ih 20 ranger hill realignment/ reconstruction...solutions – effective meetings with regulatory...
TRANSCRIPT
IH 20 RANGER HILL REALIGNMENT/ RECONSTRUCTION
Biological Issues and Compressed Schedule
Project Background – Concerns for this portion of IH 20
Three main safety concerns – Steep grade
– Sharp curve
– Steep superelevation (8% banking)
No frontage roads – No access for emergency vehicles
– No detour if lanes are closed
Need to update to current design standards
Project Description
Project Description
Removal of vegetation on 89 acres of new ROW – Wooded areas and steep slopes
Realignment & Reconstruction of IH 20 mainlanes
– Approximately 3 miles of project limits – Major road cut – Excavation of up to 65’ of bedrock (~2,000,000 CY) – Major embankment fill – Up to 60’ high – Drainage culvert for stream under embankment section
Construction of new IH 20 frontage roads
Braided, grade-separated entrance/exit ramps
– To allow access to westbound Safety Rest Area
Installation of new lighting and signage Removal of roadbed on original alignment
Challenges – Endangered Species Habitat Impacts
New alignment through potential habitat for Golden-cheeked Warbler
Challenges –Wetland and Stream Impacts
Impacts to ~850 linear feet of intermittent stream
Wetland impacts
Challenges – Project on New ROW
Environmental Surveys – Archeological investigations
– Wetland/Stream delineation
– Habitat and presence/absence surveys for GCWA
Geotechnical Investigations – Geotechnical information was needed from across the area to improve
Project Design and inform bid prices
– Project area vegetation needed to be cleared for equipment access
– Vegetation couldn’t be cleared until after NEPA clearance
Challenges – Aggressive Project Schedule
Original Project Timeline – Start April 2015 – with letting in December 2016
Actual Project Timeline – WA Executed – April 2015, started in earnest on Environmental activities – Late October 2015 – Received Environmental Clearance November 2016
On-site Visit with USFWS - March 2, 2016
TPWD Coordination - March 9, 2016 -
May 20, 2016
Conference Call with USFWS to
Discuss Survey
Results - May 2, 2016
Biological Assessment to USFWS July 1,
2016
Biological Opinion Issued -
October 21, 2016
Solutions – Effective Meetings with Regulatory Staff
Meeting on-site with USFWS Liaison and Arlington ES Office Staff – Talked through project details and
construction sequencing
– Discussed construction methodologies (e.g. use of blasting for roadcut)
– Evaluated habitat quality in project area
– Came to agreement on scope and scale of potential impacts
Follow-up Meeting with USFWS – Discussed results of surveys
– Added BCVI to consultation
Solutions – Effective Meetings with Regulatory Staff
Meeting on-site with USACE Ft Worth Regulatory Staff – Discussed project impacts
– Assessment methodology for calculating mitigation credits
– Information needed for PCN
Solutions - Early ROW Acquisition
Early ROW acquisition with state funds enabled project activities to move forward more quickly: – We were able to start ROW processes ahead of NEPA clearance
– ROW was acquired shortly after NEPA clearance
Solutions – Separate Contract for Clearing
Separate maintenance contract for clearing vegetation which:
Allowed for clearance of vegetation prior to nesting season for GCWA and BCVI
Allowed for more detailed geotechnical investigations prior to letting , which increased knowledge about excavation and potentially improved bid prices
Opened the door to other construction contractors that might not have been willing to bid
Timeline Comparison
Takeaway Messages
Start early, but not too early – Identify milestones during scoping phase
Communicate openly and effectively – Engage regulatory agencies early
– Value of site visits
– Keep everyone in the loop as things change
Look for Innovative Methods – Know what resources are available to you
A Parting Shot
Below is a link to a video from a drone shot when blasting https://youtu.be/A_ledu0dsOA