ignalina nuclear power plant presentation to the assembly of contributors
DESCRIPTION
This presentation was done in June, 2010TRANSCRIPT
Transformation of INPP for decommissioning
and
Current Status of IIDSF Projects
Osvaldas ČiukšysGeneral Director
Ignalina Nuclear Power Plant
Ignalina Nuclear Power Plant
2
December 31, 2009: change of INPP core
activity
INPP was acting as nuclear power plant operator.
December 31, 2009 Unit 2 reactor was shut down.
the Main INPP activity has been changed to decommissioning organization.
Ignalina Nuclear Power Plant
3
Successful operation of INPP: accumulated expertise and know-how of RBMK technology –
key prequalification for successful RBMK type plant decommissioning - 1974 Preparations started for construction of INPP- 1983 Unit 1, 1987 Unit 2 commissioned- It took 11 years to build the worlds most powerful nuclear plant- Originally 4 RBMK-1500 reactors planned- ~ 6000 staff employed (1989) - In 27 years 308 bln kWh of electricity
- INPP specialists were the first to start using the enriched fuel with burnable absorber – erbium
- Unique project of Unit 1 nuclear fuel reuse in Unit 2 reactor implemented 1st time in operation history of nuclear reactors- Other unique technology improvements & modifications
Safe & Cost – Effective Decommissioning:- Transformation of INPP from operation to decommissioning
- Application of the best international practice: greater ownership & full employment of all internal resources
Values
Strategy
Mission
Tasks
Vision
VisionINPP - the company, safely and efficiently terminating its operation as a nuclear power facility, gaining and sharing its experience in decommissioning as well as turning its activitiesand (infra)structure to commercially effective and business oriented opportunities.
Mission
to pioneer safe and successful RBMK type reactor decommissioning
to develop highest level of management of: human resources, time and funds processes and projects radioactive waste
to use own staff and expertise in order to gain and achieve: experience and new skills efficiency and transparency use of skills and know-how in intn’l decom projects
to maintain certain level of social security as employer
through the whole process of decommissioning
Strategy and Tasks (1) Short term 2010 – 2013
Fast reorganization of INPP to post-operational nuclear facility aiming its main activities to full extend for decommissioning :
change of management, INPP structure, work culture and attitude maintaining the highest standards for nuclear and radiological safety
implementation of project based / Horizontal vs. Vertical / static hierarchical model for processes and projects management
revision of FDP and overall decom costs, optimization of post – operational costs and public procurement
key decom projects acceleration and completion/operational acceptance: new spent fuel and waste management facilities and storages
initiation of in-house D&D (Decontamination & Dismantling) projects: both units reactors D&D, tools management, radiological characterization etc.
retention of skilled INPP specialists, application of motivation schemes
Strategy (2) Medium to long term 2014 – 2020 – 2029
2014 – 2020: fast and safe defueling of both units into the ISFSF peak of D&D in main buildings management of big waste volumes start of both units reactors D&D gradual handover of spent fuel and r-waste storages to RATA.
2020 – 2029: environment friendly and safe end-state of both units reactors D&D fill-up of r-waste storages D&D of main buildings or their adoption to possible reuse for industrial
purposes site remediation decommissioning company reorganization to: - real estate management, - radioactive waste handling - international decom projects / other supporting entities
Safety Cost-effectiveness Transparency and responsibility Professional approach and innovation Social guarantees and openness for society
Values
Main periods for the whole decommissioning planning
?
Revision of FDP / other key documents and amendments of
legislation
Ignalina Nuclear Power Plant
11
Restructured management
Accou
nts
Asset
s &
Procu
rem
ent
Perso
nnel
Labo
ur S
afet
y
Traini
ng
Centre
Info
rmat
ion
Centre
Decommissioning Directorate
Finance Directorate
Personnel Directorate Security
Department
DocumentManagement
Quality Assurance
Legal Group
Planning GroupAdvisory Group
General Director
Techn
ology
Dep
artm
ent
Projec
t
Dep
artm
ent
D&D
Dep
artm
ent
Rad. S
afet
y
Dep
artm
ent
Radwas
te
Depar
tmen
t
Further optimization of INPP management and functional structure in the course of 2010
Ignalina Nuclear Power Plant
12
• Purpose– Improved cost effectiveness
“… a number of revisions that should be made to … improve the cost effectiveness of the proposed projects.”
Independent Expert Review Group Report – March 2007
In-house project strategy
Ignalina Nuclear Power Plant
13
• Purpose– Improved cost effectiveness – Motivate and retain INPP’s engineering staff
“… motivation of INPP staff to rise to the professional challenges of integrated decommissioning and waste management, represents, in the view of the IERG, an important milestone in the ongoing gradual transition of the INPP operations function into an efficient Decommissioning Service business organisation.”
IERG Report – March 2007
In-house project strategy
Ignalina Nuclear Power Plant
14
• Purpose– Improved cost effectiveness – Motivate and retain INPP’s engineering staff– Improve horizontal coordination of D&D planning
It was important to note the need for INPP Management to reconsider their traditional vertical thinking in favour of horizontal thinking in view of the repetitive tasks ahead.
IERG to EC – March 2007
In-house project strategy
Ignalina Nuclear Power Plant
15
• Purpose– Improved cost effectiveness – Motivate and retain INPP’s engineering staff– Improve horizontal coordination of D&D planning
• Approach– Maximise own-staff involvement in project leadership/performance– Use external consultants only for specific targeted support
• Application (to date)– Radiological characterisation (replacing external project RDC.02)– Reactor D&D feasibility study (replacing external project B9-4)
* - Following the recommendations of Independent Expert Review Group Report – March 2007
Implementation of in-house projects* :
Ignalina Nuclear Power Plant
16
• Purpose– Cost saving by rationalised tool procurement (esp. consumables)
“…not all of the tools and equipment specified in each project need to be available on the start of the respective decontamination and dismantling activities. The required dates for the phased availability of the tools and equipment should form part of the optimised planning process for the individual decontamination and dismantling projects and activities.”
“… a budget [has] to be established for the routine maintenance and replacement of such tools, as needed, during the whole decommissioning period”
IERG – March 2007
Tools management
Ignalina Nuclear Power Plant
17
• Purpose– Cost saving by rationalised tool procurement (esp. consumables)
• Approach– ensure no duplication with existing INPP equipment– ensure no duplication between B9 projects– procure tools according to schedule of usage – encourage flexibility and economy in tool usage – price benefits of locally-sourced, larger-scale call-off contracts
• Application – Replacing all former “building-by-building” tool procurements
• B14 • B15 • B29
Introduction of tools management* :
* - Following the recommendations of Independent Expert Review Group Report – March 2007
FDP Key decommissioning dates 2004 -2016
Units Final Shutdown
Reactors defueling
Pools defuelling
Start of D&D activities
• Unit 1 – 31/12/2004• Unit 2 – 31/12/2009
• Unit 1 – 31/12/2009• Unit 2 – 28/02/2012
• Unit 1 – 31/08/2015• Unit 2 – 12/01/2016
• Unit 1 – 01/01/2010• Unit 2 – early 2012
achieved planned
Ignalina Nuclear Power Plant
19
B1: Interim Spent Fuel Store Key contract data
– Signed 12 January 2005 with GNS-NUKEM consortium– Completion date:
• Original contract 04 / 06 / 2009• Current amendment 29 / 03 / 2011
– Contract price:• Original contract 171,487,079.00 EUR• Current amendment 193,492,261.97 EUR
Contract amendment signed May 2009 – intended to resolve commercial issues and establish new fixed schedule
Outcome (1 year later):– Further schedule slippage: 8 months
– Completion July 2011: estimated , slippages – Further claims anticipated regarding damaged fuel– No satisfactory recovery/mitigation plan from NUKEM
+ 22 months
+ 22 MEUR (approx)
19 - 06 - 2010B1
Assessment of maintenance costs is made on the basis of EWN (Germany) calculations in the context of “Decommissioning Project for INPP Unit 2 Final Shutdown and Defuelling Phase” (Project U2DP0).
ANALYSIS OF THE IMPACT OF ISFSF COMMISSIONING DELAY (PROJECT В1) ON THE GENERAL DECOMMISSIONING PROCESS
Delay amounts to 32 months according to estimated date of completion
Due to the fuel in the reactor no reduction in safety level and safety systems maintenance costs
Next safety systems reduction is possible when fuel removed from pools
Further increase of the costs because of likely further slippages
INPP post-shutdown maintenance costs greatly depend on keeping the fuel in the Units’ reactors and pools:
Ignalina Nuclear Power Plant
21
B2/3/4: Radwaste facilitiesB2: Waste retrieval and sorting / 3: Waste management / B4: Waste storage
Key contract data:
– Contract signed 30 November 2005 with NUKEM– Completion date
• Original contract 28 / 11 / 2009• Current forecast + 49 months delay (estimated)
– Contract price• Original contract 120,065,781 EUR• Current contract 122,936,810 EUR• Current claims approx. 70 MEUR
Current status
• B2: No on-site activities at INPP• B3/4: Concrete base laid but no further progress• INPP and NUKEM explores possibility to reach
Global Settlement on unsolved commercial issues
17 – 06 - 2010B34
Ignalina Nuclear Power Plant
22
Resolution of B1/2/3/4 issues
Observations - Performance of NUKEM is unsatisfactory
• unjustified claims• failure to provide information in a timely manner
More proactive approach of INPP- engaging strong legal support team to contest NUKEM claims- calculation of INPP extra costs due to NUKEM delays- keeping key stakeholders (MoE, EC, EBRD) informed of progress in
INPP/NUKEM relations and negotiations
- Contracts create additional complications due to use of Eglish law for contract activities conducted in Lithuania
UP – 01 Project: D&D of Units 1 & 2 reactor shafts:
initiated as in-house project cost saving of the whole process: project B9-4 transformed to feasibility study on D&D of both units reactors started in- house
enables to use INPP staff expertise and develop know-how
special working group created
program of milestones and priorities set up
involvement of different research/ scientific institutions and contractors
cooperation with IAEA in project on Carbonwaste and graphite handling
Key Decommissioning Project
R1
R3
R2
Ministry of Energy of the Republic of Lithuania
Thank you / Ačiū
Ignalina International Decommissioning Support Fund
Republic of Lithuania