ieee1818 - 2017...very important parts of the substation equipment. • design of the ac and dc...
TRANSCRIPT
1
IEEE1818 - 2017 Guide for the Design of Low Voltage AC and DC Auxiliary
Systems for SubstationsSponsored by the IEEE Substations Committee
Presented By Joe Gravelle
2
Organization of the Guide1. Scope / Purpose2. Normative References3. Definitions4. AC System Design5. DC System DesignAnnex A – BibliographyAnnex B - Conductor Sizing examplesAnnex C – Battery Sizing Examples
3
Organization of the Guide1. Scope / Purpose2. Normative References3. Definitions4. AC System Design5. DC System DesignAnnex A – BibliographyAnnex B - Conductor Sizing examplesAnnex C – Battery Sizing Examples
4
1.1 Scope• This guide provides guidelines for the design of
the ac and dc systems. • This guide covers the low voltage auxiliary
systems from the source(s) to the distribution point(s).
• Reliability requirements and load characteristics
5
1.2 Purpose• The low-voltage ac and dc auxiliary systems comprise
very important parts of the substation equipment. • Design of the ac and dc auxiliary systems
• reliability, • load requirements, • system configuration, • personnel safety, • safe and reliable operation• protection
6
2.0 Normative References• IEEE 485, IEEE 525
3.0 Definitions• Definitions are provided for technical terms used
in the guide.
7
Organization of the Guide1. Scope / Purpose2. Normative References3. Definitions4. AC System Design5. DC System DesignAnnex A – BibliographyAnnex B - AC examplesAnnex C – DC Examples
8
4.0 AC System Design • Design Criteria• Source Requirements• Load Analysis• Conductor Selection• Transformer(s)• Transfer Switch • Bus Layout• Panels• Protection• Equipment Specifications• Operations and Maintenance
9
4.1 Introduction• Design Criteria• Source Requirements
• Number of sources• 1 phase or 3 phase• Load Requirements
These sections define the AC system for the substation Application.
10
4.2 Design Criteria • AC system loads• 1 or 3 phase• System stability• Protection• Voltage
This section defines the AC system design.
11
4.3 AC sources • Transformer tertiary
• Substation bus
• Distribution line
• Generators
12
4.4 AC Load Analysis • Identification
• Amps/Volts/kW
• Equipment rating
• Demand factors
• Load calculations
13
4.5 Conductor Selection• Conductor Type
• Insulation
• Temperature Rating
• Size – Ampacity
• Voltage Drop
14
4.6 Station Auxiliary Transformer • Transformer Type
15
4.6 Station Auxiliary Transformer • Number of transformers
• Single/Three phase
• Transformer Ratings
• Transformer Connections
16
4.6 Station Auxiliary Transformer • Transformer Ratings
• KVA• Voltage• Short Circuit • Impedance• BIL
17
4.6 AC System Design • Transformer Connections Single Phase
18
4.6 AC System Design • Transformer Connections Three Phase
19
4.7 Transfer Switch • Manual / Automatic
• Considerations:
• Break before Make
• Switching Neutrals
20
4.8 Bus Layout - Distribution Configuration• Essential / Non-Essential Loads
• Simple Radial System
• Expanded Radial System
• Primary / Secondary Selective systems
21
4.8 Bus Layout and Distribution Circuit Configuration
22
4.9 AC Distribution Panelboards
• Application• Ratings• Short Circuit ratings• Standards
23
4.10 AC Auxiliary System Protection • Panelboard or Switchboard
• Circuit Breaker Selection
• Fuse Selection
24
4.11 Equipment Specifications• General considerations
• Standards
25
4.12 Operation - Maintenance Consideration• Accessible Disconnects
• Indoor/Outdoor Design
• Adequate Working Space
• Standby or Backup AC System
26
27
Organization of the Guide1. Scope / Purpose2. Normative References3. Definitions4. AC System Design5. DC System DesignAnnex A – BibliographyAnnex B - AC examplesAnnex C – DC Examples
28
DC System Design • Design Criteria• DC Equipment • One Line Diagram• Batteries• Chargers• Panels• Design Considerations • Maintenance Provisions
29
Battery System
30
Battery SystemSingle cell battery with acid
containment on a two step rack
31
5.1 DC System Design Criteria • Reliability
• Redundancy
• Environment
32
5.2 Equipment Served by the DC System • System Protection Equipment• Motor Operators• Breakers• SCADA• Fire Protection• Security
33
5.3 One Line Diagram • Power System One Line
• System protection• DC System One Line
• DC Load Calculations• DC Connections• Number of Batteries• Load Transfer
34
Substation One LineOperating sequence:
12D3 is normally closed, no generation on feeder circuitsOperating time for MOS 10 seconds
Transformer T1 differential:Trip 69CB1, 69CB3, 12CB1Open 69DT1
Breaker Failure on 12CB1:Open 12CB2, Open 12D3, Reclose 12CB2
35
DC System
Battery
Battery Charger
Panel
To DC Cab.
Maint Charger & Battery
36
DC System distribution cabinet(s)
37
5.4 DC Batteries Battery System
Battery Charger(s)
Battery Disconnect(s)
DC Panel(s)
Maintenance Connections
DC Loads
38
5.4 DC Batteries
39
5.4 DC Battery Types Vented Lead Acid (VLA)
Valve Regulated Lead Acid (VRLA)
Nickel Cadmium (NiCad)
• For substation use, vented lead-acid cells are the most common
40
5.4 DC Battery
41
5.4 DC Battery
42
5.4 DC Battery
43
Battery SizingSizing the battery using IEEE 485 (Vented Lead Acid Batteries)
Defining the Duty Cycle (loading on battery based on time duration)
Continuous Load
Momentary Load
Worst Case Tripping
44
Continuous LoadsIndicating lamps, Microprocessor Relays, Electronic Meters, SCADA Systems, Annunciators, Communication Equipment
o For loads that are non-linear such as power supplies, the current increases as voltage declines.
o The watt rating is typically used to determine current at end of battery cycle discharge voltage
45
Momentary LoadsLock Out Relay (LOR) Breaker trippingMotor Operators Breaker Fail operation Considerations:
o Worst Case Tripping Scenarios
o MOD use Locked Rotor rating
o Breaker Fail use SOE not sum of all currents select highest
46
Worst Case Tripping Operating sequence:12D3 is normally closed, no generation on feeder circuitsOperating time for MOS 10 seconds
Transformer T1 differential:Trip 69CB1, 69CB3, 12CB1Open 69DT1
Breaker Failure on 12CB1:Open 12CB2, Open 12D3, Reclose 12CB2
Timing:T=0cy (0 sec)Trip 69CB1, 69CB3, 12CB1, open 69DT1Current=12+12+8+60=92A
T=12cy (0.2sec) (12CB1 breaker failure timer)Trip 12CB2, Re-Trip 12CB1 open 12D3Current=20+8+8+60=96A
T=600cy (10sec)Reclose 12CB2Current=6A
From the above, the worst case tripping load is 96A for the 12CB1 breaker failure.
47
Duty Cycle Duration1. Charger fails – Initiates Alarm to SCADA2. Dispatcher notices Alarm3. Dispatch contacts Substation Personal4. Substation Personal Drive to Substation5. Investigate Alarm6. Determines Charger Failed – contacts dispatch requesting maintenance 7. Dispatch contacts Maintenance8. Maintenance Technician Drives to Substation9. Maintenance attempts to repair charger (unsuccessful)10.Maintenance Supervisor locates spare charger11.Maintenance Supervisor contacts additional resources12.Resources drive to service center PU spare charger and drive to substation13.Replace failed Charger
48
Duty Cycle Example
49
Battery Chargers
Sizing battery Chargers
Charger Connections
Charger Circuit Protection
50
Battery Chargers
51
Battery Charger size
52
DC Panels
Considerations
Critical Loads vs non-Critical Loads
Circuit size
Number of circuits
53
DC Panels
54
DC Panels
55
Design Considerations• Battery location
• Maintenance considerations • Working clearances• Method for removing
battery cells• An eyewash station • Spill containment
systems• Terminal Covers
56
Battery Terminal Covers
57
Design Considerations
• Battery area temperature• Specifications published for sizing
• Heat and Cold impact battery performance
• Reference IEEE485 for effect on Battery Size
58
Design Considerations• Acid spill containment
• Spill Pans• Acid-resistant paint on the floor
59
Design Considerations• Battery racks
• Three types—step, tier, or stepped tier
• Height variations between cells can cause cell temperature differences within the same battery system
• acid-resistant coating applied to the structural frame
• seismic zone
60
Design Considerations • Battery rack
61
Design Considerations Circuit considerations • Grounded and ungrounded systems
• Ungrounded –Substation Control - SCADA
• Grounded ((+) grounded) – Communications
62
Design Considerations -Circuit considerations
• Isolation of Main DC cables • Recommendations - IEEE 1375
• Battery fuse • Battery circuit breaker• Battery disconnect switch • Mid-point battery fuse
63
Circuit considerations • Isolation of main dc cables - Separate the pos and neg cables
64
Design ConsiderationsCircuit considerations
• Coordination of overcurrent protection• Short-circuit levels• Fuses• Breakers• Equipment voltage ratings
65
Maintenance Provisions• Isolation switches
• Equipment accessibility
• Back-up supplies
66
Maintenance Provisions• Testing Provisions
67
DC System
Battery
Battery Charger
Panel
To DC Cab.
Maint Charger & Battery
68
AnnexAnnex A – Bibliography
Annex B - Conductor Sizing Example
Annex C – Battery Sizing Example
69
Questions?