iii pmf management solutions · “estimate costs is the process of developing an approximation of...
TRANSCRIPT
![Page 1: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/1.jpg)
PMF MANAGEMENT
SOLUTIONS
III
Cost Management
![Page 2: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/2.jpg)
Project Management Framework | A Structure for All Organisations
� Define what is cost management
� Identify different cost estimating techniques.
� Consider the types of estimating.
� Discuss how these different types of estimating techniques are
used in different phases of the project lifecycle.
� Discuss the requirements of cost management strategies and
how they are used throughout the project lifecycle.
� Define the difference between contingency funding and a
financial management reserve.
Session Objectives
2
![Page 3: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/3.jpg)
Project Management Framework | A Structure for All Organisations
� Compiling a planned project budget.
� Managing the project’s actual incoming and outgoing
costs against the planned budget.
� Evaluating quality as well as quantity prior to payment
authorisation.
� Ensuring project costs are within the baselined budget
at finalisation.
� PMBOK – “The processes involved in planning,
estimating, budgeting, financing, funding, managing,
and controlling costs so that the project can be
completed within the approved budget” (p 193).
Definition of Budgeting (Cost)
Project Management Institute (PMI), (2013), A guide to the project management body of knowledge (5th ed.), Newtown Square, Pennsylvania, PMI
3
![Page 4: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/4.jpg)
Project Management Framework | A Structure for All Organisations
� Planning the costs associated with all actions required to
complete the scope of works.
� The budget should be a true reflection of the costs that will be
incurred to deliver the project product.
� The budget should be planned to deliver the project product
within the cost limitations of the Client Organisation.
� The budget should be planned to deal with the onset of risks so
as activities, tasks and work-packages are not delayed on the
basis that a risk becoming an issue, financial reserves:
• Contingency funding.
• Financial management reserve.
Process of Budgeting
4
![Page 5: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/5.jpg)
Project Management Framework | A Structure for All Organisations
� Contingency funding – is the additional budget set aside to
respond to risk that become and issue.
• Responds to the known risks of a project.
� Financial management reserve – is the additional budget set
aside to respond to unexpected circumstances.
• Responds to the unknown risks of a project.
• Generally only required for high risk projects.
� Please Note:
• Regardless of the money set aside for a contingency fund or
financial management reserve, the project must still be delivered
within the Client Organisation’s cost limitations.
Financial Reserves
5
![Page 6: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/6.jpg)
Project Management Framework | A Structure for All Organisations
� Identify the cost of what needs to be done to
deliver the project product:
• Product Based Planning.
• Product Breakdown Structure
• Work Breakdown Structure
• Actions (activities, tasks and work packages).
• Project resources, materials and equipment.
• Known constraints.
• Costs and expected increases.
� Knowledge of the complexity of the project
and environment in which it will be delivered.
Budgeting in Practice
6
![Page 7: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/7.jpg)
Project Management Framework | A Structure for All Organisations
� Analogous estimating (historic).
� Top-Down estimating (educated guess).
� Bottom-Up estimating (calculated).
� Parametric estimating (PERT):
• Statistical relationship between history and variables.
� Vendor bid analysis (procurement).
� Delphi technique (industry judgement).
� Wide-band Delphi technique (expert judgement).
� Pre determined (set by another).
Cost Estimating Techniques
7
![Page 8: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/8.jpg)
Project Management Framework | A Structure for All Organisations
Top Down� Recursively apportions overall project estimate to the next lower level.
� Demonstrated later in this lecture, slide 32.
Project (100%)
10%
15%
15%
40%
20%
Initiation
Planning
Design
Construction
Deployment
14%
13%
13%
Frame
Exterior
Interior
Adapted from Richardson, G. L. (2010). Project management theory and practice. Boca Raton, Florida: CRC Press.
8
![Page 9: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/9.jpg)
Project Management Framework | A Structure for All Organisations
Expert Judgement� Widely used i.e.:
• >60% in software industry.
� Often an element of top-down estimating.
� Advantages:
• Little or no further data collection.
• Flexible and adaptive.
• Quick assessment.
� Disadvantages:
• Limited by expert’s objectivity, breath of expertise, and memory
• Difficult to explain and verify because an expert’s knowledge is ‘compiled’.
Richardson, G. L. (2010). Project management theory and practice. Boca Raton, Florida: CRC Press. 9
![Page 10: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/10.jpg)
Project Management Framework | A Structure for All Organisations
Analogous Estimation
If a bird looks like a duck,
swims like a duck and
quacks like a duck,
then it probably is a duck.
If a bird looks like a duck,
swims like a duck and
quacks like a duck,
then it probably is a duck.
OR
It could be a Willie Robertson
doing a duck impersonation.
OR
It could be a Willie Robertson
doing a duck impersonation.
10
![Page 11: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/11.jpg)
Project Management Framework | A Structure for All Organisations
Analogous Cost Estimation� Description:
• Compares the proposed project/activity with a similar or historic project/activity.
• Uses parameters such as scope, cost, budget, and duration or measures of scale such as size, weight, and complexity.
• Primarily used in the earlier phases of the project.
� Advantages:• Similar to expert judgement.
• Requires only limited information.
• Quick and inexpensive compared to other estimation methods.
• Can be applied to total project or segments of projects.
� Disadvantages:• Similar to expert judgement.
• Low accuracy.
• Similarity in appearance may belie dissimilarity in fact.
Project Management Institute. (2013). A guide to the project management body of knowledge (5th ed.). Newtown Square, Pennsylvania: Project Management Institute.
Richardson, G. L. (2010). Project management theory and practice. Boca Raton, Florida: CRC Press.
11
![Page 12: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/12.jpg)
Project Management Framework | A Structure for All Organisations
Other Approaches
� Phased:
• Progressively refine estimates of succeeding phases as each phase
is completed.
• I.e. revision of business case at the end of each PRINCE2 stage.
• Related to ‘Rolling Wave’ development and delivery approach.
� Heuristic
• ‘Rules of thumb’ derived from past experience.
• I.e. the support cost of a Defence system is generally 3 times the
acquisition cost.
12
![Page 13: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/13.jpg)
Project Management Framework | A Structure for All Organisations
Parametric Estimation� Description
• Uses statistical relationships between historical data and other variables to derive a cost estimating relationship (CER) for parameters such as cost, budget and duration.
• Demonstrated later in this lecture, slide 40 - 43.
� Advantages
• Can produce highly accurate estimates depending upon model sophistication and data reliability
• Requires known, specific and often only limited data
• Quick to obtain an estimate
• Growing availability of data to develop future CERS
� Disadvantages
• Need to collect data from very large number of projects
• Often requires extensive experience in industry
13
![Page 14: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/14.jpg)
Project Management Framework | A Structure for All Organisations
Bottom-Up Estimating
http://www.cedarcreekwoodshop.com/duckpull.pdf
14
![Page 15: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/15.jpg)
Project Management Framework | A Structure for All Organisations
Bottom-Up Cost Estimation
• Cost of individual work actions, (activities, tasks and work-
packages) are estimated with the greatest level of specified
detail.
• Detailed costs are “rolled up” to higher levels
• Cost and accuracy of bottom-up cost estimating are
influenced by the size and complexity of the individual action
(activity, task or work-package) and the skill set of the
resources required to complete said action.
• Demonstrated later in this lecture, slide 38 - 39.
Project Management Institute. (2013). A guide to the project management body of knowledge (5th ed.). Newtown Square, Pennsylvania: PMI, pp.193-226
15
![Page 16: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/16.jpg)
Project Management Framework | A Structure for All Organisations
Project Management Institute. (2013). A guide to the project management body of knowledge (5th ed.). Newtown Square, Pennsylvania: PMI, pp.193-226
Determining the Budget
Q1 – What is a Contingency Reserve (Fund)?
Q2 – What is a Management Reserve?
16
![Page 17: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/17.jpg)
Project Management Framework | A Structure for All Organisations
Project Management Institute. (2013). A guide to the project management body of knowledge (5th ed.). Newtown Square, Pennsylvania: PMI, pp.193-226
Contingency Reserves for ‘Known Unknowns’
Management Reserves for ‘Unknown Unknowns’
Determining the Budget
17
![Page 18: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/18.jpg)
Project Management Framework | A Structure for All Organisations
� Few estimates will ever be 100% accurate, so:
• Record how the calculation was determined.
• Record all underlying assumptions.
• Record all impacting constraints.
• Record an optimistic, pessimistic and likely range (PERT) on high
risk actions (activities, tasks or work packages).
• Record all source data.
• Record details of all stakeholders involved.
• Record the provisional / tentative nature.
• Record an acceptable tolerance level (+/- where appropriate).
Estimating Guidelines
18
![Page 19: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/19.jpg)
Project Management Framework | A Structure for All Organisations
Budgeting Priorities� Identify the cost for all project work and the cost to manage
this work:
• Every person, what they do, how they get there, what extra costs are or
may be incurred.
• Every method and type of work, material, plant, equipment and any
other resource required.
• Every aspect of work, from design, approval, order, delivery, installation,
use and waste.
� Include the cost of managing the project.
� Where possible, plan for the unexpected.
� Don’t try and fit a cost estimate to the Client Organisation’s
expected budget:
� Negotiations later may require a reduced scope to accomplish this.
19
![Page 20: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/20.jpg)
Project Management Framework | A Structure for All Organisations
Budgeting Tools
� Project budgeting can be developed manually or via
specialised software.
� Manual:
• Costing of actions.
• Manually constructed budgets.
� Specialised software:
• Microsoft Project.
• Primavera.
• Microsoft Excel.
20
![Page 21: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/21.jpg)
Project Management Framework | A Structure for All Organisations
� 7.1 Plan Cost Management—The process that establishes the policies,
procedures, and documentation for planning, managing, expending, and
controlling project costs.
� 7.2 Estimate Costs—The process of developing an approximation of the
monetary resources needed to complete project activities.
� 7.3 Determine Budget—The process of aggregating the estimated costs of
individual activities or work packages to establish an authorized cost
baseline.
� 7.4 Control Costs—The process of monitoring the status of the project to
update the project costs and managing changes to the cost baseline (p 193).
PMBOK Cost Processes
21
Project Management Institute (PMI), (2013), A guide to the project management body of knowledge (5th ed.), Newtown Square, Pennsylvania, PMI
![Page 22: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/22.jpg)
Project Management Framework | A Structure for All Organisations
PMBOK Cost Mgt Overview
22
Project Management Institute (PMI), (2013), A guide to the project management body of knowledge (5th ed.), Newtown Square, Pennsylvania, PMI, p 194
![Page 23: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/23.jpg)
Project Management Framework | A Structure for All Organisations
� “Plan Cost Management is the process that establishes the policies, procedures, and documentation for planning, managing, expending, and controlling project costs.
� The key benefit of this process is that it provides guidance and direction on how the project costs will be managed throughout the project” (p 195).
� “The cost management processes and their associated tools and techniques are documented in the cost management plan” (p 196).
� This includes:• Incoming costs; and
• Outgoing costs.
7.1 Plan Cost Management
23
Project Management Institute (PMI), (2013), A guide to the project management body of knowledge (5th ed.), Newtown Square, Pennsylvania, PMI
![Page 24: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/24.jpg)
Project Management Framework | A Structure for All Organisations
� “Estimate Costs is the process of developing an approximation of the
monetary resources needed to complete project activities.
� The key benefit of this process is that it determines the amount of
cost required to complete project work.
� Cost estimates are a prediction that is based on the information
known at a given point in time. Cost estimates include the
identification and consideration of costing alternatives to initiate and
complete the project.
� Cost trade-offs and risks should be considered, such as make versus
buy, buy versus lease, and the sharing of resources in order to achieve
optimal costs for the project.”
7.2 Estimate Costs
24
Project Management Institute (PMI), (2013), A guide to the project management body of knowledge (5th ed.), Newtown Square, Pennsylvania, PMI, p 200-201
![Page 25: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/25.jpg)
Project Management Framework | A Structure for All Organisations
� “Determine Budget is the process of aggregating the estimated
costs of individual activities or work packages to establish an
authorized cost baseline.
� The key benefit of this process is that it determines the cost
baseline against which project performance can be monitored
and controlled.
� A project budget includes all the funds authorized to execute
the project.
� The cost baseline is the approved version of the time-phased
project budget, but excludes management reserves.”
7.3 Determine Budget
25
Project Management Institute (PMI), (2013), A guide to the project management body of knowledge (5th ed.), Newtown Square, Pennsylvania, PMI, p 208-209
![Page 26: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/26.jpg)
Project Management Framework | A Structure for All Organisations
� “Control Costs is the process of monitoring the status of the project to
update the project costs and managing changes to the cost baseline.
� The key benefit of this process is that it provides the means to recognize
variance from the plan in order to take corrective action and minimize risk.
� Updating the budget requires knowledge of the actual costs spent to date.
Any increase to the authorized budget can only be approved through the
Perform Integrated Change Control process (Section 4.5).
� Monitoring the expenditure of funds without regard to the value of work
being accomplished for such expenditures has little value to the project,
other than to allow the project team to stay within the authorized funding.
� Much of the effort of cost control involves analyzing the relationship
between the consumption of project funds to the physical work being
accomplished for such expenditures.”
7.4 Control Costs
26
Project Management Institute (PMI), (2013), A guide to the project management body of knowledge (5th ed.), Newtown Square, Pennsylvania, PMI, p 214-215
![Page 27: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/27.jpg)
Project Management Framework | A Structure for All Organisations
PMF Cost Processes
27
Estimate Cost of Product Milestone
Collate Initial Project Budget Estimate
Identify Resource Costs
Cost Activities, Tasks & Work-Packages
Monitor Project Budget
Allocate Administrations & Other Costs
Finalise Project Budget
Planning
Initiation
Execution
FinalisationReview Cost Functional Processes
Control Project Budget
Establish Project Budget
Implement Cost Management Plan
![Page 28: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/28.jpg)
Project Management Framework | A Structure for All Organisations
Initiation Phase Cost Processes
28
Estimate Cost of Product Milestone
Collate Initial Project Budget Estimate
Identify Resource Costs
Cost Activities, Tasks & Work-Packages
Monitor Project Budget
Allocate Administrations & Other Costs
Finalise Project Budget
Planning
Initiation
Execution
FinalisationReview Cost Functional Processes
Control Project Budget
Establish Project Budget
Implement Cost Management Plan
![Page 29: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/29.jpg)
Project Management Framework | A Structure for All Organisations
Conditions of Approvals
Not Approved
Approved
Potential Suppliers
Supply Rep Advice
Initial Budget Estimate
Project Manager Develops Initial
Budget Estimate for Project Charter
Identify a cost estimate for each
component
Consider additional administration /
licence / permit costs
Record any cost limitations and tentative nature
Consider profit margins and tax
implications
Project Close
(Start)
Business Case / Project Brief
Decision Gate
Historic Lessons Learned Logs
Proceed to Planning
Phase
Project Charter
Project Office(Project
Assurance)
Cost Initiation Actions
29
(Start)
Business Case / Project Brief
Conditions of Approvals
Initial Budget Estimate
Project Charter
Decision Gate
Proceed to Planning
Phase
![Page 30: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/30.jpg)
Project Management Framework | A Structure for All Organisations
� Industry experts should prepare or assist in the preparation of the cost
estimation for each component of the PBS.
� Their estimation will be based on industry knowledge and their
understanding of the scope statement and the necessary resources required
to complete work.
� To ensure the project stakeholder community has a high level understanding
of the performance targets each industry expert should clarify their cost
estimation.
� Clarification of the budget estimate must include provision of the details
used to form their top-down estimate.
• This may include: the number and type of resources required and/or available (including
any essential plant and equipment), any specialised processes, practices or techniques,
and/or any high risk actions.
Estimate Cost of Product Milestones
30
![Page 31: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/31.jpg)
Project Management Framework | A Structure for All Organisations
Using the PBS – Painting a House
31
Painting House
Prepare Interior Design
Pack up Belongings
Prepare Ceilings Walls and
Skirting BoardsPaint Ceilings Paint Walls
Paint Skirting Boards
Unpack Belongings
![Page 32: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/32.jpg)
Project Management Framework | A Structure for All Organisations
� Once the cost for each component of the PBS have been
determined, the Project Management Team will be able to
collate these costs to calculate the initial budget estimate.
� For example, a top-down estimation.
Collate Initial Project Budget Estimate
32
Painting House
Prepare Interior Design
Pack up Belongings
Prepare Ceilings Walls and
Skirting BoardsPaint Ceilings Paint Walls
Paint Skirting Boards
Unpack Belongings
$1,000 $1,500 $2,000 $1,500 $3,000 $1,000 $1,500
Initial Budget $11,500
![Page 33: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/33.jpg)
Project Management Framework | A Structure for All Organisations
Planning Phase Cost Processes
33
Estimate Cost of Product Milestone
Collate Initial Project Budget Estimate
Identify Resource Costs
Cost Activities, Tasks & Work-Packages
Monitor Project Budget
Allocate Administrations & Other Costs
Finalise Project Budget
Planning
Initiation
Execution
FinalisationReview Cost Functional Processes
Control Project Budget
Establish Project Budget
Implement Cost Management Plan
![Page 34: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/34.jpg)
Project Management Framework | A Structure for All Organisations
Conditions of Approvals
Not Approved
Approved
Engaged Supplier(s)
Supply Rep Advice
Detailed Project Budget
Project Manager Develops Detailed Budget as part of
Project Management Plan
Identify all HR costs
Identify all material and equipment costs
Include all admin, fees charges & insurance
Project Close
(Start)
Approved Project Charter
Decision Gate
Historic Lessons Learned Logs
Proceed to Execution
Phase
Project Management
Plan
Potential Suppliers
Individual Product Delivery Resource
Determine the contingency funding
Consider mark-up, tax and currency rates
Identify all procurement costs
Product Delivery Team Manager
Product Delivery Team Resource
Project Office(Project
Assurance)
Cost Planning Actions
34
(Start)
Approved Project Charter
Detailed Project Budget
Conditions of Approvals
Potential Individual
Product Delivery Resource
Potential Product Delivery Team Manager
Potential Product Delivery Team
Resource
Project Management
Plan
Decision Gate
Proceed to Execution
Phase
![Page 35: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/35.jpg)
Project Management Framework | A Structure for All Organisations
� What are the market costs for the human resources?
• What are the additional costs (allowances)?
• What are the on-costs (leave entitlements)?
� What are the market costs for plant and equipment?
� What are the costs of materials and supplies?
� Other potential cost considerations:
• Resource and materials lists (Bill Of Quantities).
• Archived / historical projects.
• Consumer Price Index (CPI) increases.
• Expected movements in price from suppliers.
Identify Resource Costs
35
![Page 36: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/36.jpg)
Project Management Framework | A Structure for All Organisations
Cost Allocation Over Product Lifecycle
36
Standards Australia/Standards New Zealand. (1999). AS/NZS 4536:1999 Life cycle costing--An application guide. Sydney: Standards Australia, p. 10
![Page 37: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/37.jpg)
Project Management Framework | A Structure for All Organisations
� Using the information contained in the PBS and WBS, costs can
be allocated to all actions (activities, tasks and work-packages).
� The Project Management Team must analyse the cost of human
and other resources based on their capabilities (skill set and
experience) and the needs of the project.
� The Project Management Team can then allocate these costs to
the actions and any known cost constraints.
� For example: if the project is utilising project personnel with
extensive experience the cost of the resources is likely to be
higher, although the work should be completed quicker.
Cost Activities, Tasks & Work Packages
37
![Page 38: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/38.jpg)
Project Management Framework | A Structure for All Organisations
Using the WBS – Painting a House
38
Painting House
Prepare Interior Design
Get Client’s Ideas
Visit Display Homes
Review Design Magazines
Prepare a Colour Board
Pack up Belongings
Pack Small Items in Boxes
Organise Removalist
Store Belongings
Prepare Ceilings Walls and
Skirting Boards
Wash all Surfaces with
Sugar soap
Plaster Blemishes and
Holes
Sand Plastering
Fill Gaps
Paint Ceilings
Cut in Ceilings (Two Coats)
Roll Ceilings (Two Coats)
Paint Walls
Cut in Walls (Two Coats)
Roll Walls (Two Coats)
Paint Skirting Boards
Paint Skirting Boards
(Two Coats)
Unpack Belongings
Retrieve Items from Storage
Place all Large Items
Unpack all Small Items
![Page 39: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/39.jpg)
Project Management Framework | A Structure for All Organisations
Example Budget – Painting a House
39
Painting House
Prepare Interior Design
Get Client’s Ideas
Visit Display Homes
Review Design Magazines
Prepare a Colour Board
Pack up Belongings
Pack Small Items in Boxes
Organise Removalist
Store Belongings
Prepare Ceilings Walls and
Skirting Boards
Wash all Surfaces with
Sugar soap
Plaster Blemishes and
Holes
Sand Plastering
Fill Gaps
Paint Ceilings
Cut in Ceilings (Two Coats)
Roll Ceilings (Two Coats)
Paint Walls
Cut in Walls (Two Coats)
Roll Walls (Two Coats)
Paint Skirting Boards
Paint Skirting Boards
(Two Coats)
Unpack Belongings
Retrieve Items from Storage
Place all Large Items
Unpack all Small Items
$150
$900
$350
$600
$250
$100
$1,200
$500
$300
$300
$300
$1,200
$500
$2,500
$1,000
$1,200 $200
$800
$800
$2,000 $1,550 $1,400 $1,700 $3,500 $1,200 $1,800
Budget $13,150
Bottom-Up Estimation
![Page 40: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/40.jpg)
Project Management Framework | A Structure for All Organisations
Bottom-Up Costing
Frame, J. D. (2002). The New Project Management: Tools for an Age of Rapid Change, Complexity, and other Business Realities (2nd ed.): Jossey-Bass, Chap 10
Sum
min
g U
pw
ard
s
40
![Page 41: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/41.jpg)
Project Management Framework | A Structure for All Organisations
PERT Analysis
� A Program, Evaluation, and Review Technique (PERT)
analysis is a probabilistic process.
� The intent is to evaluate a probable outcome based on
three scenarios:
• Best-case (optimistic);
• Expected-case (most likely); and
• Worst-case (pessimistic).
� This is useful for activities, tasks or work packages that
contain a high level of risk.
� A PERT is a Weighted Average Estimation Technique.
41
![Page 42: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/42.jpg)
Project Management Framework | A Structure for All Organisations
Values can change as long as the number used to divide the calculation is the
same as the combined totals above the line, for example:
PERT Calculation
T /C = Optimistic + (4 x Most likely) + Pessimistic
6
Duration Estimation (T /C)
T /C = Optimistic + (4 x Most likely) + (2 x Pessimistic)
7
Duration Estimation (T /C)
42
![Page 43: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/43.jpg)
Project Management Framework | A Structure for All Organisations
(c) ML
$3.50
(c) p
$5
(c) o
$3
Budget PERT Calculation
43
![Page 44: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/44.jpg)
Project Management Framework | A Structure for All Organisations
Parametric Costing Example
Frame, J. D. (2002). The New Project Management: Tools for an Age of Rapid Change, Complexity, and other Business Realities (2nd ed.): Jossey-Bass, Chap 10
Simple Labour Example
Approximate Construction Cost
Size of House Quality Price Per M² Estimated Cost
160M² Low $800 $128,000
232M² Medium $1,200 $278,400
385M² High $2,500 $962,500
44
![Page 45: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/45.jpg)
Project Management Framework | A Structure for All Organisations
� Administration costs:• Facilities, office and site.
• Power, phone and internet.
• Insurance and accounting.
� Other costs:• Currency exchange rates.
• Tax implications including GST.
� Review and consider all project functional areas, particularly:
� Scope, Procurement, Quality & Risk Management.
� PMBOK – Consider “health, safety, security, performance, environmental, insurance, intellectual property, rights, licenses, permits” (p 203).
Allocate Administration and Other Costs
45
Project Management Institute (PMI), (2013), A guide to the project management body of knowledge (5th ed.), Newtown Square, Pennsylvania, PMI
![Page 46: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/46.jpg)
Project Management Framework | A Structure for All Organisations
� The budget should record details of how the project costs were
established:
• Which stakeholders were involved.
• Any assumptions that have been made.
• Any high risk actions that are associated with the project.
� Developing a budget is not a once-off activity used to get
approval of the Project Management Plan.
� Develop a comprehensive budget to suit the project and project
resources.
� Identify any contingency funding and/ or financial management
reserve separately.
Establish Project Budget
46
![Page 47: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/47.jpg)
Project Management Framework | A Structure for All Organisations
Execution Phase Cost Processes
47
Estimate Cost of Product Milestone
Collate Initial Project Budget Estimate
Identify Resource Costs
Cost Activities, Tasks & Work-Packages
Monitor Project Budget
Allocate Administrations & Other Costs
Finalise Project Budget
Planning
Initiation
Execution
FinalisationReview Cost Functional Processes
Control Project Budget
Establish Project Budget
Implement Cost Management Plan
![Page 48: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/48.jpg)
Project Management Framework | A Structure for All Organisations
Non Conformance
Conformance
Control Action Plan
Product Delivery Resource Advises Work Completed
Project Close
(Start)
Approved PMP
CostPerformance
Proceed to Finalisation
Phase
Project Reports
Product Delivery Team Resource
Product Delivery Team Manager
Individual Product Delivery
Resource
Project Manager Implements PMP
through Allocation of Work Plans
Undertake Required Work
Actions According to Work Plan
Work Plans
Contracted Product Delivery
Resource(s)
Monitor Cost of Work
Control Cost of Work
Decision Gate
Mothball / Terminate
Continue
Assurance Report
Project Office(Project/ Quality
Assurance)
Cost Execution Actions
48
(Start)
Approved PMP
Work Plans
Product Delivery Team
Resource
Product Delivery Team
Manager
Individual Product Delivery Resource
Contracted Product Delivery
Resource(s)
Monitor Cost of Work
Control Cost of Work
X Iterations to Complete
WBS
Decision Gate
Proceed to Finalisation
Phase
Project Office(Project/ Quality
Assurance)
![Page 49: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/49.jpg)
Project Management Framework | A Structure for All Organisations
� Implementing budgetary actions is generally undertaken in collaboration
with the other functional areas of project management.
� It is simply the process of undertaking WBS actions in strict accordance with
the information contained within the PMP.
� The cost management plan is one of the ancillary plan that collaboratively
forms the PMP.
� The cost of actions within the work breakdown structure (WBS) will impact
the organising and implementation of future actions within the WBS.
� Implementing actions will require the Product Delivery Resources to be
advised of the planned expenditure for their work actions and process to
advise of possible overruns in their budget.
Implementation
49
![Page 50: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/50.jpg)
Project Management Framework | A Structure for All Organisations
� Routinely monitor the costs associated with undertaking project
management actions deliver the product being produced.
• Monitoring the costs associated with performing the project’s delivery
processes will inform the Project Management Team of actions that may
need to be taken to keep budget on track and aligned with the planned
cost of actions within the PMP.
• Monitoring the costs incurred for the Product Delivery Resources to
complete assigned actions will inform the Project Management Team of
actions that may need to be taken to keep work on budget and within
the agreed parameters.
Monitoring
50
![Page 51: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/51.jpg)
Project Management Framework | A Structure for All Organisations
Cost Monitoring
� Must be routinely undertaken to ensure actual
expenditure is inline with planned expenditure.
� Must ensure effective processes are implemented to
monitor project performance to ensure it is delivered
in accordance with planned performance.
� Must ensure work and materials are used as planned.
� Must ensure work and materials are delivered in full
and on time (DIFOT).
� Must report non-conformance immediately.
51
![Page 52: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/52.jpg)
Project Management Framework | A Structure for All Organisations
Earned Value Analysis
� An Earned Value Analysis (EVA) is an
effective tool for the monitoring the
project’s progress.
� An EVA consists of:
� A review of the projects:
� Planned Value (PV);
� Earned Value (EV); and
� Actual Cost (AC).
� May also be referred to as Earned
Value Management.
52
![Page 53: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/53.jpg)
Project Management Framework | A Structure for All Organisations
Planned Value (PV)
� Planned Value (PV) is the approved
project budget.
� Otherwise known as the budget
baseline for which expenditure will be
measured.
� It should include:
� A contingency fund for the whole project;
� A financial management reserve for the
project; and
� These should be depicted as a percentage
of the budget.
What It is
Planned
to Cost
53
![Page 54: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/54.jpg)
Project Management Framework | A Structure for All Organisations
Earned Value (EV)
� Earned Value (EV) is the percentage of the approved
project budget that has been earned as of a specific date
(the date measured).
� It is determined by calculating the amount of expenditure
that has been earned by all resources for the scheduled
work on that specified date.
� For example: if the overall cost is $10,000 and 30% of work
is complete, $3,000 has been earned.
54
![Page 55: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/55.jpg)
Project Management Framework | A Structure for All Organisations
Actual Cost (AC)
� Actual Cost is the amount of the approved project
budget that has been spent for the actual work
completed on a specified date.
� It is determined by calculating the costs actually
incurred (paid and committed) for the work that has
been completed.
� For example: if the 30% of work that is complete and
the amount paid is $3,000 ($1,000 paid and $1,000
committed to be paid), the actual cost is $2,000.
55
![Page 56: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/56.jpg)
Project Management Framework | A Structure for All Organisations
EVA Analysis
� The status of the project’s expenditure can be quickly
determined via an EVA.
� If the percentage of work completed and the earned value
is the same as the planned schedule and budget, then the
project is on track.
� If not, the project is either over / under budget or ahead /
behind schedule.
56
![Page 57: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/57.jpg)
Project Management Framework | A Structure for All Organisations
Example Earned Value Management
� Planned Value (PV):
• The budgeted cost assigned to work that was scheduled to be completed by a particular date.
• Also known as ‘Budgeted Cost of Work Scheduled’ (BCWS)
• Example:
� All tasks scheduled to be completed by the end of month 8 have a budgeted cost of $717K
� PV at the end of month 8 is $717K
� Supports forecasting of Budget at Completion (BAC):
• Enables comparison of original budget or cost estimate.
57
![Page 58: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/58.jpg)
Project Management Framework | A Structure for All Organisations
PV = $717K at end of month 8
58
![Page 59: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/59.jpg)
Project Management Framework | A Structure for All Organisations
Earned Value Management
� Actual Cost (AC):
• The actual cost of the work performed by a particular date regardless of the schedule or the budget.
• Sometimes called ‘Actual Cost of Work Performed (ACWP)’
• Example:
� By the end of month 8, the actual cost of all tasks performed was $385K.
� AC = $385K.
� Supports forecasting of Budget at Completion (BAC):
• Enables comparison of actual costs at completion.
59
![Page 60: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/60.jpg)
Project Management Framework | A Structure for All Organisations
Earned Value Illustration
0
200
400
600
800
1,000
1,200
0 1 2 3 4 5 6 7 8 9 10 11 12
Months
Exp
end
itu
re (
$000
) Planned Value (PV)
Actual Cost (AC)
AC = $385K at end of month 8
Under-Budget,Behind Schedule
OrBoth?
60
![Page 61: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/61.jpg)
Project Management Framework | A Structure for All Organisations
Earned Value Illustration
0
200
400
600
800
1,000
1,200
0 1 2 3 4 5 6 7 8 9 10 11 12
Months
Exp
end
itu
re (
$000
) Planned Value (PV)
Actual Cost (AC)
Possibilities:• Project manager has performed brilliantly and will
bringing project in well under budget beyond all
expectations.
• Project manager has performed abysmally—the
project is irreversibly behind schedule and getting
worse by the day.
61
![Page 62: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/62.jpg)
Project Management Framework | A Structure for All Organisations
Earned Value Management
� Earned Value (EV)
• The budgeted (NOT actual) cost of work actually performed (NOT scheduled)
• Sometimes called ‘Budgeted Cost of Work Performed’
• Example:
� At the end of month 8, the worked actually performed had a budgeted cost of $536K
� i.e. EV = $536K
� Percentage Complete (PC): the percentage of actual work completed
� EV = PC * BAC
62
![Page 63: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/63.jpg)
Project Management Framework | A Structure for All Organisations
Earned Value Illustration
0
200
400
600
800
1,000
1,200
0 1 2 3 4 5 6 7 8 9 10 11 12
Months
Exp
end
itu
re (
$000
)
Earned Value (EV)
Actual Cost (AC)
Cost or ScheduleVariance?
Common Basis for Earned Value and Actual Cost is Work Performed
63
![Page 64: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/64.jpg)
Project Management Framework | A Structure for All Organisations
Earned Value Illustration
0
200
400
600
800
1,000
1,200
0 1 2 3 4 5 6 7 8 9 10 11 12
Months
Exp
end
itu
re (
$000
)
Earned Value (EV)
Actual Cost (AC)
Cost Variance
Under or over budget?
As the earned value is
greater than the actual
cost, the project is under
budget.
64
![Page 65: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/65.jpg)
Project Management Framework | A Structure for All Organisations
Earned Value Illustration
0
200
400
600
800
1,000
1,200
0 1 2 3 4 5 6 7 8 9 10 11 12
Months
Exp
end
itu
re (
$000
) Planned Value (PV)
Earned Value (EV)
Cost or ScheduleVariance?
Common Basis of Earned Value and Planned Value is Budgeted Cost
65
![Page 66: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/66.jpg)
Project Management Framework | A Structure for All Organisations
Earned Value Illustration
0
200
400
600
800
1,000
1,200
0 1 2 3 4 5 6 7 8 9 10 11 12
Months
Exp
end
itu
re (
$000
) Planned Value (PV)
Earned Value (EV)
Schedule VarianceSV
Ahead or behind schedule?
As the earned value is
less than the planned
value, the project is
behind schedule.
66
![Page 67: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/67.jpg)
Project Management Framework | A Structure for All Organisations
Earned Value Illustration
0
200
400
600
800
1,000
1,200
0 1 2 3 4 5 6 7 8 9 10 11 12
Months
Exp
end
itu
re (
$000
) Planned Value (PV)
Earned Value (EV)
Actual Cost (AC)+ Cost Variance
(CV)
- Schedule Variance (SV)
67
![Page 68: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/68.jpg)
Project Management Framework | A Structure for All Organisations
Earned Value Illustration
0
200
400
600
800
1,000
1,200
0 1 2 3 4 5 6 7 8 9 10 11 12
Months
Exp
end
itu
re (
$000
) Planned Value (PV)
Earned Value (EV)
Actual Cost (AC)
- Cost Variance (CV)
+ Schedule Variance (SV)
What if ?
Actual Cost (AC)
Planned Value (PV)
68
![Page 69: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/69.jpg)
Project Management Framework | A Structure for All Organisations
Earned Value Performance Measures
SV > 0, ahead-of-scheduleSV = 0, on-scheduleSV < 0, behind-schedule
SPI> 1, ahead-of-scheduleSPI = 1, on-scheduleSPI < 1, behind-schedule
CV> 0, under-budgetCV = 0, on-budgetCV < 0, over-budget
CPI> 1, under-budgetCPI = 1, on-budgetCPI < 1, over-budget
69
AC
EVCPI
ACEVCV
PV
EVSPI
PVEVSV
=
−=
=
−=
(CPI)Index rmanceCost Perfo
(CV) VarianceCost
(SPI)Index ce PerformanSchedule
(SV) Variance Schedule
![Page 70: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/70.jpg)
Project Management Framework | A Structure for All Organisations
Sch
ed
ule
Pe
rfo
rma
nce
In
dic
ato
r
0.25 1.50.75 1.00.5 1.25 1.75
0.25
0.75
0.5
1.25
1.75
0
0
2.0
2.0
Ahead-of-ScheduleAhead-of-Schedule
Behind-ScheduleBehind-Schedule
Under-BudgetUnder-Budget
Over-budgetOver-budget Over-budgetOver-budget
Ahead-of-ScheduleAhead-of-Schedule
Behind-ScheduleBehind-Schedule
Under-BudgetUnder-Budget
1.5
Cost Performance Indicator
70
![Page 71: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/71.jpg)
Project Management Framework | A Structure for All Organisations
Approved
Monthly
CostsApproved
Project
Costs
Actual
Monthly
CostsActual
Project
Costs
71
S Curve Analysis
71
![Page 72: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/72.jpg)
Project Management Framework | A Structure for All Organisations
� Cost forecasts are conducted as part of progress and status
reporting to ensure expected future costs align will project
funding.
� Forecasting includes:
• Future known payments.
• Future commitments.
• Project funding reserves.
� Enables the Project Manager to ensure any shortfall can be
identified and reported early.
Forecasting
72
![Page 73: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/73.jpg)
Project Management Framework | A Structure for All Organisations
� Taking control action is done in order to address any non-
conformance that has been identified as part of the monitoring
process.
� Non-conformance is recognised as any variance of the budget that is
outside of agreed tolerance levels.
� Control actions are those actions planned, approved if necessary, and
implemented to bring the project and/ or project product back on
track as outline within the cost management plan, and any approved
amendments.
� Control actions that require an amendment of the cost management
plan must be requested via the integrated change control process.
Controlling
73
![Page 74: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/74.jpg)
Project Management Framework | A Structure for All Organisations
Instigation of Control
74
Establish
baseline
Measure
performance
Compare actual against baseline
Variation = Actual - Planned
Take ‘Corrective Action’
Either Realign performance to baseline
Or
Formally modify baseline using
change management system
![Page 75: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/75.jpg)
Project Management Framework | A Structure for All Organisations
Finalisation Phase Cost Processes
75
Estimate Cost of Product Milestone
Collate Initial Project Budget Estimate
Identify Resource Costs
Cost Activities, Tasks & Work-Packages
Monitor Project Budget
Allocate Administrations & Other Costs
Finalise Project Budget
Planning
Initiation
Execution
FinalisationReview Cost Functional Processes
Control Project Budget
Establish Project Budget
Implement Cost Management Plan
![Page 76: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/76.jpg)
Project Management Framework | A Structure for All Organisations
Not Approved
Approved
Project Close
(Start)
Client Acceptance Agreement
Post Project Report
Product Delivery Team Resource
Product Delivery Team Manager
Individual Product Delivery
Resource
Project Manager Finalise Budget
Contracted Product Delivery
Resource(s)
Decision Gate
Not Approved
Approved
Post Project Assurance
Report
Project Budget
Product Development Documents
Post Project Cost Functional
Review
Project Manager Conducts Post Project Review
Decision Gate
Archive Project Documents
Project Management Documents
Project Office(Project
Assurance)
Cost Finalisation Actions
76
(Start)
Client Acceptance Agreement
Post Project Report
Post Project Cost
Functional Review
Product Development
Documents
Decision Gate
Project Close
![Page 77: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/77.jpg)
Project Management Framework | A Structure for All Organisations
� As part of finalising the budget it is essential to check and
confirm:
• All work has been finalised in full.
• No additional expenditure is expected.
• No warranty claim and refunds are still outstanding.
• That all final invoices have been received, paid and receipted.
� Once the budget has been finalised the Project Manager can
determine:
• The profit margin of the project (if relevant).
• The project’s financial performance.
Finalise Project Budget
77
![Page 78: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/78.jpg)
Project Management Framework | A Structure for All Organisations
� Reviewing the processes involved in cost management must, as a
minimum, investigate the following:
• Was the budget sufficient to deliver the project product within the Client
Organisation’s cost limitations?
• Were there movements in the budget due to a variation in the cost of plant,
equipment, materials and/or supplies due to unknown price increases?
• Were there movements in the budget due to a variation caused by the knock-on effect
of contracted resources having their schedule impacted by other contracts?
• Where there movements in the budget due to a variation caused by risks becoming
issues and the management process involved in their resolution?
• Where all variation that created increases in costs that exceeded the original project
budget approved via the integrated change control process?
• Could any of the cost overruns be avoided through better planning of the original
project budget?
Review Cost Functional Processes
78
![Page 79: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/79.jpg)
Project Management Framework | A Structure for All Organisations
� Defined the term cost management
� Identified different cost estimating techniques.
� Considered the different types of estimating.
� Discussed how these different types of estimating
techniques are used across the project lifecycle.
� Discussed the requirements of cost management
strategies and there use across the project lifecycle.
� Defined the difference between contingency funding
and a financial management reserve.
In Summary
79
![Page 80: III PMF MANAGEMENT SOLUTIONS · “Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of](https://reader034.vdocument.in/reader034/viewer/2022042104/5e819ba81c077d08f74dece6/html5/thumbnails/80.jpg)
Project Management Framework | A Structure for All Organisations
Intellectual Property:The material contained within this lecture slide comply with the guidelines for
educational use and is copyright © 2015 by: PMF Management Solutions.
All rights reserved:Should any person, organisation or entity require the written permission to use this
material please contact PMF Management Solutions via:
pmfmanagementsolutions.com
or
Copyright
80