iefeb07 realities

Upload: anandsap

Post on 07-Apr-2018

217 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/6/2019 IEFeb07 Realities

    1/6

    36 Industrial Engineer

    Realtes ofRskSpply chas mst scrtze the kowB y M a r k L . S p e a r M a n

  • 8/6/2019 IEFeb07 Realities

    2/6

    February 2007 37

    Companies are recognizing the severity of

    danger facing them by not addressing sup-

    ply chain risk. Indeed, more than two-thirds

    of the companies surveyed by Accenture, as

    recorded in Manufacturing Business Tech-

    nology, said they had experienced a supply

    chain disruption from which it took morethan one week to recover. Furthermore, the

    study revealed that 73 percent of the ex-

    ecutives surveyed had a major disruption

    in the past five years. Of those, 36 percent

    took more than one month to recover.

    Modern supply chains are susceptible

    to such disruption for two reasons: Supply

    chains are not designed with risk in mind,

    and modern planning and scheduling are

    not robust enough to operate under condi-

    tions significantly different from those for

    which they are planned. Why does it take

    companies so long to recover? Why are so

    many companies susceptible to disrup-tion? Are sophisticated advanced planning

    and optimization (APO) systems useful?

    Last-cetry spply chaplag Although material requirement plan-

    ning (MRP), manufacturing resources

    planning (MRP II), and even enterprise

    resource planning (ERP) are now so last-

    century, to use my daughters favorite

    phrase, it is useful to review what worked

    and what didnt. The goal of these systems

    has always been to reduce inventory, im-

    prove customer service, and reduce costby increasing the utilization of expensive

    equipment and labor. Unfortunately, these

    processes do not explicitly consider risk

    and have ignored key facts regarding the

    systems they try to control.

    The first attempt to confront supply

    chain risk dates back to the 1960s with the

  • 8/6/2019 IEFeb07 Realities

    3/6

    creation of MRP, which provided material

    plans with no consideration of capacity.

    This evolved into MRP II, which provided

    some capacity checking modules around

    the basic MRP functionality. Interestingly,

    virtually all ERP systems today (including

    high-end offerings) continue to have the

    same basic MRP calculations as the core

    of their production plan offering. Not sur-

    prisingly, a 2006 survey in CA Magazine

    showed that users gave low marks to these

    high-end systems for performance in dis-

    tribution and manufacturing (averaging

    2.5 and 2.6, respectively, out of 4.0).

    There are two basic problems with these

    systems: Lot sizing is done without consid-

    eration of capacity and planning lead-times

    are assumed to be attributes of the part.

    The first issue results in conservative (i.e.,

    large) lot sizes that increase inventory andreduce responsiveness. The second issue

    is similar. Because the planning lead-time

    does not depend on current work-in-pro-

    cess levels and because being late (result-

    ing in poor customer service) is worse than

    being early (resulting in extra inventory),

    most systems employ long lead-times. The

    result, again, is more inventory and less re-

    sponsiveness and is especially aggravated

    when the bill-of-materials is deep.

    Efforts to address these problems have

    gone on for many years. Almost 20 years

    ago, manufacturing logistics expert J.J.

    Kanet described problems with contem-

    porary planning systems that remain

    today. Consequently, most companies do

    not run their plants using the output of

    their ERP systems but instead massage

    the output using ad hoc spreadsheets.

    21st-cetry spply chaplagObviously, with this kind of work-around

    there exists an opportunity to sell more

    sophisticated software, and for some time

    now there have been numerous offerings.

    These applications are typically deter-

    ministic simulations of the process that

    assume the demand, inventory, WIP, run

    rates, and setup times are all known andthen seek to generate a schedule that is op-

    timal under some specified criteria.

    Three factors, however, prevent the

    approach of using deterministic simula-

    tion from effectively managing supply

    chain risk:

    The supply chain and plant have in-

    herent randomness that do not al-

    low for the complete specification of

    a time for each job at each process

    center with a given labor component.

    Such detailed schedules are often

    quickly out of date because of the

    intrinsic variability in the system.

    Moreover, they do not manage risk,

    which involves random events that

    may or may not happen. In the past,the unknown has been addressed us-

    ing ever more detailed models requir-

    ing ever more computer power. This

    misses the point. Variability and risk

    are facts of life and are the result of

    not only process variation (some-

    thing that one attempts to control)

    but also unforeseen events and vari-

    ability in demand (things that cannot

    be controlled). The result is the sameregardless of the variability source.

    Detailed scheduling can provide only

    a short-term solution, and in practice,

    the solution often becomes invalid

    between the time it is generated and

    the time the schedule is distributed

    and reviewed as part of production

    planning meetings.

    The detailed scheduling system must

    be re-run often because of the short-

    term nature of the solution. More-

    over, without a method for deter-

    mining whether a significant change

    has occurred, the schedule is often

    regenerated in response to random

    noise a temporary lull in demand

    which is then fed back into the sys-

    tem. Unfortunately, feeding back ran-

    dom noise increases the variability in

    the system being controlled. Because

    of these problems, many companieshave turned off their advanced plan-

    ning and scheduling systems after

    spending a great deal of money to

    install them. One of our own clients,

    a biopharmaceutical company, shut

    down its advanced planning and opti-

    mization module after having trouble

    keeping it fed.

    It is impossible to find an optimal

    schedule. Problems addressed are

    38 Industrial Engineer

    realtes of rsk

    Fgre 1. Ths otpt of a APO applcato shows a prodcto schedle ad vetory.

    apoapplicationoutput

  • 8/6/2019 IEFeb07 Realities

    4/6

    February 2007 39

    mathematically characterized as NP-

    hard, which means that no algorithm

    exists to work in polynomial time to

    solve scheduling problems. For real-

    istic problems faced in modern fac-

    tories and in the supply chain, there

    has not been enough time since thebeginning of the universe to find an

    optimal schedule regardless of the

    speed of the computer. Consequently,

    heuristics must be applied to gener-

    ate a near-optimal schedule although

    the effectiveness of these heuristics is

    typically unknown for a broad range

    of applications.

    The result is that a great deal of comput-

    er power is used to create a detailed sched-ule for a single instance that will never hap-

    pen and that becomes obsolete as soon as

    something unanticipated occurs.

    Advanced systems today offer two

    methods of planning for manufactur-

    ing supply chains: What-if analysis uses

    a deterministic simulation of the sup-

    ply chain, and optimization of a set of

    penalties (again, using a deterministic

    simulation) associated with inventory,

    on-time delivery, setups, and wasted ca-

    pacity. This combined approach may be

    tedious and less intuitive. For instance,

    the monotony of what-if analysis comes

    from all the detail that must be con-

    sidered. Figure 1 shows the output of a

    typical APO application. Visible is the

    scheduled production on six machines

    in one factory along with projected in-

    ventory plot of one of the items pro-

    duced. The planner can move jobs in theschedule and drill down on other items

    to view inventory projections.

    While this level of integration is im-

    pressive, it is not particularly useful when

    there are hundreds of machines (not to

    mention all the associated labor) to con-

    sider, along with thousands of individual

    items each with its own demand.

    Likewise, the use of penalties to deter-

    mine an optimal schedule is not intuitive.

    What should the penalty be for carrying

    additional inventory? What is the cost of

    a late order? What savings is generated by

    reducing the number of setups, particular-

    ly if there is no reduction in head count?

    What is the cost of having idle machines?

    As evidenced, huge gaps remain betweenwhat is needed and what is offered. Nev-

    ertheless, a combination of existing appli-

    cations with new technology can help cir-

    cumscribe risk without the tediousness or

    the complexity of modern APO systems.

    Lessos factory physcsInformation technology cannot serve as

    the solution to every business problem.

    Instead of faster computers and moreintegration, a fundamental change in

    managing manufacturing supply chains

    is necessary.

    Consider some basic factory phys-

    ics principles that describe how all

    manufacturing supply chains work. The

    first principle is that all manufactur-

    ing supply chains consist of demand

    and transformation. Without demand,

    there would be no market for our goods.

    Without transformation, the people de-

    manding those goods could simply find

    and use products without having to pur-

    chase them. (For example, people have

    demand for air every day, but there is no

    business case for selling air because its

    freely available to everyone.).

    Likewise, in any manufacturing sup-

    ply chain there are two primitive compo-

    nents: stocks and flows. The flows repre-

    sent both the transformation element (anoutflow) and the demand element (an

    inflow). The stocks provide a means to

    separate and coordinate these two flows.

    In a perfect world, transformation

    would exactly meet demand. This means

    that we would have perfect processes to

    produce exactly what is needed and per-

    fect customers to purchase exactly what

    is produced. Because there is variability,

    this perfect world cannot exist. To syn-chronize transformation and demand,

    buffers are required. And while a stock

    is one way to match demand to transfor-

    mation, there are two others: extra time

    and extra capacity. Another law of factory

    physics is that there are only three possi-

    ble buffers to interface between demand

    and transformation: inventory, time, and

    capacity. In other words, the transforma-

    tion can satisfy demand in several ways:

    immediately from stock, by making the

    demand wait for the product, or by main-

    taining extra capacity in order to provide

    timely production upon demand.

    Fgre 2. A make-to-order costat work--process le

    work-in-processwithbuffers

  • 8/6/2019 IEFeb07 Realities

    5/6

    40 Industrial Engineer

    Effective risk management is essen-

    tially a matter of effective buffer deploy-

    ment. It is how we determine the amount

    of risk to take on and how to buffer that

    risk, whether with extra inventory, extra

    time to satisfy the customer, or extra ca-

    pacity to have on hand to cover disrup-tions. Unfortunately, there is no single

    solution. The optimal configuration of

    risk and buffers will be different for vari-

    ous business situations.

    The aspirin operations of Bayer Corp.

    and the desktop factory of Dell Corp.

    have very different configurations. Bayer

    is likely to have a considerable amount of

    inventory with little excess capacity. Con-

    versely, Dell has no finished goods inven-tory and a significant amount of extra

    installed capacity. How else could Dell re-

    spond in a timely way to peaks in demand

    at Christmas and graduation? While nei-

    ther of these situations use a significant

    time buffer, Moog Corp., which supplies

    custom servo valves to high-tech and

    aerospace customers, requires time to

    create a customized product.

    Note that a flexible buffer is less cost-

    ly than a permanent one. This is why

    postponement the ability to delay

    committing a common component into

    the final product until the last possible

    moment is effective in reducing in-

    ventory. Likewise, having a flexible ca-

    pacity buffer such as the makeup shift

    used by Toyota or temporary workers

    that can be called upon when demand

    is higher than normal is less costly thanhaving all the workers all the time. Like-

    wise, quoting due dates with variable

    lead-times is more effective than stating

    a constant lead-time.

    So how do we use this understanding to

    create a system that can accommodate risk,

    provide a method for effective planning

    and control, and retain the ability to see

    the unknown if the need arises? Smooth

    and continuous flow has been the key tothe Toyota Production System; although

    achieving flow does not require that one try

    to duplicate exactly what Toyota has done

    in automotive assembly. If we achieve flow,

    then planning and controlling produc-

    tion become easy. Instead of attempting

    to schedule hundreds of individual jobs

    on a Gantt chart or trying to specify arti-

    ficial penalties in an APO, a planner needs

    simple tools to manage flow.

    Figure 2 shows a supply chain seg-

    ment and indicates all three buffers:

    time, inventory, and capacity. Figure 2 il-

    lustrates a simple linear flow, but it could

    contain several levels and many routings.

    The stock contains either jobs that com-

    plete before their due dates (in the case

    of make-to-order) or of finished goods

    inventory (in the case of make-to-stock).

    Coming from the left are two arrowsindicating make-to-order demand and

    raw materials. These materials would

    be supplied by a previous supply chain

    segment. From the right comes an arrow

    showing make-to-stock demand.

    This simple framework can create a

    new and more effective way to manage

    manufacturing supply chains. The key is

    to reduce the number of values that must

    be monitored as well as control variablesin the problem. This means that instead

    of providing a detailed schedule indicating

    where each job is scheduled on a machine

    during a given time slice, we determine a

    set of control variables that will dynamical-

    ly and automatically determine the sched-

    ule as the system evolves. This approach is

    called dynamic risk-based planning and

    scheduling (DRPS). Under DRPS we need

    only monitor projected inventory and pro-

    jected service levels and then control a few

    key parameters reorder points or lead-

    times, production quantities (lot sizes),

    installed capacity, makeup capacity, WIP

    level, and the virtual queue.

    A brief reflection on the design of

    the system will show that if optimized

    planning parameters listed above are in

    place, the entire system will run well so

    long as projected service and inventory

    levels stay within acceptable ranges. Lotsizes have been established that mini-

    mize WIP and finished goods subject to

    the available capacity. Lead-times (or re-

    order points) are set by considering the

    trade-offs between service and inventory

    levels. Therefore, jobs can move through

    the flow in first-in, first-out order with-

    out the need for a detailed schedule.

    Safety stocks are set considering the

    time in the virtual queue plus the time

    realtes of rsk

    Fgre 3. Statoal comparso of APO ad DRPS

    SiTuATiOn

    Capacty greatertha expected

    Capacty less thaexpected

    Demad greatertha expected

    Demad less thaexpected

    ERP APO

    Caot work ahead ofgeerated schedle

    Schedle becomescreasgly feasble,orders become late lesshgh safety lead-tme

    Shortages less very hghsafety stock

    ueeded orders released;vetory rses

    DRPS

    Ca work ahead pto defed earlestrelease dates

    Shortfall trgger dcateseed for addtoalcapacty. Do ot eedhgh safety lead-tme.

    Shortfall trgger dcateseed for addtoalcapacty; o shortages,mmal safety stock.

    no eeded ordersreleased; vetory stays plaed rage

    complexapo

  • 8/6/2019 IEFeb07 Realities

    6/6

    February 2007 41

    through the flow and with regard to the er-

    ror in the forecast. Once these parameters

    are set (reviewed periodically perhaps once

    per month), the planner need only moni-

    tor the projected inventory and service

    levels. The only time action is required is

    when these levels exceed set trigger points.

    These trigger points indicate both insuf-

    ficient capacity and more capacity than is

    needed. If the virtual queue grows beyond

    what is planned for in the lead-times, there

    is insufficient capacity and so the extra

    capacity (overtime or make-up shifts) is

    applied. If the virtual queue becomes too

    low, one can either reduce capacity or pull

    in some jobs early. The result is not only

    a much simpler supply chain to manage

    but one that can automatically respond to

    random changes in demand and supply

    without the need to reschedule. This abilityto automatically adjust is a tremendous im-

    provement and makes DRPS more effective

    than the more complex APO (Figure 3).

    This is good news for industrial engi-

    neers since these are the only engineers

    trained in the art of setting the planning

    parameters. Once these parameters are

    known, the system can be implemented.

    Fortunately, the task can be simplified

    by using the existing MRP system and

    a generalized pull system known as con-

    stant work-in-process (CONWIP).

    The CONWIP pull protocol is a meth-

    od for achieving pull production in a wide

    range of production environments and

    is key to flow management. This mecha-

    nism maintains a nearly constant level

    of WIP that is needed to keep bottleneck

    processes busy by starting a new job only

    when the WIP level has fallen below a

    given maximum level. The result is pre-

    dictable cycle times, smoother flow, and

    higher throughput than would be seen in

    an equivalent push (e.g., MRP) system.

    The CONWIP mechanism also isolates

    the variability inherent in demand from

    disturbing the flow. This is accomplished

    using the virtual queue. If demand goes

    up, WIP does not but the virtual queue

    does and the projected service levels beginto fall. Likewise, if demand begins to fall,

    the virtual queue falls but WIP stays con-

    stant and projected inventory levels rise.

    usg MRP wth pllIt is important to note that the plans gen-

    erated by good old-fashioned MRP can

    be quite good if several conditions hold:

    Average demand does not exceed ca-

    pacity.

    Jobs are released using a pull system

    that prevents WIP explosions.

    Cycle times are short enough to avoid

    expediting.

    Safety stock (or safety lead-time) is

    determined by considering demand

    and capacity. Batch sizes are determined consider-

    ing demand and capacity to ensure

    minimal WIP and low inventories.

    Due dates are checked by considering

    the characteristics of the pull system

    and the sequence of the jobs to be

    pulled.

    If the system is designed well, these

    conditions will hold. MRP is used in the

    usual way but instead of starting jobs ac-cording to MRPs planned order release

    list, the CONWIP protocol pulls them.

    The entire release list becomes the virtual

    queue. Then, knowing the cycle time of

    the line and the rate at which jobs are be-

    ing pulled into the line, we can accurately

    predict when each job will complete.

    Again, neither traditional systems

    such as MRP nor modern systems like

    APO adequately address risk issues. It is

    also apparent that more IT is not the so-

    lution to the problem without complete-

    ly rethinking the problem. Supply chain

    managers benefit greatly from a system

    that is dynamic to avoid rescheduling,

    risk-based to accommodate risk factors

    and randomness, and that links plan-

    ning and execution.

    Mark L. Spearman is president and chief ex-

    ecutive officer of Factory Physics Inc. Prior to founding Factory Physics, Spearman was a

    professor of industrial and systems engineer-

    ing in the industrial engineering department

    at Georgia Tech. For over 15 years, his research

    and teaching dealt with manufacturing enter-

    prise integration and supply chain manage-

    ment. Spearman holds a Ph.D. in industrial

    engineering, is a senior member of IIE, a full

    member of INFORMS, and is certified in pro-

    duction and inventory management by APICS.

    Fgre 4. WiP, demad, throghpt, ad cycle tme

    conwipflow

    CourtesyFactoryPhyscsinc.