ih 20 ranger hill realignment/ reconstruction...solutions – effective meetings with regulatory...
TRANSCRIPT
![Page 1: IH 20 RANGER HILL REALIGNMENT/ RECONSTRUCTION...Solutions – Effective Meetings with Regulatory Staff Meeting on -site with USACE Ft Worth ... – Information needed for PCN . Solutions](https://reader033.vdocument.in/reader033/viewer/2022042412/5f2c73bc5efd15139465f221/html5/thumbnails/1.jpg)
IH 20 RANGER HILL REALIGNMENT/ RECONSTRUCTION
Biological Issues and Compressed Schedule
![Page 2: IH 20 RANGER HILL REALIGNMENT/ RECONSTRUCTION...Solutions – Effective Meetings with Regulatory Staff Meeting on -site with USACE Ft Worth ... – Information needed for PCN . Solutions](https://reader033.vdocument.in/reader033/viewer/2022042412/5f2c73bc5efd15139465f221/html5/thumbnails/2.jpg)
Project Background – Concerns for this portion of IH 20
Three main safety concerns – Steep grade
– Sharp curve
– Steep superelevation (8% banking)
No frontage roads – No access for emergency vehicles
– No detour if lanes are closed
Need to update to current design standards
![Page 3: IH 20 RANGER HILL REALIGNMENT/ RECONSTRUCTION...Solutions – Effective Meetings with Regulatory Staff Meeting on -site with USACE Ft Worth ... – Information needed for PCN . Solutions](https://reader033.vdocument.in/reader033/viewer/2022042412/5f2c73bc5efd15139465f221/html5/thumbnails/3.jpg)
Project Description
![Page 4: IH 20 RANGER HILL REALIGNMENT/ RECONSTRUCTION...Solutions – Effective Meetings with Regulatory Staff Meeting on -site with USACE Ft Worth ... – Information needed for PCN . Solutions](https://reader033.vdocument.in/reader033/viewer/2022042412/5f2c73bc5efd15139465f221/html5/thumbnails/4.jpg)
Project Description
Removal of vegetation on 89 acres of new ROW – Wooded areas and steep slopes
Realignment & Reconstruction of IH 20 mainlanes
– Approximately 3 miles of project limits – Major road cut – Excavation of up to 65’ of bedrock (~2,000,000 CY) – Major embankment fill – Up to 60’ high – Drainage culvert for stream under embankment section
Construction of new IH 20 frontage roads
Braided, grade-separated entrance/exit ramps
– To allow access to westbound Safety Rest Area
Installation of new lighting and signage Removal of roadbed on original alignment
![Page 5: IH 20 RANGER HILL REALIGNMENT/ RECONSTRUCTION...Solutions – Effective Meetings with Regulatory Staff Meeting on -site with USACE Ft Worth ... – Information needed for PCN . Solutions](https://reader033.vdocument.in/reader033/viewer/2022042412/5f2c73bc5efd15139465f221/html5/thumbnails/5.jpg)
Challenges – Endangered Species Habitat Impacts
New alignment through potential habitat for Golden-cheeked Warbler
![Page 6: IH 20 RANGER HILL REALIGNMENT/ RECONSTRUCTION...Solutions – Effective Meetings with Regulatory Staff Meeting on -site with USACE Ft Worth ... – Information needed for PCN . Solutions](https://reader033.vdocument.in/reader033/viewer/2022042412/5f2c73bc5efd15139465f221/html5/thumbnails/6.jpg)
Challenges –Wetland and Stream Impacts
Impacts to ~850 linear feet of intermittent stream
Wetland impacts
![Page 7: IH 20 RANGER HILL REALIGNMENT/ RECONSTRUCTION...Solutions – Effective Meetings with Regulatory Staff Meeting on -site with USACE Ft Worth ... – Information needed for PCN . Solutions](https://reader033.vdocument.in/reader033/viewer/2022042412/5f2c73bc5efd15139465f221/html5/thumbnails/7.jpg)
Challenges – Project on New ROW
Environmental Surveys – Archeological investigations
– Wetland/Stream delineation
– Habitat and presence/absence surveys for GCWA
Geotechnical Investigations – Geotechnical information was needed from across the area to improve
Project Design and inform bid prices
– Project area vegetation needed to be cleared for equipment access
– Vegetation couldn’t be cleared until after NEPA clearance
![Page 8: IH 20 RANGER HILL REALIGNMENT/ RECONSTRUCTION...Solutions – Effective Meetings with Regulatory Staff Meeting on -site with USACE Ft Worth ... – Information needed for PCN . Solutions](https://reader033.vdocument.in/reader033/viewer/2022042412/5f2c73bc5efd15139465f221/html5/thumbnails/8.jpg)
Challenges – Aggressive Project Schedule
Original Project Timeline – Start April 2015 – with letting in December 2016
Actual Project Timeline – WA Executed – April 2015, started in earnest on Environmental activities – Late October 2015 – Received Environmental Clearance November 2016
On-site Visit with USFWS - March 2, 2016
TPWD Coordination - March 9, 2016 -
May 20, 2016
Conference Call with USFWS to
Discuss Survey
Results - May 2, 2016
Biological Assessment to USFWS July 1,
2016
Biological Opinion Issued -
October 21, 2016
![Page 9: IH 20 RANGER HILL REALIGNMENT/ RECONSTRUCTION...Solutions – Effective Meetings with Regulatory Staff Meeting on -site with USACE Ft Worth ... – Information needed for PCN . Solutions](https://reader033.vdocument.in/reader033/viewer/2022042412/5f2c73bc5efd15139465f221/html5/thumbnails/9.jpg)
Solutions – Effective Meetings with Regulatory Staff
Meeting on-site with USFWS Liaison and Arlington ES Office Staff – Talked through project details and
construction sequencing
– Discussed construction methodologies (e.g. use of blasting for roadcut)
– Evaluated habitat quality in project area
– Came to agreement on scope and scale of potential impacts
Follow-up Meeting with USFWS – Discussed results of surveys
– Added BCVI to consultation
![Page 10: IH 20 RANGER HILL REALIGNMENT/ RECONSTRUCTION...Solutions – Effective Meetings with Regulatory Staff Meeting on -site with USACE Ft Worth ... – Information needed for PCN . Solutions](https://reader033.vdocument.in/reader033/viewer/2022042412/5f2c73bc5efd15139465f221/html5/thumbnails/10.jpg)
Solutions – Effective Meetings with Regulatory Staff
Meeting on-site with USACE Ft Worth Regulatory Staff – Discussed project impacts
– Assessment methodology for calculating mitigation credits
– Information needed for PCN
![Page 11: IH 20 RANGER HILL REALIGNMENT/ RECONSTRUCTION...Solutions – Effective Meetings with Regulatory Staff Meeting on -site with USACE Ft Worth ... – Information needed for PCN . Solutions](https://reader033.vdocument.in/reader033/viewer/2022042412/5f2c73bc5efd15139465f221/html5/thumbnails/11.jpg)
Solutions - Early ROW Acquisition
Early ROW acquisition with state funds enabled project activities to move forward more quickly: – We were able to start ROW processes ahead of NEPA clearance
– ROW was acquired shortly after NEPA clearance
![Page 12: IH 20 RANGER HILL REALIGNMENT/ RECONSTRUCTION...Solutions – Effective Meetings with Regulatory Staff Meeting on -site with USACE Ft Worth ... – Information needed for PCN . Solutions](https://reader033.vdocument.in/reader033/viewer/2022042412/5f2c73bc5efd15139465f221/html5/thumbnails/12.jpg)
Solutions – Separate Contract for Clearing
Separate maintenance contract for clearing vegetation which:
Allowed for clearance of vegetation prior to nesting season for GCWA and BCVI
Allowed for more detailed geotechnical investigations prior to letting , which increased knowledge about excavation and potentially improved bid prices
Opened the door to other construction contractors that might not have been willing to bid
![Page 13: IH 20 RANGER HILL REALIGNMENT/ RECONSTRUCTION...Solutions – Effective Meetings with Regulatory Staff Meeting on -site with USACE Ft Worth ... – Information needed for PCN . Solutions](https://reader033.vdocument.in/reader033/viewer/2022042412/5f2c73bc5efd15139465f221/html5/thumbnails/13.jpg)
Timeline Comparison
![Page 14: IH 20 RANGER HILL REALIGNMENT/ RECONSTRUCTION...Solutions – Effective Meetings with Regulatory Staff Meeting on -site with USACE Ft Worth ... – Information needed for PCN . Solutions](https://reader033.vdocument.in/reader033/viewer/2022042412/5f2c73bc5efd15139465f221/html5/thumbnails/14.jpg)
Takeaway Messages
Start early, but not too early – Identify milestones during scoping phase
Communicate openly and effectively – Engage regulatory agencies early
– Value of site visits
– Keep everyone in the loop as things change
Look for Innovative Methods – Know what resources are available to you
![Page 15: IH 20 RANGER HILL REALIGNMENT/ RECONSTRUCTION...Solutions – Effective Meetings with Regulatory Staff Meeting on -site with USACE Ft Worth ... – Information needed for PCN . Solutions](https://reader033.vdocument.in/reader033/viewer/2022042412/5f2c73bc5efd15139465f221/html5/thumbnails/15.jpg)
A Parting Shot
Below is a link to a video from a drone shot when blasting https://youtu.be/A_ledu0dsOA