1 STEEL AUTHORITY OF INDIA LIMITED BHILAI STEEL PLANT (BSP), BHILAI EXPANSION TO 7.0MT (CRUDE STEEL) TECHNICAL SPECIFICATION FOR ILLUMINATION, EARTHING, LIGHTENING PROTECTION SYSTEM & TELECOMMUNICATION FOR SMS III (BOF, CCP, HMDS & SRU INSIDE SHOP) (Pkg. NO.: 127) MECON LIMITED RANCHI – 834002 MEC/S/9101/11/E1/ 00/14-15/127, REV-3 Jan‘2014

Upload: apurv-goyal

Post on 02-May-2017

219 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Illumination

1

STEEL AUTHORITY OF INDIA LIMITED

BHILAI STEEL PLANT (BSP), BHILAI

EXPANSION TO 7.0MT (CRUDE STEEL)

TECHNICAL SPECIFICATION FOR

ILLUMINATION, EARTHING, LIGHTENING PROTECTION SYSTEM & TELECOMMUNICATION FOR SMS III (BOF,

CCP, HMDS & SRU INSIDE SHOP) (Pkg. NO.: 127)

MECON LIMITED

RANCHI – 834002

MEC/S/9101/11/E1/ 00/14-15/127, REV-3 Jan‘2014

Page 2: Illumination

SAIL -BSP

STEEL AUTHORITY OF INDIA LIMITED BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION, EARTHING AND LIGHTENING PROTECTION SYSTEM FOR

SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP) ( Pkg. NO.: 127)

MEC/S/9101/11/E1/00/14-15/127, REV-3 2

LIST OF CONTENTS

PART PARTICULARS PAGE NO.

A. PROJECT INFORMATION 03

B. SCOPE OF WORK 06

C. DESIGN BASIS FOR EQUIPMENT AND INSTALLATION

11

D. GENERAL INSTRUCTION TO TENDERER 13

E. DRAWING AND DOCUMENTS 17

F. MISCELLANEOUS 18

G. TENTATIVE ILLUMINATION REQUIREMENT 19

H PLANT TELEPHONE CABLES & ACCESSORIES 53

I LIST OF DRAWINGS ATTACHED 58

ISSUE DATE

PREPARED BY

CHECKED BY

APPROVED BY

29.01.14 GAURAV VERMA S.S.HAMEED V.KAPILA

DE Manager DGM I/C

Page 3: Illumination

SAIL -BSP

STEEL AUTHORITY OF INDIA LIMITED BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION, EARTHING AND LIGHTENING PROTECTION SYSTEM FOR

SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP) ( Pkg. NO.: 127)

MEC/S/9101/11/E1/00/14-15/127, REV-3 3

PART A : PROJECT INFORMATION :-

1.0 General introduction

The 4.0 Mt/yr new stream plant of Bhilai Steel Plant (BSP) comprising of new Steel melting shop (SMSIII) with state of the art electrics and communication system.

This section covers complete illumination& telecommunication system including interconnecting road lighting, earthing and lightning system to be supplied by tenderer for the Steel Melting Shop (SMS) complex comprising of following areas.

SL.NO.

DESCRIPTION

CAPACITY

1. BOF 3 X 160/180 T

2.

GCP 3 X 160/180 T

3. Gas Holder

1 X 160/180 T

4. HM Desulphurization Stations

2 X 160 T

5. On-line Argon Rinsing Stations (ARS) 3 X 160 T

6. RH-Degasser

1 X 160 T

7. LadleFurnace (LF)

2 X 160 T

8. CCP 2X6 BILLET CASTER 1X6 BILLET CUM BLOOM CASTER 1x3 STRAND BEAM BLANK CASTER

9. Welfare buildings (SMS III) 10. Adminstration and other buildings

2.0 Intent of Specification This specification covers the Design, engineering, supply, packing, forwarding,

transportation, loading & unloading, erection, testing and commissioning of the following on “Turn key” basis. a) Complete illumination system including interconnecting road lighting. b) Measurement of soil resistivity, main earthing ring including earth pit,

earthing of shed, columns and buildings inside and outside SMS shop. c) Lightning protection system d) Telecommunication system as detailed in clause H

Page 4: Illumination

SAIL -BSP

STEEL AUTHORITY OF INDIA LIMITED BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION, EARTHING AND LIGHTENING PROTECTION SYSTEM FOR

SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP) ( Pkg. NO.: 127)

MEC/S/9101/11/E1/00/14-15/127, REV-3 4

I) Illumination system

Illumination system serves for a sufficient illumination within the SMS shop (BOF,LF,RH,ARS& CCP) as per the enclosed shop lay out drawing& as explained elsewhere in this specification also. Basically it comprises:

i. Bay lighting, Area/peripheral lighting, street lights, lighting towers . ii. Building lighting inside and outside SMS shop (including staircases,

platforms, pump houses, control pulpits and rooms etc.)for BOF area (BOF shop, GCP, GRP, Secondary dedusting etc.) and CCP area as Explained elsewhere in this TS.

iii. Emergency lighting iv. Cable tunnels v. Lighting for interconnecting roads to SMS.

vi. Illumination at all levels for lifts, flare stacks, chimneys, conveyor galleries. However, Aviation lighting for Chimney & flare stack is not in the scope of bidder.

a)Bay lighting

For high bay illumination, luminaries with high pressure sodium vapor lamps shall be provided. The luminaries shall be installed in illumination walkways (servicing of luminaries from walkway).As general work place illumination, luminescent lamps of adequate capacity, type of protection and design shall be provided. High bay light fittings shall be integral type , 400W HPSV luminaire.

b)Building lighting

Building lighting shall include all the illumination for electric rooms, control pulpits, pump rooms, cable floors, walk able cable channels, platforms, cable Tunnels, offices, staff rooms, sanitary rooms, chiller etc. The tentative Room list& their dimensions(tentative) is as given below for guidance.

c)Emergency lighting

Emergency lighting system in general shall be provided for all work rooms/placeslike

-Computer Rooms

- MCC,control room& PLC Rooms

- HV & Transformer Rooms

- Hydraulic Rooms

- Hydraulic Valve Stands

- Lubrication Rooms

Ankit Chanpuria
Highlight
Ankit Chanpuria
Highlight
Page 5: Illumination

SAIL -BSP

STEEL AUTHORITY OF INDIA LIMITED BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION, EARTHING AND LIGHTENING PROTECTION SYSTEM FOR

SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP) ( Pkg. NO.: 127)

MEC/S/9101/11/E1/00/14-15/127, REV-3 5

- Water Control Rooms

- Staircases’

- Entry of cable tunnel / Basement / Escape route

In case of indoor illumination, separate lighting circuit shall be provided as Emergencylighting circuit. Separate ELDB for emergency lighting to be provided.Emergency power source details are specified in the battery limit given elsewhere in this TS. Number of ELDBs shall be as per load requirements. Lighting transformer of appropriate rating shall be considered before ELDB. Lighting transformer,PDB,MLDB,LDB and SLDB specification shall be as per GS-03. 20% of light fittings shall be provided which continues to glow in case of failure of NOrmal power.

Emergency lighting shall provide safety illumination for emergency exits

(for lighting intensity refer to room list).

Portable emergency lighting including built-in battery, battery charger & lamps shall be provided in strategic locations like

- Control Rooms - Stair case - Entry of cable basement/tunnel - Emergency exit - Maintenance lighting, if any

Lighting Intensity/LUX levels/Type of fittings etc. shall be as per GS-03.

d)Plug and Socket system (as per GS – 03)

This system is used for having the possibility to get electrical power at all necessary parts of the SMS shop. Rated voltage : 240 V AC Rated frequency : 50 Hz Current Rating : 5A/15A

e) Lighting distribution system (as per GS – 03)

Rated voltage:415V / 240 V AC Rated frequency:50 Hz

Lighting distribution panels shall be made as metal enclosed design.Lighting fittings which are fitted with discharge lamps shall be equipped with

compensation load.

f) Lux level :-

Page 6: Illumination

SAIL -BSP

STEEL AUTHORITY OF INDIA LIMITED BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION, EARTHING AND LIGHTENING PROTECTION SYSTEM FOR

SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP) ( Pkg. NO.: 127)

MEC/S/9101/11/E1/00/14-15/127, REV-3 6

Sl. NO.

Premises detail Lux level MF

a) CO2 Ext Room 200 0.75 b) Ventilation room 200 0.7 c) AC Room 200 0.7 d) Clean Agent Ext Room 200 0.75 e) Store Room 200 0.7 f) Steam Exhaust Room 200 0.6 g) Reserve Room 200 0.7 h) Rest Room 200 0.7 i) Shift Room 200 0.7 j) Elevator Drive Room 300 0.75 k) Elevator 200 0.7 l) Hydraulic room 150 0.6 m) For other premises /bay/rooms, Lux level and Maintenance factor shall be as per

GTS. -Lux level for platform 10.3m (working platform) and below shall be maintained 200. -Lux level for all platforms above10.3m shall be maintained 100. Type of lighting fixtures for media tunnel and scale fume tunnel shall be Industrial fitting, 24V, 2 x 50W Halogen of sigma make or equivalent.

The tentative details/dimensions of above are given inPart G of this TS.

This specification should be read together with General Technical Specification GTS (NO.GS-03) for Electrics, Instrumentation for detailed specification of equipment /components.Alongwith the commercial documents.GTS and TS are complementary and anything laid down in one andNOt in other will be deemed as binding, as though laid down in the Tender specification as a whole. In case of conflict between the Technical specification and GTS, the Technical specification (TS) shall prevail.

PART B:SCOPE OF WORK:- The scope of work shall include the following :-

1) Design, engineering, manufacture, shop testing, inspection, supply , packing, forwarding , transportation ,loading & unloading, storage at site, erection , testing and commissioning of the complete Illumination(including interconnecting road lighting ),earthing and lightning protection systemshall be done by the Tenderer as per requirements given in this TS/ GS-03 on turnkey basis.

Receipt of material, loading/unloading, safe storage ,watch& ward till handover of the system shall be in the bidder’s scope. , safe storage of plant &equipments will be the responsibility of contractor .Equipments should be under insurance till handing over of the system.

Ankit Chanpuria
Highlight
Page 7: Illumination

SAIL -BSP

STEEL AUTHORITY OF INDIA LIMITED BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION, EARTHING AND LIGHTENING PROTECTION SYSTEM FOR

SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP) ( Pkg. NO.: 127)

MEC/S/9101/11/E1/00/14-15/127, REV-3 7

2) Local MCCB before lighting transformer (including its interlock of winding temperature alarm & trip in upstream breaker) ,MLDBs, ELDB (emergency), LDBs, SLDBs, lighting fixtures complete with lamps, cables, street light poles, feeder pillars and all other items, erection accessories& mounting structures as required shall be provided by the tenderer.

3) Supply and erection of GI pipes, saddles, MS brackets, clamps, supports for

conduits of MS angles / MS flats for fixtures and control gears, ceiling roses, junction boxes, pull boxes, earth continuity conductors, cable lugs, number ferrules, cables, conduit bushes, check nuts, GI screws, nuts and bolts, etc. as required for complete installation of luminaries and their successful testing and commissioning is in the tenderer’s scope. The Tenderer shall also provide switches ,15/5A 3 pin receptacles, sundry materials and hardware to make the system complete in all respect for efficient and trouble-free operation

4) Flame proof light fittings, panels, JB’s etc. for ESP, Primary dedusting, Secondary

dedusting, GRP near Gas holder, Control pulpit near BOF converters, Other

electrical rooms (at +10.55m level) in main BOF electrical building and as per

techNOlogicalrequirementetc.Make of Flame proof light fitting shall be as per

“Preferred make list “ of BSP.

5) Two NOs.ofhighmast shall be considered, one at gas holder area and other at

secondary dedusting area.

6) 60 NOs. of 150W HPSV flood light along with supporting structure at appropriate

height at 27m at suitable location between column D-E bay, E-Fbay, H-I bay and I-

J bay for clear visibility of ladle trunion from crane operator’s cabin shall be

provided.

7) Latest energy efficient light fittingsand ballasts shall be considered for entire

illumination system.

8) Earthing electrodes and other materials required for complete earthing system. 9) Preparation of earth pits, earthing ring with interconnection to main plant earth

ringfortheentire illumination system and lightening protection system including secondary dedusting,Tundish de-slulling shop, ESP and Gas holder area.

10) Earthing compound shall be considered/ NOs. of earthing pits shall be increased for

good earthing(overall earthing value less than 01 ohm) . 11) Lightning arrestors, air termination network including down conductors,horizontal

and vertical termination network with separate earth pits (including preparation and their interconnection)and other items required for the complete lightning system.

12) 415V welding socket outlets including power supply arrangement with ELCB’s of suitable rating(one number of welding sockets at an interval of 30 metres in each bay)

13) All Statutory clearances/ obligations required. Three licenses for spot frequency from WPC,GOI(Government of India) shall be in the scope of bidder.

Ankit Chanpuria
Highlight
Ankit Chanpuria
Highlight
Ankit Chanpuria
Highlight
Ankit Chanpuria
Highlight
Page 8: Illumination

SAIL -BSP

STEEL AUTHORITY OF INDIA LIMITED BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION, EARTHING AND LIGHTENING PROTECTION SYSTEM FOR

SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP) ( Pkg. NO.: 127)

MEC/S/9101/11/E1/00/14-15/127, REV-3 8

14) 5/ 15 A socket shall also be provided at each column of the shop. Bidder to provide sockets near fan/FCU and control switch at respective load location room Switch Board.

15) 5/ 15 A socket shall also be provided at each column of the shop on crane walkway

for power supply to repeaters for crane radio LAN communication system. 16) Provide 5 NOs. ,63A welding socket additionally for G’H bay( ladle preparation ba

y) and other areas 100A welding sockets to be provided. 17) 24V Sockets shall be provided near the staircases of cable tunnel. 18) For machine tools, 2 nos.of socket per caster shall be provided. 19) Fuses will be NOt be accepted, MCB/MCCB/MPCB shall be used. 20) Power Distribution scheme, technical specification of electrical equipment shall be

as per GTS. 21) Bidder to note that in case of variation in quantity, NO unit rate payment will be

done, as this tender is a turnkey package. 22) Make of Luminaries shall be only as per Preferred make list of BSP.All wiring in

premises (for civil buildings) shall be concealed type . However ladder trays / conduits shall be used for bay lighting .

23) In premises illumination lighting shall be group controlled by MCB with modular type switch board with switch and socket.

24) Each room shall have minimum one 15 A modular type 240VAC socket. 25) In bay lighting shall be group controlled by MCB. 26) All MCB shall be class B type. 27) 2 NOs. of 100A MCCB spare feeders shall be provided in each MLDB for

purchaser use for BOF and CCP area. 28) Following feeder shall be kept as sparefor purchaser use in SLDB/LDB(at 240V)

for the area as specified below:- a. Single feeder of 1kW at Main Electrical Building. b. Single feeder of 0.2kW at Primary Dedusting Electrical Bldg. c. Single feeder of 1kW at Secondary Dedusting Electrical Bldg. d. Single feeder of 0.2kW at BOF -Crane Substation 01 Electrical Building. e. Single feeder of 1.2kW at BOF -Primary Dedusting Hydraulic Room. f. Single feeder of 0.2kW at Valve Control Remote I/O Room. g. Single feeder of 0.2kW at Scrap Yard Control Building. h. Single feeder of 0.3kW at Hot Metal Reladling Control Room. i. Single feeder of 0.3kW at Hot Metal Reladling Electrical Room. j. Single feeder of 0.3kW at Hot Metal Reladling Control Room-BSP Electrical Room for

Torpedo k. Single feeder of 0.1kW at Hot Metal Reladling Control Pulpit for HM Reladling Plant-1. l. Single feeder of 0.1kW at Hot Metal Reladling Control Pulpit for HM Reladling Plant-2 m. Single feeder of 0.1kW at Hot Metal Reladling Control Pulpit for HM Reladling Plant-3 n. Single feeder of 0.1kW at Hot Metal Reladling Control Pulpit for HM Reladling Plant-4 o. Single feeder of 0.1kW at Charging Control Pulpit BOF 01- Charging Control Pulpit p. Single feeder of 0.1kW at Charging Control Pulpit BOF 02- Charging Control Pulpit q. Single feeder of 0.1kW at Charging Control Pulpit BOF 03- Charging Control Pulpit r. Single feeder of 0.1kW at Tapping Control Pulpit BOF 01- Tapping Control Pulpit s. Single feeder of 0.1kW at Tapping Control Pulpit BOF 02- Tapping Control Pulpit t. Single feeder of 0.1kW at Tapping Control Pulpit BOF 03- Tapping Control Pulpit u. Single feeder of 1.1kW at Gas Holder Hydraulic Room - Hydraulic Room. v. Single feeder of 0.2kW at Skirt Hydraulic Room BOF 01- Hydraulic Room.

Ankit Chanpuria
Highlight
Ankit Chanpuria
Highlight
Ankit Chanpuria
Highlight
Ankit Chanpuria
Highlight
Ankit Chanpuria
Highlight
Ankit Chanpuria
Highlight
Ankit Chanpuria
Highlight
Ankit Chanpuria
Highlight
Ankit Chanpuria
Highlight
Ankit Chanpuria
Highlight
Ankit Chanpuria
Highlight
Ankit Chanpuria
Highlight
Ankit Chanpuria
Highlight
Page 9: Illumination

SAIL -BSP

STEEL AUTHORITY OF INDIA LIMITED BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION, EARTHING AND LIGHTENING PROTECTION SYSTEM FOR

SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP) ( Pkg. NO.: 127)

MEC/S/9101/11/E1/00/14-15/127, REV-3 9

w. Single feeder of 0.2kW at Skirt Hydraulic Room BOF 02- Hydraulic Room. x. Single feeder of 0.2kW at Skirt Hydraulic Room BOF 03- Hydraulic Room. y. Single feeder of 0.2kW at SVAICONE Hydraulic Room BOF 01- Hydraulic Room z. Single feeder of 0.2kW at SVAICONE Hydraulic Room BOF 02- Hydraulic Room aa. Single feeder of 0.2kW at SVAICONE Hydraulic Room BOF 03- Hydraulic Room bb. Single feeder of 0.2kW at GAS Recovery Station Electrical Building. cc. Single feeder of 1.0kW at Billet Caster 1 Main Building. dd. Single feeder of 1.0kW at Billet Caster 2 Main Building. ee. Single feeder of 0.75kW at Billet Bloom Caster Main Building. ff. Single feeder of 2.5kW at Billet Caster 1 gg. Single feeder of 2.5kW at Billet Caster 2 hh. Single feeder of 3.0kW at Bloom dispatch. ii. Single feeder of 0.10kW at Billet storage. jj. Single feeder of 0.70kW at Convertor Platform, Shift Room - 9 NOs. Row G & G' Column

11 to 14. kk. Single feeder of 0.15kW at Ladle Preparation Bay, Shift Room 2 NOs. Row G & G'

Column 8 to 10. ll. Single feeder of 0.2kW at Substation Billet Bloom Caster, Rest Room-2. mm. Single feeder of 0.5kW at CCP - Beam Blank Caster Main Building. nn. Single feeder of 4.0kW at Welfare Building.

29) 20 % spare feeders shall be provided in each Distribution board. 30) Suitable Trafo protection shall be ensured by bidder. 31) Control cable size shall be 2.5 Sqmm. 32) For bay lighting, wiring will be in open execution directly cleated on perforated GI

cable tray. 33) Cables will be fixed on racks or trays as required for proper support and

accessibility. Cable tags will be provided for each cable at a regular interval of 30M and at both ends.

34) Cable glands will be used with power and control cables at the entry to any metal clad enclosure.

35) For the incoming breaker size for all distribution board following philosophy shall be maintained. For 3 phase supply and below 630 A 4P MCCB shall be used and for 630 and above ACB shall be used.

36) Integrated testing and commissioning of all equipments supplied bythe tenderer. 37) Liquidation of PAC & FAC defects.

38) Preparation of drgs including cable schedule and external connection diagram forall the cables.

39) Excavation, back filling and leveling of cable trenches. Excavation should be done safely. If any underground communication line/pipes are damaged, repair if any , will be in Bidder’s scope.

40) Survey if required, will be under the scope of Bidder. 41) Bidder shall visit the site for understanding / clarifications about the requirements. 42) Provision of safety items like rubber mats, danger boards for each panel shall be

provided. 43) Supply of commissioning spares.

Ankit Chanpuria
Highlight
Ankit Chanpuria
Highlight
Ankit Chanpuria
Highlight
Ankit Chanpuria
Highlight
Ankit Chanpuria
Highlight
Ankit Chanpuria
Highlight
Ankit Chanpuria
Highlight
Page 10: Illumination

SAIL -BSP

STEEL AUTHORITY OF INDIA LIMITED BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION, EARTHING AND LIGHTENING PROTECTION SYSTEM FOR

SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP) ( Pkg. NO.: 127)

MEC/S/9101/11/E1/00/14-15/127, REV-3 10

44) Item wise Price for supply of 2 years maintenance spares (NOt part of this package).

45) As Built drawings and documents. 46) All tools, tackles, instruments, man power (skilled & unskilled) required for testing

and commissioning of their equipment shall be arranged bythetenderer.Any special tools, tackles and instruments that may be required for erection, testing, commissioning and maintenance shall be included in the scope of supply.

47) Any item or equipment NOt specifically mentioned but essential for proper installation, reliable operation, maintenance and safety of plant,Equipment and personnel will be included by the tenderer in his scope of work.

4.0)BATTERY LIMITS

The battery limits under the Tenderer’s scope shall be as given below.

A) ILLUMINATION INCLUDING INTERCONNECTING ROAD LIGHTING

a) BOF ,GCP,Gasholder area :

Bidder’s scope starts from outgoing terminal of the feeders provided by purchaser at LT substation (LTSS 13 (Crane substation 05, feeder NO. 5F1 & 9F1) location between row A & B and column 27 & 29). Further, supplying laying and termination (at both ends) of incoming cables from LTSS to bidder’s lighting transformer/PDB located in other premises and subsequent power supply arrangements, PDBs, MLDBs and other lighting distribution boards etc including all the supporting erection structures and accessories shall be under Bidder’s scope. Maximum demand of each incoming feeder to be furnished by the bidder’s along with offers.

b) Secondary refining units ( LF’s & RH ) area :

Bidder’s scope starts from outgoing terminal of the feeders provided by purchaser at MCC 1 of LF1 (100KW single feeder with feeder NO. +21-29-NA007, location is HI bay and between column 11 to 13) and MCC 2 of LF2 (100KW single feeder with feeder NO. +22-29-NA007, location is HI bay and between column 20 to 22). Further, supplying laying and termination (at both ends) of incoming cables from LTSS/PDB to bidder’s lighting transformer/PDB located in other premises and subsequent power supply arrangements, PDBs, MLDBs and other lighting distribution boards etc including all the supporting erection structures and accessories shall be under Bidder’s scope. Maximum demand of each incoming feeder to be furnished by the bidder’s along with offers.

c) CCP Area including Tundish deskulling shop and SMS3 welfare building.: Bidder’s scope starts from outgoing terminals of the feeders provided by

purchaser at LT substation.Further, supply, laying and termination (at both ends) of incoming cables from Purchaser LTSS(Row L, Column 1 and Row H Column 30) to bidder’s lighting transformer/PDB located in other premises and subsequent power supply arrangements to PDB’s, MLDBs and other

Ankit Chanpuria
Highlight
Ankit Chanpuria
Highlight
Ankit Chanpuria
Highlight
Page 11: Illumination

SAIL -BSP

STEEL AUTHORITY OF INDIA LIMITED BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION, EARTHING AND LIGHTENING PROTECTION SYSTEM FOR

SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP) ( Pkg. NO.: 127)

MEC/S/9101/11/E1/00/14-15/127, REV-3 11

lighting distribution boards etc. including all the supporting erection structures and accessories shall be under bidder’s scope. Maximum demand of each incoming feeder to be furnished by the bidder along with revised offer.

B) Emergency Lighting power supplyTwonumber (2 NOs.) feeders shall beProvided by the purchaser near SMS shop. However, bidder to supply, laying and termination (at both ends) of incoming cables from purchaser LT Board to bidder’s ELDB. Bidder to consider 500meters. Per run for estimation purpose. Bidder has to consider separate ELDB(Quantity ofELDBs shall be decided by the bidder as per the load) for the Emergency lighting. 20% of the total light fitting shall be fed from this ELDB)

EARTHING & LIGHTNING SYSTEM

Earthing system :

Plant main earth ring / grid including required number of earth pits, each column ( located in all bays) earthing and their interconnectivity with main earthing ring etc. of SMS Shop as per the enclosed shop lay out drawing shall be under tenderer scope. All shops and buildings as well as the electrical sub-stations and electrical rooms shall be provided by bidder with a ring main earthing system each. Individual ring main earthing systems shall again be interconnected as a network. Measurement of soil resistivity is under bidder’s scope. Individual equipment earthing is covered under separate technological package. Entire system shall be earthed in accordance with the provisions of the relevant IEC recommendations/ IS code of practice IS 3043-1987 and Indian Electricity Rules, so that the values of the step and contact potentials in case of faults are kept within safe permissible limits.

Since the soil is NOt good, use of earthing compound shall be considered/ nos. of earthing pits shall be increased for good earthing.

Lightening Protections System :

lightnening system for shop , all buildings and plant structures located outside the shop in accordance with stipulations of IS : 2309 – 1969 shall be under Bidder’s scope.

PART C: DESIGN BASIS FOR EQUIPMENT AND INSTALLATIONS:- 1. General Environmental design criteria: -

Sl. NO.

Environmental condition Data

1.0 Maximum ambient temp. 50 0C

2.0 Humidity 100 %

(not occurring simultaneously with

Ankit Chanpuria
Highlight
Ankit Chanpuria
Highlight
Page 12: Illumination

SAIL -BSP

STEEL AUTHORITY OF INDIA LIMITED BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION, EARTHING AND LIGHTENING PROTECTION SYSTEM FOR

SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP) ( Pkg. NO.: 127)

MEC/S/9101/11/E1/00/14-15/127, REV-3 12

Sl. NO.

Environmental condition Data

maximum temperature)

3.0 Height Less than 1000 m

4.0 Environment Dusty and NOn Corrosive

2. Ambient conditions of various units

Equipment selection and derating will generally be based on ambient temperature

of +500C (minimum) for all equipments. For specific areas and shops, the ambient

temperature conditions indicated below will be taken into consideration and

equipment will be suitably de-rated accordingly incase temperature is more than 50

deg C.

Sl. NO.

Area Data

A. Steel Melting Shop

1. Converter bay + 600C

2 Ladle Furnace Area/ Desulphurization Area /RH-

Degasser unit/ Argon Rinsing station + 550C

3. Other areas in the shop + 550C

B. Pump Houses + 500C

C. Electrical Rooms

1.

LT Sub-station switchgear room (Pressurised

ventilation) + 450C

2.

MCC rooms (housing intelligent MCCs, VFD panels,

RI/Osetc) + 350C

3.

Cable basements / tunnels (Ventilated)

+ 450C

D. Control Rooms

1. Control rooms – Air conditioned + 24 Deg. C

3. POWER SUPPLY CONDITIONS :-

3.1 The following standard voltage levels shall be adopted:

Page 13: Illumination

SAIL -BSP

STEEL AUTHORITY OF INDIA LIMITED BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION, EARTHING AND LIGHTENING PROTECTION SYSTEM FOR

SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP) ( Pkg. NO.: 127)

MEC/S/9101/11/E1/00/14-15/127, REV-3 13

Sl.NO

Description

Data

1.

LT AC 415V +10% & -15%, 3 Phase, 50 Hz +4% & -6%, 4 wire, solidly earthed.

2. Illumination system 240V AC, 50Hz.

3. Control voltage 240V AC +/- 10% obtained using suitable control transformer.

4.

Machine tools lighting 24VAC.

5.

Sockets for Welding purposes 415V, 100A, 3 pin plus earth with plug

interlocked switch

6.

Sockets for hand tools 240V, 15A, 2 pin plus earth with plug

interlocked switch

7. Special socket outlets for portable

lamps

24V, single phase, 50 Hz, AC obtained

through suitable transformers

3.2 The three phase symmetrical short-circuit ratings of the switchgear at the different

voltage levels shall be as follows :

Sl.NO. Description Data

1. 415 V switchgear 50 kA for 1 sec.

PART D:GENERAL INSTRUCTIONS TO TENDERER:-

1. General Specification for instruction to tenderer’s (GS-01) shall be followed by tenderer which shall be attached separately with this document.

2. The tenderer has to strictly agree to all the terms and conditionsmentioned in the tender documents and any deviation from them shall be categorically stated in writing & accepted by Purchaser in writing priortoplacementof order.

3. The tenderer shall submit a bar chart indicating starting and completion time of each activity such as preparation of drawings, manufacture, and inspection at works, packaging and forwarding.

4. The tenderer shall study the specification and satisfy himself regarding performance, etc of the equipment.

5. Purchaser shall NOt arrange any foreign exchange or import license for the tenderer for various components and spares. In case foreign exchange is required, the same shall be arranged by the tenderer

6. All panels in a room shall be of same height and colour so as to form a panel line up which will have good aesthetic appearance.

7. Number of light fittings will be decided on the basis of specified lux level, maintenance factor and appropriate co-efficient of utilization as per manufacturer's recommendation.

Page 14: Illumination

SAIL -BSP

STEEL AUTHORITY OF INDIA LIMITED BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION, EARTHING AND LIGHTENING PROTECTION SYSTEM FOR

SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP) ( Pkg. NO.: 127)

MEC/S/9101/11/E1/00/14-15/127, REV-3 14

8. HPSV lamp fittings will be provided with electronic ignitor and a built in sensor to sense failure of lamp and switch off ignitor.

9. TPN LDB's are to be used for illumination Lighting loads will be distributed in single phase/ three phase circuits. Each circuit is to be loaded upto a maximum 1200 watt (per phase)

10. All the LDBs will be located indoor and will have degree of protection IP 55. For outdoor light, outdoor type feeder pillars will be used having double door and caNOpy on the top. The LDBs for out door light will be provided with power contactors, timers, manual and automatic ON/OFF facility using twi-lights.

11. Single phase/three phase circuits are connected to RYB phase such that total connected load to each phase equal and phase balancing is achieved.

12. Incoming power cable from MLDBs to LDBs will be 1100V grade PVC insulated, PVC sheathed and armoured with Aluminum conductors of size 3.5x70/50/35/25 sq.mm. or as required.

13. For all point wiring and power circuit wiring (e.g.airconditioners,heaters, room heaters, exhaust fanetc) stranded copper wire shall be provided .The same shall be throughGI conduit (everywhere).

14. GI conduit shall be used for telecommunication cable for the open area,like shop etc.

15. PVC conduits will be used in civil buildings for telecommunication cable. 16. All wiring in the room /building shall be concealed wiring. 17. Finishing of wall/premises after concealed wiring like plastering ,painting etc shall

be in the scope of bidder 18. Armoured,Insulated PVC sheathedCopper cable shall be used for bay lighting.

Minimum 4 sq.mm stranded copper conductor for 3/5 pin 15A and 5/15A socket outlet and for lighting circuitforhighbaywill be considered. In highbay lighting circuit, from JB to fitting 2.5 sq.mm stranded copper conductor shall be used.

19. In building ,conduit wiring shall be used 3x2.5 sq.mm cu wire) for power circuit, however in point wiring for ceiling fans , tube lightsetc. 2 x1.5sq.mm stranded cu wire) shall be used from switchboard to fittings.

20. Single phase 3 pin 15A / 5A, 240V switch-socket outlets will be provided with interlocked switches, scrapping earth connection, male and female units in the switch gear room, control room and office room etc.

21. Each fitting or a group of three will be distributed through a dedicated junction box. Additional junction boxes will be provided at branching of connection. All the junction boxes will be supplied by contractor without any extra cost.

22. The junction boxes and flexible cables will be supplied as part of light fittings. 23. Group control and sectorial control will be envisaged through MCBs provided in

the respective LDBs/SLDBs. Separate control switches will be envisaged for light points

24. Provision of master switch for each room in welfare buildings shall be considered for energy saving.

25. GI pipes shall be of medium duty. 26. All PDBs, LDBs, MLDBs and SLDBs shall have 20 % spare feeders. 27. Incoming cable size for MLDBs, PDBs shall be 3.5C x 185 Sq mm. Aluminium

(nos. of runs shall be decided during engineering). 28. Connection of fittings on high bays and all other areas shall be in zig-zag

configuration . 29. In area lighting, if towers are considered anywhere, then they shall be High Mast

systems of appropriate height and not structural towers.

Ankit Chanpuria
Highlight
Ankit Chanpuria
Highlight
Ankit Chanpuria
Highlight
Ankit Chanpuria
Highlight
Ankit Chanpuria
Highlight
Ankit Chanpuria
Highlight
Ankit Chanpuria
Highlight
Ankit Chanpuria
Highlight
Ankit Chanpuria
Highlight
Ankit Chanpuria
Highlight
Ankit Chanpuria
Highlight
Ankit Chanpuria
Highlight
Page 15: Illumination

SAIL -BSP

STEEL AUTHORITY OF INDIA LIMITED BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION, EARTHING AND LIGHTENING PROTECTION SYSTEM FOR

SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP) ( Pkg. NO.: 127)

MEC/S/9101/11/E1/00/14-15/127, REV-3 15

30. Road lighting shall be with HPSV ,All HID lighting wherever considered shall be of HPSV type only

31. All luminaries shall be IS/ IEC compliant. 32. Two NOs high mast shall be considered, one at gas holder area and other at

secondary dedusting area. 33. Power circuit wiring and points shall also be provided for air conditioners, heaters,

room heaters, exhaust fan etc. 34. Points shall also be provided for ceiling fan . 35. Suitable heat protection of cable shall be provided at heat zone.

36. TIME/DELIVERY SCHEDULE:-

The delivery of all the equipment covered under this specification shall be for BSP site

stores at. Completion time shall be 15 months from the date of Contract signing for BOF and CCP area.

36 A) GUARANTEE

The tenderer shall stand guarantee for the trouble free operation and satisfactory

performance of all the equipment supplied by him as per TS. The guarantee shall also cover faulty design or materials or workmanship. The supplier free of cost shall do all rectification or replacement under the guarantee.

The supplier shall replace the wrong/defective equipment supplied by them, missing

items (observed during inspection at site after receipt of materials) or any damages caused to equipment during transportation free of cost after receipt of information from the Purchaser. In case of any dispute, decision of purchaser shall be final. The supplier shall depute his representative to site for replacement/rectification work without any extra cost to purchaser.

B)Pre Acceptance Test (PAC): PAC shall include the following 1)Placement/installation of all light fittings, lighting distribution panels and its associated items as per scope of work. 2) Charging of individual lighting panels and its lighting network.

C) Commissioning: Commissioning means charging of complete illumination system.

D) Performance Guarantee: PG Test includes meeting the specified Lux levels and establishing trouble free operation of the system.

37. INSPECTION AND TESTING The tenderer has to submit QAP for all items to be supplied by him. The inspection

procedure shall be finalized and approved by purchaser and / or their authorized representative. Inspection will be carried out as per the approved drawings / specifications and quality assurance plan approved by the purchaser. All inspection shall be carried out at the manufacturer's shop/works. NO equipment or part items shall be dispatched without final acceptance certificate and dispatch instructions issued by purchaser and/or their authorized representatives.

Ankit Chanpuria
Highlight
Ankit Chanpuria
Highlight
Ankit Chanpuria
Highlight
Page 16: Illumination

SAIL -BSP

STEEL AUTHORITY OF INDIA LIMITED BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION, EARTHING AND LIGHTENING PROTECTION SYSTEM FOR

SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP) ( Pkg. NO.: 127)

MEC/S/9101/11/E1/00/14-15/127, REV-3 16

All panels/equipment shall be fully tested in accordance with the relevant clauses of the applicable latest Indian Standards.

Type test certificates for similar equipment/panels shall be submitted to the Purchaser & MECON before routine test. Routine tests as per latest relevant Indian standards and other tests as agreed with the purchaser shall be carried out on all panels/equipment the presence of Purchaser/his authorized representatives. In all the cases, test certificates shall be submitted.

The vendor shall make all arrangements for conducting tests. The purchaser or their

authorized representative shall have the option to visit the place of manufacture for stage inspection and/or final inspection before dispatch of the equipment. The supplier has to make all arrangements for providing the necessary tools, tackles and instruments free of cost to carry out the inspection. The supplier shall extend all facilities for inspection purpose free of cost. Before giving final inspection call the supplier shall inspect the equipment at his works so that the equipment will fit properly at site and perform the desired function within acceptable limits.

The supplier shall give the final inspection call with a clear margin of minimum 15

days. The final inspection call shall be sent along with copies of internal/ shop test/ inspection reports and acceptance, material test certificates from Govt. approved test laboratory (physical and chemical, etc.). The supplier shall ensure that all equipment / parts must be available for inspection in the vendor’s shop prior to inspection. All loose parts are to be labeled with reference numbers corresponding to the bill of materials and the approved drawings.

Acceptance of equipment after inspection does not absolve or relieve the supplier from

any of his obligations and he shall be wholly and solely responsible for the satisfactory operation and guaranteed performance of his supply. The supplier shall be responsible for replacement of the equipment if any defect is noticed at site or during subsequent stage of installation, testing and commissioning which will impair its satisfactory performance. The supplier shall fully bear the cost arising out of replacement without any claim and without affecting the project schedule.

Any delay in the schedule of delivery due to re-inspection/rejection of items shall be

solely on the account of the supplier. If the equipment and / or parts thereof are found to be defective at site on site

inspection even after prior inspection at manufacturer's works and dispatch clearance duly issued, then also the manufacturer shall bear the sole responsibility of replacing all defective parts / equipment without any additional financial implication to the purchaser.

38. SHIPPING PROTECTION

All equipment shall be packed properly for prevention of damage during transit and deterioration during storage.

Page 17: Illumination

SAIL -BSP

STEEL AUTHORITY OF INDIA LIMITED BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION, EARTHING AND LIGHTENING PROTECTION SYSTEM FOR

SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP) ( Pkg. NO.: 127)

MEC/S/9101/11/E1/00/14-15/127, REV-3 17

39. MAKE OF EQUIPMENT

Makes of all Electrical equipment, instruments etc. accessories, shall be selected out of Purchaser's "List of Preferred makes ". Only one make shall be adopted for each type of equipment considering plant standardization.

In case make of some equipment/components are Not indicated in the purchaser's list, approval of makes for the same shall be obtained from Purchaser.

40. SPECIFICATIONS OF EQUIPEMENTS/ITEMS

The specifications of equipments/items shall be as per General Technical Specification GTS (NO.GS-03) for Electrics & Instrumentation.

PART E:DRAWINGS AND DOCUMENTS:-

1.1. GENERAL All design, engineering and manufacturing drawings shall be required to be approved by BSP / MECON. It shall be the responsibility of the tenderer to get the equipment/drawings approved/cleared by BSP / MECON without any price implication. Work shall be carried out exactly as indicated on the approved drawings and specification. NO alterations shall be made without prior written approval by purchaser / his consultant.

The tenderer shall check all the drawings prepared by them and/or received from their vendors/supplier/sub-supplier and satisfy themselves about the correctness of drawings before issuing to BSP /MECON. After checking them properly, stamped drawings shall be sent to BSP / MECON for approval / clearance.

Comments on all drawings will be forwarded to tenderer for incorporation and resubmission. The approval of drawings wherever applicable by purchaser or their authorized representative does NOt absolve or relieve the supplier from any of his obligations under this contract and he shall be wholly and solely responsible for the satisfactory operation and guaranteed performance of his supply.

Tenderer’s scope of work for all drawings and documents shall be as given below unless specifically indicated and agreed by Purchaser in writing.

1.2. TO BE FURNISHED ALONG WITH THE OFFER

Un priced copy of list of equipment. Technical details of illumination (indicating make and model) fittings and accessories,

lamps, earthing and lightning materials etc. Overall power distribution Single line diagram. Technical particulars / manuals / catalogues. Bar chart List of deviations, if any.

Page 18: Illumination

SAIL -BSP

STEEL AUTHORITY OF INDIA LIMITED BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION, EARTHING AND LIGHTENING PROTECTION SYSTEM FOR

SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP) ( Pkg. NO.: 127)

MEC/S/9101/11/E1/00/14-15/127, REV-3 18

List of 2 years maintenance spares. List of commissioning spares. List of special tools & tackles, if any. Make to be specified for the light fittings.(Make shall be as per the Approved make list)

1.3 DRAWINGS / DOCUMENTS TO BE FURNISHED FOR APPROVAL OF

PURCHASER / CONSULTANT: - (6 sets of the following drawings shall be submitted for approval) List of complete drawings (of all categories).

Drawing List(Indicating all the B.E, D.E and Reference category drawings) SLD, Wiring Scheme and GA of MLDB,ELDB, LDB, SLDB and PDB’s. Layout drawings for all the areas.(i.e Shop lighting layout and room lighting lay out

etc) Illumination, earthing &lightning protection layout drawings with complete

dimensions, weights, foundation details, Details of cable routing &openings etc. Calculation for Illumination, Lightning& earthing system Operation procedures. Power and control schemes. Bill of material of all panels complete illumination , earthing & lightning protection

system. External and internal views with door closed and open condition of all panels. - QAP

1.4 DRAWINGS /DOCUMENTS TO BE FURNISHED FOR REFERENCE:- (The following drawings/documents shall be submitted in 6 sets)

All drawings and documents approved by MECON Catalogues and manuals. Heat losses (Heat load data), ventilation requirements External connection diagram. Internal wiring and terminal plan drawings. Spare part list and drawings Instruction for storage / erection, testing and commissioning Operation and maintenance manual for all the components of the complete illumination,

earthing and lightning system. Final test certificates As built drawings

As built drawings should be submitted in 3 sets of soft copy also for all equipment shall be submitted immediately after commissioning of equipment / system.

PART F:MISCELLANEOUS:-

1.0) SPARES

The tenderer shall quoteitem wise price for 2 years maintenance spares in their offer. The list of 2 years maintenance spares is to be indicated in the schedule of quantity.

Page 19: Illumination

SAIL -BSP

STEEL AUTHORITY OF INDIA LIMITED BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION, EARTHING AND LIGHTENING PROTECTION SYSTEM FOR

SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP) ( Pkg. NO.: 127)

MEC/S/9101/11/E1/00/14-15/127, REV-3 19

Order for same may be placed by purchaser separately. The Purchaser reserves the right to buy anyrecommended spare. Any variation in quantity of spares based on contracted unit rates, if desired by Purchaser, shall be acceptable to the tenderer.

The tenderer shall also include supply of commissioning spares as required during erection, testing, start-up and commissioning without any extra cost to the purchaser.

2.0) ERECTION, TESTING & COMMISSIONING

All equipments within tenderer’s scope shall be erected, tested and commissioned by Tenderer.

3.0) PRESENTATION OF TENDER

The tenderer shall present his tender in the following three parts. A) Technical B) Commercial C) Price. Unpriced copy of the price schedule as furnished by the tenderer shall also be enclosed in the “Technical” part to ensure that all items of equipment and services are covered by the tenderer.

Part G:Tentative ILLUMINATION REQUIREMENT (BOF & SRU Area)

Sl. NO.

Building Room

Flo

or

Lev

el

Len

gth

Wid

th

Heig

ht

typ

e

Lu

x r

eq

uir

ed

lam

p t

yp

e

M.F

1

Primary Dedusting Electrical Building

Cable Cellar -3.55 15.90 10.40 3.30 WELL GLASS 70 1 70 0.6

2

Primary Dedusting Electrical Building

Cable Cellar -3.55 27.00 10.40 3.30 WELL GLASS 70 1 70 0.6

3

Primary Dedusting Electrical Building

Stair Case -3.55 5.85 3.00 3.30 T5 70 2 28 0.6

4

Primary Dedusting Electrical Building

Stair Case 0.00 10.40 3.00 5.00 T5 70 2 28 0.6

5

Primary Dedusting Electrical Building

VVVF-Converter Room

0.00 32.00 4.10 5.00 T5 200 2 28 0.7

6 Primary Dedusting Electrical Building

Ventilation Room 0.00 7.55 4.70 5.00 T5 200 2 28 0.7

7 Primary Dedusting Electrical Building

Transformer Room 0.00 8.80 6.00 5.00 WELL GLASS 200 1 70 0.7

8 Primary Dedusting Electrical Building

Transformer Room 0.00 8.80 6.00 5.00 WELL GLASS 200 1 70 0.7

9 Primary Dedusting Electrical Building

Transformer Room 0.00 8.80 6.00 5.00 WELL GLASS 200 1 70 0.7

10 Primary Dedusting Electrical Building

Electrical Room MCC/PLC

0.00 12.60 10.40 5.00 Mirror optic T5 200 2 28 0.7

Page 20: Illumination

SAIL -BSP

STEEL AUTHORITY OF INDIA LIMITED BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION, EARTHING AND LIGHTENING PROTECTION SYSTEM FOR

SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP) ( Pkg. NO.: 127)

MEC/S/9101/11/E1/00/14-15/127, REV-3 20

11

Primary Dedusting Electrical Building

AC Room 5.25 10.40 8.80 3.50 T5 200 2 28 0.7

12

Primary Dedusting Electrical Building

Stair Case 5.25 8.25 3.00 3.50 T5 70 2 28 0.6

13

Primary Dedusting Electrical Building

Lavatory 5.25 3.00 2.00 3.50 T5 200 2 28 0.7

14

Primary Dedusting Electrical Building

Fire Fighting Room 5.25 8.30 5.00 3.50 T5 200 2 28 0.7

15

Primary Dedusting Electrical Building

AC Room 5.25 8.30 5.10 3.50 T5 200 2 28 0.7

16

Primary Dedusting Electrical Building

Gas Analysis Room

5.25 4.55 4.20 3.50 T5 200 2 28 0.7

17

Gas Recovery Station Electrical Building

Rest Room 0.00 4.50 4.20 5.00 T5 200 2 28 0.7

18

Gas Recovery Station Electrical Building

Storage 0.00 2.88 1.00 5.00 T5 200 2 28 0.7

19

Gas Recovery Station Electrical Building

Lavatory 0.00 2.88 2.00 5.00 T5 200 2 28 0.7

20

Gas Recovery Station Electrical Building

Corridor 0.00 14.40 2.60 5.00 T5 150 2 28 0.7

21

Gas Recovery Station Electrical Building

AC Room 0.00 8.30 4.70 5.00 T5 200 2 28 0.7

22

Gas Recovery Station Electrical Building

Transformer Room 0.00 4.00 3.82 5.00 WELL GLASS 200 1 70 0.7

23

Gas Recovery Station Electrical Building

Transformer Room 0.00 4.00 3.82 5.00 WELL GLASS 200 1 70 0.7

24

Gas Recovery Station Electrical Building

Transformer Room 0.00 4.00 3.82 5.00 WELL GLASS 200 1 70 0.7

25

Gas Recovery Station Electrical Building

Transformer Room 0.00 4.00 3.82 5.00 WELL GLASS 200 1 70 0.7

26

Gas Recovery Station Electrical Building

Electrical Room 0.00 11.40 8.30 5.00 T5 200 2 28 0.7

27

Gas Recovery Station Electrical Building

Control Room 0.00 7.90 7.05 3.00 Mirror optic T5 300 2 28 0.75

28

Gas Recovery Station Electrical Building

Fire Fighting Room 0.00 7.90 2.55 5.00 T5 200 2 28 0.7

29

Gas Recovery Station Electrical Building

AC Room 5.25 10.10 5.95 4.50 T5 200 2 28 0.7

30

Primary Dedusting Analysing Room BOF-01

Gas Analysis Room

0.50 6.00 4.00 3.00 T5 200 2 28 0.7

31

Primary Dedusting Analysing Room BOF-02

Gas Analysis Room

0.50 6.00 4.00 3.00 T5 200 2 28 0.7

32

Primary Dedusting Analysiing Room BOF-03

Gas Analysis Room

0.50 6.00 4.00 3.00 T5 200 2 28 0.7

33

Primary Dedusting Hydraulic Room BOF-01

Hydraulic Room 0.00 6.40 4.00 3.50 WELL GLASS 150 1 70 0.6

Page 21: Illumination

SAIL -BSP

STEEL AUTHORITY OF INDIA LIMITED BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION, EARTHING AND LIGHTENING PROTECTION SYSTEM FOR

SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP) ( Pkg. NO.: 127)

MEC/S/9101/11/E1/00/14-15/127, REV-3 21

34 Primary Dedusting

Hydraulic Room BOF-02

Hydraulic Room 0.00 6.40 4.00 3.50 WELL

GLASS 150 1 70 0.6

35

Primary Dedusting Hydraulic Room BOF-03

Hydraulic Room 0.00 6.40 4.00 3.50 WELL GLASS 150 1 70 0.6

36

Gas Holder Hydraulic Room

Hydraulic Room 0.00 6.40 4.00 3.50 WELL GLASS 150 1 70 0.6

37

Secondary Dedusting Electrical Building

Cable Cellar 3.55 20.20 10.40 3.30 WELL GLASS 70 1 70 0.6

38

Secondary Dedusting Electrical Building

Cable Cellar 3.55 27.00 10.40 3.30 WELL GLASS 70 1 70 0.6

39

Secondary Dedusting Electrical Building

Stair Case 3.55 5.85 3.00 3.30 T5 70 2 28 0.6

40

Secondary Dedusting Electrical Building

Stair Case 0.00 10.40 3.00 15.60 T5 70 2 28 0.6

41

Secondary Dedusting Electrical Building

VVVF-Converter Room

0.00 27.00 4.10 5.00 T5 200 2 28 0.7

42

Secondary Dedusting Electrical Building

Electrical Room 0.00 16.90 5.10 5.00 T5 200 2 28 0.7

43

Secondary Dedusting Electrical Building

Transformer Room 0.00 8.30 5.00 5.00 WELL GLASS 200 1 70 0.7

44

Secondary Dedusting Electrical Building

Transformer Room 0.00 8.30 5.00 5.00 WELL GLASS 200 1 70 0.7

45

Secondary Dedusting Electrical Building

Transformer Room 0.00 8.80 6.00 5.00 WELL GLASS 200 1 70 0.7

46

Secondary Dedusting Electrical Building

Transformer Room 0.00 8.80 6.00 5.00 WELL GLASS 200 1 70 0.7

47

Secondary Dedusting Electrical Building

Transformer Room 0.00 8.80 6.00 5.00 WELL GLASS 200 1 70 0.7

48

Secondary Dedusting Electrical Building

Cable Room 5.25 27.00 10.40 3.25 WELL GLASS 70 1 70 0.6

49

Secondary Dedusting Electrical Building

Cable Room 5.25 16.90 10.40 3.25 WELL GLASS 70 1 70 0.6

50

Secondary Dedusting Electrical Building

Lavatory 5.25 3.00 2.00 2.70 T5 200 2 28 0.7

51

Secondary Dedusting Electrical Building

Electrical Room ESP/MCC

8.75 27.00 10.40 3.25 Mirror optic T5 200 2 28 0.7

52

Secondary Dedusting Electrical Building

Electrical Room LT/MCC/PLC

8.75 16.90 10.40 3.25 Mirror optic T5 200 2 28 0.7

53

Secondary Dedusting Electrical Building

Control Room 8.75 7.45 5.00 2.85 Mirror optic T5 300 2 28 0.75

54

Secondary Dedusting Electrical Building

Corridor 12.25 5.45 1.80 3.35 T5 150 2 28 0.7

55

Secondary Dedusting Electrical Building

Fire Fighting Room 12.25 6.50 3.15 3.35 T5 200 2 28 0.7

Page 22: Illumination

SAIL -BSP

STEEL AUTHORITY OF INDIA LIMITED BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION, EARTHING AND LIGHTENING PROTECTION SYSTEM FOR

SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP) ( Pkg. NO.: 127)

MEC/S/9101/11/E1/00/14-15/127, REV-3 22

56

Secondary Dedusting Electrical Building

Ventilation Room 12.25 10.40 10.25 3.35 T5 200 2 28 0.7

57

Secondary Dedusting Electrical Building

AC Room 12.25 10.53 5.15 3.35 T5 200 2 28 0.7

58

Secondary Dedusting Electrical Building

Lavatory 12.25 3.00 1.40 3.35 T5 200 2 28 0.7

59

Secondary Dedusting Electrical Building

Lavatory 12.25 3.45 3.00 3.35 T5 200 2 28 0.7

60

Secondary Dedusting Electrical Building

Corridor 12.25 6.70 4.25 3.35 T5 150 2 28 0.7

61

Secondary Dedusting Electrical Building

Rest Room 12.25 4.25 3.55 3.35 T5 200 2 28 0.7

62

Secondary Dedusting Electrical Building

Meeting Room, Office

12.25 13.70 10.40 3.35 Mirror optic T5 300 4 14 0.75

63

Secondary Dedusting Electrical Building

AC Room 12.25 10.40 8.80 3.35 T5 200 2 28 0.7

64

BOF - Main Control and Electrical Building

Stair Case -3.65 4.70 2.60 23.15 T5 70 2 28 0.6

65

BOF - Main Control and Electrical Building

Cable Cellar -3.65 19.40 8.90 3.50 WELL GLASS 70 1 70 0.6

66

BOF - Main Control and Electrical Building

Tunnel -3.65 12.00 1.80 3.50 WELL GLASS 70 1 70 0.6

67

BOF - Main Control and Electrical Building

Stair Case -3.65 4.70 2.60 27.50 T5 70 2 28 0.6

68

BOF - Main Control and Electrical Building

Cable Cellar -3.65 19.40 17.40 3.50 WELL GLASS 70 1 70 0.6

69

BOF - Main Control and Electrical Building

Tunnel -3.65 12.00 1.80 3.50 WELL GLASS 70 1 70 0.6

70

BOF - Main Control and Electrical Building

Cable Cellar -3.65 19.40 17.90 3.50 WELL GLASS 70 1 70 0.6

71

BOF - Main Control and Electrical Building

Stair Case -3.65 4.70 2.60 23.15 T5 70 2 28 0.6

72

BOF - Main Control and Electrical Building

Corridor 0.15 4.70 1.35 5.00 T5 150 2 28 0.7

73

BOF - Main Control and Electrical Building

Cable and Ventilation Shaft

0.15 4.70 3.20 5.00 WELL GLASS 70 1 70 0.6

74

BOF - Main Control and Electrical Building

Electrical Room 0.15 17.90 9.10 5.00 T5 200 2 28 0.7

75

BOF - Main Control and Electrical Building

Transformer Room 0.15 8.80 5.30 5.00 WELL GLASS 200 1 70 0.7

76

BOF - Main Control and Electrical Building

Transformer Room 0.15 8.80 5.30 5.00 WELL GLASS 200 1 70 0.7

77

BOF - Main Control and Electrical Building

Transformer Room 0.15 8.80 5.30 5.00 WELL GLASS 200 1 70 0.7

Page 23: Illumination

SAIL -BSP

STEEL AUTHORITY OF INDIA LIMITED BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION, EARTHING AND LIGHTENING PROTECTION SYSTEM FOR

SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP) ( Pkg. NO.: 127)

MEC/S/9101/11/E1/00/14-15/127, REV-3 23

78

BOF - Main Control and Electrical Building

Ventilation Room 0.15 9.00 4.20 5.00 T5 200 2 28 0.7

79

BOF - Main Control and Electrical Building

Corridor 0.15 4.70 1.35 5.00 T5 150 2 28 0.7

80

BOF - Main Control and Electrical Building

Cable and Ventilation Shaft

0.15 4.70 2.92 5.00 WELL GLASS 70 1 70 0.6

81

BOF - Main Control and Electrical Building

Electrical Room 0.15 9.10 8.55 5.00 T5 200 2 28 0.7

82

BOF - Main Control and Electrical Building

Transformer Room 0.15 6.25 5.30 5.00 WELL GLASS 200 1 70 0.7

83

BOF - Main Control and Electrical Building

Transformer Room 0.15 6.30 5.30 5.00 WELL GLASS 200 1 70 0.7

84

BOF - Main Control and Electrical Building

Transformer Room 0.15 6.25 5.30 5.00 WELL GLASS 200 1 70 0.7

85

BOF - Main Control and Electrical Building

Corridor 0.15 20.00 3.25 5.00 T5 150 2 28 0.7

86

BOF - Main Control and Electrical Building

Transformer Room 0.15 8.55 5.30 5.00 WELL GLASS 200 1 70 0.7

87

BOF - Main Control and Electrical Building

Ventilation Room 0.15 9.00 4.20 5.00 T5 200 2 28 0.7

88

BOF - Main Control and Electrical Building

Corridor 0.15 4.70 1.35 5.00 T5 150 2 28 0.7

89

BOF - Main Control and Electrical Building

Cable and Ventilation Shaft

0.15 4.70 3.25 5.00 WELL GLASS 70 1 70 0.6

90

BOF - Main Control and Electrical Building

Electrical Room 0.15 9.10 8.90 5.00 T5 200 2 28 0.7

91

BOF - Main Control and Electrical Building

Transformer Room 0.15 8.90 5.30 5.00 WELL GLASS 200 1 70 0.7

92

BOF - Main Control and Electrical Building

Ventilation Room 0.15 7.40 5.00 5.00 T5 200 2 28 0.7

93

BOF - Main Control and Electrical Building

Compressor Room 0.15 7.40 5.30 5.00 WELL GLASS 200 1 70 0.6

94

BOF - Main Control and Electrical Building

E-Auxil. Room 5.40 7.40 4.55 5.00 T5 200 2 28 0.7

95

BOF - Main Control and Electrical Building

AC Room 5.40 8.95 7.40 5.00 T5 200 2 28 0.7

96

BOF - Main Control and Electrical Building

Cable Room 5.40 17.90 14.40 5.00 WELL GLASS 70 1 70 0.6

97

BOF - Main Control and Electrical Building

E-Auxil. Room 5.40 5.00 4.30 5.00 T5 200 2 28 0.7

98

BOF - Main Control and Electrical Building

Corridor 5.40 12.97 2.40 5.00 T5 150 2 28 0.7

99

BOF - Main Control and Electrical Building

AC Room 5.40 8.70 4.85 5.00 T5 200 2 28 0.7

Page 24: Illumination

SAIL -BSP

STEEL AUTHORITY OF INDIA LIMITED BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION, EARTHING AND LIGHTENING PROTECTION SYSTEM FOR

SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP) ( Pkg. NO.: 127)

MEC/S/9101/11/E1/00/14-15/127, REV-3 24

100

BOF - Main Control and Electrical Building

Battery Room 5.40 11.85 5.00 5.00 T5 200 2 28 0.7

101

BOF - Main Control and Electrical Building

Cable Room 5.40 14.40 12.25 5.00 WELL GLASS 70 1 70 0.6

102

BOF - Main Control and Electrical Building

E-Auxil. Room 5.40 4.85 4.65 5.00 T5 200 2 28 0.7

103

BOF - Main Control and Electrical Building

Cable Room 5.40 14.40 8.90 5.00 WELL GLASS 70 1 70 0.6

104

BOF - Main Control and Electrical Building

Laboratory 5.40 10.75 9.20 4.40 T5 200 2 28 0.7

105

BOF - Main Control and Electrical Building

Fire Fighting Room 5.40 9.15 4.50 4.40 T5 200 2 28 0.7

106

BOF - Main Control and Electrical Building

Fire Fighting Room 5.40 9.15 4.50 4.40 T5 200 2 28 0.7

107

BOF - Main Control and Electrical Building

Cable Floor 7.75 12.60 4.55 2.65 WELL GLASS 70 1 70 0.6

108

BOF - Main Control and Electrical Building

Cable Floor 7.75 12.60 4.25 2.65 WELL GLASS 70 1 70 0.6

109

BOF - Main Control and Electrical Building

Cable Floor 7.75 12.60 5.00 2.65 WELL GLASS 70 1 70 0.6

110

BOF - Main Control and Electrical Building

Cable Floor 7.75 12.60 4.55 2.65 WELL GLASS 70 1 70 0.6

111

BOF - Main Control and Electrical Building

Cable Floor 7.75 12.60 4.25 2.65 WELL GLASS 70 1 70 0.6

112

BOF - Main Control and Electrical Building

Cable Floor 7.75 12.60 5.00 2.65 WELL GLASS 70 1 70 0.6

113

BOF - Main Control and Electrical Building

Corridor 10.65 55.75 2.40 4.85 T5 150 2 28 0.7

114

BOF - Main Control and Electrical Building

Control Room 1 10.65 22.60 9.55 3.50 Mirror optic T5 300 2 28 0.75

115

BOF - Main Control and Electrical Building

Control Room 2 10.65 9.37 4.85 3.00 Mirror optic T5 300 2 28 0.75

116

BOF - Main Control and Electrical Building

Dispatcher Office 10.65 5.25 4.85 4.85 Mirror optic T5 300 2 28 0.75

117

BOF - Main Control and Electrical Building

Level 1 + 2 Server&Progr. Room

10.65 11.87 4.85 4.85 Mirror optic T5 200 2 28 0.7

118

BOF - Main Control and Electrical Building

Control Room 3 10.65 9.60 4.85 3.00 Mirror optic T5 300 2 28 0.75

119

BOF - Main Control and Electrical Building

Tea Kitchen 10.65 2.42 2.10 4.85 Flurocent lamp 150 2 36 0.7

120

BOF - Main Control and Electrical Building

Lavatory 10.65 2.42 2.20 4.85 T5 200 2 28 0.7

121

BOF - Main Control and Electrical Building

Lavatory 10.65 3.10 2.30 4.85 T5 200 2 28 0.7

Page 25: Illumination

SAIL -BSP

STEEL AUTHORITY OF INDIA LIMITED BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION, EARTHING AND LIGHTENING PROTECTION SYSTEM FOR

SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP) ( Pkg. NO.: 127)

MEC/S/9101/11/E1/00/14-15/127, REV-3 25

122

BOF - Main Control and Electrical Building

Office and Meeting Room

10.65 9.55 8.80 4.85 Mirror optic T5 300 4 14 0.75

123

BOF - Main Control and Electrical Building

MCC / PLC - Room 10.65 35.55 11.85 4.85 Mirror optic T5 200 2 28 0.7

124

BOF - Main Control and Electrical Building

UPS Room 10.65 11.85 9.35 4.85 T5 200 2 28 0.7

125

BOF - Main Control and Electrical Building

VVVF + PLC - Room

10.65 24.20 11.85 4.85 Mirror optic T5 200 2 28 0.7

126

BOF - Main Control and Electrical Building

Corridor 15.70 64.85 2.00 3.80 T5 150 2 28 0.7

127

BOF - Main Control and Electrical Building

Meeting Room 15.70 9.55 4.40 3.80 Mirror optic T5 300 4 14 0.75

128

BOF - Main Control and Electrical Building

Office 15.70 7.40 4.40 3.80 Mirror optic T5 300 4 14 0.75

129

BOF - Main Control and Electrical Building

Office 15.70 7.40 5.90 3.80 Mirror optic T5 300 4 14 0.75

130

BOF - Main Control and Electrical Building

Archiv 15.70 2.90 2.40 3.80 Mirror optic T5 200 2 28 0.7

131

BOF - Main Control and Electrical Building

Office 15.70 7.40 3.75 3.80 Mirror optic T5 300 4 14 0.75

132

BOF - Main Control and Electrical Building

Office 15.70 7.40 5.10 3.80 Mirror optic T5 300 4 14 0.75

133

BOF - Main Control and Electrical Building

Office 15.70 7.40 5.15 3.80 Mirror optic T5 300 4 14 0.75

134

BOF - Main Control and Electrical Building

Office 15.70 7.40 4.90 3.80 Mirror optic T5 300 4 14 0.75

135

BOF - Main Control and Electrical Building

Office 15.70 7.40 4.30 3.80 Mirror optic T5 300 4 14 0.75

136

BOF - Main Control and Electrical Building

Archiv 15.70 2.90 2.40 3.80 Mirror optic T5 200 2 28 0.7

137

BOF - Main Control and Electrical Building

Office 15.70 7.40 3.20 3.80 Mirror optic T5 300 4 14 0.75

138

BOF - Main Control and Electrical Building

Office 15.70 7.40 6.00 3.80 Mirror optic T5 300 4 14 0.75

139

BOF - Main Control and Electrical Building

Tea Kitchen 15.70 4.97 2.10 3.80 Flurocent lamp 150 2 36 0.7

140

BOF - Main Control and Electrical Building

Store 15.70 2.40 2.20 3.80 T5 200 2 28 0.7

141

BOF - Main Control and Electrical Building

Lavatory 15.70 2.42 2.20 3.80 T5 200 2 28 0.7

142

BOF - Main Control and Electrical Building

Lavatory 15.70 3.10 2.30 3.80 T5 200 2 28 0.7

143

BOF - Main Control and Electrical Building

Archiv 15.70 2.75 2.40 3.80 Mirror optic T5 200 2 28 0.7

Page 26: Illumination

SAIL -BSP

STEEL AUTHORITY OF INDIA LIMITED BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION, EARTHING AND LIGHTENING PROTECTION SYSTEM FOR

SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP) ( Pkg. NO.: 127)

MEC/S/9101/11/E1/00/14-15/127, REV-3 26

144

BOF - Main Control and Electrical Building

AC Room 19.85 12.00 7.40 4.00 T5 200 2 28 0.7

145

BOF - Main Control and Electrical Building

AC Room 19.85 17.40 7.40 4.00 T5 200 2 28 0.7

146

BOF - Main Control and Electrical Building

AC Room 19.85 5.85 7.40 4.00 T5 200 2 28 0.7

147

Pump House Electrical Building

Cable Cellar -3.50 19.80 10.10 3.30 WELL GLASS 70 1 70 0.6

148

Pump House Electrical Building

Cable Cellar -3.50 15.30 10.10 3.30 WELL GLASS 70 1 70 0.6

149

Pump House Electrical Building

Stair Case 3.55 6.60 2.60 3.30 T5 70 2 28 0.6

150

Pump House Electrical Building

Stair Case 0.00 10.10 2.60 5.00 T5 70 2 28 0.6

151

Pump House Electrical Building

Electrical + PLC Room

0.00 15.30 10.10 5.00 Mirror optic T5 200 2 28 0.7

152

Pump House Electrical Building

Transformer Room 0.00 8.30 5.00 5.00 WELL GLASS 200 1 70 0.7

153

Pump House Electrical Building

Transformer Room 0.00 8.30 5.00 5.00 WELL GLASS 200 1 70 0.7

154

Pump House Electrical Building

Electrical Room 0.00 16.90 5.10 5.00 T5 200 2 28 0.7

155

Pump House Electrical Building

Stair Case 5.25 10.10 2.60 4.50 T5 70 2 28 0.6

156

Pump House Electrical Building

Fire Fighting Room 5.25 8.30 5.00 4.50 T5 200 2 28 0.7

157

Pump House Electrical Building

AC Room 5.25 8.45 4.80 4.50 T5 200 2 28 0.7

158

Pump House Electrical Building

Corridor 6.25 9.20 2.15 3.50 T5 150 2 28 0.7

159

Pump House Electrical Building

Electrical Room 6.25 7.80 5.25 3.50 T5 200 2 28 0.7

160

Pump House Electrical Building

Control Room 6.25 7.80 3.80 3.50 Mirror optic T5 300 2 28 0.75

161

Pump House Electrical Building

Ventilation Room 4.90 10.10 8.30 4.50 T5 200 2 28 0.7

162

Crane Substation 01 Electrical Building

Cable Cellar -3.55 17.60 14.40 3.30 WELL GLASS 70 1 70 0.6

163

Crane Substation 01 Electrical Building

Stair Case -3.55 5.80 3.60 3.30 T5 70 2 28 0.6

164

Crane Substation 01 Electrical Building

Stair Case 0.00 5.80 3.60 4.40 T5 70 2 28 0.6

165

Crane Substation 01 Electrical Building

Transformer Room 0.20 8.70 4.70 5.00 WELL GLASS 200 1 70 0.7

166

Crane Substation 01 Electrical Building

Transformer Room 0.20 8.30 4.70 5.00 WELL GLASS 200 1 70 0.7

167

Crane Substation 01 Electrical

Electrical Room 0.00 12.80 9.70 4.40 T5 200 2 28 0.7

Page 27: Illumination

SAIL -BSP

STEEL AUTHORITY OF INDIA LIMITED BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION, EARTHING AND LIGHTENING PROTECTION SYSTEM FOR

SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP) ( Pkg. NO.: 127)

MEC/S/9101/11/E1/00/14-15/127, REV-3 27

Building

168

Crane Substation 01 Electrical Building

Ventilation Room 0.00 5.80 4.70 4.40 T5 200 2 28 0.7

169

Crane Substation 01 Electrical Building

Stair Case 4.65 5.80 3.60 3.00 T5 70 2 28 0.6

170

Crane Substation 01 Electrical Building

Office 4.65 12.60 9.70 3.00 Mirror optic T5 300 4 14 0.75

171

Crane Substation 01 Electrical Building

Rest Room 4.65 4.70 3.65 3.00 T5 200 2 28 0.7

172

Crane Substation 01 Electrical Building

Storage 4.65 2.00 1.75 3.00 T5 200 2 28 0.7

173

Crane Substation 01 Electrical Building

Lavatory 4.65 2.80 2.00 3.00 T5 200 2 28 0.7

174

Crane Substation 02 Electrical Building

Stair Case 3.55 7.90 1.20 3.30 T5 70 2 28 0.6

175

Crane Substation 02 Electrical Building

Cable Cellar 3.55 25.10 12.40 3.30 WELL GLASS 70 1 70 0.6

176

Crane Substation 02 Electrical Building

Electrical Room 0.00 20.80 7.40 5.00 T5 200 2 28 0.7

177

Crane Substation 02 Electrical Building

Corridor 0.00 6.05 2.60 5.00 T5 150 2 28 0.7

178

Crane Substation 02 Electrical Building

Ventilation Room 0.00 12.40 4.00 5.00 T5 200 2 28 0.7

179

Crane Substation 02 Electrical Building

Transformer Room 1

0.20 8.80 4.70 4.80 WELL GLASS 200 1 70 0.7

180

Crane Substation 02 Electrical Building

Transformer Room 2

0.20 8.80 4.70 4.80 WELL GLASS 200 1 70 0.7

181

Crane Substation 03 Electrical Building

Stair Case -3.50 5.95 3.50 8.50 T5 70 2 28 0.6

182

Crane Substation 03 Electrical Building

Cable Cellar -3.50 14.40 8.70 3.25 WELL GLASS 70 1 70 0.6

183

Crane Substation 03 Electrical Building

Stair Case 0.00 6.25 3.50 5.00 T5 70 2 28 0.6

184

Crane Substation 03 Electrical Building

Ventilation Room 0.00 7.85 3.50 5.00 T5 200 2 28 0.7

185

Crane Substation 03 Electrical Building

Electrical Room 0.00 9.40 8.70 5.00 T5 200 2 28 0.7

186

Crane Substation 03 Electrical Building

Transformer Room 0.20 8.70 4.70 4.80 WELL GLASS 200 1 70 0.7

187

Scrap Yard Control Building

Control Room 7.00 5.00 3.30 2.70 Mirror optic T5 300 2 28 0.75

188 Cabel Tunnels Cable Tunnels

2500.00

3.50 3.50 WELL GLASS 70 1 70 0.6

Page 28: Illumination

SAIL -BSP

STEEL AUTHORITY OF INDIA LIMITED BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION, EARTHING AND LIGHTENING PROTECTION SYSTEM FOR

SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP) ( Pkg. NO.: 127)

MEC/S/9101/11/E1/00/14-15/127, REV-3 28

189

Flux and Alloy System Electric Building - BOF 1

Control Room 53.00 3.60 3.00 2.60 Mirror optic T5 300 2 28 0.75

190

Flux and Alloy System Electric Building - BOF 1

AC Room 53.00 8.25 3.00 3.00 T5 200 2 28 0.7

191

Flux and Alloy System Electric Building - BOF 1

Electric Room 56.50 11.40 3.00 3.00 T5 200 2 28 0.7

192

Flux and Alloy System Electric Building - BOF 2

Electric Room 45.30 11.15 3.40 3.00 T5 200 2 28 0.7

193

Flux and Alloy System Electric Building - BOF 2

AC Room 48.55 8.25 3.40 3.00 T5 200 2 28 0.7

194

Flux and Alloy System Electric Building - BOF 3

Electric Room 45.30 11.15 3.40 3.00 T5 200 2 28 0.7

195

Flux and Alloy System Electric Building - BOF 3

AC Room 48.55 8.25 3.40 3.00 T5 200 2 28 0.7

196

ACVS and Lighting Substation

Stair Case -3.65 5.15 2.60 11.60 T5 70 2 28 0.6

197

ACVS and Lighting Substation

Cable Cellar -3.65 11.50 10.90 3.55 WELL GLASS 70 1 70 0.6

198

ACVS and Lighting Substation

Electric Room 0.15 11.50 10.90 4.05 T5 200 2 28 0.7

199

ACVS and Lighting Substation

Corridor 4.45 2.35 2.00 3.00 T5 150 2 28 0.7

200

ACVS and Lighting Substation

Reserve Room 4.45 5.75 5.45 3.00 T5 200 2 28 0.7

201

ACVS and Lighting Substation

AC and Ventilation Room

4.45 11.50 10.90 3.00 T5 200 2 28 0.7

202

ACVS and Lighting Substation

Lavatory 4.45 2.80 2.00 3.00 T5 200 2 28 0.7

203

Valve Control Remote I/O Room

Valve Control Remote I/O Room

48.80 8.50 4.00 3.00 Mirror optic T5 200 2 28 0.7

204

Valve Control Remote I/O Room

AC Room 48.80 4.00 2.50 3.00 T5 200 2 28 0.7

205

Hot Metal Reladling Control Room

Control Room 6.20 8.00 4.00 3.00 Mirror optic T5 300 2 28 0.75

206

Hot Metal Reladling Electrical Room

Electric Room 6.20 8.00 4.00 3.00 T5 200 2 28 0.7

207

Hot Metal Reladling Electrical Room

AC Room 0.00 4.00 4.00 3.00 T5 200 2 28 0.7

208 Pump House Pump House 0.00 60.00 26.00 13.40 WELL

GLASS 200 1 70 0.6

209

Charging Control Pulüpit BOF-01

Charging Control Pulpit

10.30 2.00 2.00 2.50 Mirror optic T5 200 4 14 0.7

210

Charging Control Pulüpit BOF-02

Charging Control Pulpit

10.30 2.00 2.00 2.50 Mirror optic T5 200 4 14 0.7

211

Charging Control Pulüpit BOF-03

Charging Control Pulpit

10.30 2.00 2.00 2.50 Mirror optic T5 200 4 14 0.7

212

Tapping Control Pulpit BOF-01

Taping Control Pulpit

10.30 2.00 2.00 2.50 Mirror optic T5 200 4 14 0.7

Page 29: Illumination

SAIL -BSP

STEEL AUTHORITY OF INDIA LIMITED BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION, EARTHING AND LIGHTENING PROTECTION SYSTEM FOR

SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP) ( Pkg. NO.: 127)

MEC/S/9101/11/E1/00/14-15/127, REV-3 29

213

Tapping Control Pulpit BOF-02

Taping Control Pulpit

10.30 2.00 2.00 2.50 Mirror optic T5 200 4 14 0.7

214

Tapping Control Pulpit BOF-03

Taping Control Pulpit

10.30 2.00 2.00 2.50 Mirror optic T5 200 4 14 0.7

215

Skirt Hydraulic Room BOF-01

Hydraulic Room 23.00 3.64 1.60 2.50 WELL GLASS 150 1 70 0.6

216

Skirt Hydraulic Room BOF-02

Hydraulic Room 23.00 3.64 1.60 2.50 WELL GLASS 150 1 70 0.6

217

Skirt Hydraulic Room BOF-03

Hydraulic Room 23.00 3.64 1.60 2.50 WELL GLASS 150 1 70 0.6

218

SVAICONE Hydraulic Room BOF-01

Hydraulic Room 28.50 3.64 1.60 2.50 WELL GLASS 150 1 70 0.6

219

SVAICONE Hydraulic Room BOF-02

Hydraulic Room 28.50 3.64 1.60 2.50 WELL GLASS 150 1 70 0.6

220

SVAICONE Hydraulic Room BOF-03

Hydraulic Room 28.50 3.64 1.60 2.50 WELL GLASS 150 1 70 0.6

221 Hot metal relading electrical room

Electrical room for torpedo cars

0.60 9.80 5.50 3.15 T5 200 2 28 0.7

222 Hot metal relading electrical room

Electrical room for torpedo cars

0.60 9.80 5.50 3.15 T5 200 2 28 0.7

223

Secondary dedusting electrical building

Isol. Switches 0.00 21.90 5.10 5.00 T5 200 2 28 0.7

224

Primary dedusting electrical building

Corridor 5.25 8.30 1.65 3.50 T5 150 2 28 0.7

225 BOF main control room building

Office 15.75 7.35 4.45 3.80 Mirror optic T5 300 4 14 0.75

226 BOF main control room building

Office 15.75 7.35 4.30 3.80 Mirror optic T5 300 4 14 0.75

227 ECR control room in slag yard

Control room 15 12.00 4.50 Mirror optic T5 300 2 28 0.75

228 Office /shift room in slag yard.

Office room 15 12.00 4.50 Mirror optic T5 300 4 14 0.75

229 Office /shift room in slag yard.

Office room 15 12.00 4.50 Mirror optic T5 300 4 14 0.75

230

Lime milk spray unit. (4 story structural building )

7 8.00 14.50 HPSV 200 1 70 0.6

231 Ferro alloy storage building

130 30.00 14.00 HPSV 200 1 70 0.6

232

ESP (Secondary De dusting complex)

110 50.00 40.00 HPSV 200 1 70 0.6

233 Illumination for 10.3m Ramp

177 8.00 HPSV 70 1 150 0.6

234 Illumination for Reladling pits

55 13.00 6.00 HPSV 200 1 70 0.6

235 Illumination for Reladling pits

55 13.00 6.00 HPSV 200 1 70 0.6

236

ET-71 MH Dedusting area

237

ET-71 MH Dedusting area

238 Ladle preperation bay Store room

239 Toilet block Near Col. C-30&

LTSS 3

Page 30: Illumination

SAIL -BSP

STEEL AUTHORITY OF INDIA LIMITED BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION, EARTHING AND LIGHTENING PROTECTION SYSTEM FOR

SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP) ( Pkg. NO.: 127)

MEC/S/9101/11/E1/00/14-15/127, REV-3 30

240 Toilet block Near Col. E-25 &

PH

241 Toilet block Near Col. F-18

242 Toilet block Near Col. F-13

243 Toilet block Near Col. F-5

244 Toilet block Near Col. H-1 & HT

SS-63

245 Toilet block Near Col. D-6

246

Toilet block Near Primary De-dusting ID fan Flare

Stack Near Gas Booster

Fan

247

10T ELEVATOR,NEAR

COLUMN

248

5T ELEVATOR,NEAR

COLUMN

249

1T ELEVATOR,NEAR

COLUMN

Bays

250 A-B (Slag yard) Bay 252 38 38 HPSV 200 1 400 0.6

251 C-E Bay Scrap yard

Bay 159 36 25 HPSV 200 1 400 0.6

252 E-F Bay(Charging bay)

Bay 456 28 48 HPSV 200 1 400 0.6

253 D-E Bay(Torpedo bay)

Bay 171 26.5 43 HPSV 200 1 400 0.6

254 F-G Bay(Converter bay)

Bay 456 23 70 HPSV 200 1 400 0.6

255 G-G’ Bay9Ladle preparation bay)

Bay 372 9 56 HPSV 200 1 400 0.6

256 G’-H Bay Bay 432 27 56 HPSV 200 1 400 0.6

257 H-I Bay(Secondary refining bay)

Bay 336 27 33 HPSV 200 1 400 0.6

258

I-J Bay(Ladle Handling

preparation bay) Bay

336 30 33 HPSV 200 1 400

0.6

PLATFORM

259 Platform at +3500 FG’ 7-13 75 5 6.8 HPSV 200 1 70 0.6

260 Platform at +5000 FG’ 10-11 5 5 5.3 HPSV 200 1 70 0.6

261 Platform at +6000 Converter (3 NOs.) 30 23 4.3 HPSV 200 1 70 0.6

262 Platform at +6800 Converter (3 NOs.) 30 23 3.5 HPSV 200 1 70 0.6

263 Platform1 at +6200 Reladling plant 48 14 4.1 HPSV 200 1 70 0.6

264 Platform 2 at +6200 Reladling plant 48 14 4.1 HPSV 200 1 70 0.6

265 Platform at +10300 Converter area 288 60 6.4 HPSV 200 1 70 0.6

266 Platform at +16700 Converter area 153 23 6.3 HPSV 100 1 70 0.6

267 Platform at +23 Converter area 156 32 5.5 HPSV 100 1 70 0.6

268 Platform at +25.7m Converter area 156 32 7.4 HPSV 100 1 70 0.6

269 Platform at +28.5m Converter area 156 32 7.4 HPSV 100 1 70 0.6

270 Platform at +30.05m

Converter area 156 32 7.4 HPSV

100 1 70 0.6

Page 31: Illumination

SAIL -BSP

STEEL AUTHORITY OF INDIA LIMITED BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION, EARTHING AND LIGHTENING PROTECTION SYSTEM FOR

SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP) ( Pkg. NO.: 127)

MEC/S/9101/11/E1/00/14-15/127, REV-3 31

271

Platform at +33m(include platform of +31.02,+31.87,+32.08 level also)

Primary dedusting 153 23 6

HPSV

100

1 70 0.6

272

Platform at +34m(include platform of +34.27,+34.9,+35.07 level also)

Primary dedusting 153 23 6

HPSV

100

1 70 0.6

273

Platform at +37m(include platform of +37.60 level also)

Primary dedusting 153 23 6

HPSV

100

1 70 0.6

274

Platform at +28.5 (include platform of +26.57 level also)

Primary dedusting 51 31 7 HPSV

100

1 70 0.6

275

Platform at +38m(include platform of +38.87level also)

Primary dedusting 156 32 6

HPSV

100

1 70 0.6

276

Platform at +41m(include platform of +40.2,+41.93 level also)

Primary dedusting 156 32 7

HPSV

100

1 70 0.6

277 Platform at +45.3 Primary dedusting 150 23 7 HPSV 100 1 70 0.6

278 Platform at +50.25m

Primary dedusting 90 3 7 HPSV

100 1 70 0.6

279 Platform at +53.00m

Primary dedusting 153 18 7 HPSV

100 1 70 0.6

280 Platform1 at +57.5m

Primary dedusting 84 4 7 HPSV

100 1 70 0.6

281 Platform2 at +57.5m

Primary dedusting 84 4 7 HPSV

100 1 70 0.6

282 Platform at +48.8m Lance 90 18 7 HPSV 100 1 70 0.6

283 Platform at +51 Lance 45 7 7 HPSV 100 1 70 0.6

284 Platform at +53.5 Lance 90 7 7 HPSV 100 1 70 0.6

285 Platform at 36.5

Row F-G and column 12B-14

24 18 5 HPSV 100 1 70 0.6

286 Platform at 36.5

Row F-G and column 12B-14

24 18 5 HPSV 100 1 70 0.6

287 Platform at 36.5

Row F-G and column 17-20

36 11 5 HPSV 100 1 70 0.6

288 Platform at 36.5

Row F-G and column 14-17

90 10 5 HPSV 100 1 70 0.6

289

Platform at 32.30 & 33.650

90 3 5

HPSV 100 1 70

0.6

Road lighting with 2.0m burmoneither side.

290 4m road –1.5Km 1500 4 HPSV 70 1 150 0.6

291 7m road – 2.5Km 2500 7 HPSV 70 1 150 0.6

292 11m road – 1.0Km 1000 11 HPSV 70 1 150 0.6

293

Room Sizes for ACVS Buildings/ Rooms,Shiftincharge etc. will be indicated during tender discussion.

200 0.7

Page 32: Illumination

SAIL -BSP

STEEL AUTHORITY OF INDIA LIMITED BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION, EARTHING AND LIGHTENING PROTECTION SYSTEM FOR

SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP) ( Pkg. NO.: 127)

MEC/S/9101/11/E1/00/14-15/127, REV-3 32

294 Cable celler 76 2 3 HPSV 70 1 70 0.6

VI

LIGHTNING SYSTEM

SMS Shop, Buildings and Plant structures Located outside the shop.

Tentative ILLUMINATION REQUIREMENT (CCP Area)

Sl .NO. Building Room Floor level Length Width Height

1. Substation Billet Casters Cable Cellar -3.00 78.00 3.95 2.70 2. Substation Billet Casters Transformer + PCC Room 0.00 78.00 10.00 5.20 3. Substation Billet Casters Ventilation Room 0.00 12.00 9.00 5.00 4. Billet Caster 1 MainBuilding Pump Room 1 -3.00 27.72 9.72 2.60 5. Billet Caster 1 MainBuilding Cable Cellar -3.35 30.10 15.60 3.00 6. Billet Caster 1 MainBuilding Elevator 0.00 5.50 4.00 16.60 7. Billet Caster 1 MainBuilding Pump Room 1 0.00 37.10 13.03 5.15 8. Billet Caster 1 MainBuilding Hydraulik Room 1 0.00 37.10 6.87 5.15 9. Billet Caster 1 MainBuilding Pump Room 2 0.00 9.00 5.76 5.35 10. Billet Caster 1 MainBuilding Water Room 2 0.00 9.00 2.39 5.25 11. Billet Caster 1 MainBuilding MCC Room 0.00 30.10 15.60 2.95 12. Billet Caster 1 MainBuilding Torch Cutting Control Room 1.40 6.80 4.30 4.15 13. Billet Caster 1 MainBuilding Ventilation Room 0.00 11.00 10.00 4.85 14. Billet Caster 1 MainBuilding CO2 Ext. Room 0.00 5.50 4.00 2.95 15. Billet Caster 1 MainBuilding Ventilation & Air Cond. Room 0.00 11.10 10.10 4.85 16.

Billet Caster 1 MainBuilding Clean Agent Ext. Room Billet Caster

1 0.00 13.10 3.30 2.95

17. Billet Caster 1 MainBuilding CO2 Ext. Room Billet Caster 2 0.00 5.00 4.00 2.95 18. Billet Caster 1 MainBuilding Water Room 1 5.30 37.10 20.25 4.12 19. Billet Caster 1 MainBuilding Steam Exhaust Room 1 5.60 20.25 9.00 3.82 20. Billet Caster 1 MainBuilding Hydraulic Room 2 5.60 9.00 5.76 2.48 21. Billet Caster 1 MainBuilding Steam Exhaust Room 2 5.60 15.60 9.00 3.82 22. Billet Caster 1 MainBuilding PLC Room 5.90 22.25 15.60 3.52 23. Billet Caster 1 MainBuilding Cable Floor 3.30 30.10 15.60 2.25 24. Billet Caster 1 MainBuilding Remote I/O Room 5.90 8.00 4.90 4.20 25. Billet Caster 1 MainBuilding AC Room 5.20 10.10 7.52 4.40 26. Billet Caster 1 MainBuilding Caster Control Room 10.60 8.20 4.70 3.40 27. Billet Caster 1 MainBuilding AC Room 10.00 4.82 2.90 4.00 28. Billet Caster 1 MainBuilding Clean Agent Ext. Room 10.00 4.82 2.00 4.00 29. Billet Caster 1 MainBuilding Elevator Drive Room 15.10 5.50 4.00 2.98 30. Billet Caster 1 Discharge Hydraulic

Building 1 Hydraulic Room 3 0.00 21.50 11.00 5.65

31. Billet Caster 1 Discharge Hydraulic Building 1

Ventilation Room 0.00 7.90 5.60 5.65

32. Billet Caster 1 Discharge Hydraulic Building 1

CO2 Ext. Room 0.00 6.10 4.10 4.00

33. Billet Caster 1 DischargeElectricBuilding 1

Discharge Area MCC Room 0.00 14.55 5.90 4.00

34. Billet Caster 1 DischargeElectricBuilding 1

AC Room 0.00 6.10 3.70 4.00

35. Billet Caster 1 DischargeElectricBuilding 1

Clean Agent Ext. Room 0.00 6.10 2.10 4.00

36. Billet Caster 1 DischargeElectricBuilding 1

Discharge Control Room 4.90 6.05 4.15 2.80

37. Billet Caster 2 MainBuilding Pump Room 1 -3.00 19.65 7.03 2.60 38. Billet Caster 2 MainBuilding Cable Cellar 0.00 30.70 16.27 3.00 39. Billet Caster 2 MainBuilding Pump Room 1 0.00 19.65 17.20 5.00

Page 33: Illumination

SAIL -BSP

STEEL AUTHORITY OF INDIA LIMITED BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION, EARTHING AND LIGHTENING PROTECTION SYSTEM FOR

SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP) ( Pkg. NO.: 127)

MEC/S/9101/11/E1/00/14-15/127, REV-3 33

40. Billet Caster 2 MainBuilding Hydraulic Room 1 0.00 17.10 11.45 5.25 41. Billet Caster 2 MainBuilding Pump Room 2 0.00 9.00 5.76 5.35 42. Billet Caster 2 MainBuilding Water Room 2 0.00 9.00 2.39 5.25 43. Billet Caster 2 MainBuilding MCC Room 0.00 30.70 16.27 2.95 44. Billet Caster 2 MainBuilding Torch Cutting Control Room 1.40 6.80 4.30 4.15 45. Billet Caster 2 MainBuilding Ventilation & Air Cond. Room 0.00 11.00 5.90 4.85 46. Billet Caster 2 MainBuilding Clean Agent Ext. Room 0.00 6.65 6.25 2.95 47. Billet Caster 2 MainBuilding Water Room 1 5.60 27.75 17.20 4.02 48. Billet Caster 2 MainBuilding Steam Exhaust Room 1 5.60 11.45 9.00 3.82 49. Billet Caster 2 MainBuilding Hydraulic Room 2 5.60 9.00 5.76 2.48 50. Billet Caster 2 MainBuilding Steam Exhaust Room 2 5.60 16.27 8.98 3.82 51. Billet Caster 2 MainBuilding PLC Room 5.90 21.35 16.27 3.52 52. Billet Caster 2 MainBuilding Cable Floor 3.30 30.70 16.27 2.25 53. Billet Caster 2 MainBuilding Remote I/O Room 5.90 7.55 5.15 4.20 54. Billet Caster 2 MainBuilding AC Room 5.20 9.00 5.90 4.40 55. Billet Caster 2 MainBuilding Caster Control Room 10.60 8.20 4.70 3.40 56. Billet Caster 2 MainBuilding AC Room 10.00 4.82 2.90 4.00 57. Billet Caster 2 MainBuilding Clean Agent Ext. Room 10.00 4.82 2.00 4.00 58. Billet Caster 2 Discharge Hydraulic

Building 1 Hydraulic Room 3 0.00 21.50 11.00 5.65

59. Billet Caster 2 Discharge Hydraulic Building 1

Ventilation Room 0.00 7.90 5.60 5.65

60. Billet Caster 2 Discharge Hydraulic Building 1

CO2 Ext. Room 0.00 6.10 4.10 4.00

61. Billet Caster 2 DischargeElectricBuilding 1

Discharge Area MCC Room 0.00 14.00 6.40 4.00

62. Billet Caster 2 DischargeElectricBuilding 1

AC Room 0.00 6.40 4.10 4.00

63. Billet Caster 2 DischargeElectricBuilding 1

Clean Agent Ext. Room 0.00 6.40 2.40 4.00

64. Billet Caster 2 DischargeElectricBuilding 1

Discharge Control Room 4.90 6.05 4.15 2.80

65. BilletBloomCasterMainBuilding Pump Room 1 -3.00 30.64 8.25 3.00 66. BilletBloomCasterMainBuilding Cable Cellar -3.35 27.66 25.50 3.00 67. BilletBloomCasterMainBuilding Pump Room 1 0.00 36.30 12.50 5.50 68. BilletBloomCasterMainBuilding Hydraulic Room 1 0.00 24.99 11.84 5.50 69. BilletBloomCasterMainBuilding Grease Room 0.00 10.30 8.97 5.50 70. BilletBloomCasterMainBuilding Water Control Room 2 0.00 6.12 4.70 5.65 71. BilletBloomCasterMainBuilding MCC Room 0.00 25.50 23.12 4.05 72. BilletBloomCasterMainBuilding Elevator -1.80 5.50 4.00 19.40 73. BilletBloomCasterMainBuilding Clean Agent Ext. Room - Reserve 0.00 6.69 4.35 5.65 74. BilletBloomCasterMainBuilding Clean Agent Ext. Room - Main 0.00 9.50 4.35 5.65 75. BilletBloomCasterMainBuilding Ventilation Room 0.00 15.00 12.00 6.00 76. BilletBloomCasterMainBuilding CO2 Ext. Room 0.00 6.50 4.00 2.95 77. BilletBloomCasterMainBuilding Ventilation & Air Condition Room 0.00 16.92 5.40 5.00 78. BilletBloomCasterMainBuilding Water Control Room 1 6.00 36.30 24.69 6.40 79. BilletBloomCasterMainBuilding Steam Exhaust Room 1 6.00 7.99 8.08 6.25 80. BilletBloomCasterMainBuilding Hydraulic Room 2 6.00 6.12 4.70 4.88 81. BilletBloomCasterMainBuilding Steam Exhaust Room 2 6.00 13.23 7.99 6.25 82. BilletBloomCasterMainBuilding PLC & Drives Room 6.00 25.50 23.12 4.80 83. BilletBloomCasterMainBuilding Cable Floor 4.40 25.50 23.12 2.85 84. BilletBloomCasterMainBuilding Remote I/O Room 6.00 10.40 4.60 6.40 85. BilletBloomCasterMainBuilding AC Room 6.00 11.50 3.90 6.50 86. BilletBloomCasterMainBuilding Caster Control Room 13.40 8.20 4.70 3.40 87. BilletBloomCasterMainBuilding Computer Room 13.40 8.20 5.73 3.70 88. BilletBloomCasterMainBuilding Shift Office(1) 13.10 5.60 2.60 3.00 89. BilletBloomCasterMainBuilding AC Room 12.80 8.20 4.80 4.00 90. BilletBloomCasterMainBuilding Clean Agent Ext. Room 12.80 4.45 2.00 4.00 91. BilletBloomCasterMainBuilding Elevator Drive Room 17.90 5.50 4.00 2.98 92. Substation Billet Bloom Caster Cable Cellar -3.00 41.20 5.60 3.00 93. Substation Billet Bloom Caster Transformer + PCC Room 0.00 41.20 11.40 5.70 94. Substation Billet Bloom Caster Store Room 2 6.00 5.00 4.00 3.75 95. Substation Billet Bloom Caster Shift Room 2 6.00 5.00 4.00 3.75 96. Substation Billet Bloom Caster Rest Room 1 6.00 5.00 4.00 3.75 97. Billet Bloom Caster Discharge Hydraulic Hydraulic Room 4 0.00 13.50 8.50 5.70

Page 34: Illumination

SAIL -BSP

STEEL AUTHORITY OF INDIA LIMITED BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION, EARTHING AND LIGHTENING PROTECTION SYSTEM FOR

SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP) ( Pkg. NO.: 127)

MEC/S/9101/11/E1/00/14-15/127, REV-3 34

Building 2 98. Billet Bloom Caster Discharge Hydraulic

Building 2 Ventilation Room 0.00 5.85 4.10 4.50

99. Billet Bloom Caster Discharge Hydraulic Building 2

CO2 Ext. Room 0.00 3.80 2.75 3.00

100. Billet Bloom Caster Torch Cutting Control Room

Torch Cutting Control Room 1.40 6.80 4.30 3.45

101. Billet Bloom Caster Torch Cutting Control Room

Clean Agent Ext. Room 0.00 3.00 2.00 2.95

102. Billet Bloom Caster Torch Cutting Control Room

Air Conditioning Room 0.00 4.45 3.20 4.85

103. Billet Bloom Caster Discharge Hydraulic &SubstationBuilding 1

Cable Cellar -3.00 13.60 5.50 3.00

104. Billet Bloom Caster Discharge Hydraulic &SubstationBuilding 1

Hydraulic Room 3 0.00 21.40 11.40 5.65

105. Billet Bloom Caster Discharge Hydraulic &SubstationBuilding 1

Ventilation Room 0.00 10.10 7.30 4.00

106. Billet Bloom Caster Discharge Hydraulic &SubstationBuilding 1

Discharge Area MCC Room 0.00 10.10 8.40 4.00

107. Billet Bloom Caster Discharge Hydraulic &SubstationBuilding 1

AC Room 0.00 5.00 4.00 4.00

108. Billet Bloom Caster Discharge Hydraulic &SubstationBuilding 1

CO2 Ext. Room 0.00 6.05 4.00 4.00

109. Billet Bloom Caster Discharge Hydraulic &SubstationBuilding 1

Clean Agent Ext. Room 0.00 4.00 2.00 4.00

110. Billet Bloom Caster Discharge Hydraulic &SubstationBuilding 1

Substation Billet Cum Bloom Caster 0.00 13.60 11.40 5.65

111. Billet Bloom Caster Discharge Hydraulic &SubstationBuilding 1

Discharge Control Room 6.60 6.05 4.15 2.80

112. BilletBloomCasterDischargeElectricBuilding 1

Discharge Area MCC Room 0.00 37.70 3.60 4.00

113. BilletBloomCasterDischargeElectricBuilding 1

AC Room 0.00 10.00 3.60 4.00

114. BilletBloomCasterDischargeElectricBuildin

g 2 Discharge Area MCC Room 0.00 9.50 3.45 4.00

115. BilletBloomCasterDischargeElectricBuilding 2

AC Room 0.00 3.75 3.45 4.00

116. BilletBloomCasterDischargeElectricBuilding 2

Shift Room 8 (ADDITIONAL) 0.00 4.90 4.20 4.00

117. BeamBlankCasterMainBuilding Pump Room 1 -3.00 30.64 8.25 3.00 118. BeamBlankCasterMainBuilding Water Control Room 3 - Cellar -3.00 7.00 6.00 2.60 119. BeamBlankCasterMainBuilding Cable Cellar -3.35 29.72 16.28 3.00 120. BeamBlankCasterMainBuilding Hydraulic Room 1 0.00 24.82 13.89 5.50 121. BeamBlankCasterMainBuilding Grease Room 0.00 8.25 6.00 5.50 122. BeamBlankCasterMainBuilding Water Control Room 3 0.00 7.00 6.00 5.50 123. BeamBlankCasterMainBuilding Water Control Room 2 0.00 6.12 4.65 5.65 124. BeamBlankCasterMainBuilding Reserve Room 0.00 6.12 6.05 5.65 125. BeamBlankCasterMainBuilding Clean Agent Ext. Room 0.00 9.51 7.40 5.65 126. BeamBlankCasterMainBuilding MCC Room 0.00 29.72 14.75 4.05 127. BeamBlankCasterMainBuilding Substation Transformer + PCC Room 0.00 29.72 10.65 4.05 128. BeamBlankCasterMainBuilding Ventilation Room 0.00 10.50 6.80 5.65 129. BeamBlankCasterMainBuilding Ventilation Room 0.00 18.80 14.05 5.00 130. BeamBlankCasterMainBuilding AC Room 0.00 4.70 3.20 4.85 131. BeamBlankCasterMainBuilding Clean Agent Ext. Room 0.00 3.20 2.00 2.95 132. BeamBlankCasterMainBuilding Torch Cutting Control Room 1.40 6.80 4.30 3.45 133. BeamBlankCasterMainBuilding CO2 Ext. Room 0.00 7.90 3.90 2.95 134. BeamBlankCasterMainBuilding Pump Room 1 0.00 36.30 12.50 5.00 135. BeamBlankCasterMainBuilding Water Control Room 1 6.00 31.17 11.90 6.22 136. BeamBlankCasterMainBuilding Steam Exhaust Room 1 6.00 11.30 7.90 6.22 137. BeamBlankCasterMainBuilding Hydraulic Room 2 6.00 6.12 4.65 4.65 138. BeamBlankCasterMainBuilding Steam Exhaust Room 2 6.00 13.23 7.40 6.22 139. BeamBlankCasterMainBuilding PLC Room 7.40 21.97 20.25 4.80 140. BeamBlankCasterMainBuilding Cable Floor 4.40 21.97 20.25 2.85

Page 35: Illumination

SAIL -BSP

STEEL AUTHORITY OF INDIA LIMITED BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION, EARTHING AND LIGHTENING PROTECTION SYSTEM FOR

SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP) ( Pkg. NO.: 127)

MEC/S/9101/11/E1/00/14-15/127, REV-3 35

141. BeamBlankCasterMainBuilding Remote I/O Room 6.00 6.00 5.80 6.40 142. BeamBlankCasterMainBuilding AC Room 6.00 17.36 5.15 6.40 143. BeamBlankCasterMainBuilding

Store Room 6.00 16.21 7.40 6.22

144. BeamBlankCasterMainBuilding Caster Control Room 13.40 8.35 4.70 3.40 145. BeamBlankCasterMainBuilding Clean Agent Ext. Room 12.80 4.00 2.00 4.00 146. BeamBlankCasterDischargeElectricBuildi

ng 1 Discharge Area MCC Room 0.00 20.00 6.80 4.00

147. BeamBlankCasterDischargeElectricBuilding 1

AC Room 0.00 7.95 4.00 4.00

148. BeamBlankCasterDischargeElectricBuilding 1

Clean Agent Ext. Room 0.00 3.00 2.00 4.00

149. BeamBlankCasterDischargeElectricBuilding 1

Discharge Control Room 4.90 7.10 4.40 2.80

150. Beam Blank Caster Discharge Hydraulic Building 1

Hydraulic Room 3 -6.80 21.50 11.00 6.50

151. Beam Blank Caster Discharge Hydraulic Building 1

Ventilation Room 0.00 10.00 6.00 4.00

152. Beam Blank Caster Discharge Hydraulic Building 1

CO2 Ext. Room 0.00 5.80 4.00 3.00

153. Substation 1 & 6 Cable Cellar -3.35 25.90 5.60 3.00 154. Substation 1 & 6 Transformer + PCC Room 0.50 25.90 11.40 5.45 155. Substation 1 & 6 Ventilation Room 0.50 17.10 5.75 8.75 156. Substation 1 & 6 Cable Floor 5.85 24.40 11.40 3.15 157. Substation 1 & 6 Transformer + PCC Room 9.35 20.70 11.40 5.60 158. Substation 2 Cable Cellar -3.00 14.00 5.50 2.70 159. Substation 2 Transformer + PCC Room 0.00 14.00 11.40 5.70 160. Substation 2 Ventilation Room 0.00 9.00 6.00 5.70 161. Substation 3 Cable Cellar -3.00 14.00 5.80 2.70 162. Substation 3 Transformer + PCC Room 0.00 14.00 12.00 5.70 163. Substation 3 Ventilation Room 0.00 9.00 6.00 5.70 164. Substation 4 Cable Cellar -3.00 16.00 4.80 2.70 165. Substation 4 Transformer + PCC Room 0.00 16.00 10.00 5.70 166. Substation 4 Ventilation Room 0.00 9.00 6.00 5.70 167. Substation 5 Cable Cellar -3.00 14.00 5.80 2.70 168. Substation 5 Transformer + PCC Room 0.00 14.00 12.00 5.70 169. Substation 5 Ventilation Room 0.00 9.00 6.00 5.70 170. E-Tunnels Cable Tunnels 600 2.4 3 171. M-Tunnel Media Tunnel 200 2.4 3 172. scale flume tunnel (CK2 & CV1)& other

interconnecting tunnels scale flume tunnel 200 2.8 2.0

173. Bays 174. J-K Tundish preparation area 393 36 47.9 175.

K-L Mould& Segment preparation area

393 27 44.9 176.

L-M Billet storage area

393 36 35.7 177.

M-N Billet storage area

393 33 32.7 178. N-P BLOOM storage area 393

24 28 179. A’-B’ Beam Blank Storage area 72 36 27 180. B’-C’ Beam Blank Storage area 72 36 27 181. Beam Blank storage shed(FG bay) Beam Blank Area 155 40 27 182. Road lighting 1000 7 183. AB bay Tundishdeskulling shop 96 27 24 184. LT substation Tundishdeskulling shop 22 10 4 185. Office block Tundishdeskulling shop 10 3 3.5 186. Staff room Tundishdeskulling shop 12 3 3.5 187. PDB room Tundishdeskulling shop 4 3 3.5

Page 36: Illumination

SAIL -BSP

STEEL AUTHORITY OF INDIA LIMITED BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION, EARTHING AND LIGHTENING PROTECTION SYSTEM FOR

SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP) ( Pkg. NO.: 127)

MEC/S/9101/11/E1/00/14-15/127, REV-3 36

188. Toilet block Tundishdeskulling shop 3.5 3.5 3 189. Shift room N1 Shift room 10 0.00 5.50 4.50 4.00 190. Shipping room N26 Shipping room 0.00 6.40 4.40 4.00 191. Documentation room N28 Documentation room 0.00 6.40 4.40 4.00 192. Store room M1 Store room 10 0.00 5.00 4.50 4.00 193. PPC room M8 PPC room 0.00 6.40 4.40 4.00 194. Rest room M26 Rest room 7 0.00 5.40 4.40 4.00 195. Store room M28 Store room 9 0.00 5.80 4.50 4.00 196. Toilet Block M29 Toilet block 0.00 3.50 3.50 3.00 197. Shift room L1 Shift room 6 0.00 5.50 4.50 4.00 198. Shift room L29 Shift room 8 0.00 5.50 4.50 4.00 199. Rest room L14-14a Rest room 5 0.00 5.50 4.40 4.00 200. Shift room L19a-20 Shift room 7 0.00 5.50 4.50 4.00 201. Shift room L29 Shift room 8 0.00 5.50 4.50 4.00 202. Toilet block L29 Toilet block 0.00 3.50 3.50 3.00 203. Rest room K1 Rest room 4 0.00 4.40 5.40 4.00 204. Toilet block K1 Toilet block 0.00 3.50 3.50 3.00 205. Shift room K15 Shift room 5 0.00 5.50 4.50 4.00 206. Store room K29 Store room 4 0.00 5.50 4.30 4.00 207. Shift room K29 Shift room 4 0.00 5.00 4.50 4.00 208. Toilet block K30 Toilet block 0.00 3.50 3.50 3.00 209. Toilet block B’8’ Toilet block 0.00 3.50 3.50 3.00 210. Toilet block C’1’ Toilet block 0.00 3.50 3.50 3.00 211. Toilet block K14-14a Toilet block +5.2 3.50 3.50 3.00 212. Store room for Radio-active sources

(ck,cv1&cv2) Near 12a (mid of KL bay) 10.6 4.0 4.0 4.0

213. Billet Bloom Caster Main Building Shift Office 12.80 5.8 4.0 3.00 214. Billet Bloom Caster Main Building Shift Office 12.80 5.8 4.0 3.00 215. Substation Billet Bloom Caster J14a-

15 Store Room 3 6.60 3.00 5.40 3.4

216. Substation Billet Bloom Caster J14a-15 Rest Room 2 10.00 3.00 5.40 3.4 217. Substation Billet Bloom Caster J14a-

15 Shift room 3 10.00 3.00 5.40 3.4

218. Substation Billet Bloom Caster J14a-15

Shift room 4 10.00 3.00 5.40 3.4

219. Substation Billet Bloom Caster J14a-15

Shift room 5 10.00 3.00 5.40 3.4

220. Near CK1 Disch. Control Room(added) Shipping Room 0.00 6.2 4.2 2.80 221. Near Column I-3 Store Room 1 0.00 5.50 4.5 3.4 222. Near Column K-15A Store Room 5 0.00 5.50 4.5 3.4 223. Near Column L-8 Store Room 7 0.00 5.50 4.5 3.4 224. Near Column L-14 Store Room 8 0.00 5.90 4.6 3.4 225. Near Column J-25 Rest Room 2 0.00 5.00 4.0 3.4 226. Near Column N-15 Store Room 11 0.00 5.50 4.5 3.4 227. Near Column I-1 Shift Room 1 0.00 6.00 4.6 3.4 228. Near Column M-29 Shift Room 9 0.00 5.50 4.5 3.4 229. Near Column N-18 Shift Room 11 0.00 5.50 4.5 3.4 230. Near Column L-27 Rest Room 6 0.00 5.50 4.5 3.4 231. Near Column N-19 Rest Room 8 0.00 5.50 4.5 3.4 232. Near Column N-14 Rest Room 9 0.00 7.00 4.1 3.4 233.

Near Column-16, E Row E- Building Container Lab-1 +7.5

234. Near Column-16, E Row E- Building Container Lab-2 +7.5

235. SMS 3 Welfare Building First floor 26 nos. rooms, total 900 square meter

236. SMS 3 Welfare Building Second floor 26 nos. rooms, total 900 square meter

237. SMS 3 Welfare Building Third floor 26 nos. rooms, total 900 square meter

238. SMS 3 Welfare Building 4th floor 26 nos. rooms, total 900 square meter

Page 37: Illumination

SAIL -BSP

STEEL AUTHORITY OF INDIA LIMITED BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION, EARTHING AND LIGHTENING PROTECTION SYSTEM FOR

SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP) ( Pkg. NO.: 127)

MEC/S/9101/11/E1/00/14-15/127, REV-3 37

239. SMS 3 Welfare Building

Ground floor 26 nos. rooms, total 900 square meter

Note : Illumination for additional 35 rooms/ areas/platforms shall be considered for BOF & CCP, which were not mentioned in the TS. However, details shall be provided during techno commercial discussions.

TENTATIVE CEILING FAN / EXHAUST FAN REQUIREMENT (BOF Area)

Sl. NO.

Building Room

Flo

or

Leve

l

Length

Wid

th

Heig

ht

Ceili

ng f

an

Exha

ust fa

n

Remarks

1 Primary Dedusting Electrical Building

Cable Cellar -3.55 15.9 10.4 3.3 NO NO

2 Primary Dedusting Electrical Building

Cable Cellar -3.55 27 10.4 3.3 NO NO

3 Primary Dedusting Electrical Building

Stair Case -3.55 5.85 3 3.3 NO NO

4 Primary Dedusting Electrical Building

Stair Case 0 10.4 3 5 NO NO

5 Primary Dedusting Electrical Building

VVVF-Converter

Room 0 32 4.1 5

NO NO

6 Primary Dedusting Electrical Building

Ventilation Room

0 7.55 4.7 5 NO NO

7 Primary Dedusting Electrical Building

Transformer Room

0 8.8 6 5 NO YES

8 Primary Dedusting Electrical Building

Transformer Room

0 8.8 6 5 NO YES

9 Primary Dedusting Electrical Building

Transformer Room

0 8.8 6 5 NO YES

10 Primary Dedusting Electrical Building

Electrical Room

MCC/PLC 0 12.6 10.4 5

NO NO

11 Primary Dedusting Electrical Building

AC Room 5.25 10.4 8.8 3.5 NO NO

12 Primary Dedusting Electrical Building

Stair Case 5.25 8.25 3 3.5 NO NO

13 Primary Dedusting Electrical Building

Lavatory 5.25 3 2 3.5 NO NO

14 Primary Dedusting Electrical Building

Fire Fighting Room

5.25 8.3 5 3.5 NO NO

15 Primary Dedusting Electrical Building

AC Room 5.25 8.3 5.1 3.5 NO NO

16 Primary Dedusting Electrical Building

Gas Analysis Room

5.25 4.55 4.2 3.5 NO NO

17 Gas Recovery Station Electrical Building

Rest Room 0 4.5 4.2 5 YES NO

18 Gas Recovery Station Electrical Building

Storage 0 2.88 1 5 YES YES

19 Gas Recovery Station Electrical Building

Lavatory 0 2.88 2 5 NO NO

Page 38: Illumination

SAIL -BSP

STEEL AUTHORITY OF INDIA LIMITED BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION, EARTHING AND LIGHTENING PROTECTION SYSTEM FOR

SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP) ( Pkg. NO.: 127)

MEC/S/9101/11/E1/00/14-15/127, REV-3 38

20 Gas Recovery Station Electrical Building

Corridor 0 14.4 2.6 5 NO YES

21 Gas Recovery Station Electrical Building

AC Room 0 8.3 4.7 5 NO NO

22 Gas Recovery Station Electrical Building

Transformer Room

0 4 3.82 5 NO YES

23 Gas Recovery Station Electrical Building

Transformer Room

0 4 3.82 5 NO YES

24 Gas Recovery Station Electrical Building

Transformer Room

0 4 3.82 5 NO YES

25 Gas Recovery Station Electrical Building

Transformer Room

0 4 3.82 5 NO YES

26 Gas Recovery Station Electrical Building

Electrical Room

0 11.4 8.3 5 NO NO

27 Gas Recovery Station Electrical Building

Control Room

0 7.9 7.05 3 YES NO

28 Gas Recovery Station Electrical Building

Fire Fighting Room

0 7.9 2.55 5 NO YES

29 Gas Recovery Station Electrical Building

AC Room 5.25 10.1 5.95 4.5 NO NO

30 Gas Recovery Station Electrical Building

Crew room 0 YES NO

30 Primary Dedusting Analysing Room BOF-01

Gas Analysis Room

0.5 6 4 3 NO NO

31 Primary Dedusting Analysing Room BOF-02

Gas Analysis Room

0.5 6 4 3 NO NO

32 Primary DedustingAnalysiing Room BOF-03

Gas Analysis Room

0.5 6 4 3 NO NO

33 Primary Dedusting Hydraulic Room BOF-01

Hydraulic Room

0 6.4 4 3.5 NO NO

34 Primary Dedusting Hydraulic Room BOF-02

Hydraulic Room

0 6.4 4 3.5 NO NO

35 Primary Dedusting Hydraulic Room BOF-03

Hydraulic Room

0 6.4 4 3.5 NO NO

36 Gas Holder Hydraulic Room Hydraulic

Room 0 6.4 4 3.5

NO NO

37 Secondary Dedusting Electrical Building

Cable Cellar 3.55 20.2 10.4 3.3 NO NO

38 Secondary Dedusting Electrical Building

Cable Cellar 3.55 27 10.4 3.3 NO NO

39 Secondary Dedusting Electrical Building

Stair Case 3.55 5.85 3 3.3 NO NO

40 Secondary Dedusting Electrical Building

Stair Case 0 10.4 3 15.6 NO NO

41 Secondary Dedusting Electrical Building

VVVF-Converter

Room 0 27 4.1 5

NO NO

42 Secondary Dedusting Electrical Building

Electrical Room

0 16.9 5.1 5 NO NO

43 Secondary Dedusting Electrical Building

Transformer Room

0 8.3 5 5 NO YES

Page 39: Illumination

SAIL -BSP

STEEL AUTHORITY OF INDIA LIMITED BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION, EARTHING AND LIGHTENING PROTECTION SYSTEM FOR

SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP) ( Pkg. NO.: 127)

MEC/S/9101/11/E1/00/14-15/127, REV-3 39

44 Secondary Dedusting Electrical Building

Transformer Room

0 8.3 5 5 NO YES

45 Secondary Dedusting Electrical Building

Transformer Room

0 8.8 6 5 NO YES

46 Secondary Dedusting Electrical Building

Transformer Room

0 8.8 6 5 NO YES

47 Secondary Dedusting Electrical Building

Transformer Room

0 8.8 6 5 NO YES

48 Secondary Dedusting Electrical Building

Cable Room 5.25 27 10.4 3.25 NO NO

49 Secondary Dedusting Electrical Building

Cable Room 5.25 16.9 10.4 3.25 NO NO

50 Secondary Dedusting Electrical Building

Lavatory 5.25 3 2 2.7 NO NO

51 Secondary Dedusting Electrical Building

Electrical Room

ESP/MCC 8.75 27 10.4 3.25

NO NO

52 Secondary Dedusting Electrical Building

Electrical Room

LT/MCC/PLC 8.75 16.9 10.4 3.25

NO NO

53 Secondary Dedusting Electrical Building

Control Room

8.75 7.45 5 2.85 YES NO

54 Secondary Dedusting Electrical Building

Corridor 12.25 5.45 1.8 3.35 NO YES

55 Secondary Dedusting Electrical Building

Fire Fighting Room

12.25 6.5 3.15 3.35 NO YES

56 Secondary Dedusting Electrical Building

Ventilation Room

12.25 10.4 10.25 3.35 NO NO

57 Secondary Dedusting Electrical Building

AC Room 12.25 10.53 5.15 3.35 NO NO

58 Secondary Dedusting Electrical Building

Lavatory 12.25 3 1.4 3.35 NO NO

59 Secondary Dedusting Electrical Building

Lavatory 12.25 3.45 3 3.35 NO NO

60 Secondary Dedusting Electrical Building

Corridor 12.25 6.7 4.25 3.35 NO YES

61 Secondary Dedusting Electrical Building

Rest Room 12.25 4.25 3.55 3.35 YES NO

62 Secondary Dedusting Electrical Building

Meeting Room, Office

12.25 13.7 10.4 3.35 YES NO

63 Secondary Dedusting Electrical Building

AC Room 12.25 10.4 8.8 3.35 NO NO

64 BOF - Main Control and Electrical Building

Stair Case -3.65 4.7 2.6 23.15 NO NO

65 BOF - Main Control and Electrical Building

Cable Cellar -3.65 19.4 8.9 3.5 NO NO

66 BOF - Main Control and Electrical Building

Tunnel -3.65 12 1.8 3.5 NO NO

67 BOF - Main Control and Electrical Building

Stair Case -3.65 4.7 2.6 27.5 NO NO

68 BOF - Main Control and Electrical Building

Cable Cellar -3.65 19.4 17.4 3.5 NO NO

Page 40: Illumination

SAIL -BSP

STEEL AUTHORITY OF INDIA LIMITED BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION, EARTHING AND LIGHTENING PROTECTION SYSTEM FOR

SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP) ( Pkg. NO.: 127)

MEC/S/9101/11/E1/00/14-15/127, REV-3 40

69 BOF - Main Control and Electrical Building

Tunnel -3.65 12 1.8 3.5 NO NO

70 BOF - Main Control and Electrical Building

Cable Cellar -3.65 19.4 17.9 3.5 NO NO

71 BOF - Main Control and Electrical Building

Stair Case -3.65 4.7 2.6 23.15 NO NO

72 BOF - Main Control and Electrical Building

Corridor 0.15 4.7 1.35 5 NO YES

73 BOF - Main Control and Electrical Building

Cable and Ventilation

Shaft 0.15 4.7 3.2 5

NO NO

74 BOF - Main Control and Electrical Building

Electrical Room

0.15 17.9 9.1 5 NO NO

75 BOF - Main Control and Electrical Building

Transformer Room

0.15 8.8 5.3 5 NO YES

76 BOF - Main Control and Electrical Building

Transformer Room

0.15 8.8 5.3 5 NO YES

77 BOF - Main Control and Electrical Building

Transformer Room

0.15 8.8 5.3 5 NO YES

78 BOF - Main Control and Electrical Building

Ventilation Room

0.15 9 4.2 5 NO NO

79 BOF - Main Control and Electrical Building

Corridor 0.15 4.7 1.35 5 NO YES

80 BOF - Main Control and Electrical Building

Cable and Ventilation

Shaft 0.15 4.7 2.92 5

NO NO

81 BOF - Main Control and Electrical Building

Electrical Room

0.15 9.1 8.55 5 NO NO

82 BOF - Main Control and Electrical Building

Transformer Room

0.15 6.25 5.3 5 NO YES

83 BOF - Main Control and Electrical Building

Transformer Room

0.15 6.3 5.3 5 NO YES

84 BOF - Main Control and Electrical Building

Transformer Room

0.15 6.25 5.3 5 NO YES

85 BOF - Main Control and Electrical Building

Corridor 0.15 20 3.25 5 NO YES

86 BOF - Main Control and Electrical Building

Transformer Room

0.15 8.55 5.3 5 NO YES

87 BOF - Main Control and Electrical Building

Ventilation Room

0.15 9 4.2 5 NO NO

88 BOF - Main Control and Electrical Building

Corridor 0.15 4.7 1.35 5 NO YES

89 BOF - Main Control and Electrical Building

Cable and Ventilation

Shaft 0.15 4.7 3.25 5

NO NO

90 BOF - Main Control and Electrical Building

Electrical Room

0.15 9.1 8.9 5 NO NO

91 BOF - Main Control and Electrical Building

Transformer Room

0.15 8.9 5.3 5 NO YES

92 BOF - Main Control and Electrical Building

Ventilation Room

0.15 7.4 5 5 NO NO

93 BOF - Main Control and Electrical Building

Compressor Room

0.15 7.4 5.3 5 NO YES

Page 41: Illumination

SAIL -BSP

STEEL AUTHORITY OF INDIA LIMITED BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION, EARTHING AND LIGHTENING PROTECTION SYSTEM FOR

SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP) ( Pkg. NO.: 127)

MEC/S/9101/11/E1/00/14-15/127, REV-3 41

94 BOF - Main Control and Electrical Building

E-Auxil. Room

5.4 7.4 4.55 5 YES NO

95 BOF - Main Control and Electrical Building

AC Room 5.4 8.95 7.4 5 NO NO

96 BOF - Main Control and Electrical Building

Cable Room 5.4 17.9 14.4 5 NO NO

97 BOF - Main Control and Electrical Building

E-Auxil. Room

5.4 5 4.3 5 YES NO

98 BOF - Main Control and Electrical Building

Corridor 5.4 12.97 2.4 5 NO YES

99 BOF - Main Control and Electrical Building

AC Room 5.4 8.7 4.85 5 NO NO

100 BOF - Main Control and Electrical Building

Battery Room

5.4 11.85 5 5 NO NO

101 BOF - Main Control and Electrical Building

Cable Room 5.4 14.4 12.25 5 NO NO

102 BOF - Main Control and Electrical Building

E-Auxil. Room

5.4 4.85 4.65 5 YES NO

103 BOF - Main Control and Electrical Building

Cable Room 5.4 14.4 8.9 5 NO NO

104 BOF - Main Control and Electrical Building

Laboratory 5.4 10.75 9.2 4.4 YES NO

105 BOF - Main Control and Electrical Building

Fire Fighting Room

5.4 9.15 4.5 4.4 NO NO

106 BOF - Main Control and Electrical Building

Fire Fighting Room

5.4 9.15 4.5 4.4 NO NO

107 BOF - Main Control and Electrical Building

Cable Floor 7.75 12.6 4.55 2.65 NO NO

108 BOF - Main Control and Electrical Building

Cable Floor 7.75 12.6 4.25 2.65 NO NO

109 BOF - Main Control and Electrical Building

Cable Floor 7.75 12.6 5 2.65 NO NO

110 BOF - Main Control and Electrical Building

Cable Floor 7.75 12.6 4.55 2.65 NO NO

111 BOF - Main Control and Electrical Building

Cable Floor 7.75 12.6 4.25 2.65 NO NO

112 BOF - Main Control and Electrical Building

Cable Floor 7.75 12.6 5 2.65 NO NO

113 BOF - Main Control and Electrical Building

Corridor 10.65 55.75 2.4 4.85 NO YES

114 BOF - Main Control and Electrical Building

Control Room 1

10.65 22.6 9.55 3.5 YES NO

115 BOF - Main Control and Electrical Building

Control Room 2

10.65 9.37 4.85 3 YES NO

116 BOF - Main Control and Electrical Building

Dispatcher Office

10.65 5.25 4.85 4.85 YES NO

117 BOF - Main Control and Electrical Building

Level 1 + 2

Server &Progr. Room

10.65 11.87 4.85 4.85

YES NO

118 BOF - Main Control and Electrical Building

Control Room 3

10.65 9.6 4.85 3 YES NO

Page 42: Illumination

SAIL -BSP

STEEL AUTHORITY OF INDIA LIMITED BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION, EARTHING AND LIGHTENING PROTECTION SYSTEM FOR

SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP) ( Pkg. NO.: 127)

MEC/S/9101/11/E1/00/14-15/127, REV-3 42

119 BOF - Main Control and Electrical Building

Tea Kitchen 10.65 2.42 2.1 4.85 NO YES

120 BOF - Main Control and Electrical Building

Lavatory 10.65 2.42 2.2 4.85 NO YES

121 BOF - Main Control and Electrical Building

Lavatory 10.65 3.1 2.3 4.85 NO YES

122 BOF - Main Control and Electrical Building

Office and Meeting Room

10.65 9.55 8.8 4.85 YES NO

123 BOF - Main Control and Electrical Building

MCC / PLC - Room

10.65 35.55 11.85 4.85 NO NO

124 BOF - Main Control and Electrical Building

UPS Room 10.65 11.85 9.35 4.85 NO NO

125 BOF - Main Control and Electrical Building

VVVF + PLC - Room

10.65 24.2 11.85 4.85 NO NO

126 BOF - Main Control and Electrical Building

Corridor 15.7 64.85 2 3.8 YES NO

127 BOF - Main Control and Electrical Building

Meeting Room

15.7 9.55 4.4 3.8 YES NO

128 BOF - Main Control and Electrical Building

Office 15.7 7.4 4.4 3.8 YES NO

129 BOF - Main Control and Electrical Building

Office 15.7 7.4 5.9 3.8 YES NO

130 BOF - Main Control and Electrical Building

Archiv 15.7 2.9 2.4 3.8 YES NO

131 BOF - Main Control and Electrical Building

Office 15.7 7.4 3.75 3.8 YES NO

132 BOF - Main Control and Electrical Building

Office 15.7 7.4 5.1 3.8 YES NO

133 BOF - Main Control and Electrical Building

Office 15.7 7.4 5.15 3.8 YES NO

134 BOF - Main Control and Electrical Building

Office 15.7 7.4 4.9 3.8 YES NO

135 BOF - Main Control and Electrical Building

Office 15.7 7.4 4.3 3.8 YES NO

136 BOF - Main Control and Electrical Building

Archiv 15.7 2.9 2.4 3.8 YES NO

137 BOF - Main Control and Electrical Building

Office 15.7 7.4 3.2 3.8 YES NO

138 BOF - Main Control and Electrical Building

Office 15.7 7.4 6 3.8 YES NO

139 BOF - Main Control and Electrical Building

Tea Kitchen 15.7 4.97 2.1 3.8 NO YES

140 BOF - Main Control and Electrical Building

Store 15.7 2.4 2.2 3.8 YES YES

141 BOF - Main Control and Electrical Building

Lavatory 15.7 2.42 2.2 3.8 NO NO

142 BOF - Main Control and Electrical Building

Lavatory 15.7 3.1 2.3 3.8 NO NO

143 BOF - Main Control and Electrical Building

Archiv 15.7 2.75 2.4 3.8 YES NO

Page 43: Illumination

SAIL -BSP

STEEL AUTHORITY OF INDIA LIMITED BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION, EARTHING AND LIGHTENING PROTECTION SYSTEM FOR

SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP) ( Pkg. NO.: 127)

MEC/S/9101/11/E1/00/14-15/127, REV-3 43

144 BOF - Main Control and Electrical Building

AC Room 19.85 12 7.4 4 NO NO

145 BOF - Main Control and Electrical Building

AC Room 19.85 17.4 7.4 4 NO NO

146 BOF - Main Control and Electrical Building

AC Room 19.85 5.85 7.4 4 NO NO

147 Pump House Electrical Building

Cable Cellar -3.5 19.8 10.1 3.3 NO NO

148 Pump House Electrical Building

Cable Cellar -3.5 15.3 10.1 3.3 NO NO

149 Pump House Electrical Building

Stair Case 3.55 6.6 2.6 3.3 NO NO

150 Pump House Electrical Building

Stair Case 0 10.1 2.6 5 NO NO

151 Pump House Electrical Building

Electrical + PLC Room

0 15.3 10.1 5 NO NO

152 Pump House Electrical Building

Transformer Room

0 8.3 5 5 NO YES

153 Pump House Electrical Building

Transformer Room

0 8.3 5 5 NO YES

154 Pump House Electrical Building

Electrical Room

0 16.9 5.1 5 NO NO

155 Pump House Electrical Building

Stair Case 5.25 10.1 2.6 4.5 NO NO

156 Pump House Electrical Building

Fire Fighting Room

5.25 8.3 5 4.5 NO NO

157 Pump House Electrical Building

AC Room 5.25 8.45 4.8 4.5 NO NO

158 Pump House Electrical Building

Corridor 6.25 9.2 2.15 3.5 NO YES

159 Pump House Electrical Building

Electrical Room

6.25 7.8 5.25 3.5 NO NO

160 Pump House Electrical Building

Control Room

6.25 7.8 3.8 3.5 YES NO

161 Pump House Electrical Building

Ventilation Room

4.9 10.1 8.3 4.5 NO NO

162 Crane Substation 01 Electrical Building

Cable Cellar -3.55 17.6 14.4 3.3 NO NO

163 Crane Substation 01 Electrical Building

Stair Case -3.55 5.8 3.6 3.3 NO NO

164 Crane Substation 01 Electrical Building

Stair Case 0 5.8 3.6 4.4 NO NO

165 Crane Substation 01 Electrical Building

Transformer Room

0.2 8.7 4.7 5 NO YES

166 Crane Substation 01 Electrical Building

Transformer Room

0.2 8.3 4.7 5 NO YES

167 Crane Substation 01 Electrical Building

Electrical Room

0 12.8 9.7 4.4 NO NO

168 Crane Substation 01 Electrical Building

Ventilation Room

0 5.8 4.7 4.4 NO NO

169 Crane Substation 01 Electrical Building

Stair Case 4.65 5.8 3.6 3 NO NO

170 Crane Substation 01 Electrical Building

Office 4.65 12.6 9.7 3 YES NO

171 Crane Substation 01 Electrical Building

Rest Room 4.65 4.7 3.65 3 YES NO

Page 44: Illumination

SAIL -BSP

STEEL AUTHORITY OF INDIA LIMITED BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION, EARTHING AND LIGHTENING PROTECTION SYSTEM FOR

SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP) ( Pkg. NO.: 127)

MEC/S/9101/11/E1/00/14-15/127, REV-3 44

172 Crane Substation 01 Electrical Building

Storage 4.65 2 1.75 3 YES YES

173 Crane Substation 01 Electrical Building

Lavatory 4.65 2.8 2 3 NO YES

174 Crane Substation 02 Electrical Building

Stair Case 3.55 7.9 1.2 3.3 NO NO

175 Crane Substation 02 Electrical Building

Cable Cellar 3.55 25.1 12.4 3.3 NO NO

176 Crane Substation 02 Electrical Building

Electrical Room

0 20.8 7.4 5 NO NO

177 Crane Substation 02 Electrical Building

Corridor 0 6.05 2.6 5 NO YES

178 Crane Substation 02 Electrical Building

Ventilation Room

0 12.4 4 5 NO NO

179 Crane Substation 02 Electrical Building

Transformer Room 1

0.2 8.8 4.7 4.8 NO YES

180 Crane Substation 02 Electrical Building

Transformer Room 2

0.2 8.8 4.7 4.8 NO YES

181 Crane Substation 03 Electrical Building

Stair Case -3.5 5.95 3.5 8.5 NO NO

182 Crane Substation 03 Electrical Building

Cable Cellar -3.5 14.4 8.7 3.25 NO NO

183 Crane Substation 03 Electrical Building

Stair Case 0 6.25 3.5 5 NO NO

184 Crane Substation 03 Electrical Building

Ventilation Room

0 7.85 3.5 5 NO NO

185 Crane Substation 03 Electrical Building

Electrical Room

0 9.4 8.7 5 NO NO

186 Crane Substation 03 Electrical Building

Transformer Room

0.2 8.7 4.7 4.8 NO YES

187 Scrap Yard Control Building Control Room

7 5 3.3 2.7 NO NO

188 Cabel Tunnels Cable

Tunnels 2500 3.5 3.5

NO NO

189 Flux and Alloy System Electric Building - BOF 1

Control Room

53 3.6 3 2.6 NO NO

190 Flux and Alloy System Electric Building - BOF 1

AC Room 53 8.25 3 3 NO NO

191 Flux and Alloy System Electric Building - BOF 1

Electric Room

56.5 11.4 3 3 NO NO

192 Flux and Alloy System Electric Building - BOF 2

Electric Room

45.3 11.15 3.4 3 NO NO

193 Flux and Alloy System Electric Building - BOF 2

AC Room 48.55 8.25 3.4 3 NO NO

194 Flux and Alloy System Electric Building - BOF 3

Electric Room

45.3 11.15 3.4 3 NO NO

195 Flux and Alloy System Electric Building - BOF 3

AC Room 48.55 8.25 3.4 3 NO NO

196 ACVS and Lighting Substation Stair Case -3.65 5.15 2.6 11.6 NO NO

197 ACVS and Lighting Substation Cable Cellar -3.65 11.5 10.9 3.55 NO NO

198 ACVS and Lighting Substation Electric Room

0.15 11.5 10.9 4.05 NO NO

Page 45: Illumination

SAIL -BSP

STEEL AUTHORITY OF INDIA LIMITED BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION, EARTHING AND LIGHTENING PROTECTION SYSTEM FOR

SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP) ( Pkg. NO.: 127)

MEC/S/9101/11/E1/00/14-15/127, REV-3 45

199 ACVS and Lighting Substation Corridor 4.45 2.35 2 3 NO YES

200 ACVS and Lighting Substation Reserve Room

4.45 5.75 5.45 3 YES NO

201 ACVS and Lighting Substation AC and

Ventilation Room

4.45 11.5 10.9 3 NO NO

202 ACVS and Lighting Substation Lavatory 4.45 2.8 2 3 NO YES

203 Valve Control Remote I/O Room

Valve Control

Remote I/O Room

48.8 8.5 4 3

NO NO

204 Valve Control Remote I/O Room

AC Room 48.8 4 2.5 3 NO NO

205 Hot Metal Reladling Control Room

Control Room

6.2 8 4 3 NO NO

206 Hot Metal Reladling Electrical Room

Electric Room

6.2 8 4 3 NO NO

207 Hot Metal Reladling Electrical Room

AC Room 0 4 4 3 NO NO

208 Pump House Pump House 0 60 26 13.4 NO NO

209 Charging Control Pulüpit BOF-01

Charging Control Pulpit

10.3 2 2 2.5 YES NO

210 Charging Control Pulüpit BOF-02

Charging Control Pulpit

10.3 2 2 2.5 YES NO

211 Charging Control Pulüpit BOF-03

Charging Control Pulpit

10.3 2 2 2.5 YES NO

212 Tapping Control Pulpit BOF-01

Taping Control Pulpit

10.3 2 2 2.5 YES NO

213 Tapping Control Pulpit BOF-02

Taping Control Pulpit

10.3 2 2 2.5 YES NO

214 Tapping Control Pulpit BOF-03

Taping Control Pulpit

10.3 2 2 2.5 YES NO

215 Skirt Hydraulic Room BOF-01 Hydraulic

Room 23 3.64 1.6 2.5

NO NO

216 Skirt Hydraulic Room BOF-02 Hydraulic

Room 23 3.64 1.6 2.5

NO NO

217 Skirt Hydraulic Room BOF-03 Hydraulic

Room 23 3.64 1.6 2.5

NO NO

218 SVAICONE Hydraulic Room BOF-01

Hydraulic Room

28.5 3.64 1.6 2.5 NO NO

219 SVAICONE Hydraulic Room BOF-02

Hydraulic Room

28.5 3.64 1.6 2.5 NO NO

220 SVAICONE Hydraulic Room BOF-03

Hydraulic Room

28.5 3.64 1.6 2.5 NO NO

221 Hot metal relading electrical room

Electrical room for

torpedo cars 0.6 9.8 5.5 3.15

NO NO

222 Hot metal relading electrical room

Electrical room for

torpedo cars 0.6 9.8 5.5 3.15

NO NO

223 Secondary dedusting electrical building

Isol. Switches

0 21.9 5.1 5 NO NO

224 Primary dedusting electrical building

Corridor 5.25 8.3 1.65 3.5 NO YES

Page 46: Illumination

SAIL -BSP

STEEL AUTHORITY OF INDIA LIMITED BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION, EARTHING AND LIGHTENING PROTECTION SYSTEM FOR

SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP) ( Pkg. NO.: 127)

MEC/S/9101/11/E1/00/14-15/127, REV-3 46

225 BOF main control room building

Office 15.75 7.35 4.45 3.8 YES NO

226 BOF main control room building

Office 15.75 7.35 4.3 3.8 YES NO

227 ECR control room in slag yard Control room 15 12 4.5 YES NO

228 Office /shift room in slag yard. Office room 15 12 4.5 YES NO

229 Office /shift room in slag yard. Office room 15 12 4.5 YES NO

230 Lime milk spray unit. (4 story structural building )

7 8 14.5 NO NO

231 Ferro alloy storage building 130 30 14 NO NO

232 ESP (Secondary De dusting complex)

110 50 40 NO NO

233 Illumination for 10.3m Ramp 177 8 NO NO

234 Illumination for Reladling pits 24 13 6 NO NO

235 Illumination for Reladling pits 24 13 6 NO NO

236 A-B (Slag yard) Bay 252 38 38 NO NO

237 C-E Bay Scrap yard Bay 159 36 25 NO NO

238 E-F Bay(Charging bay) Bay 456 28 48 NO NO

239 D-E Bay(Torpedo bay) Bay 171 26.5 43 NO NO

240 F-G Bay(Converter bay) Bay 456 23 70 NO NO

241 G-G’ Bay9Ladle preparation bay)

Bay 372 9 56 NO NO

242 G’-H Bay Bay 432 27 56 NO NO

243 H-I Bay(Secondary refining bay)

Bay 336 27 33 NO NO

244 I-J Bay(Ladle Handling preparation bay)

Bay 336 30 33 NO NO

245 Platform at +3500 FG’ 7-1 75 5 6.8 NO NO

246 Platform at +5000 FG’ 7-1 5 5 5.3 NO NO

247 Platform at +6000 Converter 30 23 4.3 NO NO

248 Platform at +6800 Converter 30 23 3.5 NO NO

249 Platform1 at +6200 Reladling

plant 48 14 4.1

NO NO

250 Platform 2 at +6200 Reladling

plant 48 14 4.1

NO NO

251 Platform at +10300 Converter

area 288 60 6.4

NO NO

252 Platform at +16700 Converter

area 153 23 6.3

NO NO

253 Platform at +23 Converter

area 156 32 5.5

NO NO

254 Platform at +26m Converter

area 156 32 7.4

NO NO

255 Platform at +29m Converter

area 156 32 7.4

NO NO

256 Platform at +30m Converter

area 156 32 7.4

NO NO

257 Platform at +33m Primary

dedusting 153 23 6

NO NO

258 Platform at +34m Primary

dedusting 153 23 6

NO NO

Page 47: Illumination

SAIL -BSP

STEEL AUTHORITY OF INDIA LIMITED BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION, EARTHING AND LIGHTENING PROTECTION SYSTEM FOR

SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP) ( Pkg. NO.: 127)

MEC/S/9101/11/E1/00/14-15/127, REV-3 47

259 Platform at +37m Primary

dedusting 153 23 6

NO NO

260 Platform at +28.5 Primary

dedusting 51 31 7

NO NO

261 Platform at +38m Primary

dedusting 156 32 6

NO NO

262 Platform at +41m Primary

dedusting 156 32 7

NO NO

263 Platform at +45.3 Primary

dedusting 150 23 7

NO NO

264 Platform at +50.25m Primary

dedusting 90 3 7

NO NO

265 Platform at +53,56m Primary

dedusting 153 18 7

NO NO

266 Platform1 at +57.5m

Primary dedusting

84 4 7 NO NO

267 Platform2 at +57.5m Primary

dedusting 84 4 7

NO NO

268 Platform at +48.8m Lance 90 18 7 NO NO

269 Platform at +51 Lance 15 7 7 NO NO

270 Platform at +53.5 Lance 90 7 7 NO NO

271 4m road –1.5Km 1500 4 NO NO

272 7m road – 2.5Km 2500 7 NO NO

273 11m road – 1.0Km 1000 11 NO NO

274

Room Sizes for ACVS Buildings/ Rooms, Shiftincharge etc. will be indicated during tender discussion.

NO NO

275 Cable celler 76 2 3 NO NO

276 Welfare building

YES YES

1. ceiling fan,officeroom,shiftinchargeroom,shiftroom,restroom,telecommunicationroom,officeroom,corridor,store room and all others rooms of welfare building (except toilet ,wash room) etc. 2 single phase exhaust fan shall be considered for toilet ,kitchen/pantry room,wash room and store etc.

277 operation shift room common shift rooms of BOF

10.3 YES NO Location of room is at row G and between column 11 and 12a,Area is 20 Sqmeter

278

dispatcher room common shift rooms of BOF

10.3

YES NO

Location of room is at row G and between column 11 and 12a,Area is 20 Sqmeter

279 Lab room

common shift rooms of BOF

10.3

YES NO Location of room is at row G and between column 11 and 12a,Area is 20 Sqmeter

280 Mechanical shift room

common shift rooms of BOF

10.3

YES NO Location of room is at row G' and between column 11 and 12a,Area is 20 Sqmeter

Page 48: Illumination

SAIL -BSP

STEEL AUTHORITY OF INDIA LIMITED BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION, EARTHING AND LIGHTENING PROTECTION SYSTEM FOR

SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP) ( Pkg. NO.: 127)

MEC/S/9101/11/E1/00/14-15/127, REV-3 48

281 Electrical shift room

common shift rooms of BOF

10.3

YES NO Location of room is at row G' and between column 11 and 12a,Area is 20 Sqmeter

282 Instrumentation shift room

common shift rooms of BOF

10.3

YES NO Location of room is at row G' and between column 11 and 12a,Area is 20 Sqmeter

283 Rest room -1(operation)

common shift rooms of BOF

10.3

YES NO Location of room is at row G' and between column 11 and 12a,Area is 20 Sqmeter

284 Rest room -2(Crane operator)

common shift rooms of BOF

10.3

YES NO Location of room is at row G' and between column 11 and 12a,Area is 20 Sqmeter

285 Rest room -3(Mechnical)

common shift rooms of BOF

10.3

YES NO Location of room is at row G' and between column 11 and 12a,Area is 20 Sqmeter

286 Rest room -4(Electrical

common shift rooms of BOF

10.3

YES NO Location of room is at row G' and between column 11 and 12a,Area is 20 Sqmeter

287 Store room

common shift rooms of BOF

10.3

YES

NO

Location of room is at row G' and between column 11 and 12a,Area is 20 Sqmeter

288 Store room

common shift rooms of BOF

10.3

YES

NO

Location of room is at row G' and between column 11 and 12a,Area is 20 Sqmeter

289 Store room

common shift rooms of BOF

10.3

YES NO Location of room is at row G' and between column 11 and 12a,Area is 20 Sqmeter

290 Secondary dedusting electrical building

Crew room 12.25 YES NO Area is 16 sqmeter

291 Crane Substation 01 Electrical Building

Transformer Room

0.2 8.3 4.7 5 NO YES

292 Crane Substation 01 Electrical Building

Telephone room

5.2 YES YES

293

Crane Substation 02 Electrical Building

Office 5.2 YES NO

294

Crane Substation 02 Electrical Building

Rest room 5.2 YES NO

295 Crane Substation 03 Electrical Building

Transformer Room

0.2 8.7 4.7 4.8 NO YES

296 Hot metal reladling control pulpit

control pulpit at column D-4

6.2 YES NO

297 Hot metal reladling control pulpit

control pulpit at column D-6

6.2 YES NO

298 Hot metal reladling control pulpit

control pulpit at column F-4

6.2 YES NO

299 Hot metal reladling control pulpit

control pulpit at column F-6

6.2 YES NO

300 Ladle preperation bay Shift room YES NO 301 Ladle preperation bay Rest room YES NO 302 Slag yard control room YES

303 Slag yard strore room

304 Material handling dedusting ET-71 control room

305 Material handling dedusting control room

Page 49: Illumination

SAIL -BSP

STEEL AUTHORITY OF INDIA LIMITED BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION, EARTHING AND LIGHTENING PROTECTION SYSTEM FOR

SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP) ( Pkg. NO.: 127)

MEC/S/9101/11/E1/00/14-15/127, REV-3 49

ET-72

306 Ladle preperation bay Store room YES

307

Toilet block Near Col. C-30& LTSS 3 YES

308

Toilet block Near Col. E-25 & PH YES

309

Toilet block Near Col. F-18 YES

310

Toilet block Near Col. F-13 YES

311

Toilet block Near Col. F-5 YES

312

Toilet block Near Col. H-1 & HT SS-63 YES

313

Toilet block Near Col. D-6 YES

314

Toilet block Near Primary

De-dusting ID fan Flare

Stack YES

315

Toilet block Near Gas Booster

Fan YES

316 10T ELEVATOR,NEAR

COLUMN G-12b &

13 YES 20sq.m area

317 5T ELEVATOR,NEAR

COLUMN F 3-18 &

19a YES 15sq.m area

318 1T ELEVATOR,NEAR

COLUMN F 1-13

YES 10sq.m area

Page 50: Illumination

SAIL -BSP

STEEL AUTHORITY OF INDIA LIMITED BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION, EARTHING AND LIGHTENING PROTECTION SYSTEM FOR

SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP) ( Pkg. NO.: 127)

MEC/S/9101/11/E1/00/14-15/127, REV-3 50

TENTATIVE CEILING FAN / EXHAUST FAN REQUIREMENT(CCP Area)

SN ROOM CODE DESCRIPTON AREA Sq.Mt

LEVEL (Mtrs)

LOCATION (COLUMN

NO)

CEILING FAN,

(Pkg-127)

EXHUAST FAN,

(Pkg-127)

REMARKS

COMMON ROOMS

PROTECTION BOX FOR RADIO ACTIVE SOURCE

CK1, BILLET CASTER NO.1

1 CK1 OR 61 CASTER CONTROL ROOM 37 10.6 J-11, J-12a & K-11, K-12a

YES NO

2 CK1 OR 62

TORCH CUTTING CONTROL

ROOM 29 0 K-11 YES NO

3 CK1 OR 63

DISCHARGE AREA CONTROL

ROOM 29 4.9 M-9 & M-10 YES NO

CK2, BILLET CASTER NO.2

4 CK2 EF 61 CABLE CELLAR 477 -3.35

J-14,J-14a & K-14,K-14a NO NO

5 CK2 OR 61 CASTER CONTROL ROOM 37 10.6 J-14,J-14a & K-14,K-14a

YES NO

6 CK2 OR 62 TORCH CUTTING CONTROL

ROOM 29 1.4 K-14,K-14a YES NO

7 CK2 OR 63 DISCHARGE AREA CONTROL

ROOM 23 4.3 N-13 & N-14 YES NO

CV1, BILLET CUM BLOOM CASTER NO.3

8 PUMP ROOM 1 163 -3.1 J16,J-16a,J-17 & J16,J-

16a,J-17 NO NO

9 CV1 FF 06 CLEAN GAS EXTNG ROOM 7 0 K-18,K-19a &

L-18,L-19a NO NO

10 CV1 OR 61 CASTER CONTROL ROOM 37 13.4 J-18,J-19a & K-18,K-19a

YES NO

11 CV1 CP 01 L2 COMPUTER ROOM 47 13.4 J-18,J-19a & K-18,K-19a

YES NO

12 CKV1 OR 62 TORCH CUTTING CONTROL

ROOM 28 1.4 K-18 YES NO

13 CV1 OR 63 DISCHARGE AREA CONTROL

ROOM 30 6.6 M-16 & M-

16a YES NO

14 HYDRAULIC VALVE STANDS

(1-25 NOs) NO YES

15 WATER VALVE STANDS (1-15

NOs) NO YES

CV2, BEAM BLANK CASTER NO.4

16 CV2 WR 61 WATER ROOM 1 298 6 J-26 & J-27 NO YES

17 CV2 WR 62 WATER ROOM 2 29 0 J-25, I-25 NO YES

18 CV2 WR 63 WATER ROOM 3 42 0 J-27 NO YES

19 CV2 ER 60 SUB STSTION ROOM 313 0 H-26 & H-28 NO YES

20 CV2 OR 61 CASTER CONTROL ROOM 37 13.4 I-27 YES NO

Page 51: Illumination

SAIL -BSP

STEEL AUTHORITY OF INDIA LIMITED BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION, EARTHING AND LIGHTENING PROTECTION SYSTEM FOR

SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP) ( Pkg. NO.: 127)

MEC/S/9101/11/E1/00/14-15/127, REV-3 51

21 CV1 CP 01 L2 COMPUTER ROOM YES NO

22 CV2 OR 62

TORCH CUTTING CONTROL

ROOM 30 1.4

I-28 & I-29

YES

NO

23 CV 2 OR 63

DISCHARGE AREA CONTROL

ROOM 29 4.9 C'-5 & C'-6 YES NO

24 Shipping Room

0.00

Near CK1 Disch.Control Room(added)

YES

25 Store Room 1

0.00

Near Column I-3

YES

26 Store Room 5

0.00

Near Column K-15A

YES

27 Store Room 7

0.00

Near Column L-8

YES

28 Store Room 8

0.00

Near Column L-14

YES

29 Store Room 11

0.00

Near Column N-15

YES

30 Shift Room 1

0.00

Near Column I-1

YES

31 Shift Room 9

0.00

Near Column M-29

YES

32 Shift Room 11

0.00

Near Column N-18

YES

33 Rest Room 2

0.00

Near Column J-25

YES

34 Rest Room 6

0.00

Near Column L-27

YES

35 Rest Room 8

0.00

Near Column N-19

YES

36 Rest Room 9

0.00

Near Column N-14

YES

37

Shipping Room

0.00

Near CK1 Disch. Control

Room(added)

YES

38

Toilet block 0.00 Toilet Block

M29

YES

39

Toilet block 0.00

Toilet block

L29

YES

40

Toilet block 0.00

Toilet block K

1

YES

41

Toilet block 0.00

Toilet block

K30

YES

42

Toilet block 0.00

Toilet block

B’8’

YES

43

Toilet block

Toilet block

K14-14a

YES

44

Toilet block 0.00

Toilet block

C’1’

YES

45

5t Elevator for 300t EOT crane 22 0.00

Near Col. I-1

YES

46

5t Elevator,CK1 up to +10m 22

Near Col. K-7,K-8

YES

47 5t Elevator,CV1 up to 22 YES

Page 52: Illumination

SAIL -BSP

STEEL AUTHORITY OF INDIA LIMITED BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION, EARTHING AND LIGHTENING PROTECTION SYSTEM FOR

SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP) ( Pkg. NO.: 127)

MEC/S/9101/11/E1/00/14-15/127, REV-3 52

+12.8m Near Col. K-19B & K20

TUN4838DISH DESKULLING SHOP

48 OFFICE ROOM YES NO

49 STAFF ROOM YES NO

50 Toilet Block 0.00

Tundish Deskulling Shop

YES

YES

Note : Supply and installation of 20 sets of ceiling fans and 20 sets of

exhaust fans shall be considered by bidder for execution at the time of

erection, to take care of any uncovered areas of BOF & CCP together.

List of Tools and Tackles of TAPADIA/EVEREST Make

SNO. Item Description Quantity

1. Hammer Drill 15 Nos. 2. Electrical Drilling machine medium and small portable. 8 3. Meggar (500V,1000V) 2 Nos. each 4. Earth meggar 2Nos. 5. Tong tester and multimeter 3Nos. 6. Digital multimeter 6 Nos. 7. Lux meter 3 Nos. 8. Hand crimping Tools of 300,255,185,50,16,6, sqmm. 51 Nos. 9. Ring Spanner sets 8 sets

10. D-spanner sets 8 sets 11. Box spanner sets 8 sets 12. Pliers 5 sets 13. Screw drivers 5 sets 14. Testers 12 Nos. 15. Soldering Iron 6 Nos. 16. Phase sequence meter 6 Nos. 17. Air blower 5 Nos. 18. Allen keys set 5 sets.