid: A Conceptual Solution," in Proc. IEEE 35th Power Electronics Specialists Conference,2004. Capstone technical reference- Dual Mode System Controller [Online], 2009. https:lldocs.capstoneturbine.com/home.asp .. "DER Performance Testing of a Microturbine-Based Combined Cooling, Heating, and Power (CHP) System," Proceedings of Power System 2002 Conference, Clemson, SC, March 2002. S.-J. Huang and F.-S. Pai. "A new approach to islanding detection of dispersed generators with self-commuted static power converters." IEEE Transactions on Power Delivery, vol. IS, no. 2, April 2000.
[5] O.Fethi, L.-A. Dessaint, K. AI-Haddad, "Modeling and simulation of the electric part of a grid connected microturbine" Power Engineering Society General Meeting, 2004. IEEE 6-10 June 2004 Page(s): 2212-2219VoL2.
VII. BIOGRAPHIES
Xiaoqing Xiao received the B.E. and M.S. degree in Thermal engineering from Tsinghua University , China, in 2000 and 2003, respectively. He then started work in Guangdong Power Test and Research Institute, China where he is presently a Senior Engineer. His major is in gas turbine operation and simulation,
large-scare rotating machine diagnosis and distributed
generation technology research, etc.