ilcta_mdb hts update

7
ILCTA_MDB HTS Update Andy Hocker 31-AUG-2006

Upload: joshua-cruz

Post on 30-Dec-2015

37 views

Category:

Documents


1 download

DESCRIPTION

ILCTA_MDB HTS Update. Andy Hocker 31-AUG-2006. Cryostat arrived at MDB 12-JUL. Since then…. Cryostat leak-checked by TD T&I mechanical techs Cryostat support frame moved into cave Needed fixes identified New rupture disc Heat leak Cryostat safety document written - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: ILCTA_MDB HTS Update

ILCTA_MDB HTS Update

Andy Hocker

31-AUG-2006

Page 2: ILCTA_MDB HTS Update

31-AUG-2006 A. Hocker, ILCTA Meeting 2

Cryostat arrived at MDB 12-JUL

Page 3: ILCTA_MDB HTS Update

31-AUG-2006 A. Hocker, ILCTA Meeting 3

Since then…

• Cryostat leak-checked by TD T&I mechanical techs

• Cryostat support frame moved into cave

• Needed fixes identified– New rupture disc– Heat leak

• Cryostat safety document written

• LL dewar design sent to MS for fabrication

4 K

4 K

2 K

Page 4: ILCTA_MDB HTS Update

31-AUG-2006 A. Hocker, ILCTA Meeting 4

To do

• Install/leak check new rupture disc• Install insulating shims around pipes• Install/leak check LL dewar and piping

– Dummy load for commissioning• Move cryostat into MDB cave• Problem: nobody available in TD to do this for ~3 weeks

– T&I mechanical group are swamped with magnet work– Not likely to provide any continued support– So, what to do?

• AD will be working on instrumentation infrastructure in meantime

Page 5: ILCTA_MDB HTS Update

31-AUG-2006 A. Hocker, ILCTA Meeting 5

Milestones

• 20-SEP: All parts in hand/tech help available• 29-SEP: Cryostat work finished• 6-OCT: Cryostat installed in MDB cave and

connected to feedbox• 13-OCT: Safety review• 20-OCT: Dummy load cooled to 1.8 K

Ready to accept a cavity

Page 6: ILCTA_MDB HTS Update

31-AUG-2006 A. Hocker, ILCTA Meeting 6

Misc.

• 3 dressed cavities from DESY to arrive in ~3 weeks?– We get one– Will need an engineering document, I’m told

• AD guys were procuring cavity/coupler clean vacuum carts --- need to follow up

• Good progress at CC2 reading out coupler data via EPICS, using it to control synthesizer– First step in automation (and datalogging)

Page 7: ILCTA_MDB HTS Update

31-AUG-2006 A. Hocker, ILCTA Meeting 7

HTS has an e-log

Get a password from Michele McCusker ([email protected])

E-log tutorial from Suzanne Gysin today at 15:30, here